Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

This article has been accepted for inclusion in a future issue of this journal.

Content is final as presented, with the exception of pagination.

CANIZES et al.: OPTIMAL APPROACH FOR RELIABILITY ASSESSMENT IN RADIAL DISTRIBUTION NETWORKS 7

TABLE II TABLE III


REPAIR TIME REDUCTIONS AND COSTS FOR EACH ACTION FAILURE RATE REDUCTIONS AND COSTS FOR EACH ACTION

A set of 1000 random weights is determined. The NSE cost


the considered value for equivalent hour loss Te is 4500 h. is 2 m.u./kVAh, and the loss cost is 0.07 m.u./kVAh. For the
More detailed information on equivalent hour loss can be NSE cost, investment cost, loss cost, and capacitor cost, a
found in [36]. discount rate of 1.75% is considered for a ten-year project
The detailed data related to the repair time and failure rate lifetime, which leads to a CRF equal to 0.110.
reductions, as well as their costs, can be found in Tables II MATLAB has been used to develop the algorithm to obtain
and III. the Pareto front, to generate randomly the set of weights, and
Only lines, cables, and distributed generators were consid- to deal with the results. Based on the weighted Pareto front
ered for possible failures for this case study. It is assumed that method, mixed-integer nonlinear programming is developed
the substation has 100% availability. For the distributed [see (14)–(41)] and applied in order to identify the distribution
generators, only actions to reduce repair time can be applied. network components. A computer with one processor Intel
The actions that the system operator can apply to reduce the Xeon E3-1225 3.20 GHz with four cores, 4 GB of random
repair time are as follows: access memory, and Windows 8 Professional 64-bit operating
system was used for this case study.
a) increasing the operation personnel (IOP); Fig. 5 depicts the diagram of the 33-bus distribution
b) automation system upgrade (ASU); network [25]. Two DG units with 500 kW, 250 kVAr in buses
c) communications upgrade (CUp). 11 and 27 have been considered. Due to the nonexistence of
the outage data for this test system, an outage database has
The actions that the system operator can apply to reduce the been created in order to apply the proposed methodology.
failure rate are as follows: This database can be found in Table IV. The initial data of the
a) reinforcing a line (RL); network are presented in Table V.
b) placing a new line in parallel with an existing one (PNL); The initial losses are obtained running a power flow for
c) redesign link layout (RLL). distribution networks based on the algorithm of Thukaram et
al. [38].A total of 223 non dominated solutions
Each one of these actions has a cost and results in a repair (corresponding to 223 investment plans) was obtained in the
time and failure rate reduction for each system component. network of the case study is by the weighted ac optimization
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.

8 IEEE SYSTEMS JOURNAL

TABLE V
INITIAL DATA FOR 33-BUS DISTRIBUTION NETWORK

TABLE VI
COSTS FOR PLAN 35 CONSIDERING TEN YEARS OF PROJECT LIFETIME

TABLE VII
INCOME FOR TEN YEARS OF PROJECT LIFETIME CONSIDERING PLAN 35

Fig. 5. Single-line 33-bus distribution network (adapted from [25]).

TABLE IV
OUTAGE DATA FOR 33-BUS DISTRIBUTION NETWORK TABLE VIII
FINAL BENEFIT FOR TEN YEARS OF PROJECT LIFETIME
CONSIDERING PLAN 35

method. This multiobjective is developed to achieve reduction


in repair times and failure rate of considered distribution
network components, reduces forced outage rate and which
improves the reliability.
The fuzzy satisfying decision method [30]–[32] is used to
select the preferred solution among nondominated solutions
obtained in optimization stage. Thus, plan 35 is selected. This
plan presents as weights w1 = 0.8379, w2 = 0.0931, w3 =
0.0346, and w4 = 0.0344. Table VI presents the results for each
term of the objective function, which lead to a total of 1 506
118 m.u. for ten years of project lifetime.
Table VII presents the incomings for NSE and losses.
Table VIII presents an economic evaluation and the total
benefit for the system operator. As can be seen in this table,
considering plan 35, the operator has 119 908 m.u. of benefit
with 8.1 years and 12.04% of payback and internal rate of
return, respectively.
Table IX presents the optimized reliability indexes when plan
35 is considered. The methodology leads to a high reduction in
NSE (69%), as we can see in this table, and in CAIDI (63%).

You might also like