Professional Documents
Culture Documents
Deepwater Subsea Controls, Power, and Chemical Distribution Manufacturing Specification
Deepwater Subsea Controls, Power, and Chemical Distribution Manufacturing Specification
DEP 37.80.02.37-Gen.
February 2011
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global
Solutions International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference
international, regional, national and industry standards.
The objective is to set the recommended standard for good design and engineering practice to be applied by Shell
companies in oil and gas production, oil refining, gas handling, gasification, chemical processing, or any other such
facility, and thereby to help achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at
each locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by
these Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part
of a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI
disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any company or
person whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination
of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell
Company. The benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies
affiliated to these companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and
the DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be
returned after use, including any copies which shall only be made by users with the express prior written consent of
Shell GSI. The copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe
custody and Shell GSI may at any time require information satisfactory to them in order to ascertain how users
implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
DEP 37.80.02.37-Gen.
February 2011
Page 3
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................4
1.1 SCOPE........................................................................................................................4
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS .........4
1.3 DEFINITIONS .............................................................................................................4
1.4 ABBREVIATIONS .......................................................................................................5
1.5 CROSS-REFERENCES .............................................................................................6
1.6 SUMMARY OF MAIN CHANGES...............................................................................6
1.7 COMMENTS ON THIS DEP .......................................................................................7
1.8 DUAL UNITS...............................................................................................................7
2. SUBSEA DISTRIBUTION LOGIC DESIGN ...............................................................8
2.1 GENERAL DESCRIPTION .........................................................................................8
2.2 DISTRIBUTION LOGIC REQUIREMENTS ................................................................8
2.3 SUBSEA DISTRIBUTION BREAKAWAY PHILOSOPHY ........................................11
2.4 PARKING PHILOSOPHY .........................................................................................12
3. SUBSEA DISTRIBUTION HARDWARE WELDING SPECIFICATION...................15
3.1 GENERAL DESCRIPTION .......................................................................................15
3.2 WELDING AND WELDER QUALIFICATION REQUIREMENTS .............................15
3.3 PRODUCTION WELD TEST REQUIREMENTS ......................................................25
3.4 DOCUMENTATION ..................................................................................................26
4. SUBSEA DISTRIBUTION HARDWARE REQUIREMENTS....................................27
4.1 UTH and MV-UTH.....................................................................................................27
4.2 HDM ..........................................................................................................................33
4.3 EDM ..........................................................................................................................38
4.4 SFL AND ESFL.........................................................................................................43
4.5 HFL ...........................................................................................................................49
4.6 EFL............................................................................................................................55
4.7 UTAJ .........................................................................................................................60
4.8 PF AND IA.................................................................................................................65
4.9 HYDRAULIC COUPLERS ........................................................................................70
4.10 ELECTRICAL CONNECTORS .................................................................................71
4.11 BALL, CHECK, AND BACK PRESSURE VALVES ..................................................71
5. FIGURES ..................................................................................................................72
6. REFERENCES .........................................................................................................73
DEP 37.80.02.37-Gen.
February 2011
Page 4
1. INTRODUCTION
1.1 SCOPE
This new DEP specifies the framework for controls, power, and chemical distribution
equipment. Requirements of the design and manufacture of the following equipment are
included:
a) Subsea distribution logic design
b) Subsea distribution hardware welding
c) Subsea distribution hardware equipment requirements including:
d) Umbilical termination head (UTH) and Medium voltage-umbilical termination head
(MV-UTH)
e) Hydraulic distribution manifold (HDM)
f) Electrical distribution manifold (EDM)
g) Steel flying lead (SFL) and Electrical steel flying lead (ESFL)
h) Hydraulic flying lead (HFL)
i) Electrical flying lead (EFL)
j) Umbilical termination assembly jumper (UTAJ)
k) Parking frame (PF) and Installation aids (IA)
l) Hydraulic couplers
m) Electrical connectors
n) Ball valves and check valves
1.3 DEFINITIONS
1.3.1 General definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier is the party that manufactures or supplies equipment and
services to perform the duties specified by the Contractor.
DEP 37.80.02.37-Gen.
February 2011
Page 5
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
The word shall indicates a requirement.
The word should indicates a recommendation.
1.4 ABBREVIATIONS
CP Cathodic Protection
CSWIP Certified Senior Welding Inspector
CWI Certified Welding Inspector
DAF Dynamic Amplification Factor
EDM Electrical Distribution Manifold
EFL Electrical Flying Lead
ESFL Electrical Steel Flying Lead
FAT Factory Acceptance Test
FITA Field Installed Termination Assembly
GTAW Gas Tungsten Arc Welding
HAZ Heat Affected Zone
HDM Hydraulic Distribution Manifold
HFL Hydraulic Flying Lead
IA Installation Aids
ID Inner Diameter
IQI Image Quality Indicator
LC Logic Cap
MAOP Maximum Allowable Operating Pressure
MBR Minimum Bend Radius
MCS Master Control System
MOC Management of Change
MQC Multi-Quick Connection
MV-UTH Medium Voltage Umbilical Termination Head
NDE Non-Destructive Examination
OD Outer Diameter
PF Parking Frame
PLET Pipeline End Termination
PQR Procedure Qualification Record
ROV Remotely Operated Vehicle
RT Radiology Testing
SCM Subsea Control Module
SCWI Senior Certified Welding Inspector
SF Safety Factor
DEP 37.80.02.37-Gen.
February 2011
Page 6
1.5 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section
number is shown in brackets. Other documents referenced by this DEP are listed in (6).
Additional project specific functional requirements for EDM distribution are as per
the Project Scope of Work.
and tube breakage in tension at lower values than the full tensile strength of the tube. This
will also assist is establishing the sequence of tube breakage. The LP lines shall be the first
to break such that the well will shut-in in a preferred sequence. Methodology shall ensure
the LP lines to vent from both ends of the snagged component to prevent trapped pressure
and ensure bleed down of the LP lines.
Breakaway loads from any direction shall ensure the SFL/ESFL outboard MQC plate will
remain connected to the inboard MQC. This helps ensure bleed off of hydraulic pressure
(from both ends), and protection of the inboard MQC plate and male couplers. After the
breakaway event, the ROV interface to the SFL/ESFL outboard MQC shall be still be
accessible with ROV tooling for subsequent removal.
The SFL/ESFL break away termination heads shall be designed to withstand installation
loads while maintaining breakaway capability once installed.
2.3.1.2 HFL
Each end of the HFL shall be designed to breakaway at or below the maximum breakaway
load. This shall be the standard design for the project. The HFL shall be designed to
breakaway at both ends to ensure that the subsea tree will not experience the maximum
loading condition. If only one end was designed to breakaway, it is feasible for the subsea
tree to still experience loads greater than the allowable maximum.
The LP lines shall be the first to break such that the well will shut-in in a preferred
sequence. Methodology shall ensure the LP lines to vent from both ends of the snagged
component to prevent trapped pressure and ensure bleed down of the LP lines.
The connection between the inboard and outboard MQC plates shall remain intact and
undamaged onto the mated structure in order for hydraulic circuits to vent. After the
breakaway, the ROV interface to the HFL outboard MQC shall be accessible with ROV
tooling for subsequent removal and replacement.
The HFL termination heads shall be design to withstand installation loads while maintaining
breakaway capability once installed.
If it can be shown that the HFL cannot support the maximum allowable snag load due to the
limited strength of components at critical connections, then the breakaway design is not
required. However, the breaking point(s) shall allow all lines to vent.
2.3.1.3 EFL
The EFL shall be designed to breakaway unless analysis can show that the strength of
components at critical connections will fail below the maximum allowable snag load.
• Interventions shall utilize existing parking positions within the immediate area as
the primary parking locations. External PFs can be available for assistance as
needed, but shall generally be viewed as a contingency (except for parking near
the UTA)
• All other subsea assets shall be designed such that for Interventions they do not
require the use of external PFs
• Parking for EFLs connected to the EDM to facilitate EDM recovery
Parking position design shall accommodate the retrieval of subsea assets. Recovering
subsea assets (both subsea hardware and distribution equipment) may require the removal
of distribution components. Parking positions shall be designed to accommodate the
following:
• Recovery of the EDM shall not require an external PF. All electrical parking
positions shall be local to the EDMs position on the UTA mudmat
• Recovery of the HDM and UTH shall require the use of external, temporary PFs to
park the flying leads
• Recovery of the UTAJ(s) shall require the use of the UTAJ deployment/recovery
frame. UTAJs shall not be parked subsea
• Recovery of a subsea tree shall require the flying leads to utilize existing parking
positions on a subsea tree/wellhead adapter base as the primary parking location.
An alternative method is to use an external PF, if a wellhead adapter is not
available
Recovery of other subsea hardware shall require the flying leads to utilize existing parking
positions on a nearby asset as the primary parking location. An alternative method is to
use an external PF
2.4.4.2 UTA
MQC parking positions are not required on the UTA and mudmat in order to reduce the size
and complexity of the assembly. As an alternative, external-PFs may be used to park
SFL/ESFL outboard MQCs at the UTA.
Project specific variables pertinent to this specification shall be listed in the Project Scope
of Work.
Note that for all subsea distribution system equipment Manufacturer/Supplier shall be solely
responsible for providing a complete and operable system in full compliance with all
applicable Government regulations, applicable Principal specifications, and applicable
industry codes and standards.
b. All welders shall be qualified or renewed for each purchase order as detailed in this
paragraph. New or expired welders and weld operators shall be qualified in
accordance with the WPQ requirements of this specification. Previously qualified
welders and weld operators who have performed welding with GTAW, inclusive of the
significant variables, within six months and performed welding according to Principal
approved WPS for appropriate tube size within 12 months (with a documented record)
may renew their WPQ at the start of the CONTRACT work through radiography and
data logging only. All welder qualifications and renewals shall be performed in
advance of production welding.
c. Super duplex filler metal shall be used in all welds, including socket welds. The PRE for
this filler material shall be ≥ 42.5 where/when possible. Filler metal with PRE < 42.5
may be used with written permission by Principal, but the weld shall be required to
pass all testing as per this specification. All production welds shall be performed using
filler wire with PRE ≥ qualification wire PRE value.
d. Socket welding configuration shall meet the requirements of ASME B31.3, Figures
328.5.2A and 328.5.2C. Socket fittings shall be made from super duplex material and
shall have a PRE number ≥ 42.5 where/when possible. Socket fittings with PRE
< 42.5 may be used with written permission by Principal, but the fitting shall be
required to pass all testing as per this specification. Additionally, socket fittings for
super duplex to couplers and for super duplex to other corrosion resistant alloy
materials shall be made from appropriate materials intended for use (e.g., Nitronic 50
and 60 for super duplex to coupler welds etc.). Tubes inserted into sockets for welding
shall not be allowed to completely seat in the bottom of the socket.
e. Manufacturer/Supplier shall endeavour to maintain a minimum distance between welds
in any given tubing run sufficient to allow for inboard coupler “float” in the subsea
hardware.
f. During qualification weld testing, calibrated equipment for measuring the following
variables shall be available at all times:
i. Welding current (amperage)
ii. Arc voltage
iii. Interpass temperatures (digital)
iv. Oxygen and other potential contaminate levels of backing gas (maximum
500ppm oxygen level) which shall be measured with an instrument capable
of measuring in ppm (parts per million) to within an accuracy limit of ± 1ppm
v. Wire feed speed (for automatic welding)
vi. Welding head travel speed (for automatic and manual welding)
vii. Shielding and backing gas flow rate
g. The G-48A Corrosion test is only required to qualify automatic and manual super
duplex to super duplex tube girth weld PQRs and WPQs.
3.2.2 Welding Procedure Specification Requirements
The WPS shall be supplied by Manufacturer/Supplier to Principal. To ensure that the WPS
is documented consistently, Principal requests that the welding process be fully defined in
accordance with ASME Section IX, QW-251 using ASME Form QW-482 for documentation.
All essential variables for welding shall be listed in the ASME Form QW-482, including any
“other” significant variables as defined in this specification, such as pre-weld and/or post-
weld preparation. The WPS shall require qualification to a low and high heat input. Position
is an essential variable of the WPS. The WPS shall clearly specify the cleanliness standard
and the cleanliness procedure for the welds, i.e., pickling and/or passivation. Welds
prepared for the PQR shall be cleaned according to this cleanliness procedure to the visible
standard and the standard maintained throughout the course of production welding. The
residual oxide layer (visible heat tint) shall be removed from each weld pass.
DEP 37.80.02.37-Gen.
February 2011
Page 17
Weld penetration at 0° 2
Weld penetration at 180° 2
Cap Height and Root Protrusion 1 1
NOTES: 1. G48A Corrosion tests for full weld sections shall be tested.
2. Selenium isotopes as source energy may be acceptable with written permission of Principal.
3. All Qualification welds shall be monitored via data logging. Weld travel speed and length, and
weld amperage and voltage values shall be recorded and used to calculate and record heat input
values
Acceptance Criteria No defects or cracks in heat affected zone (HAZ) or weld metal.
If test fails Retest two(2) samples
Definition of retest Two (2) samples from additional qualification welds from the
same welder
If either retest fails Change WPS to correct issue and re-test qualification
3.2.1.4.2 Hardness
Rockwell macro-hardness and Vickers micro-hardness traverses shall be taken generally at
the outer diameter, midwall, and the inner diameter. Three readings shall be taken in the
base metal, each HAZ, and in the weld metal. The hardness criteria and proposed
hardness test plan are shown in the table below:
DEP 37.80.02.37-Gen.
February 2011
Page 20
Cap
Mid
Root
Acceptance The microstructure of the base material, HAZ, and Weld Metal
Criteria shows no deleterious constituents. Total deleterious content
shall not exceed 0.05%
If test fails Retest two samples
Definition of retest Two samples from additional qualification welds from the same
welder
If either retest fails Change WPS to correct issue and re-test qualification
DEP 37.80.02.37-Gen.
February 2011
Page 23
Acceptance Maximum value = 2.29 mm (0.090 in) for all tube sizes
Criteria
If test fails Retest two (2) samples
Definition of retest Two (2) samples from additional qualification welds from the
same welder
If either retest fails Change WPS to correct issue and re-test qualification
DEP 37.80.02.37-Gen.
February 2011
Page 24
Five (5) separate exposures [three (3) straight and two (2) elliptical] are required for each
weld. Sensitivity verification shall be performed at every shift change or at least once per
shift.
A minimum of 50% of the images from each equipment assembly shall be audited by a
Level III NDE Operator. An assembly shall not be released to the next process until
radiography records have been developed and reviewed for compliance with the
specification. All digital images from each assembly shall be burned to CD(s) and issued to
the Principal Inspector at least 7 days before release of the assembly for shipping. All film
images shall be retained by Manufacturer/Supplier for a minimum of 5 years.
3.3.3 Visual Inspection (All Welds)
All welds shall be visually inspected for uniformity and quality.
Socket welds shall have their throat thickness and profile assessed to determine that the
weld throat is of adequate thickness. The throat thickness shall be checked using a fillet
weld gauge (See socket welding configuration in ASME B31.3, Figures 328.5.2A and
328.5.2C).
3.3.4 Data Logging (All Welds)
Manufacturer/Supplier shall provide data logging equipment. All manual girth and socket
production welds shall be monitored via data logging. Per pass segment (arc start to arc
stop) averages of weld travel speed and length, and weld amperage and voltage values
shall be recorded and used to calculate and record heat input values. The data logging
shall be done by Manufacturer/Supplier or by a qualified third party SUB-
Manufacturer/Supplier to be approved in writing by Principal. Heat input for acceptable
welds shall be between 0.5 and 1.5 kjoules/mm (12.82 to 46.15 kjoules/in), or as
established by the PQR. Momentary spikes in individual welding parameters shall not
constitute cause for rejecting a particular weld as long as it can be demonstrated that the
spikes do not drive the average heat input outside of the qualified heat input range.
3.3.5 Outside Agency or Laboratories
Agencies or laboratories performing non-destructive testing on behalf of
Manufacturer/Supplier shall satisfy the minimum requirements of ASTM E543-04, Standard
Practice for Agencies Performing Nondestructive Testing.
3.4 DOCUMENTATION
The Manufacturer/Supplier shall submit the following documentation to Principal as a
minimum:
a) Mill test reports for all components (base material and weld wire)
b) Weld Procedure Specifications (WPSs); Include details of pre-weld and post-weld
preparations, i.e., solvents, ScotchBrite, passivation techniques, etc.
c) Procedure Qualification Records (PQRs)
d) Welder Performance Qualifications (WPQs)
e) Shielding and backing gas certification
f) Register of Qualified Welders (This record shall list the welders who have
successfully completed the requirements of Sections (3.5.3) and (3.5.4). Each
welder shall be given a unique welder identification number)
g) Non-destructive examination procedures and personnel qualifications
h) Non-destructive examination reports (This record shall list the categories of defect
and flaw and note against each rejected weld the type of failure exhibited)
i) Data Log Reports
DEP 37.80.02.37-Gen.
February 2011
Page 27
This section specifies Principal’s minimum requirements for subsea distribution hardware
equipment. If needed, additional requirements shall be included in the Project Scope of
Work. Manufacturer/supplier shall comply with all requirements.
4.2 HDM
Table 12 Summary of HDM Requirements
GENERAL DESCRIPTION The HDM is used to distribute hydraulic power and injection chemicals
from an umbilical to multiple subsea assemblies. The HDM consists of
multiple inboard MQC plates on a frame that is mounted on an
Umbilical Termination Assembly Mudmat (UTA-MM).
SYSTEM REQUIREMENTS
Design Life • All components per Project Scope of Work
Maximum Pressure and • All circuits within component rated to same design pressure
Minimum/Maximum and temperature as per Project Scope of Work
Temperature
Maximum External • All mechanical structures and forms to be sized or designed to
Hydrostatic Pressure/Water be functional without distortion due to external hydrostatic pressure
Depth
• Any tubulars must either withstand hydrostatic head pressures
or vented and pressure balanced with special consideration for
internal corrosion
• Maximum external hydrostatic pressure/water depth as per
Project Scope of Work
Tubing Cleanliness • All hydraulic and chemical tubing circuits SAE AS4059
compliant
Redundancy/Reliability • See (2), Subsea Distribution Logic Design
Load Capability (Design Forces)
Minimum Installation • Assembly weight x 1.3 (DAF) x 1.25 (SF)
Initiation / Abandonment /
Recovery Load Through
Single Point Lift Padeye
Minimum Sustain Residual • NA
Umbilical Tension Load
Minimum ROV Impact Load • 0.45 t (1 kip) from any direction
Lifting Padeyes Design • Manufacturer/Supplier to submit internal lifting and hoisting
specifications Principal’s review and approval
• Allows for ROV hooks and shackles
Minimum Handling Load • Assembly weight x 1.3 (DAF) x 1.25 (SF)
through Handling Padeyes
Envelope (Maximum • Per Project Scope of Work
Dimensions)
DEP 37.80.02.37-Gen.
February 2011
Page 34
Stab and/or Hinge Over a) Stab to provide alignment of structure during engagement
Design
b) Manufacturer/Supplier’s manufacturing process to ensure
standard stabs and funnels are interchangeable. Testing includes fit
with master receptacle or stab to verify interchangeability
c) Stab design to allow for unconstrained vertical movement to
allow for vessel heave motion during installation mating and
alignment operations (i.e., stab not to engage in keyway in
receiving funnel preventing free rise and fall of stab prior to full
engagement and umbilical layaway)Stab to have an alignment
method to fix orientation of assembly once installed on mudmat
d) ROV operated latch mechanism used to secure frame to
mudmat
e) Stab to allow for up to ±30° pitch, roll, and yaw misalignment of
assembly during installation
f) Stab design to allow for installation and retrieval of assembly
on an 8° seabed slope of mudmat
g) Stab weight maximized to react against potential residual
torsion in umbilical and/or allow proper mating with funnel and CP
points
MQC Positions • Minimum 2.4 m (8 ft) off seafloor; MQC plates mounted for
horizontal stab/installation. Position of MQC plates considers field
layout for direction of flying leads to prevent/minimize lead
crossings
Electrical/Fibre Optic • NA
Connector Positions
Hydraulic Couplers a) Male type poppetted and unpoppetted
b) Unpoppetted: Methanol and Annulus Vent, unless otherwise
stated in Project Scope of Work
c) No ventingcouplers used unless specifically approved by
Principal
d) Poppetted: All other lines, unless stated in Project Scope of
Work
e) Maximize coupler float to allow for variances in manufacturing
tolerances and aid in outboard MQC installations
Electrical Bulkhead • NA
Connectors/Connectors
Transportability • If transported by road, structure size and configuration allows
shipment without special permits, considering all local and/or
international transportation restrictions
Interconnection Piping • Welded construction. See (3), Subsea Distribution Hardware
Welding. Socket welding allowed only on outboard MQC logic caps
and pressure caps
• Tubing secured to eliminate damage caused by vibration while
allowing coupler float in MQC plate. Tubing clamp material either
compatible with tubing material (i.e., shall not be dissimilar metals)
or have non-metallic components (i.e., liner) in contact with tubing
DEP 37.80.02.37-Gen.
February 2011
Page 35
4.3 EDM
Table 13 Summary of EDM Requirements
GENERAL DESCRIPTION The EDM is used to distribute electrical power and communication
signals from an umbilical cable to multiple subsea electronics devices.
The EDM consist of an electrical harness (or multiple harnesses)
mounted on a frame which is generally connected to an UTA-MM or
similar structure and provides connection points for EFL to other
subsea equipment.
SYSTEM REQUIREMENTS
Design Life • All components per Project Scope of Work
Maximum Pressure and • All circuits within component rated to same design temperature
Minimum/Maximum as per Project Scope of Work
Temperature
Maximum External • All mechanical structures and forms to be sized or designed to
Hydrostatic Pressure/Water be functional without distortion due to external hydrostatic pressure
Depth
• Maximum external hydrostatic pressure/water depth as per
Project Scope of Work
Tubing Cleanliness • NA
Redundancy/Reliability • See (2), Subsea Distribution Logic Design
Load Capability (Design Forces)
Minimum Installation • Assembly weight x 1.3 (DAF) x 1.25 (SF)
Initiation / Abandonment /
Recovery Load Through
Single Point Lift Padeye
Minimum Sustain Residual • NA
Umbilical Tension Load
Minimum ROV Impact Load • 0.45 t (1 kip) from any direction
Lifting Padeyes Design • Manufacturer/Supplier to submit internal lifting and hoisting
specifications for Principal’s review and approval
• Allows for ROV hooks and shackles
Minimum Handling Load • Assembly weight x 1.3 (DAF) x 1.25 (SF)
through Handling Padeyes
Envelope (Maximum • Per Project Scope of Work
Dimensions)
DEP 37.80.02.37-Gen.
February 2011
Page 39
Stab and/or Hinge Over a) Stab to provide alignment of structure during engagement
Design
b) Manufacturer/Suppliers manufacturing process to ensure
standard stabs and funnels are interchangeable. Testing includes
fit with master receptacle or stab to verify interchangeability
c) Stab design to allow for unconstrained vertical movement to
allow for vessel heave motion during installation mating and
alignment operations (i.e., stab not to engage in keyway in
receiving funnel preventing free rise and fall of stab prior to full
engagement and umbilical layaway)Stab to have an alignment
method to fix orientation of assembly once installed on mudmat
d) ROV operated latch mechanism used to secure frame to
mudmat
e) Stab to allow for up to ±30°pitch, roll, and yaw misalignment of
assembly during installation
f) Stab design to allow for installation and retrieval of assembly
on an 8° seabed slope of mudmat
g) Stab weight maximized to react against potential residual
torsion in umbilical and/or allow proper mating with funnel and CP
points
MQC Positions • NA
Electrical/Fibre Optic • Minimum 1.5 m (5 ft) off seafloor; position of connectors
Connector Positions consider field layout for direction of flying leads to prevent/minimize
lead crossings
• Fixed harness legs secured to frame so that excess lengths of
hose are protected from snagging during installation and retrieval
operations
• Each flying lead of harness mounted with bulkhead connector
in a vertical position
Hydraulic Couplers • NA
Electrical Bulkhead a) Female type pins
Connectors/Connectors
b) Voltage and amperage requirements per Project Scope of
Work
c) Electrical cables terminated into a dielectric oil-filled vessel and
bulkhead connector assembly.Any oil-filled vessel to include
pressure compensating mechanism allowing internal oil pressure to
adjust to equal external hydrostatic pressure without expelling or
ingesting any fluids.
d) Electrical bulkhead connector arrangement will minimize space
requirements, account for ROV access, flying lead lay direction,
and avoid interference with stab and hinge over operation
e) Equipped with bend stiffeners at connector interface to avoid
damaging electrical cables
f) Electrical connectors make/break under full system power
Transportability • If transported by road, structure size and configuration allows
shipment without special permits, considering all local and/or
international transportation restrictions
Interconnection Piping • NA
DEP 37.80.02.37-Gen.
February 2011
Page 40
Tubing Size/Material/MBR • NA
Minimum Distances • NA
Fitting, Adapter, Valve • NA
Material
Installation / Initiation / • Stab / NA / NA / single point lift
Abandonment / Recovery
Mechanism
Structural Analysis • Structural analysis conducted for assembly to address
following load cases: overboarding and initiation, recovery, ROV
impact, onshore handling, loadout with umbilical.
• Assembly designed such that centre of gravity is balanced
between padeyes
Handling • Assembly includes two (2) point lift provisions without spreader
bar for handling during manufacture, loadout, and overboarding
during installation
INTERFACES
Umbilical • NA
Installation • ROV installable
ROV • ROV grab rails provided to aid ROV operations
• Removable grab rails on structure to avoid damage during pre-
installation activities
• Grab rails included on stab support structure to aid in
orientation during installation
• All ROV interfaces shall be according to API Specification
17H/ISO 13628-8
UTH/MV UTH • NA
HDM • NA
EDM • NA
SFL/ESFL • NA
HFL • NA
EFL • Yes
UTAJs • NA
Parking/Installation Frame • NA
MATERIALS AND FABRICATION
Material Selection • Equipment constructed from materials suitable for marine duty
over lifetime specified in Project Scope of Work. All materials
compatible with fresh water, seawater, CP in presence of seawater,
and fluids listed in Project Scope of Work
Material Tracking • Manufacturer/Supplier to provide tracking details for all
materials
DEP 37.80.02.37-Gen.
February 2011
Page 41
Fasteners and Serrated • 316 stainless steel per ISO 3506-1. Fasteners not connected to
Washers CP system must be Ti 6Al-4V Ru Grade 29 titanium or other
Principal approved self-protecting alloy. Titanium components
electrically isolated from CP system
Coating • Coating designed, qualified, and applied in accordance with
DEP 30.48.00.32- DWP, Painting of Offshore-Pipeline Components
and Marine Equipment
Cathodic Protection a) CP designed, qualified, manufactured and installed in
accordance with DEP 37.81.40.11-EPP, Design of Cathotic
Protection Systems for Deepwater Pipeline Components
b) ROV accessible electrical continuity test points provided to
allow subsea testing of CP system per DEP 37.81.40.11-EPP,
Design of Cathotic Protection Systems for Deepwater Pipeline
Components
c) Anode placement shall not interfere with mating equipment or
create potential snag points for ROV operations
d) Provide CP for all components and ensure CP continuity and
protection over design life per Project Scope of Work
e) CP design considers internal corrosion
TESTING
FAT Minimum a) Document all testing and inspection
Requirements
b) Electrical/anode continuity of all metallic components to
assembly (except Titanium components)
c) ROV shackle and ROV hook fit test performed on installation
padeyes; shackle fit test performed on handling padeyes
d) Verify labelling and marking
e) Verify critical assembly tolerances
f) Weight measurement
g) Interchangeability test for critical assemblies: stab, funnel,
electrical connectors, installation tooling, and subassemblies
h) Centre of gravity verification against calculated values
i) Pull test on padeyes per Manufacturer/Supplier internal lifting
and hoisting specifications
Hydrotest Fluid • NA
Hydrotest • NA
Hydrotest Duration • NA
Hydrotest Acceptance • NA
Criteria
DEP 37.80.02.37-Gen.
February 2011
Page 42
Break Away Design • In order to limit potential umbilical snagging loads, assembly
structure breaks away at a minimum of 50% of load that could
damage subsea tree. This load not to exceed 9 t (20 kips) under
any circumstances. Following solution shall be employed:
o Termination head tubes break away from bracket and
MQC plate in order to minimize potential damage to
mating equipment
o Termination head tubing lengths staggered in length and
configured such that no more than one (1) tube subjected
to breaking loads at any given time
o Termination head tubing configuration and order of
breaking ensures that LP hydraulic tubes fail first and HP
hydraulic tubes fail last enabling orderly shut-in of well
o MQC plate connection of both inboard and outboard MQC
plates remains intact and undamaged onto mated
structure
o Termination head tubing breaks away from bracket at
design breakaway loads but withstand installation loads
Envelope (Maximum • Termination structure envelope (without protective caps) is
Dimensions) ≤ 1.5 m high x 0.6 m wide x 3.7 m long (5 ft high x 2 ft wide x 12 ft
long) including splice box and bend restrictors in order to fit onto
typical installation vessel carousel, vertical lay system, and/or
overboarding chute
Stab and/or Hinge Over • NA
Design
MQC Positions • Minimum 2.4 m (8 ft) off seafloor; MQC plates mounted for
horizontal stab/installation. Position of MQC plates consider field
layout for direction of flying leads to prevent/minimize lead
crossings
Electrical/Fibre Optic • Minimum 1.5 m (5 ft) off seafloor; position of connectors
Connector Positions consider field layout for direction of flying leads to prevent/minimize
lead crossings
• Electrical connectors located at each end of ESFL and
connected to FITA. Cables from umbilical section routed through
ESFL umbilical and ESFL termination head to FITA and connector
Hydraulic Couplers a) Female type poppetted and unpoppetted
b) Unpoppetted: Methanol and Annulus Vent, unless otherwise
stated in Project Scope of Work
c) No ventingcouplers used unless specifically approved by Principal
d) Poppetted: All other lines, unless stated in Project Scope of Work
e) Maximize coupler float to allow for variances in manufacturing
tolerances and aid in outboard MQC installations
DEP 37.80.02.37-Gen.
February 2011
Page 45
Hydrotest Duration • Hold Period = 4 hours. Hold period starts after pressure and
temperature stabilization occur and equipment with pressure-
monitoring device is isolated from pressure source
Hydrotest Acceptance a) Pressure considered stabilized when rate of change is no
Criteria more than 5% of test pressure per hour or 35 bar/hr (500 psi/hr),
whichever is less
b) Temperature considered stabilized when rate of change is less
than 0.5°C/min (1°F/min)
c) Maximum of 2% unexplainable drop over test duration, decay
or increase due to temperature variation is allowable up to 5%.
Chart not trending downward at end of hold period or have signs of
visible leaks
d) Circuit pressure not to drop below required test pressure
e) Test pressure and temperature monitored and charted through
entire test duration
f) Test recording equipment shall have proof of test certification
within one (1) year and must accompany test reports
g) Test conducted indoors in dry area with dry paper underneath
test surface
h) Test fluid purged from non-poppetted tubing with nitrogen
i) Immediately cap couplers and MQC plates
MARKING, PACKAGING, AND STORAGE
Marking • Bulkhead connectors and MQC plates clearly labelled for
identification with legibal markings suitable for the environment and
approved by Principal
• Labels are placed in position where visibility is not obstructed
by components
• Label text distinguishes each item with unique designation
Packaging • All MQC plates covered for shipping with test caps. Test caps
used for shipping include needle valves with plugs
Storage • Equipment stored in covered dry area to ensure:
o No impact/damage from adjacent or overhead operations
o No degradation from excessive exposure to elements or
sunlight
o No iron contamination of tubing
DEP 37.80.02.37-Gen.
February 2011
Page 49
4.5 HFL
Table 15 Summary of HFL Requirements
GENERAL DESCRIPTION The HFL assemblies are typically installed between subsea trees and
manifolds or sleds. HFL assemblies are only approved for use in
water-based hydraulic fluid service downstream of a SCM, typically for
controlling pipeline sled or manifold valves. The HFL consists of a
series of thermoplastic hoses bundled and enclosed within a protective
cover, and two termination assemblies located at each end of the HFL.
SYSTEM REQUIREMENTS
Design Life • All components per Project Scope of Work
Maximum Pressure and • All circuits within component rated to same design pressure
Minimum/Maximum and temperature as per Project Scope of Work
Temperature
Maximum External • All mechanical structures and forms sized or designed to be
Hydrostatic Pressure/Water functional without distortion due to external hydrostatic pressure
Depth
• Any tubulars either to withstand hydrostatic head pressures or
vented and pressure balanced with special consideration for
internal corrosion
• Maximum external hydrostatic pressure/water depth as per
Project Scope of Work
Tubing Cleanliness • All hydraulic and chemical tubing circuits SAE AS4059
compliant
Redundancy/Reliability • See (2), Subsea Distribution Logic Design
Load Capability (Design Forces)
Minimum Installation • 2 x flying lead termination weight x umbilical unit weight (in air
Initiation / Abandonment / with tubes filled) x 1.3 (DAF) x 1.25 (SF)
Recovery Load Through
Single Point Lift Padeye
Minimum Sustainable • NA
Residual Umbilical Tension
Load
Minimum ROV Impact Load • 0.45 t (1 kip) from any direction
Lifting Padeyes Design • Manufacturer/Supplier to submit internal lifting and hoisting
specifications for Principal’s review and approval
• Allows for ROV hooks and shackles
• Attachment points for installation buoyancy modules designed
to withstand required load to offset between 4.5 m (15 ft) and 9 m
(30 ft) off seabed and account for any additional loads during
deployment and installation
• Attachment points for installation clump weight provided and
designed to withstand maximum installation loads
Minimum Handling Load • 2 x flying lead termination weight x umbilical unit weight (in air
through Handling Padeyes with tubes filled) x 1.3 (DAF) x 1.25 (SF)
DEP 37.80.02.37-Gen.
February 2011
Page 50
Break Away Design • In order to limit potential umbilical snagging loads, assembly
structure shall break away at a minimum of 50% of load that could
damage a subsea tree. This load not to exceed 9 t (20 kips) under
any circumstances. Following solution shall be:
o Termination head tubes break away from bracket and
MQC plate in order to minimize potential damage to
mating equipment
o Termination head tubing lengths staggered in length and
configured such that no more than one (1) tube is
subjected to breaking loads at any given time
o Termination head tubing configuration and order of
breaking ensures that LP hydraulic tubes fail first and HP
hydraulic tubes fail last enabling orderly shut-in of well
o MQC plate connection of both inboard and outboard MQC
plates remains intact and undamaged onto mated
structure
o Termination head tubing breaks away from bracket at
design breakaway loads but withstand installation loads
Envelope (Maximum • Per Project Scope of Work
Dimensions)
Stab and/or Hinge Over • NA
Design
MQC Positions • Minimum 2.4 m (8 ft) off seafloor; MQC plates mounted for
horizontal stab/installation. Position of MQC plates consider field
layout for direction of flying leads to prevent/minimize lead
crossings
Electrical/Fibre Optic • NA
Connector Positions
Hydraulic Couplers • Female type poppetted unless otherwise stated in Project
Scope of Work
• Maximize coupler float to allow for variances in manufacturing
tolerances and aid in outboard MQC installation
• No ventingcouplers used unless specifically approved by
Principal
Electrical Bulkhead • NA
Connectors/Connectors
Transportability • If transported by road, structure size and configuration allows
shipment without special permits, considering all local and/or
international transportation restrictions
Interconnection Piping • Welded construction. See (3), Subsea Distribution Hardware
Welding
• Hydraulic hoses and termination head tubing designed from a
suitable, crevice corrosion resistant material such as super duplex
or 316 stainless steel
• Material or welds not subject to cracking in seawater in
presence of CP
• Hose bundle enclosed in a protective sheath to prevent
abrasion or snagging during handling and installation
DEP 37.80.02.37-Gen.
February 2011
Page 51
Check Valves • NA
Tubing Size/Material/MBR • Hose size as per Project Scope of Work
Minimum Distances • 63.5 mm (2.5 in) of straight tubing length between coupler and
tangent of any tubing bends, between welds, between bends and
clamps, and between bends/welds/clamps and any valve
connection
Fitting, Adapter, & Valve a) UNS 2507 super duplex steel
Material
b) Fittings between hoses and tubing on bulkhead plate to be of
bulkhead style for secure fastening to plate
c) A strain relief device to be used at each end of hose bundle to
eliminate tensile strain on hose end fittings
d) Tube fittings to be 316 stainless steel with 37° flare
e) All wetted parts are subject to Principal approval
Length Tolerance/Storage • +2%, -0% / 0.6 m (2 ft) / 0.9 m (3 ft)
MBR/Installation MBR
Installation / Initiation / a) Provide MQC plate installation and handling attachment point
Abandonment / Recovery and/or ROV handle to aid installation, recovery, and manoeuvring
Mechanism operations
b) Include MQC latch visual indicator, visible by ROV without
interference from termination head tubing
c) Allow for ROV and MQC override tooling clearance
requirements
d) Provide installation assistance points for downline and/or
temporary buoyancy modules
e) Provide a single-point lift for recovery or movement of entire
assembly
f) Design allows for either termination head to be connected and
disconnected at a time
Structural Analysis • Structural analysis conducted to address following load cases:
operating condition, overboarding and initiation, recovery, ROV
impact, onshore handling
• Load path for installation or recovery load passes through
assembly, installation/recovery padeye, and abandonment
recovery cable in axis exactly coinciding with centre line of
umbilical
• Termination structural frame and connection plate designed to
withstand loads from unsupported lengths[ 6 m (20 ft) height above
mudline] in installed condition
Handling • Assembly includes lifting provisions for handling during
manufacture, loadout, and overboarding during installation
INTERFACES
Umbilical • NA
Installation • ROV installable
• Design includes buoyancy attachment points designed
oversized to aid in installation
DEP 37.80.02.37-Gen.
February 2011
Page 52
TESTING
FAT Minimum • Assemblies include inboard MQC test plates for flushing,
Requirements continuity testing, pressure testing, and precharging. Plates
available for onshore and offshore for pressure testing and
flushing. Test plates include live couplers, with needle valves with
plugs, and tube fittings for each line
• Hydrotest
• Document all testing and inspection
• Continuity of all hydraulic and/or chemical circuits to ensure
proper routing and marking
• Flowrate verification of all hydraulic and/or chemical circuits for
consistency between lines
• Electrical/anode continuity of all metallic components to
assembly per Project Scope of Work (except Titanium
components)
• ROV shackle and ROV hook fit test performed on installation
padeyes; shackle fit test performed on handling padeyes
• Verify labelling and marking
• Verify critical assembly tolerances
• Fluid cleanliness
• Pull test on padeyes per Manufacturer/Supplier internal lifting
and hoisting specifications
Hydrotest Fluid • Per Project Scope of Work
Hydrotest Pressure • Test pressure = 1.25 x DWP stated Project Scope of Work
Hydrotest Duration • Hold Period = 4 hours. Hold period starts after pressure and
temperature stabilization occur and equipment with pressure-
monitoring device has been isolated from pressure source
Hydrotest Acceptance • Pressure considered stabilized when rate of change is no
Criteria more than 5% of test pressure per hour or 35 bar/hr (500 psi/hr),
whichever is less
• Temperature considered stabilized when rate of change is less
than 0.5°C/min (1°F/min)
• Maximum of 2% unexplainable drop over test duration, decay
or increase due to temperature variation is allowable up to 5%.
Chart shall not be trending downward at end of hold period or have
signs of visible leaks
• Circuit pressure not to drop below required test pressure
• Test pressure and temperature monitored and charted through
entire test duration
• Test recording equipment shall have proof of test certification
within one (1) year and must accompany test reports
Test conducted indoors in dry area and with dry paper underneath test
surface
DEP 37.80.02.37-Gen.
February 2011
Page 54
4.6 EFL
Table 16 Summary of EFL Requirements
GENERAL DESCRIPTION An EFL is used to distribute electrical power and communication
signals from the EDM or UTH to subsea electronic devices located on
subsea tree’s or manifold’s.
SYSTEM REQUIREMENTS
Design Life • All components per Project Scope of Work
Maximum Pressure and • All circuits within component rated to same design
Maximum/Minimum temperature as per Project Scope of Work
Temperature
Maximum External • All mechanical structures and forms to be sized or designed to
Hydrostatic Pressure/Water be functional without distortion due to external hydrostatic pressure
Depth
• Maximum external hydrostatic pressure/water depth as per
Project Scope of Work
• Electrical cables in pressure-balanced oil-filled hoses
• Electrical junctions for multi-leg designs in an oil-filled vessel.
Oil-filled vessel includes a pressure compensating mechanism
allowing internal oil pressure to adjust to equal external hydrostatic
pressure without expelling or ingesting any fluids
Tubing Cleanliness • NA
Redundancy/Reliability See (2), Subsea Distribution Logic Design
DEP 37.80.02.37-Gen.
February 2011
Page 56
Envelope (Maximum • NA
Dimensions)
Stab and/or Hinge Over • NA
Design
MQC Positions • NA
Electrical/Fibre Optic • Minimum 1.5 m (5 ft) off seafloor; position of connectors
Connector Positions consider field layout for direction of flying leads to prevent/minimize
lead crossings
Hydraulic Couplers • NA
Electrical Bulkhead a) EDM to Tree – Male to Female type pins
Connectors/Connectors
b) UTH to UTH or Tree – Female to Female type pins
c) Electrical cables terminated into dielectric oil-filled vessel and
bulkhead connector assembly. Any oil-filled vessel to include
pressure compensating mechanism allowing internal oil pressure
to adjust to equal external hydrostatic pressure without expelling or
ingesting any fluids
d) Electrical contact between two (2) electrical connector halves
completed in insulating fluid environment
e) Equipped with bend stiffeners at connector interface to avoid
damaging electrical cables
f) Electrical connectors able to make/break under full system power
g) All electrical cables manufactured of Raychem 44A0221-16-9/9
(16 AWG twisted wire, 1,000 V)
h) Electrical wire to be continuous length between connectors. No
splices used for conductors
i) Dual sealing barriers between seawater and electrical conductors
Transportability • If transported by road, structure size and configuration allows
shipment without special permits, considering all local and/or
international transportation restrictions
Interconnection Piping • NA
Check Valves • NA
Tubing Size/Material/MBR • NA
Minimum Distances • NA
Fitting, Adapter, & Valve • NA
Material
Length Tolerance / Storage • +2% / -0% / 152 mm (6 in) / 305 mm (12 in)
MBR / Installation MBR
Installation / Initiation / • Design allows for either termination head to be connected and
Abandonment / Recovery disconnected at a time
Mechanism
Structural Analysis • NA
Handling • NA
DEP 37.80.02.37-Gen.
February 2011
Page 58
INTERFACES
Umbilical • NA
Installation • ROV installable
ROV • All ROV interfaces in accordance with API Specification
17 H/ISO 13628-8
• Provide installation interface through a ISO 13628-8
Class 4 ROV bucket
UTH/MV UTH • Yes
HDM • NA
EDM • Yes
SFL/ESFL • NA
HFL • NA
EFL • NA
UTAJs • NA
Parking/Installation Frame • Yes
MATERIALS AND FABRICATION
Material Selection • Equipment constructed from materials suitable for marine duty
over lifetime specified. All materials compatible with fresh water,
seawater, CP in presence of seawater, and fluids listed in Project
Scope of Work
Material Tracking • Manufacturer/Supplier provides tracking details for all
materials
Fasteners and Serrated • NA
Washers
Coating • NA
Cathodic Protection • NA
TESTING
FAT Minimum • Document all testing and inspection
Requirements
• Continuity of all electrical circuits to ensure proper routing and
marking
• Verify labelling and marking
• Verify critical assembly tolerances
Hydrotest Fluid • NA
Hydrotest Pressure • NA
Hydrotest Duration • NA
Hydrotest Acceptance • NA
Criteria
DEP 37.80.02.37-Gen.
February 2011
Page 59
4.7 UTAJ
Table 17 Summary of UTAJ Requirements
GENERAL DESCRIPTION The UTAJ is designed to provide a flow path for hydraulic power and
chemical injection from the UTH to the HDM. The number of umbilical
functions to connect determines the number necessary, but typically
two UTAJs are used on each UTH, allowing for redundant hydraulic
and chemical flow paths.
SYSTEM REQUIREMENTS
Design Life • All components per Project Scope of Work
Maximum Pressure and • All circuits within component rated to same design pressure
Minimum / Maximum and temperature as per Project Scope of Work
Temperature
Maximum External • All mechanical structures and forms sized or designed to be
Hydrostatic Pressure/Water functional without distortion due to external hydrostatic pressure
Depth
• Any tubulars to either withstand hydrostatic head pressures or
vented and pressure balanced with special consideration for
internal corrosion
• Maximum external hydrostatic pressure/water depth as per
Project Scope of Work
Tubing Cleanliness • All hydraulic and chemical tubing circuits SAE AS4059
compliant
Redundancy/Reliability • See (2), Subsea Distribution Logic Design
Load Capability (Design Forces)
Minimum Installation • Consider weight of assembly
Initiation / Abandonment /
Recovery Load Through
Single Point Lift Padeye
Minimum Sustainable • NA
Residual Umbilical Tension
Load
Minimum ROV Impact Load • 0.45 t (1 kip) from any direction
Lifting Padeyes Design • Manufacturer/Supplier to submit internal lifting and hoisting
specifications for Principal’s review and approval
• Allows for ROV hooks and shackles
• Attachment points for installation buoyancy modules designed
to withstand required load to offset between 4.5 m (15 ft) and 9 m
(30 ft) off seabed and account for any additional loads during
deployment and installation
Minimum Handling Load • Consider weight of assembly
though Handling Padeye
Break Away Design • NA
Envelope (Maximum • NA
Dimensions)
Stab and/or Hinge Over • NA
Design
DEP 37.80.02.37-Gen.
February 2011
Page 61
MQC Positions • Minimum 2.4 m (8 ft) off seafloor; MQC plates mounted for
horizontal stab/installation. Position of MQC plates consider field
layout for direction of flying leads to prevent/minimize lead
crossings
Electrical/Fibre Optic • NA
Connector Positions
Hydraulic Couplers a) Female type poppetted and unpoppetted
b) Unpoppetted: Methanol and Annulus Vent, unless otherwise
stated in Project Scope of Work.
c) No ventingcouplers used unless specifically approved by
Principal
d) Poppetted: All other lines, unless stated in Project Scope of
Work
e) Maximize coupler float to allow for variances in manufacturing
tolerances and aid in outboard MQC installations
Electrical Bulkhead • NA
Connectors/Connectors
Transportability • If transported by road, structure size and configuration allows
shipment without special permits, considering all local and/or
international transportation restrictions
Interconnection Piping • Welded construction. See (3), Subsea Distribution Hardware
Welding
• Tubing secured to eliminate damage caused by vibration while
allowing coupler float in MQC plate. Tubing clamp material either
compatible with tubing material (i.e., shall not be dissimilar metals)
or have non-metallic components (i.e., liner) in contact with tubing
Check Valves • NA
Tubing Size/Material/MBR • 690 bar (10 ksi) system: 16 mm OD x 12.7 mm ID (0.625 in
OD x 0.500 in ID) / UNS 2507 super duplex steel/63.5 mm (2.5 in)
• 1034 bar (15 ksi) system: 17.6 mm OD x 12.7 mm ID (0.694 in
OD x 0.500 in ID) / UNS 2507 super duplex steel/63.5 mm (2.5 in)
Minimum Distances • 63.5 mm (2.5 in) of straight tubing length between coupler and
tangent of any tubing bends, between welds, between bends and
clamps, and between bends/welds/clamps and any valve
connection
Fitting, Adapter, & Valve • UNS 2507 super duplex steel
Material
• All wetted parts are subject to Principal approval
Length Tolerance/Storage • NA
MBR/Installation MBR
DEP 37.80.02.37-Gen.
February 2011
Page 62
Installation / Initiation / a) Provide MQC plate installation and handling attachment point
Abandonment / Recovery and/or ROV handle to aid installation, recovery, and manoeuvring
Mechanism operations
b) Include MQC latch visual indicator, visible by ROV without
interference from termination head tubing
c) Allow for ROV and MQC override tooling clearance
requirements
d) Provide installation assistance points for downline and/or
temporary buoyancy modules
e) Provide a single-point lift for recovery or movement of entire
assembly
f) Allow for either termination head to be connected and
disconnected at a time
g) Jumper tubing shaped in a manner to increase structural
flexibility such that ROV may install jumper without special tooling
Structural Analysis • Structural analysis conducted to address following load cases:
operating condition, overboarding, recovery, ROV impact, onshore
handling
Handling • Assembly includes lifting provisions for handling during
manufacture, loadout, and overboarding during installation
INTERFACES
Umbilical • NA
Installation • ROV installable
• Design includes buoyancy attachment points designed
oversized to aid in installation
ROV • All ROV interfaces accordance with API Specification
17H/ISO 13628-8
• Provide installation interface through ISO 13628-8 Class 4
ROV bucket
UTH/MV UTH • Yes
HDM • Yes
EDM • NA
SFL/ESFL • NA
HFL • NA
EFL • NA
UTAJs • NA
Parking/Installation Frame • Yes
MATERIALS AND FABRICATION
Material Selection • Equipment constructed from materials suitable for marine duty
over lifetime specified. All materials compatible with fresh water,
seawater, CP in presence of seawater, and fluids listed in Project
Scope of Work
Material Tracking • Manufacturer/Supplier provides tracking details for all
materials
DEP 37.80.02.37-Gen.
February 2011
Page 63
Fasteners and Serrated • 316 stainless steel per ISO 3506-1. Fasteners not connected
Washers to CP system must be Ti 6Al-4V Ru Grade 29 titanium or other
Principal approved self-protecting alloy. Titanium components
electrically isolated from CP system
Coating • Coating designed, qualified, and applied in accordance with
DEP 30.48.00.32-DWP, Painting of Offshore-Pipeline Components
and Marine Equipment
Cathodic Protection • CP designed, qualified, manufactured and installed in
accordance with DEP 37.81.40.11-EPP, Design of Cathotic
Protection Systems for Deepwater Pipeline Components
• Provide CP for all components and ensure CP continuity and
protection over design life per Project Scope of Work
TESTING
FAT Minimum a) Assemblies include inboard MQC test plates for flushing,
Requirements continuity testing, pressure testing, and precharging. Plates
available for onshore and offshore for pressure testing and
flushing. Test plates include live couplers, with needle valves with
plugs, and tube fittings for each line
b) Hydrotest
c) Document all testing and inspection
d) Continuity of all hydraulic and/or chemical circuits to ensure
proper routing and marking
e) Flowrate verification of all hydraulic and/or chemical circuits for
consistency between lines
f) Electrical/anode continuity of all metallic components to
assembly (except Titanium components)
g) ROV shackle and ROV hook fit test performed on installation
padeyes; shackle fit test performed on handling padeyes
h) Verify labelling and marking
i) Verify critical assembly tolerances
j) Fluid cleanliness
k) Pull test on padeyes per Manufacturer/Supplier internal lifting
and hoisting specifications
Hydrotest Fluid • Per Project Scope of Work
Hydrotest Pressure • Test pressure = 1.25 x DWP stated in Project Scope of Work
Hydrotest Duration • Hold Period = 1 hour. Hold period starts after pressure and
temperature stabilization occurs and equipment with pressure-
monitoring device has been isolated from pressure source
DEP 37.80.02.37-Gen.
February 2011
Page 64
4.8 PF AND IA
Table 18 Summary of PF and IA Requirements
GENERAL DESCRIPTION A PF is primarily used for temporary storage of flying lead termination
heads, such as an EFL or SFL, during an intervention or installation
program. PFs may have additional uses during commissioning and
testing activities but require MQC or electrical connectors to be
configured for the intended purpose.
The distribution hardware IA, including UTAJ installation frame buoys,
clump weights, and rigging are equipment necessary for the
installation of UTAJs and flying leads.
SYSTEM REQUIREMENTS
Design Life • All components per Project Scope of Work
Maximum Pressure and • All circuits within component rated to same design pressure
Minimum/Maximum and temperature as per Project Scope of Work
Temperature
Maximum External • All mechanical structures and forms sized or designed to be
Hydrostatic Pressure/Water functional without distortion due to external hydrostatic pressure
Depth
• Any tubulars to either withstand hydrostatic head pressures or
vented and pressure balanced with special consideration for
internal corrosion
• Maximum external hydrostatic pressure/water depth as per
Project Scope of Work
Tubing Cleanliness • All hydraulic and chemical tubing circuits SAE AS4059
compliant
Redundancy/Reliability • See (2), Subsea Distribution Logic Design
Load Capability (Design Forces)
Minimum Installation • Assembly weight x 1.3 (DAF) x 1.25 (SF)
Initiation / Abandonment /
Recovery Load Through
Single Point Lift Padeye
Minimum Sustainable • NA
Residual Umbilical Tension
Load
Minimum ROV Impact Load • 0.45 t (1 kip) from any direction
Lifting Padeyes Design • Manufacturer/Supplier to submit internal lifting and hoisting
specifications for Principal’s review and approval
• Allows for ROV hooks and shackles
Minimum Handling Load • Assembly weight x 1.3 (DAF) x 1.25 (SF)
through Handling Padeyes
Envelope (Maximum • Designed to overall dimensions allowing for ground
Dimensions) transportation from fabrication facility to final destination
Stab and/or Hinge Over • NA
Design
DEP 37.80.02.37-Gen.
February 2011
Page 66
MQC Positions • Minimum 2.4 m (8 ft) off seafloor; MQC plates mounted for
horizontal stab/installation. Position of MQC plates consider field
layout for direction of flying leads to prevent/minimize lead
crossings
• PF to provide a minimum of four (4) MQC parking positions
• UTAJ deployment frame designed for installation of two (2)
UTAJ assemblies on frame at the same time
Electrical/Fibre Optic • Minimum 1.5 m (5 ft) off seafloor; position of connectors
Connector Positions consider field layout for direction of flying leads to prevent/minimize
lead crossings
• PF provide minimum of four (4) EFL parking positions
Hydraulic Couplers a) Female type poppetted and unpoppetted
b) Unpoppetted: Methanol and Annulus Vent, unless otherwise
stated in Project Scope of Work.
c) No ventingcouplers used unless specifically approved by Principal
d) Poppetted: All other lines, unless stated in Project Scope of Work
e) Maximize coupler float to allow for variances in manufacturing
tolerances and aid in outboard MQC installations
Electrical Bulkhead • NA
Connectors/Connectors
Transportability • If transported by road, structure size and configuration allows
shipment without special permits, considering all local and/or
international transportation restrictions
Interconnection Piping • Welded construction. See (3), Subsea Distribution Hardware
Welding. Socket welding allowed only on outboard MQC logic
caps and pressure caps
Tubing Size/Material/MBR • 690 bar (10 ksi) system: 16 mm OD x 12.7 mm ID (0.625 in
OD x 0.500 in ID) / UNS 2507 super duplex steel/63.5 mm (2.5 in)
• 1034 bar (15 ksi) system: 17.6 mm OD x 12.7 mm ID (0.694 in
OD x 0.500 in ID) / UNS 2507 super duplex steel/63.5 mm (2.5 in)
Minimum Distances • 63.5 mm (2.5 in) of straight tubing length between coupler and
tangent of any tubing bends, between welds, between bends and
clamps, and between bends/welds/clamps and any valve
connection
Fitting, Adapter, & Valve • UNS 2507 super duplex steel
Material
• All wetted parts are subject to Principal approval
DEP 37.80.02.37-Gen.
February 2011
Page 67
INTERFACES
Umbilical • NA
Installation • ROV installable
ROV • ROV grab rails shall be provided to aid ROV operations
• Grab rails on structure shall be removable to avoid damage
during pre-installation activities
• All ROV interfaces shall be according to Project Specifications
(API Specification 17H/ISO 13628-8)
UTH/MV UTH • NA
HDM • NA
EDM • NA
SFL/ESFL • Yes
HFL • Yes
EFL • Yes
UTAJs • Yes
Parking/Installation Frame • NA
MATERIALS AND FABRICATION
Material Selection • Equipment constructed from materials suitable for marine duty
over lifetime specified. All materials compatible with fresh water,
seawater, CP in presence of seawater, and fluids listed in Project
Scope of Work
Material Tracking • Manufacturer/Supplier provides tracking details for all
materials
Fasteners and Serrated • 316 stainless steel per ISO 3506-1. Fasteners not connected
Washers to CP system must be Ti 6Al-4V Ru Grade 29 titanium or other
Principal approved self-protecting alloy. Titanium components shall
be electrically isolated from CP system
Coating • Coating designed, qualified, and applied in accordance with
DEP 30.48.00.32-DWP, Painting of Offshore-Pipeline Components
and Marine Equipment
Cathodic Protection • CP designed, qualified, manufactured and installed in accordance
with DEP 37.81.40.11-EPP, Design of Cathotic Protection Systems
for Deepwater Pipeline Components
• ROV accessible electrical continuity test points provided to allow
subsea testing of CP system per DEP 37.81.40.11-EPP, Design of
Cathotic Protection Systems for Deepwater Pipeline Components
• Provide CP for all components and ensure CP continuity and
protection over design life per Project Scope of Work
• CP design considers internal corrosion
DEP 37.80.02.37-Gen.
February 2011
Page 69
TESTING
FAT Minimum a) Document all testing and inspection
Requirements
b) Hydrotest
c) Continuity of all hydraulic and/or chemical circuits to ensure
proper routing and marking
d) Flowrate verification of all hydraulic and/or chemical circuits for
consistency between lines
e) Electrical/anode continuity of all metallic components to
assembly (except Titanium components)
f) ROV shackle and ROV hook fit test performed on installation
padeyes; shackle fit test performed on handling padeyes
g) Verify labelling and marking
h) Verify critical assembly tolerances
i) Weight measurement
j) Interchangeability test for critical assemblies: electrical
connectors, MQC plates, installation tooling, and subassemblies
k) Fluid cleanliness
l) Centre of gravity verification against calculated values
m) Pull test on padeyes per Manufacturer/Supplier internal lifting
and hoisting specifications
Hydrotest Fluid • Per Project Scope of Work
Hydrotest • Test pressure = 1.25 x DWP in Project Scope of Work
Hydrotest Duration • Hold Period = 1 hour. Hold period starts after pressure and
temperature stabilization occur and equipment with pressure-
monitoring device is isolated from pressure source
DEP 37.80.02.37-Gen.
February 2011
Page 70
4.9.1 Design
All designs shall be submitted to Principal for approval.
4.9.2 Vendors
• The approved vendors list for hydraulic couplers are as per the Project Scope of
Work.
DEP 37.80.02.37-Gen.
February 2011
Page 71
4.10.1 Design
All designs shall be submitted to Principal for approval.
4.10.2 Vendors
• The approved vendors list for electrical connectors are as per the Project Scope of
Work.
4.11.1 Design
All designs shall be submitted to Principal for approval.
4.11.2 Vendors
The approved vendors list for valves are as per the Project Scope of Work.
DEP 37.80.02.37-Gen.
February 2011
Page 72
5. FIGURES
6. REFERENCES
SHELL STANDARDS
Issued by:
American Society for Testing and Materials
100 Barr Harbor Drive
West Conshohocken, PA 19428-2959
USA
Aerospace Fluid Power - Cleanliness Classification for Hydraulic SAE AS4059
Fluids
Issued by:
SAE World Headquarters
400 Commonwealth Drive
Warrendale, PA 15096-0001
USA
BRITISH STANDARDS
Power Cables and Auxiliary Cables 600/1000 V BS 5467
Issued by:
British Standards Institution
389 Chiswick High Road
London
W4 4AL
United Kingdom
INTERNATIONAL STANDARDS
Mechanical Properties of Corrosion-resistant Stainless-steel ISO 3506-1
Fasteners -- Part 1: Bolts, Screws, and Studs
Petroleum and natural gas industries - Design and operation of ISO 13628-8
subsea production systems - Part 8: ROV interfaces on subsea
production systems
Issued by:
International Organization for Standardization
1, ch. de la Voie-Creuse,
Chase postale 56
CH-1211 Geneva 20
Switzerland