Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 9

PT.

GLOBAL TWIN STAR Phone 5399032 )021( :


Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero APD Medal PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Engineer
ADDRESS : PERSON INCHARGE : Dwi Apriyanto
PAGE : 1 of 5
PHONE/FAX : DATE : 14 Maret. - 17 Maret. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

14 Maret 2018 06 00 Mobilisasi dari jakarta ke Medan Ok


15:00

15 Maret 2018 08.00 coba Alat Actas BTT dan Epos MC 3 Ok


17:00

16 Maret 2018 08.00 Mencoba Alat Ke GI Pancing Ok


17:00

17 Maret 2018 08.00 Mobilisasi dari Medan Ke jakartar Ok


17:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

DWI APRIYANTO ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero APD Medal PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Engineer
ADDRESS : PERSON INCHARGE : M. Idris Kurniawan
PAGE : 1 of 5
PHONE/FAX : DATE : 30 Jan. - 2 Feb. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

30 January 2018 06 00 Mobilisasi dari jakarta ke Medan Ok


15:00

31 January 2018 08.00 coba Alat Actas BTT dan Epos MC 3 Ok


17:00

1 February 2018 08.00 Mencoba Alat Ke GI Kualanamu Medan Ok


17:00

2 February 2018 08.00 Trouble Shoting Alat Actas BTT dan Epos MC3 Ok
17:00 Mobilisasi dari Medan Ke jakartar

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

M. Idris Kurniawan ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero APD Medan PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Engineer
ADDRESS : PERSON INCHARGE : Alfiyansyah
PAGE : 1 of 5
PHONE/FAX : DATE : 30 Jan. - 2 Feb. 2018
14 Maret. - 17 Maret. 2018
SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

30 January 2018 06 00 Mobilisasi dari jakarta ke Medan Ok


15:00

31 January 2018 08.00 coba Alat Actas BTT dan Epos MC 3 Ok


17:00

1 February 2018 08.00 Mencoba Alat Ke GI Kualanamu Medan Ok


17:00

2 February 2018 08.00 Trouble Shoting Alat Actas BTT dan Epos MC3 Ok
17:00 Mobilisasi dari Medan Ke jakartar

14 Maret 2018 06 00 Mobilisasi dari jakarta ke Medan Ok


15:00

15 Maret 2018 08.00 coba Alat Actas BTT dan Epos MC 3 Ok


17:00

16 Maret 2018 08.00 Mencoba Alat Ke GI Pancing Ok


17:00

17 Maret 2018 08.00 Mobilisasi dari Medan Ke jakartar Ok


17:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

ALFIYANSYAH ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero P2B Gandul PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Teknisi
ADDRESS : PERSON INCHARGE : Jana Mudin
PAGE : 1 of 5
PHONE/FAX : DATE : 22 Feb. - 23 DFeb. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

22 February 2018 12 00 Mobilisasi dari jakarta ke Cianjur Ok


19:00

23 February 2018 08.00 Pengantian Fiber Optic ( FO ) Ok


17:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

Jana Mudin ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero P2B Gandul PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Pengawas K3
ADDRESS : PERSON INCHARGE : Alfiyansyah
PAGE : 1 of 5
PHONE/FAX : DATE : 22 Feb. - 23 DFeb. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

22 February 2018 12 00 Mobilisasi dari jakarta ke Cianjur Ok


19:00

23 February 2018 08.00 Pengantian Fiber Optic ( FO ) Ok


17:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

ALFIYANSYAH ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero P2B Gandul PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Pengawas Pekerjaan
ADDRESS : PERSON INCHARGE : Jana Mudin
PAGE : 1 of 5
PHONE/FAX : DATE : 4 Feb. - 10 DFeb. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

04 February 2018 12 00 Mobilisasi dari jakarta ke Cirebon Ok


19:00

05 February 2018 08.00 Pembuatan Working Permit Di APP Cirebon, Dan Ok


17:00 perjalanan menuju PLTU

06 February 2018 08.00 Penarikan Kabel CT dan VT Ok


17:00

07 February 2018 08.00 Finishing Panel Wams persiapan untuk tapping CT dan VT Ok
17:00

08 February 2018 08.00 Pemadaman Tapping CT Dan VT Ok


18:00

09 February 2018 08.00 Finishing dan pengangkutan material dari Gardu Induk
18:00

10 February 2018 08.00 Demobilisasi menuju jakarta

18:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

Jana Mudin ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero P2B Gandul PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Pengawas Pekerjaan
ADDRESS : PERSON INCHARGE : Jana Mudin
PAGE : 1 of 5
PHONE/FAX : DATE : 10 Jan . - 21 Jan. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

10 January 2018 12 00 Mobilisasi dari jakarta ke Cirebon Ok


19:00

11 January 2018 08.00 Pembuatan Working Permit Di APP Cirebon, Dan Ok


17:00 perjalanan menuju PLTU

12 January 2018 08.00 Penarikan Kabel CT dan VT Ok


17:00

13 January 2018 08.00 Finishing Panel Wams persiapan untuk tapping CT dan VT Ok
17:00

14 January 2018 08.00 Pemadaman Tapping CT Dan VT Ok


18:00

15 January 2018 08.00 Demobilisasi menuju jakarta


18:00

16 January 2018 08.00 Mobilisasi dari jakarta ke Pacitan

18:00

17 January 2018 08.00 Penarikan Kabel CT dan VT, Pemasangan Antena GPS

18:00

18 January 2018 08.00 Finishing Panel Wams persiapan untuk tapping CT dan VT

18:00

19 January 2018 08.00 Pemadaman Tapping CT Dan VT

18:00

20 January 2018 08.00 Packing peralatan dan penyerahan berita acara ke GI PLTU Pacitan

18:00

21 January 2018 08.00 Packing peralatan dan penyerahan berita acara ke GI PLTU Pacitan

18:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

Jana Mudin ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero P2B Gandul PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Pengawas K3
ADDRESS : PERSON INCHARGE : Alfiyansyah
PAGE : 1 of 5
PHONE/FAX : DATE : 4 Feb. - 10 DFeb. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

04 February 2018 12 00 Mobilisasi dari jakarta ke Cirebon Ok


19:00

05 February 2018 08.00 Pembuatan Working Permit Di APP Cirebon, Dan Ok


17:00 perjalanan menuju PLTU

06 February 2018 08.00 Penarikan Kabel CT dan VT Ok


17:00

07 February 2018 08.00 Finishing Panel Wams persiapan untuk tapping CT dan VT Ok
17:00

08 February 2018 08.00 Pemadaman Tapping CT Dan VT Ok


18:00

09 February 2018 08.00 Finishing dan pengangkutan material dari Gardu Induk
18:00

10 February 2018 08.00 Demobilisasi menuju jakarta

18:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

ALFIYANSYAH ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation
PT.GLOBAL TWIN STAR Phone 5399032 )021( :
Ruko Union Square No.21 53129050 )021( :
Jl. Boulevard Raya Gading Serpong 53129051 )021(
Tangerang 15810 Fax 5399187 )021( :
Banten-Indonesia

SERVICE REPORT
CUSTOMER : PT PLN Persero P2B Gandul PROJ. ENGINEER : Nelma Loly
END USER : PROJECT NO. :
CONTACT PERSON : ACTION ( * ) : Pengawas K3
ADDRESS : PERSON INCHARGE : Alfiyansyah
PAGE : 1 of 5
PHONE/FAX : DATE : 10 Jan . - 21 Jan. 2018

SPARE PART(S)/MATERIAL
ITEM QUANTITY DESCRIPTIONS
Tool boxes 1 set
APD 1 set

TIME
DATE DESCRIPTION OF WORK RESULT/STATUS
FROM UNTIL

10 January 2018 12 00 Mobilisasi dari jakarta ke Cirebon Ok


19:00

11 January 2018 08.00 Pembuatan Working Permit Di APP Cirebon, Dan Ok


17:00 perjalanan menuju PLTU

12 January 2018 08.00 Penarikan Kabel CT dan VT Ok


17:00

13 January 2018 08.00 Finishing Panel Wams persiapan untuk tapping CT dan VT Ok
17:00

14 January 2018 08.00 Pemadaman Tapping CT Dan VT Ok


18:00

15 January 2018 08.00 Demobilisasi menuju jakarta


18:00

16 January 2018 08.00 Mobilisasi dari jakarta ke Pacitan

18:00

17 January 2018 08.00 Penarikan Kabel CT dan VT, Pemasangan Antena GPS

18:00

18 January 2018 08.00 Finishing Panel Wams persiapan untuk tapping CT dan VT

18:00

19 January 2018 08.00 Pemadaman Tapping CT Dan VT

18:00

20 January 2018 08.00 Packing peralatan dan penyerahan berita acara ke GI PLTU Pacitan

18:00

21 January 2018 08.00 Packing peralatan dan penyerahan berita acara ke GI PLTU Pacitan

18:00

Serv. Eng. Acknowledged by, Clarification above services at our full satisfaction, Customer's Comment:
Authorized Customer's Representative:

ALFIYANSYAH ( ) ( )
(*) C - Commissioning CI - Completion/Installation PM - Preventive Maintenance
TS - Trouble Shooting M - Modification CB - Calibrations
T - Training P - Project E - Expertise
I - Inspection R - Repair A - Adaptation

You might also like