WPR (21-Apr-2021 To 27-Apr-2021)
WPR (21-Apr-2021 To 27-Apr-2021)
CC ARCHIVE/FILE
Page 1 of 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
TABLE OF CONTENTS
Page 2 of 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
LIST OF PICTURES
LIST OF TABLES
Page 3 of 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Main Building 537,889 Sft (LGF, GF, FF, SF, TF & Roof Top)
PAGE 4 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
OVERALL PROGRESS
ETCH NISHTER‐II, MULTAN
40.00%
35.24%
30.00%
20.00%
14.11%
PROGRESS %AGE
10.00%
0.00%
‐10.00%
‐20.00%
‐21.13%
‐30.00%
PAGE 5 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
%age Progress
BL
This
Project BL Project Planned Achieved Overall
Description Period Remarks
Start Finish Date Variance
Variance
Date This This
Prev. Cum Prev. Cum
Period Period
Nishtar Hospital‐2 Multan 30‐Dec‐19 29‐Jun‐22 30.71% 1.08% 31.79% 12.19% 0.44% 12.63% ‐0.64% ‐19.16%
Engineering & Procurement 30‐Dec‐19 25‐Dec‐21 43.66% 2.20% 45.86% 13.02% 0.24% 13.26% ‐1.96% ‐32.60%
Drawings 30‐Dec‐19 31‐Jul‐20 100.00% 0.00% 100.00% 32.61% 0.00% 32.61% 0.00% ‐67.39%
IFC Drawings 30‐Dec‐19 17‐May‐20 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% 0.00% 0.00%
Shop Drawings 14‐Jan‐20 31‐Jul‐20 100.00% 0.00% 100.00% 0.00% 32.61% 32.61% 32.61% ‐67.39%
Procurement 09‐Jan‐20 25‐Dec‐21 100.00% ‐54.15% 45.85% 83.24% ‐69.99% 13.25% ‐15.84% ‐32.60%
Local Procurement 09‐Jan‐20 15‐Dec‐21 100.00% ‐47.76% 52.24% 7.85% 16.35% 24.20% 64.11% ‐28.04%
Foreign Procurement
18‐Feb‐20 25‐Dec‐21 76.34% ‐38.23% 38.11% 56.12% ‐56.12% 0.00% ‐17.89% ‐38.11%
(Long Lead Items)
Construction 30‐Dec‐19 26‐Jun‐22 100.00% ‐72.79% 27.21% 0.00% 14.75% 14.75% 87.54% ‐12.46%
Main Building 30‐Dec‐19 26‐Jun‐22 100.00% ‐74.65% 25.35% 0.00% 14.30% 14.30% 88.95% ‐11.05%
Sub Structure 30‐Dec‐19 16‐Sep‐20 100.00% 0.00% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
Earthworks 30‐Dec‐19 30‐Mar‐20 100.00% 0.00% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
Foundations 05‐Feb‐20 04‐May‐20 10.37% 89.63% 100.00% 0.00% 33.26% 33.26% ‐56.37% ‐66.74%
Backfilling 29‐May‐20 16‐Sep‐20 0.00% 100.00% 100.00% 0.00% 100.00% 100.00% 0.00% 0.00%
Lower Ground Floor 28‐Feb‐20 07‐May‐22 100.00% ‐70.96% 29.04% 0.00% 26.28% 26.28% 97.24% ‐2.76%
Structural Works 28‐Feb‐20 17‐Sep‐20 100.00% 0.00% 100.00% 0.00% 85.56% 85.56% 85.56% ‐14.44%
Civil/Finishes/Architectural
23‐May‐21 07‐May‐22 0.00% 0.00% 0.00% 0.00% 5.47% 5.47% 5.47% 5.47%
Fit outs
MEP Works 02‐Jun‐21 27‐Apr‐22 0.00% 0.00% 0.00% 0.35% 0.08% 0.43% 0.08% 0.43%
Ground Floor 24‐May‐20 21‐Jun‐22 24.43% 0.00% 24.43% 5.53% 6.18% 11.71% 6.18% ‐12.72%
Structural Works 24‐May‐20 18‐Oct‐20 100.00% 0.00% 100.00% 22.64% 22.16% 44.80% 22.16% ‐55.20%
Civil/Finishes/Architectural
23‐May‐21 21‐Jun‐22 0.00% 0.00% 0.00% 0.00% 2.16% 2.16% 2.16% 2.16%
Fit outs
MEP Works 02‐Jun‐21 06‐Jun‐22 0.00% 0.00% 0.00% 0.00% 0.05% 0.05% 0.05% 0.05%
First Floor 21‐Jul‐20 15‐May‐22 28.42% 0.00% 28.42% 0.56% 2.00% 2.56% 2.00% ‐25.86%
Structural Works 21‐Jul‐20 06‐Jan‐21 100.00% 0.00% 100.00% 1.97% 7.02% 8.99% 7.02% ‐91.01%
PAGE 6 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Civil/Finishes/Architectural
05‐Jul‐21 15‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Fit outs
MEP Works 15‐Jul‐21 15‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Second Floor 29‐Sep‐20 21‐May‐22 26.35% 0.00% 26.35% 0.00% 0.00% 0.00% 0.00% ‐26.35%
Structural Works 29‐Sep‐20 02‐Apr‐21 100.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% ‐100.00%
Civil/Finishes/Architectural
11‐Jul‐21 21‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Fit outs
MEP Works 21‐Jul‐21 21‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Third Floor, Roof & Mumty 23‐Dec‐20 09‐Jun‐22 9.71% 6.10% 15.81% 0.00% 0.00% 0.00% ‐6.10% ‐15.81%
Structural Works 23‐Dec‐20 08‐Aug‐21 38.74% 24.30% 63.04% 0.00% 0.00% 0.00% ‐24.30% ‐63.04%
Civil/Finishes/Architectural
09‐Aug‐21 09‐Jun‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Fit outs
MEP Works 19‐Aug‐21 30‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Conveying System 29‐Mar‐22 27‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plant Room / Control Room
15‐Sep‐21 12‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
/ Specialty Areas
Elevational and External
22‐Nov‐21 26‐Jun‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Finishes
Ancillary Buildings 14‐Mar‐20 02‐Oct‐21 51.90% 20.35% 72.25% 24.97% 0.77% 25.74% ‐19.58% ‐46.51%
Cafeteria 21‐Mar‐20 09‐Aug‐21 63.51% 28.41% 91.92% 28.98% 0.87% 29.85% ‐27.54% ‐62.07%
Sub Structure 21‐Mar‐20 30‐Nov‐20 100.00% 0.00% 100.00% 98.71% 0.00% 98.71% 0.00% ‐1.29%
Ground Floor 14‐May‐20 24‐May‐21 68.84% 31.16% 100.00% 24.64% 0.99% 25.63% ‐30.17% ‐74.37%
Structural Works 14‐May‐20 12‐Jul‐20 100.00% 0.00% 100.00% 96.66% 0.00% 96.66% 0.00% ‐3.34%
Finishing/Architectural
12‐Oct‐20 24‐May‐21 93.87% 6.13% 100.00% 3.11% 2.49% 5.60% ‐3.64% ‐94.40%
Works
MEP Works 22‐Oct‐20 06‐May‐21 20.71% 79.29% 100.00% 0.00% 0.00% 0.00% ‐79.29% ‐100.00%
First Floor 08‐Jul‐20 09‐Aug‐21 62.95% 36.86% 99.81% 25.37% 1.52% 26.89% ‐35.34% ‐72.92%
Structural Works 08‐Jul‐20 30‐Nov‐20 100.00% 0.00% 100.00% 78.19% 0.00% 78.19% 0.00% ‐21.81%
Finishing/Architectural
01‐Dec‐20 09‐Aug‐21 71.92% 28.08% 100.00% 0.00% 4.06% 4.06% ‐24.02% ‐95.94%
Works
MEP Works 11‐Dec‐20 05‐May‐21 11.95% 87.43% 99.38% 0.00% 0.00% 0.00% ‐87.43% ‐99.38%
Sarai 21‐Mar‐20 02‐Oct‐21 37.91% 12.09% 50.00% 21.30% 0.67% 21.97% ‐11.42% ‐28.03%
Sub‐Structure 21‐Mar‐20 17‐Dec‐20 100.00% 0.00% 100.00% 96.77% 2.26% 99.03% 2.26% ‐0.97%
Ground Floor 24‐May‐20 02‐Oct‐21 46.80% 20.33% 67.13% 17.82% 0.00% 17.82% ‐20.33% ‐49.31%
PAGE 7 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Structural works 24‐May‐20 11‐Jul‐20 100.00% 0.00% 100.00% 86.66% 0.00% 86.66% 0.00% ‐13.34%
Finishing/Architectural
03‐Nov‐20 02‐Oct‐21 51.83% 41.75% 93.58% 5.74% 0.00% 5.74% ‐41.75% ‐87.84%
Works
MEP Works 13‐Nov‐20 20‐May‐21 13.57% 1.42% 14.99% 0.00% 0.00% 0.00% ‐1.42% ‐14.99%
First Floor 02‐Jul‐20 19‐Jul‐21 36.34% 6.33% 42.67% 18.65% 0.25% 18.90% ‐6.08% ‐23.77%
Structural Works 02‐Jul‐20 28‐Aug‐20 100.00% 0.00% 100.00% 89.22% 0.00% 89.22% 0.00% ‐10.78%
Finishing/Architectural
28‐Dec‐20 19‐Jul‐21 28.31% 11.88% 40.19% 5.29% 0.48% 5.77% ‐11.40% ‐34.42%
Works
MEP Works 07‐Jan‐21 14‐Jul‐21 12.47% 0.35% 12.82% 0.00% 0.00% 0.00% ‐0.35% ‐12.82%
Second Floor 19‐Aug‐20 18‐Aug‐21 36.57% 5.57% 42.14% 19.07% 1.89% 20.96% ‐3.68% ‐21.18%
Structural Works 19‐Aug‐20 02‐Nov‐20 100.00% 0.00% 100.00% 87.91% 0.00% 87.91% 0.00% ‐12.09%
Overhead Water Tank 11‐Oct‐20 17‐Dec‐20 100.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% ‐100.00%
Finishing/Architectural
21‐Feb‐21 08‐Aug‐21 27.59% 8.69% 36.28% 0.00% 4.32% 4.32% ‐4.37% ‐31.96%
Works
MEP Works 03‐Mar‐21 18‐Aug‐21 2.78% 5.40% 8.18% 0.00% 0.00% 0.00% ‐5.40% ‐8.18%
Metering Room‐1 14‐Mar‐20 29‐May‐20 100.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% ‐100.00%
Metering Room‐2 14‐Mar‐20 29‐May‐20 100.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% ‐100.00%
External Developments 30‐Dec‐19 10‐Jun‐22 28.20% 5.65% 33.85% 6.45% 1.38% 7.83% ‐4.27% ‐26.02%
Roads/Footpath/Parking’s 01‐Jun‐21 10‐Jun‐22 0.00% 0.00% 0.00% 0.00% 1.19% 1.19% 1.19% 1.19%
Boundary Wall 30‐Dec‐19 16‐Mar‐22 90.20% 0.00% 90.20% 23.07% 0.17% 23.24% 0.17% ‐66.96%
Boundary Wall Front 30‐Dec‐19 16‐Mar‐22 76.34% 0.00% 76.34% 55.72% 0.40% 56.12% 0.40% ‐20.22%
Boundary Wall Sides 30‐Dec‐19 30‐Aug‐20 100.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% ‐100.00%
Main Gate‐1 28‐Feb‐20 27‐Mar‐22 45.60% 11.07% 56.67% 9.50% 1.10% 10.60% ‐9.97% ‐46.07%
Structure 28‐Feb‐20 18‐Feb‐21 100.00% 0.00% 100.00% 25.17% 2.92% 28.09% 2.92% ‐71.91%
Finishing 19‐Feb‐21 27‐Mar‐22 12.61% 17.80% 30.41% 0.00% 0.00% 0.00% ‐17.80% ‐30.41%
Main Gate‐2 28‐Feb‐20 25‐Feb‐22 45.59% 17.72% 63.31% 31.38% 0.28% 31.66% ‐17.44% ‐31.65%
Grey Structure 28‐Feb‐20 18‐Feb‐21 100.00% 0.00% 100.00% 83.13% 0.76% 83.89% 0.76% ‐16.11%
Finishing 19‐Feb‐21 25‐Feb‐22 12.60% 28.46% 41.06% 0.00% 0.00% 0.00% ‐28.46% ‐41.06%
External Electrical Works 02‐Jun‐20 01‐Apr‐22 65.28% 0.03% 65.31% 0.00% 0.00% 0.00% ‐0.03% ‐65.31%
External Electrical Works 16‐May‐21 01‐Apr‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
External Electrical Works
02‐Jun‐20 05‐Feb‐21 100.00% 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% ‐100.00%
(Feeder Connectivity)
PAGE 8 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
LT, HT Apparatus 06‐Feb‐21 06‐Apr‐21 99.39% 0.61% 100.00% 0.00% 0.00% 0.00% ‐0.61% ‐100.00%
Civil Works for IT System 27‐Aug‐21 14‐Mar‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Public Health Works 31‐Dec‐20 03‐May‐22 27.29% 16.62% 43.91% 15.11% 2.98% 18.09% ‐13.64% ‐25.82%
Water Supply Network 12‐Mar‐21 09‐Jul‐21 1.62% 24.97% 26.59% 0.00% 0.00% 0.00% ‐24.97% ‐26.59%
Tube Well 05‐Dec‐21 03‐May‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Storm Water Drainage
31‐Dec‐20 14‐Jan‐22 60.06% 32.33% 92.39% 36.22% 7.16% 43.38% ‐25.17% ‐49.01%
Work
RCC Drains 31‐Dec‐20 07‐Aug‐21 62.12% 33.03% 95.15% 37.46% 7.41% 44.87% ‐25.62% ‐50.28%
Catch Basins 16‐Mar‐21 14‐Jan‐22 0.15% 11.87% 12.02% 0.00% 0.00% 0.00% ‐11.87% ‐12.02%
Storm Water Disposal
07‐Oct‐21 06‐Feb‐22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Station
Sewerage Network 31‐Dec‐20 30‐Nov‐21 25.31% 22.60% 47.91% 0.00% 0.00% 0.00% ‐22.60% ‐47.91%
Progress S‐Curve
100 6,000
90
5,000
80
70
Millions
4,000
Millions
60
50 3,000
40
2,000
30
20
1,000
10
0 0
8‐Mar‐20
12‐Jul‐20
26‐Jul‐20
1‐Nov‐20
7‐Mar‐21
11‐Jul‐21
25‐Jul‐21
9‐Jan‐22
6‐Mar‐22
29‐Dec‐19
12‐Jan‐20
26‐Jan‐20
9‐Feb‐20
23‐Feb‐20
22‐Mar‐20
5‐Apr‐20
19‐Apr‐20
3‐May‐20
17‐May‐20
31‐May‐20
14‐Jun‐20
28‐Jun‐20
9‐Aug‐20
23‐Aug‐20
6‐Sep‐20
20‐Sep‐20
4‐Oct‐20
18‐Oct‐20
15‐Nov‐20
29‐Nov‐20
13‐Dec‐20
27‐Dec‐20
10‐Jan‐21
24‐Jan‐21
7‐Feb‐21
21‐Feb‐21
21‐Mar‐21
4‐Apr‐21
18‐Apr‐21
2‐May‐21
16‐May‐21
30‐May‐21
13‐Jun‐21
27‐Jun‐21
8‐Aug‐21
22‐Aug‐21
5‐Sep‐21
19‐Sep‐21
3‐Oct‐21
17‐Oct‐21
31‐Oct‐21
14‐Nov‐21
28‐Nov‐21
12‐Dec‐21
26‐Dec‐21
23‐Jan‐22
6‐Feb‐22
20‐Feb‐22
20‐Mar‐22
3‐Apr‐22
17‐Apr‐22
1‐May‐22
15‐May‐22
29‐May‐22
12‐Jun‐22
26‐Jun‐22
PAGE 9 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Manpower Plan Vs Actual
377 377 356 359 364
Manpower 400 349 343
300
187 191 175 189 190
200 168 168
100
‐
21‐Apr‐21 22‐Apr‐21 23‐Apr‐21 24‐Apr‐21 25‐Apr‐21 26‐Apr‐21 27‐Apr‐21
1 Retaining Walls 28 Days 92.94% 93.36% 0.42% 100% 21-Jun-20 23-Aug-21 In progress
2 Columns (LGF) 28 Days 99.03% 99.19% 0.16% 100% 21-Jun-20 9-Jun-21 In progress
4 Columns (FF) 28 Days 14.14% 34.17% 20.03% 100% 15-Feb-21 27-May-21 In progress
Drop Panels, Beams & 85.92% 87.27% 1.35% 100% 21-Sep-20 9-Jul-21 In progress
5 28 Days
Main Building
Slab (LGF)
Drop Panels, Beams & 43.72% 48.20% 4.48% 100% 21-Jan-21 24-Jul-21 In progress
6 28 Days
Slab (GF)
Drop Panels, Beams & 8.34% 12.40% 4.06% 100% 17-Mar- 2-Oct-21 In progress
7 28 Days 21
Slab (FF)
8 Stairs (LGF) 28 Days 7.85% 20.02% 12.17% 100% 6-Apr-21 19-Jun-21 In progress
10 Block Masonry (LGF) 28 Days 21.88% 23.41% 1.53% 100% 5-Mar-21 19-Apr-22 In progress
PAGE 10 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Solid Block Masonry 45.0% 51.31% 6.31% 100% 22-Feb-21 27-Jun-21 In progress
15 28 Days
(GF)
Solid Block Masonry 30.0% 34.41% 4.41% 100% 25-Mar- 16-Aug-21 In progress
16 28 Days 21
(FF)
2nd level
Solid Block Masonry 60.0% 65.28% 5.28% 100% 16-Feb-21 19-Jun-21 In progress
22 28 Days
(GF)
Solid Block Masonry 60.0% 62.59% 2.59% 100% 12-Mar- 13-Aug-21 In progress
23 28 Days 21
(FF)
Solid Block Masonry 35.0% 37.79% 2.79% 100% 31-Mar- 7-Oct-21 In progress
24 28 Days 21
(SF)
barbed wire
Wall (with
Boundary
Pacca Brick Work in 99% 100.00% 3.00% 100% 22-Jun-20 27-May-21 In progress
27 28 Days
Foundations
Boundary Wall (Front)
Pacca Brick Work 65% 68.00% 3.00% 100% 28-Jan-21 21-Jul-21 In progress
29 28 Days
Above Plinths
30 Rebar of Lintel Beams 28 Days 90% 93.00% 3.00% 100% 28-Jan-21 6-Jun-21 In progress
32 Backfilling 28 Days
20
PAGE 11 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Foundations
2
Rebar of Beams & 85% 95.00% 2.33% 100% 21-May- 11-Jun-21 In progress
42 28 Days 21
Slab
Layout & Excavation 55% 57.10% 2.10% 100% 9-Sep-20 24-Sep-21 In progress
47 28 Days
of Drains
48 PCC (1:4:8) 28 Days 51% 53.08% 2.08% 100% 13-Sep-20 9-Oct-21 In progress
RCC Drains
49 Rebar of Drains 28 Days 49% 51.16% 2.16% 100% 6-Oct-20 9-Oct-21 In progress
PAGE 12 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
FINANCIAL STATUS
Financial Status
10.82%
IPCs Amount Verified
14.76%
Total To be Recovered Amount (A+B)
74.41% Remaining Financial Progress
PAGE 13 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Submittal Status
300 271
250
200
150 128115
100 77
56 56 59
45 38
50 19 19 30 29 23 22 20
12 9 3 0 0 0 1 0 2 0 6 1 12 1
0
CIVIL & HVAC PLUMBING FIRE FIGHTING ELECTRICAL TOTAL
ARCHITECTRE
TOTAL IN
DESCRIPTION SUBMITTED APPROVED REJECTED
SUBMITTALS REVIEW
CIVIL &
ARCHITECTRE 77 12 9 3 0
HVAC 56 19 19 0 0
PLUMBING 56 30 29 1 0
FIRE FIGHTING 23 22 20 2 0
ELECTRICAL 59 45 38 6 1
PAGE 14 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
MAJV 29 0 28 0 1 0
Discipline
This This This
Total Previous Previous
Week Week Week
PAGE 15 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
DISCIPLINE
This This
Total Previous This Week Previous
Week Week
Filed Instructions
93 4 81 0 8 4
(Civil)
Filed Instructions
8 0 4 0 4 0
(MEP)
HSE Instructions 52 0 50 0 2 0
NCR's 1 0 1 0 0 0
Test Performed/
Pass/ Approval Status Fail/ Rejection Status Remarks
DISCIPL TEST Report Submitted
INE DESCRIPTION This This This
Total Previous Previous
Week Week Week
Field Dry Density
Test (FDT)
1243 9 1126 6 108 3
Steel Test
(Chemical Test)
6 0 6 0 0 0
Civil /
Steel Test
Architec
(Physical Test)
40 3 37 3 0 0
ture
Cement Test
(Chemical Test)
25 0 25 0 0 0
Cement Test
(Physical Test)
78 0 78 0 0 0
PAGE 16 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
Sieve Analysis
(Coarse 249 3 246 3 0 0
Aggregate)
Sieve Analysis
(Fine Aggregate)
266 2 264 2 0 0
Proctor Test 14 0 14 0 0 0
Brick Test 31 0 30 0 1 0
Test Performed/ Pass/ Approval Status Pass/ Approval Status Fail/ Rejection
TEST Report Submitted (7 Days) (28 days) Status
DESCRIPTION
This This This This
Total Previous Previous Previous
Week Week Week Week
Mix Design Test
(External Lab)
9 0 9 - 7 - - -
Mix Design Test
(Site Lab)
39 0 11 - 5 - - -
Cylinder Crushing
Tests (3000 PSI)
433 9 182 2 242 7 - -
Cylinder Crushing
Tests (4000 PSI)
3930 69 1776 27 2085 42 - -
Cylinder Crushing
Tests (6000 PSI)
1628 59 594 11 968 48 7 -
Test Performed/
Pass/ Approval Status Fail/ Rejection Status Remarks
Report Submitted
DESCRIPTION
TOTA This This This
Previous Previous
MEP L Week Week Week
Electrical
HVAC
Plumbing 29 0 29 0 0 0
Misc Misc
PAGE 17 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
2 HSE Trainings 00
6 Lifting Operations 00
Man-hours Total
13,128 13,128
PAGE 18 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
GROUND FLOOR
SECTIONAL
DETAILS FOR
14 134P P 15 1 20‐04‐21 Pending
OPENINGS IN
WALL
LIGHTING
15 135E LAYOUT FOR E 1 5 20‐04‐21 Pending
SECOND FLOOR
UPS LIGHTING
16 136E LAYOUT FOR E 1 5 20‐04‐21 Pending
SECOND FLOOR
SECTIONAL
DETAILS FOR
17 137W P 17 1 20‐04‐21 21‐4‐21 Approved
OPENINGS IN
WALL
SECTIONAL
DETAILS FOR
18 138H H 16 1 20‐04‐21 21‐4‐21 Approved
OPENINGS IN
WAL
HVAC STANDARD
19 139H H 0 2 20‐04‐21 21‐4‐21 Approved
DETAILS
Emergency
20 140E Lighting Layout E 1 5 26‐04‐21 Pending
for Second Floor
WC Location
21 141P Change For P 0 1 27‐04‐21 Pending
Second Floor
Lighting Layout
22 142E E 1 5 28‐04‐21 Pending
for First Floor
Emergency
23 143E Lighting Layout E 1 5 28‐04‐21 Pending
for First Floor
UPS Lighting
24 144E Layout for First E 1 5 28‐04‐21 Pending
Floor
PAGE 20 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
PAGE 21 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
PAGE 22 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
PAGE 23 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
PAGE 24 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
PAGE 25 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
PAGE 26 OF 27
ESTABLISHMENT OF TERTIARY CARE HOSPITAL,
NISHTAR-II MULTAN
PAGE 27 OF 27