Professional Documents
Culture Documents
Offshore Construction Specification For Deepwater Pipelines, Flowlines and Risers
Offshore Construction Specification For Deepwater Pipelines, Flowlines and Risers
DEP 37.81.41.33-Gen.
September 2011
(Amendment A01 has been incorporated – September 2012)
ECCN EAR99
This document contains information that is classified as EAR99 and, as a consequence, can neither be exported nor re-exported to any country which is under an
embargo of the U.S. government pursuant to Part 746 of the Export Administration Regulations (15 C.F R. Part 746) nor can be made available to any national of such
country. In addition, the information in this document cannot be exported nor re-exported to an end-user or for an end-use that is prohibited by Part 744 of the Export
Administration Regulations (15 C.F.R. Part 744).
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 2
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions
International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international,
regional, national and industry standards.
The objective is to set the recommended standard for good design and engineering practice to be applied by Shell
companies in oil and gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility,
and thereby to help achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each
locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own respons bility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by these
Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part of
a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims
any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person
whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs
or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The
benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these
companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the
DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned after
use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The
copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell
GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 3
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................ 5
1.1 SCOPE........................................................................................................................ 5
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS ......... 5
1.3 DEFINITIONS ............................................................................................................. 5
1.4 CROSS-REFERENCES ............................................................................................. 6
1.5 SUMMARY OF MAIN CHANGES ............................................................................... 6
1.6 COMMENTS ON THIS DEP ....................................................................................... 7
1.7 DUAL UNITS ............................................................................................................... 7
2. GENERAL................................................................................................................... 8
2.1 REVIEW OF PROJECT PLANS, PROCEDURES AND CALCULATIONS ................ 8
2.2 PROGRESS MEETINGS AND REPORTS................................................................. 8
2.3 ACCESS AND AUTHORITY ....................................................................................... 8
2.4 OFFICE, FACILITIES AND ACCOMMODATIONS..................................................... 9
2.5 CHANGE CONTROL .................................................................................................. 9
2.6 MARINE VESSEL AUDITS AND COMPLIANCE ....................................................... 9
3. ONSHORE FABRICATION AND HANDLING OF MATERIALS AND LOAD-
OUT........................................................................................................................... 10
3.1 ONSHORE FABRICATION OF PIPE AND RELATED APPURTENANCES ............ 10
3.2 LOAD-OUT AND OFFSHORE SUPPLY .................................................................. 10
3.3 RETURN OF MATERIALS........................................................................................ 10
4. PIPELINE CONSTRUCTION.................................................................................... 11
4.1 ATMOSPHERIC WELDING AND NDE .................................................................... 11
4.2 FIELD JOINT COATING ........................................................................................... 11
4.3 CATHODIC PROTECTION SYSTEMS .................................................................... 11
4.4 MARINE PAINTING .................................................................................................. 11
4.5 ALLOWABLE STRESSES AND STRAINS DURING CONSTRUCTION ................. 11
4.6 INSTALLATION ENGINEERING .............................................................................. 12
4.7 INSTALLATION MANUAL AND PROCEDURES ..................................................... 12
4.8 PIPELAY MONITORING........................................................................................... 14
4.9 PRE-MOBILIZATION TESTS ................................................................................... 15
4.10 REELED FLOWLINES AND PIPELINES ................................................................. 18
4.11 BOLTED CONNECTIONS ........................................................................................ 19
4.12 PULL-TUBE RISER INSTALLATION ....................................................................... 20
4.13 CONVENTIONAL RISER INSTALLATION ............................................................... 20
4.14 INITIATION FROM EXITING PLATFORMS ............................................................. 21
4.15 INSTALLATION OF DEEPWATER RISERS ............................................................ 21
4.16 FLEXIBLE PIPE INSTALLATION ............................................................................. 23
4.17 PIPE-IN-PIPE INSTALLATION ................................................................................. 23
4.18 ELECTRICALLY HEATED PIPE............................................................................... 23
4.19 FLOWLINE SLED (PLET) INSTALLATION .............................................................. 23
4.20 UTILITY AND PIPELINE CROSSINGS .................................................................... 24
4.21 TRENCHING ............................................................................................................. 24
4.22 ANCHORING OPERATIONS ................................................................................... 25
4.23 SURVEY AND POSITIONING .................................................................................. 25
4.24 REMOTE COMMUNICATIONS WITH PLATFORMS............................................... 25
4.25 LIFTS AND LOWERING OF EQUIPMENT .............................................................. 26
4.26 MINIMUM REQUIREMENTS FOR HSSE ................................................................ 26
4.27 DEMOBILIZATION .................................................................................................... 26
5. SUBSEA HOT-TAP CONNECTIONS ...................................................................... 26
6. HYDROSTATIC PRESSURE TESTING AND PRE-COMMISSIONING .................. 26
7. MINIMUM REQUIREMENTS FOR REMOTE OPERATED VEHICLE (ROV)
OPERATIONS .......................................................................................................... 26
8. MINIMUM REQUIREMENTS FOR DIVING OPERATIONS ..................................... 27
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 4
1. INTRODUCTION
1.1 SCOPE
This new DEP specifies offshore construction of deepwater pipelines, flowlines and risers,
and related hardware and appurtenances, including but not limited to pipeline end
manifolds PLETs (pipeline end termination) (sleds), in-line sleds, jumpers, and spool
pieces. “Deep Water” is generally defined as water depth in which diver access is not
possible or impractical. For general purposes this depth is approximately 300 m (985 ft).
This DEP is intended to cover the complete installation of facilities described in the Scope
of Work. However, the omission of any essential provisions from this document cannot be
construed to relieve the Contractor of any duty or obligation necessary for the complete
installation and testing of the facilities ready for use and operation.
This DEP may be applied to shallow water construction of pipelines, flowlines and risers, if
so specified by the Principal. All requirements of this DEP apply, unless a deviation for
shallow water construction is specifically identified by the Principal. Where appropriate, the
adjective “deepwater” can then be removed from the specific language in the specifications.
This DEP covers the following main topics:
• Offshore Project Management,
• Requirements for installation engineering and installation procedures, and
• Offshore installation activities.
This DEP supersedes the deepwater projects DEP 37.81.41.33-EPP dated February 2010;
see (1.5) regarding the changes.
1.3 DEFINITIONS
1.3.1 General Definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier is the party that manufactures or supplies equipment and
services to perform the duties specified by the Contractor.
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 6
Term Definition
AFC Approved for Construction
ASOG Activity Specific Operation Guidelines
A&R Abandonment and Recovery
DP Dynamic Positioning
ECA Engineering Critical Assessment
FAT Factory Acceptance Testing
FEA Finite Element Analysis
FMEA Failure Mode and Effects Analysis
HSSE Health, Safety, Security and Environmental
MOC Management of Change
NDE Non Destructive Examination
PLET Pipeline End Termination
RAO Response Amplitude Operator
ROV Remotely Operated Vehicle
ROW Right of Way
SCR Steel Catenary Riser
UPS Uninterrupted Power Supply
VIV Vortex Induced Vibration
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section
number is shown in brackets ( ). Other documents referenced by this DEP are listed in (11).
Comments on this DEP may be submitted to the Administrator using the DEP Feedback
Form by:
• Entering comments directly in the DEP Feedback System on the Technical
Standards Portal http://sww.shell.com/standards (mandatory for users with access to
Shell Wide Web);
• Clicking on the DEP Feedback Form button on the DEPs DVD-ROM main page (for
users without access to Shell Wide Web);
• Requesting a copy of the DEP Feedback Form from the Administrator at
standards@shell.com (for users without access to Shell Wide Web).
For the last two options, the completed DEP Feedback Form can be attached to an email
and submitted to the Administrator at standards@shell.com. Only feedback that is entered
into the Feedback Form will be considered.
2. GENERAL
All marine construction vessels shall meet the requirements of DEP 35.00.00.10-Gen.
NOTE: Circular September 2012: Added reference to DEM1 DEP 35.00.00.10-Gen.
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 10
4. PIPELINE CONSTRUCTION
A proposal for maximum bending strain in pipe of up to 0.0035 while on the stinger can be
proposed by the Contractor for the Principal’s approval. The Contractor shall include in the
proposal adequate evidence that:
a. There is no significant change in size to “as-welded” defects
b. Residual strains are less than or equal to 0.002
c. Factor of safety against collapse is preserved (no excessive permanent out-of-
roundness)
d. Integrity of the coating system including field joints is maintained
e. Remaining ovality of pipe, as defined in API RP 1111 to be less than 0.5%.
f. Total axial strain (i.e., bending plus tension, including dynamics) at any of the welds
in the pipeline does not exceed 0.5%.
No concrete coated pipe shall be subjected to these higher strains, unless adequate
provisions are made to accommodate such strains.
If the Contractor is responsible for pipe weld engineering critical assessment (ECA), the
Contractor shall conduct the required finite element analysis (FEA) to determine strains in
welds adjacent to buckle arrestors, at transition joints, etc. to determine maximum strains in
such welds, and adjust the allowable weld defect acceptance criteria accordingly.
Guidelines (ASOG) and the AFC Installation Manual shall be provided at least 30 days prior
to the scheduled start of offshore work.
After approval by the Principal of the AFC Installation Manual, each subsequent revision to
the Installation Manual shall require approval of the Principal in writing. The Contractor shall
ensure that the AFC Installation Manual, and each revision thereof has been reviewed and
approved by the vessel captain and project superintendent prior to submittal to the
Principal. One (1) month prior to start of offshore work, the Contractor shall deliver to the
Principal one (1) hard copy and one (1) electronic copy of the AFC Installation Manual, with
current revisions. Prior to going offshore, Contractor shall supply four (4) copies of the AFC
Installation Manual shot down to 5½” x 8”, printed on both sides, and spiral bound. Prior to
going offshore, the Principal should have the most recent revision of the Installation Manual
in the above-mentioned formats. The Installation Manual shall contain at a minimum the
following detailed procedures and analysis:
a. Pipe transportation, transfer, storage, and tallying procedures with format for record.
Contractors who propose the use of semi-submersible vessels shall submit detailed
procedures for positioning cargo vessels alongside the vessel. These procedures
shall be submitted for Principal approval at least 45 days in advance of the start of
any pipe transportation, transfer, storage, and tallying operations.
b. Welding and non-destructive examination procedures. These procedures shall be
completed no later than 60 days prior to the start of mobilization or first construction
welding of pipe (if multiple jointing takes place prior to offshore work). Welder
qualification shall be completed no later than 30 days prior to scheduled start of
mobilization, or first construction welding of pipe whichever comes first. A welding
procedure and NDE procedure summary table shall be submitted four (4) months
prior to start of mobilization or first construction welding of pipe. Procedure
qualification includes successful completion of any reeling or fatigue testing
qualification.
c. Procedures for onshore multiple jointing operations, if part of the Work. These
procedures shall be completed no later than 60 days prior to first construction
welding of pipe.
d. Pipelay analysis results and procedures for pipelay tension control, operation, and
monitoring, and relative sequence of pipe joint welding, pipe joint pay out and vessel
movement. Copies of “computer analysis” for the Principal to review.
e. Installation of vortex induced vibration (VIV) suppression devices, if required (for
example, at the location of anticipated spans). Should VIV suppression make
contact with any pipelay equipment, such as stinger rollers, the Contractor shall
demonstrate by actual testing that this contact will not damage the VIV suppression
devices.
f. Pipeline crossing procedures.
g. Flowline initiation and termination procedures, including handling of all PLETs
(sleds) and manifolds and contingency procedures for recovery of a PLET (sled)
when the pipe is flooded.
h. Riser installation procedures, including installation of VIV suppression devices and
buoyancy and go-no-go philosophy.
i. Installation procedures for subsea hardware, including PLETs (sleds), manifolds,
jumpers, if part of the Scope of Work.
j. ROV operating procedures.
k. Vessel Positioning and Surveying Procedures. Procedures shall include detailed
vessel positioning procedures for each incremental water depth of 60 m (200 ft)
increments maximum.
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 14
instrumentation readout shall be located near the DP control console. Separate monitors
shall be placed in the Principal’s inspection office.
The pipelay control tower shall be able to read and adjust tension and operate the brakes
on all tension machines. The amount of tension applied by each tension machine during
pipelay shall be monitored and continuously recorded on a calibrated chart recorder.
Unless this requirement is waived by the Principal, the Contractor shall monitor suspended
pipe during pipelay with either an ROV deployed from the pipelay vessel or from a separate
Contractor supplied ROV vessel.
The Contractor shall have on board the following supplemental environmental monitoring
systems:
a. Weather Radar to track movement of incoming squalls at a distance of at least
65 km (40 mi) away.
b. Current meter (S4 Interocean Systems or equivalent) with data acquisition system.
Current meter shall be run through the water column at least twice each day in
depths greater than 800 ft. Hard copy of data print-out shall be maintained for
review by the Principal.
c. Weather reports shall be obtained by the Contractor every 12 hours and the
Principal shall receive copy of these reports.
d. Vessel motions shall be monitored and continuously recorded using Motion
Response Units (MRUs). The Principal shall have unrestricted access to this data.
inserting a piece of pipe in the tensioner and pulling against a calibrated load cell.
Deadband settings shall be confirmed to be in operational order. Squeeze pressure shall
be applied to a thoroughly wetted coated pipe joint to verify holding capabilities at the
maximum expected lay tensions. All tensioner pads shall be checked and their condition
noted.
4.9.2.2 Abandonment and Recovery (A&R) Systems
The A&R winch shall be tested and confirmed to be in good working order. The load
gauges and payout gauges shall be verified to be in working order and a calibration
certificate provided for calibration six (6) months prior to start of mobilization. A load test
shall be performed for a load 1.25 times the anticipated value required for the Work. With
respect to pipeline A&R, the Contractor agrees to have a qualified A&R winch operator on
board at all times, who is designated to operate the A&R winch and is thoroughly familiar
with the working of the winch.
If required in the Scope of Work, the Contractor shall load test the A&R system intended for
use. The load test is to verify that the intended A&R system is capable of completely
abandoning the pipeline in either the event of a planned abandonment and recovery or in
the event of severe weather or other problems that require pipeline abandonment. Each
and every separate A&R head shall be installed on a piece of test pipe and tested to at
least 1.25 times the maximum expected load (including dynamics).
4.9.2.3 Davits operation
If the Contractor plans to use davit winches for any reason, either for normal operations or
as a contingency measure, all davit winches shall be tested and confirmed in good working
order. For each davit winch, the load gauges and payout gauges shall be verified in
working order and calibration certificate provided for calibration six (6) months prior to start
of mobilization. If the Contractor decides not to conduct these tests and later wants to use
the davits, the Contractor shall then bear stand-by costs incurred during performance of
these tests.
4.9.2.4 Stinger operation
The stinger ballasting procedure shall be performed and all compartments shall be
completely flooded (individually) and evacuated with air in the Contractor’s yard or from the
stinger shack on the deck of the lay vessel. The pneumo gauges shall be confirmed to be
in working order and the depth readout shall be calibrated with the dead weight tester. The
position of the pneumo gauges on the stinger shall be verified. All stinger rollers shall be
checked and the condition noted and repaired as required. Rollers shall “roll” freely and
their condition for use is subject to the Principal’s approval.
4.9.2.5 Heli-Deck safety
The Contractor shall comply with the standards for Aircraft Operation as defined in the
HSSE Section of the Contract.
4.9.2.6 Pipe abandonment & recovery and buckle recovery system
The Contractor shall be responsible for providing suitable pipe abandonment and recovery
and buckle recovery systems for all diver depth and diverless work. The required tools
shall be provided at the Contractor’s expense and shall also be load tested at the
Contractor’s expense at a load no less than 1.25 times the anticipated maximum load
during recovery. Specific attention shall be paid in design of pipe lay down and recovery
heads to providing adequate safety for collapse. Where practical, such heads shall be
subjected to collapse test at 1.25 times the maximum external hydrostatic pressure. In
addition, the A&R heads shall be subjected to internal hydrostatic test pressure at a
pressure to be defined by the Principal, if any intermediate testing of the pipeline with A&R
head attached may be required.
4.9.2.7 DP system requirements
The Contractor shall comply with the requirements as defined in DEP 37.90.10.32-Gen.
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 17
D/t edab
D/t < 15 0.5 t/D
15 < D/t < 20 1.1 t/D - 0.04
20 < D/t < 30 0.5 t/D - 0.01
The Contractor shall demonstrate that remaining ovality in the pipe, as defined in
API RP 1111, after the pipe departs the pipelay vessel does not exceed 0.5 %, unless the
Contractor demonstrates that a higher value, but no more than 1 %, does not result in a
collapse performance in the sag bend that does not meet API RP 1111 requirements, with
a bending strain of 0.5 %.
Strain amplification at the welds, in particular at the transition from base metal to weld shall
also be considered for the weld ECA to establish allowable defect sizes. The maximum
allowable tensile strain, including the effect of strain amplification, shall not exceed 3 % for
reeled welds or the maximum strain value used for the weld ECA, whichever is less.
Should the Principal conduct the weld ECA, the Contractor shall provide the requisite
information of maximum weld strains to the Principal at the earliest opportunity, and keep
the Principal informed of any significant changes as a result of more detailed analyses or
changing conditions. Allowable weld defect sizes can be strongly influenced by the
maximum strain at the welds.
Fastener coating shall comply with DEP 30.48.00.32-Gen. For bolts in subsea use on
flanges or other pressure containing connections, the following coatings are acceptable:
• Ceramic-Aluminum filled coatings (e.g. Sermagard® 1105/1280)
• Zinc electroplated as per ISO 2081 or equivalent ASTM standard
• Hot dip or mechanically galvanized.
Bolts coated with a fluorocarbon coating only are not acceptable for use subsea.
Amendment A01
For submerged service where cathodic protection is applied to the bolts, if bolt end caps or
flange protectors are used, the design shall prevent shielding of bolts from the cathodic
protection. The flange mating surfaces shall be bare to ensure electrical continuity.
An electrical contact between the bolt and the flange connector shall be designed to
achieve protection by the remote sacrificial anodes (electrical contact can be established
strapping or by using a serrated washer).
For low alloy bolts on a bare flange of a high alloy material (e.g., duplex stainless steel) the
current demand will increase and may reduce the ability to adequately polarise the bolt in
crevices
NOTE: Circular September 2012: added reference to new DEP for coating of Fasteners
DEP 30.48.00.32_Gen and provided additional important requirement regarding electrical contact
between flange and bolts.
Bolts exposed to the marine environment in the splash zone cannot be effectively
cathodically protected. Unless otherwise specified by Principal, Alloy 625 bolts, specified to
UNS 06625, shall be used on both pipe flanges and piping clamps in the splashzone. Use
of flanges in the splash zone shall be avoided wherever practical.
Bolt tightening of flanges shall be either by hydraulic torque wrench or hydraulic bolt
tensioning. Hydraulic bolt tensioning equipment shall be used to make flanged connections
as follows:
• for all subsea flanged connections;
• for bolt diameters ≥ 50 mm regardless of pressure;
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 20
• for bolt diameters ≥ 38 mm for pressures PN 250 (ANSI 1500) and above;
• other critical applications, as specified by Principal.
The bolt tension shall be calculated on the following basis:
a. the bolt tension shall not cause a stress in the bolt greater than 50% SMYS;
b. the relaxation of the bolt is a function of the method of tensioning and the coating on
the bolt;
c. the bolt tension shall not lead to excessive yielding of the gasket;
d. the bolt tension shall be sufficient to ensure the gasket remains seated under the
worst combination of tension, bending and bolt relaxation.
with the sled installation, especially if work needs to be conducted while the sled is
suspended in the pipe string. See also (4.9.2.10).
a. When the lay vessel enters the 500 m (1640 ft) zone of the drill rig or host, a formal
DP system check shall be completed. Under no circumstance shall the installation
vessel come closer to the rig than the distance agreed to in the procedures.
b. Detailed rigging analysis and load testing shall be performed for the pull-in rigging
prior to use.
c. Contingency procedures shall be developed for abnormal weather during the
initiation process (i.e. how to abandon if pipe string has not reached seafloor).
d. The entire pull-in procedure shall be monitored via ROV with remote video screens
available on the ROV vessel, lay vessel, and drill rig.
e. Appropriate acoustic array, transponders, and inclinometers shall be installed to
ensure accurate positioning of the PLET (sled).
f. Where PLET (sled) rotation is a concern (i.e. for any installation method that
creates torque in the suspended pipe span), the Contractor shall use appropriate
measures, including use of supplemental buoyancy, to ensure that the PLET (sled)
lands within specified tolerances on the seabed and shall develop contingency
procedures to correct sled attitude should the sled land outside tolerances.
g. A dropped objects assessment shall be made and in general, the Contractor shall
maintain a safe stand-off distance from existing subsea equipment during PLET
(sled) or manifold lowering, and only approach the subsea equipment during the
latter stage of lowering, to minimize the risk of dropped objects onto the subsea
equipment. Supply barge offloading over existing subsea equipment shall be
minimized to the extent practical. As a general rule of thumb, a safe stand-off
distance can assumed to be the water depth multiplied by the tangent of 15 deg.
h. Any onshore piping connections that can be made by welding shall be welded
connections. The Contractor shall assume in the bid proposal that all pressure
pipe connections offshore shall also be welded connections. Should the Contractor
wish to propose other type connections, such as flanged or Grayloc® type
connections offshore, the Contractor shall demonstrate for Principal approval that
making such connections rather than welded connections offshore will lower overall
HSSE risk and that they are suitable for cyclic loading during operating conditions.
If this cannot be demonstrated, welded connections shall be used offshore. The
metal seal selection shall comply with the Manufacturer's/Supplier’s
recommendations and be subject to the Principal’s approval and the FAT shall
include an external seal test at actual field hydrostatic pressure conditions.
Evidence shall be presented with such a proposal that the seal has been qualified
for project water depth and pressures.
i. Unless specified otherwise on the AFC Drawings or in the Scope of Work, the
default maximum allowable PLET (sled) installation tolerances shall be as specified
in DEP 31.40.11.32-Gen. for as-built survey and positioning.
4.21 TRENCHING
4.21.1 Depth
Trenching is required in United States waters in water depths of 60 m (200 ft) or less. The
top of the pipe shall be lowered to a minimum of 1 m (3 ft) below the seabed for the entire
length of the pipeline located in a water depth of less than 60 m (200 ft). If additional depth
is required, it will be indicated on the AFC drawings.
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 25
4.27 DEMOBILIZATION
Upon demobilization from the field, all surplus materials shall be handled in accordance
with (3.3). All temporary equipment and materials, including installation aids, utilized for
installation shall be removed by the Contractor. Where removal damages the permanent
facility’s coating system, it shall be repaired at the Contractor’s cost.
• Completed as-built pipe tally with joint numbers and weld numbers clearly identified
• All applicable inspection records, including weld NDE records
• Originals of all hydrostatic test records
• Welding procedure and welder qualification records
• Contractor to provide Principal with a disk with JSA, MOC, etc. data
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 29
11. REFERENCES
In this DEP, reference is made to the following publications:
NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used,
together with any amendments/supplements/revisions thereto.
2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell
Wide Web) at http://sww.shell.com/standards/.
Amendment A01
SHELL STANDARDS
Cathodic protection systems for subsea pipelines and hardware DEP 30.10.73.32-Gen.
(amendments/Supplements to ANSI/NACE SP0607-2007/ISO
15589-2)
Coating of fasteners DEP 30.48.00.32-Gen
Hot-tapping on pipelines, piping and equipment DEP 31.38.60.10-Gen.
Riser design DEP 31.40.10.10-Gen.
Pipelay survey, positioning and as-built reportings offshore DEP 31.40.11.32-Gen.
pipelines
Pipeline isolating joints (amendments/supplements to ISO 15590-2) DEP 31.40.21.31-Gen.
Hydrostatic pressure testing of new pipelines DEP 31.40.40.38-Gen.
Precommissioning of pipelines DEP 31.40.50.30-Gen.
Vessel integrity, marine systems - Requirements for selection and DEP 35.00.00.10-Gen
operation of vessels (endorsement of DNV RP-H104)
Galvanic anodes for marine structures and pipelines – Specification DEP 37.81.20.31-Gen.
and qualification – Modifications to ISO 15589-2
Deepwater syntactic foam for flowlines DEP 37.81.40.30-Gen.
Welding of deepwater pipelines, flowlines, and steel catenary risers DEP 37.81.40.31-Gen.
(amendments/ supplements to API 1104)
Automated Ultrasonic Inspection (AUT) of girth welds for carbon DEP 37.81.40.32-Gen.
steel pipelines, flowlines and catenary risers
Onshore fabrication of deepwater pipelines, flowlines, risers and DEP 37.81.41.30-Gen.
their appurtenances
Offshore pipeline and umbilical/cable crossings DEP 37.81.41.35-Gen.
ROV operations for work-class vehicles DEP 37.81.42.34-Gen.
Dynamically positioned (DP) vessels for construction, DEP 37.90.10.32-Gen.
drilling/completions/well intervention activities - Selection and
operation
Selection of materials for life cycle performance (upstream DEP 39.01.10.12-Gen
facilities) - Equipment
Welding of pipelines and related facilities DEP 61.40.20.30-Gen.
(amendments/supplements to ISO 13847:2000)
AMERICAN STANDARDS
Design, construction, operation, and maintenance of offshore API RP 1111
hydrocarbon pipelines (Limit state design) – 4th Edition, December
2009
ECCN EAR99 DEP 37.81.41.33-Gen.
September 2011
Page 30
Standard specification for alloy-steel and stainless steel bolting for ASTM A193/A193M
high temperature or high pressure service and other special
purpose applications
Standard specification for carbon and alloy steel nuts for bolts for ASTM A194/A194M
high pressure or high temperature service, or both
Standard specification for alloy-steel and stainless steel bolting for ASTM A320/A320M
low-temperature service
BRITISH STANDARDS
Code of Practice for fatigue design and assessment of steel BS 7608
structures
NORWEGIAN STANDARDS
Rules for planning and execution of marine operations
INTERNATIONAL STANDARDS
Metallic and other inorganic coatings – Electroplated coatings of ISO 2081
zinc with supplementary treatments on iron or steel
Lifting and hoisting safety recommended practice OGP 376