Professional Documents
Culture Documents
Agriculture Extension Short Notes
Agriculture Extension Short Notes
THEORIES OF LEARNING:
Models of communication:
Management theories:
Fathers:
Entrepreneurship Theories
Farm Publication
Leaflet
Folder
Bulletin
News letter
Journal
Magazine
Leaflet
Folder
Bulletin
Newsletter
Clear
Concise
Correct
ABC of poster
Accuracy
Brevity
Clarity
Community Development
1952 CDP Community Development Programme
1953 NES National Extension Service
1957 Panchayati Raj Decentralization
Technological Development
1960 IADP Intensive Agricultural District Programme
1964 IAAP Intensive Agricultural Area Programme
1965 ICDP Intensive Cattle Development Project
1966 HYVP High Yielding Variety Programme
Adopter category:
Innovators(Venturesome): 2.5
Late Majority(Skeptical): 34
Laggards(Traditional): 16
Stages of diffusion: awareness- interest- evaluation- trial- adoption
Posters
Hoardings
Television Brainstorming
Flash card
Critical Path: The longest time path through the task network.
Dummy activity: An imaginary activity with no duration, used to show either an indirect
relationship between 2 tasks or to clarify the identities of the tasks.a dummy activity (an
activity which begins and ends at the same time) is inserted into the model to distinguish the
two activities.
Milestone: A significant task which represents a key accomplishment within the project.
Typically requires special attention and control.
Network Diagram: A wire diagram, also known as a PERT network diagram. A diagram that
shows tasks and their relationships; it is limited because it shows only task relationships. Its
key strength is easy-to-read task relationships.
Slack Time: The amount of time a task can be delayed before the project finish date is
delayed. Total slack can be positive or negative. If total slack is a positive it indicates the
amount of time that the task can be delayed without delaying the project finish date. If
negative, it indicates the amount of time that must be saved so that the project finish date is
not delayed. (Slack time is also known as float time)
By default and by definition, a task with 0 slack is considered a critical task. If a critical task
is delayed, the project finish date is also delayed.
Lead time: the time by which a predecessor event must be completed in order to allow
sufficient time for the activities that must elapse before a specific PERT event reaches
completion.
Optimistic time (O): the minimum possible time required to accomplish a task, assuming
everything proceeds better than is normally expected
pessimistic time (P): the maximum possible time required to accomplish a task, assuming
everything goes wrong (but excluding major catastrophes).
Most likely time (M): the best estimate of the time required to accomplish a task, assuming
everything proceeds as normal.
Expected time (TE): the best estimate of the time required to accomplish a task, accounting
for the fact that things don't always proceed as normal (the implication being that the
expected time is the average time the task would require if the task were repeated on a
number of occasions over an extended period of time).
TE = (O + 4M + P) ÷ 6