Professional Documents
Culture Documents
Creative Mini Project
Creative Mini Project
AND DESIGN
OF A SHOPPING MALL
A PROJECT REPORT
Submitted by
ARAVINDH S 621717103001
MADHUSUTHANAN J 621717103009
RAJESH K 621717103013
SATHISH KUMAR M 621717103016
Of
BACHELOR OF ENGINEERING
In
DECEMBER 2020
BONAFIDE CERTIFICATE
ARAVIND.S 621717103001
MADHUSUTHANAN.J 621717103009
RAJESH.K 621717103013
SATHISH KUMAR.M 621717103016
Internal Examiner
External Examiner
ACKNOWLEDGEMENT
This is the time to express foremost thanks and gratitude to our Honorable Chairman
Shri. R. KANDASAMY, Muthayammal Education Trust and Research Foundation for
providing me the excellent infrastructure to carry this projject work.
This is the time to express foremost thanks and gratitude to our Secretary Honorable
Dr. K. GUNASEKARAN, M.E., Ph.D., F.I.E., for providing me the excellent infrastructure
to carry out this project work.
We also express our sncere thanks to the respect Principal Dr. P. VENUGOPAL,
M.E., Ph.D., F.I.E., for allowing me to use facilities that are in the college, to complete the
project.
We would like to express our grateful thanks to Dr. P. PRASATH, M.E., Ph.D.,
MISTE., Head of the Department for lending a hand for this project.
In this project planning, analysis and structural design has been done for a
commercial building of shopping mall based on all Indian Standard Codes of practice.
Detailing drawings pertaining to the structural design of shopping mall are presented.
Analysis of the structure was done using STAAD.Pro V8i. All the structural members like
slabs, beams, columns and footings are designed using Indian Standard Code IS 456-2000,
IS-875 and design aid SP-16. The structural components are designed by limit state method.
Materials were used as specified by National Building Code. Concrete M20 grade and Fe415
steel bars were considered for all the design. Brick walls are worked in C.M 1:5 mix 230 mm
thick. The mall is built with almost all the amenities required for the people to get entertained
in their busy schedule. This structure is going to be designed with the view that all the
entertainment facilities should be made available under one roof. The overall plot area of the
mall is 90,000 sq.ft. and the built area is around 30,000 sq.ft.
LIST OF SYMBOLS
A – Area
Ag – Gross section of section
As – Area of flexural steel
A – Area of compression steel
sc
2.4 ELEVATION 10
5 CONCLUSION 53
6 REFERENCES 54
CHAPTER 1
INTRODUCTION
1.1 GENERAL
This project deals with the design of planning, analysis and designing of a
Shopping mall. A Shopping Mall is a building designed for entertaining the
people.
1.2 OBJECTIVES
Planning of shopping building with proper ventilation and sunlight.
Analysis of frame by STAAD.Pro.
Designing of all structural members based on limit state method of
design.
Designing of other miscellaneous structures like septic tank by
working stress method.
To suggest a cost effective building.
1.3 SCOPE
Design of slab by using limit state method.
Preliminary design of beam and slab is done to adopt the beam and
column size for the respective designs.
Analysis of frame is done using STAAD.Pro V8i
Design of beam is done as per IS code.
Design of column is done according to SP-16.
Design of footing is done by using limit state method.
Design of dog-legged and open wall staircase.
Design of septic tank as per NBC requirements.
1.4 SELECTION OF PLOT AND STUDY
Huff (1964 and 1966): concluded that the comparative size of the
centers and the convenience of access were the primary characteristics
that consumers sought when choosing a shopping center to visit.
Cox and Cooke (1970): determined customer preference for shopping
centers and the importance of driving time. The authors concluded that
location and attractiveness are important determinants of consumer
shopping center preferences.
Mehrabian and Russell (1974): noted that the response that store
atmosphere elicits from consumers, varies along three dimensions of
pleasantness, arousal and dominance.
Kang and Kim (1999): also conducted surveys at three malls in San
Diego, Cleveland and Atlanta to examine the impact of ‘entertainment
as motivation for shopping.’ Their survey asked mall patrons to rate.
ULI–the Urban Land Institute, Michael D. Beyard, Mary Beth
Corrigan, Anita Kramer, Michael Pawlukiewicz, and Alexa Bach:
In addition to having possible code problems, many building systems
are notsized adequately for current demands; serviceable but aging
systems have been known. To literally fall apart when worked on
extensively. Water, gas, electrical, fire sprinkler, Sewer, and smoke-
control systems may not withstand extensive rework without overall
reconstruction. It is crucial to assess building systems and utility
demands, and to work with utility companies early many older malls
predate current standards for hazardous materials, such as asbestos.
These materials can be difficult to discover before construction starts.
Hazardous-materials abatement is expensive and time-consuming.
Unfortunately, if abatement is needed, it is likely to take.
Sonia Longjam1, S. Aravindan: As traffic congestion reaches crisis
proportions in many locations, the vaunted convenience of mall
shopping is disappearing. Most malls can be reached by only one means
—the automobile—and, in more and more metropolitan areas, this puts
them at a disadvantage in relation to locations that are walkable or
linked to public transit, and that offer more multidimensional urban
environments. While it’s probably true that most customers will always
drive to the mall, their busy lives are reducing the time they are willing
to spend shopping.
2.1.1 General
A building should be planned to make it comfortable economical and to
meet all requirements. All the requirements should be taken up and the
number of alternative proposal should be prepared. On comparing its
advantage and disadvantage the best one should be adopted. Planning mainly
depends upon the climatic condition.
3 Orientation
2.1.3 Ventilation
Unless there are windows reaching the top of the wall and capable of
being opened, ventilators are necessary near the top of the wall. The
ventilators should be regularly distributed in the same way as windows.
No plinth or any part of the building should be less than 30cm above
the determined level of:
The center part of abutting street.
The foot path of the abutting street.
The highest part of the service lane which determines the drainage
of the premises.
Any portion of the ground within 3m distance of such a building.
Undulating or slopping land 1.2m above the drainage or country
water level.
3 Rest Room
The height of the water closets measure from the surface of the floor
to the lowest point to the ceiling shall not be less than 2m.
The area of water closet shall be 1.1m with the minimum width of 0.9m.
It should have a ventilator opening to the shaft of open pace of area not less
than 0.3m2 with side not less than 0.3m.
4 Parapet Wall
For shopping complex building the minimum width of stair case is 1.2m
The rise should not be more than 200 mm and the tread should not
be less than 200mm
2.3 PLAN:
2.3.1 SITE PLAN
2.3.1 Ground Floor Plan
2.3.2 First Floor Plan
2.3.2 Second Floor Plan
2.3.3 Third Floor Plan
2.4 ELEVATION:
CHAPTER 3
ANALYSIS
3.1 GENERAL
The analysis of the structure that is determination of the internal forces
like bendingoment, shear force, etc. in the component members, for which
these members have to be designed, under the action of given external loads.
This process requires the knowledge of structural mechanics which includes
mechanics of rigid bodies (i.e. mechanics of forces), mechanics of deformable
bodies (i.e. mechanics of deformations) and the theory of structures (i.e. the
science dealing with response of structural system to external loads). A brief
review is taken of structural analysis to refresh the basic principles.
2.1 ANANLYSIS REPORT
The bending moments in the beam and columns of a substitute frame may be
computed by STAAD.Pro
Section Properties
I I
Area yy zz J
Prop Section Material
(cm2) (cm ) 4
(cm ) 4
(cm4)
1 Rect 0.60x0.30 18.0E 3 1.15E 6 1.15E 6 1.94E 6
4 STRUCTURAL COMPONETS
✔ Design of slab
✔ Design of beam
✔ Design of column
✔ Design of footing
✔ Design of stair case
✔ Design of septic tank
4.1 SLAB
4.1.1 DEFINITIONS
A concrete slab is a common structural element of modern buildings.
Horizontal slabs of steel reinforced concrete, typically between 100 and 500
millimeters thick, are most often used to construct floors and ceilings, while
thinner slabs are also used for exterior paving.
5 TYPES OF SLAB
One way slab
An One way slab is a simply a very wide beam that’s span between
supports. A rectangular reinforced concrete slab which spans a distance very
much greater in one direction than the other; under these conditions, most of
the load is carried on the shorter span.
Ly/Lx > 2
Two way slab
A concrete lab supported by beams along all four edges and reinforced
with steel bar arranged perpendicularly.
A concrete floor slab in which the main reinforcement runs in two direction
Rectangular reinforced concrete slab having a span on long side.
Ly/Lx < 2
= 3.143 m
L = c/c support
eff
= 3.278 m
L = 3.143 m
eff
Bending moment:
2
Mu = Wu x Leff /8
= 10.1965 kNm
= 17197000 Nmm
Step:4 Check for effective depth
M = 0.138 x fck x bd2
u lim
2 = 3694.203
d
d = 60.779
= 60.78 mm
D = 100 mm (minimum)
Overall depth D = 115 mm
Calculation of Ast:
From IS 456:2000 annexure G, clause 38.1, equation
Mu = 0.87xfyxAstxdx(1-((fyxAst)/(fckxbxd))
Ast = 301.226
Ast = 4518.051
Ast = 301.226 mm2
Assume :
Dia of bars = 10 mm
Ast = ᴨd2/4
= 78.5 mm2
No. of bars = Ast/ast
= 3.83
= 4 bars
Spacing = 1000/no of bars
= 250 mm
Step:5 Check for spacing:
3 x eff depth = 300 mm
Provide 10mm dia of spacing 300 mm
Step:6 Design of distributory reinforcement:
Astd = 0.12% of crosss sectional area
= 138 mm2
assume :
D = 8 mm
Ast = 50.24 mm2
No of bars = 2.746
= 3 bars
Spacing = 300 mm
Step:7 Check for spacing:
5 x eff depth = 500 mm
Provide 3 number of 8 mm dia bars
Step:8 Shear calculation:
τv = vu/bd
vu = wu x Leff/2
= 19.463 kN
τv = 0.000194 N/mm2
τc max>τC>Τv Refer table 19 of IS 456-2000
Pt = 100 x (Ast/bd)
= 0.3012
= 0.3 %
τc = 0.384 N/mm2
τ = 2.8 N/mm2
c max
Longer span:
Positive moment co-efficient at mid span, αyp = 0.024
Negative moment co-efficient at support, αyn = 0.032
Design bending moment:
Shorter span:
Positive moment at mid span, Mxp = Co-eff x Load x Span x Span = 2.981 kN-m
Negative moment at support, Mxn = 3.974 kN-m
Longer Span:
Positive moment at mid span, Myp = 2.981 kN-m
Negative moment at support, Myn = 3.974 kN-m
Middle strip reinforcement:
width of middle strip in shorter span = 2.286 m
width of middle strip in longer span = 2.286 m
Shorter span:
Mid span reinforcement
M = 0.87xfyxAstxd (1-(fy x Ast/fck x b x d))
xp
Ast = 88.385
Ast = 4501.976
Ast = 88.385 mm2
Minimum reinforcement:
[For Fe415 grade steel]
Ast (min)
Spacing at midspan:
Assume diameter, φ = 10mm
Ast = 78.5mm2
1 S = ast/Ast x 1000 = 568.75mm
2 3d = 285.75mm
3 300 = 300mm
Spacing = 300mm
Provide 10 mm dia bar @ 300 mm c-c spacing
Area of steel provided at mid span:
Ast (pro) = (ast/spacing) x 1000 = (78.5/300) x 1000
= 274.715mm2
Support reinforcement:
Mxn =0.87 x fy x Ast x d (1(fy x Ast/fck x b x d))
Ast =118.644
Ast =4471.716
Ast =118.644mm2
Spacing at supports:
Assume diameter, φ
Ast = 78.5mm2
1 ast/Ast x 1000 = 661.639mm
2 3d = 285.36 mm
3 300 =300mm
Spacing =300mm
Provide 10 mm dia bar @ 300mm c-c spacing
Longer Span:
Midspan reinforcement:
Myp = 0.87 x fy x Ast x d (1-(fy x Ast/fck x b x d))
Ast =88.385
Ast =4501.976
Ast = 88.385mm2
Spacing at midspan :
Assume diameter, φ=10mm
Ast = 78.5mm2
1 ast/Ast x 1000 = 567.26mm
2 3d = 285.75 mm
3 300 = 300mm
Spacing = 300mm
Provide 10 mm dia bar @ 300 mm c-c spacing
Support reinforcement:
Myn = 0.87 x fy x Ast x d (1-(fy x Ast/fck x b x d))
Ast = 118.644mm2
Ast = 4471.716
Ast = 118.644mm2
Spacing at supports:
Assume diameter, φ=10mm
Ast =78.5mm2
1. ast/Ast x 1000 = 567.264mm
2 3d = 285.75mm
3 300 = 300mm
Spacing = 300mm
Provide 10 mm dia bar @ 300 mm c-c spacing
Edge Strip reinforcement:
Distance of edge strip in shorter span = 0.381m
Distance of edge strip in longer span = 0.381
m Area of steel required = 118.644 mm2
Spacing:
Assume diameter, φ = 10 mm
ast = 78.5 mm2
1 S = ast/Ast x 1000 = 661.64 mm
2 5d = 476.25 mm
3 300 = 300 mm
Spacing = 300 mm
5.2.1 DEFINITION
Horizontal or inclined structural member spanning a distance
between one more supports, and carrying vertical loads across its longitudinal
axis as a girder, joist, purlin, or rafter.
6 TYPES OF BEAM
Cantilever Beam
A cantilever beam is one whose one end is fixed and the other end
carries a point or concentrated load.
Simply Supported Beam
A simply supported beam is one which carries two reaction forces at
its two ends & a point load at its mid-point.
Overhanging Beam
It is a type of simply supported beam which overhangs from its
supports. An overhanging beam may overhang on one side only or on both
sides of the supports.
Rigidly Fixed or Built-In-Beam
It is a type of beam in which both ends are fixed and carries a point
load at its centre.
Continuous Beam
It is a type of overhanging beam which consists of a numerous
reaction forces and point load
7 DESIGN OF BEAM
Data:
Clean Span l = 9.144 m
Wall thickness t = 230 mm
Concrete Grade fck = 20 N/mm²
Steel Grade fy = 415 N/mm²
Dia of Bars = 20 mm
Design:
Width of the beam = 300 mm
Overall depth of the beam = 600 mm
Effective depth d = 565 mm (approx)
Effective span calculation:
Effective Span
Leff =l + wall thickness = 9374 mm
Load calculation:
Total load on the slab = 15.938 kN/m
Wall load = 13.004 kN/m
Dead load (b x D x 25) = 4.5 kN/m
Total load W = 33.439 kN/m
Ultimate load Wu = 50.159 kN/m
Bending moment calculation:
From Analysis, Mumax= 364.07 kNm
Mu = Wu x l2/12 = 367.298
kNm Mulim = 0.138 fck
bd²
Mulim = 396.477 kNm
Since, Mulim>Mu The beam is designed as under reinforced beam
Main reinforcement design:
Tension zone:
From IS 456:2000 annex G, clause 38.1, equ b
Mu = 0.87xfy x Ast x d x(1-((fy x Ast)/(fck x b x d))
364070000 = 203993.25 Ast(1-0.000122 x 10-5Ast)
Ast = 2634.148 mm²
Ast = 5533.526 mm²
Ast = 2634.148 mm²
Assume: 20 mm dia bars
ast = 314 mm²
No of bars 'n'= Ast/ast
= 7.68
Spacing = (1/n) x 1000 = 119.203 mm
= 6 bars
RESULT:
Main Reinforcement:
Using 16 mm Dia of bars,
Number of Bars n = 8 Nos
Shear Reinforcement:
Using 8 mm Dia of bars,
Number of bars n = 2 legged vertical stirrups
Spacing Sv = 230 mm c/c
7.1.1 STRUCTURAL DRAWING OF BEAM
7.2 COLUMN
7.2.1 DEFINITION
7.2.2 TYPES
Uniaxial column:
The column having axial lad acted in such a way that it is eccentric
about one axis of the plane column then it is called uni-axial column
Biaxial column:
If the load is eccentric about both the axes in the plane of column then
it is called biaxial column
7.2.3 DESIGN OF COLUMN:
Breadth of beam , b = 300 mm
Depth of beam D = 600 mm
Axial force , pu = 2046.3 kN
Grade of concrete, f = 20 N/mm2
ck
Longitudinal reinforcement:
pu = 0.4xfckxAg+(0.67xfy-
0.4xfck)xAsc Asc =(pu – 0.4xfckxAg)/(0.67xfy-
0.4xfck) = 2245.139mm2
Assume:
φm = 20 mm
asc = 314mm2
No of bars n = 8 bars
Lateral spacing:
Spacing s = 960 mm
Provide 8 mm dia bars @ 300 mm c-c spacing.
7.2.4 STRUCTURAL DRAWING OF COLUMN
7.3 FOOTING
7.3.1 DEFINITION
In a typical structure built on ground, the part which lies below the
ground is referred to as the substructure or the foundation structure. The
purpose of foundation to effectively support the superstructure. The
foundation provided for a RC column is called as column base or a column
footing reinforced concrete footing are designed to resist the design factored
moments and shear force due to the imposed loads. The area of the footing
should be such that the bearing pressure developed at the base of footing does
not exceed the safe bearing capacity of the soil.
Isolated footing
Combined footing
Wall footing
Spread footing
Raft or mat foundation
Strap footing
Cantilever footing
Pile footing
7.3.3 DESIGN OF
FOOTING Available data:
Width of column = 300 mm = 0.3 m
Depth of column = 600 mm = 0.6 m
Factored load Pu = 2246.93 kN
(including 10% of column load as self-weight of
footing) Safe bearing capacity of soil q = 200
kN/m2
Grade of concrete fck = 20 N/mm2
Grade of steel fy = 415 N/mm2
Solution:
Step 1: Size of footing
Area of footing A = (Load)/SBC
= 11.23 m2
Let, 6.5x X 4.73x =
11.23 X2 =
0.3652
X = 0.6043
Short side of footing = 4.73x = 4.75 x 0.6043
= 2.9 m
Long side of footing = 6.5x = 6.5 x 0.6043
= 3.9 m
Step 2: Determination of soil pressure
Soil pressure P = (load)/provided
area P = 200 kN/m2
Step 3: Bending Moment
Cantilever projection of short side of footing,
= 0.5(3.9-0.6) = 1.65 m
Cantilever projection of short side of footing,
= 0.5(2.9-0.3) = 1.3 m
Bending moment @ short face of column,
= (P x L 2)/2 = (200 x 1.652)/2
= 272.25 kNm
Bending moment @ long face of column,
= (P x L 2)/2 = (200 x 1.32)/2
= 169 kNm
Step 4: Determination of depth of footing
1) Based on flexure
Mulim = 0.138 x fck x b x d2
d = √Mu/(0.138 x fck x b x
d2) d = 314.07 mm
2) Based on one way shear
Vu = Soil pressure x {(L/2-B/2)-
d} Vu = 200 x (1650 – d)
Permisible shear stress is taken from IS 456 2000
Take Pu=0.25% τper = 0.36
N/mm2
τc = Vu/bd
200(1650−d)
=
1000 x d
d = 600 mm
Depth of footing d = 0.6 m
D = 650 mm
Overall depth D = 0.65 mm
Step 5: Area of reinforcement
i) Longer Direction
Mu = 0.87 x fy x Ast x (1-(Ast x fy/(fck x b xd)))
= 1985.30 mm2
Minimum reinforcement = 0.0012 x 1000 x 650
= 780 mm2
Provide 16 mm dia bars at 100 mm c/c spacing
Step 7: Check for shear
Shear force = 200(1650 – 600)/103
= 210 kN
Pt = 100Ast/bd
100 x 1315.2
P =
1000 x 600
= 0.2192 mm2
ks x τc = 1 x 0.3354 = 0.3354 N/mm2
✔ Straight stairs
✔ Quarter turn stairs
✔ Dog legged stairs
✔ Three Quarter turn stairs
✔ Geometrical stairs
✔ Bifurcated stairs
✔ Multiple flight stairs
Straight stairs:
These types of stairs are provided when there is need for change of
direction by 90’. The change in direction may be accompanied by providing
either introducing quarter space landing or by providing winders.
Dog legged stairs:
These types of stairs are provided with change of direction through 180’.
This type of stair is called as half turn stair.
These type of stairs are provided with change in direction through 270’.
That is the direction is changed three times.
Geometrical stairs:
These stairs have no newel post and may be of any geometrical shape.
The directional changes are effected by providing winders.
Bifurcated stairs:
These stairs with a wide flight. This is subdivided after the landing into
two narrow flights from either side of the landing.
It is an open well type stair which has four flights each flight turn 90’. It
has an excellent view in a building.
8 DESIGN OF STAIRCASE
Data:
Assume
Tread = 300mm
Rise = 150mm
No of tread require = 12 - 1 = 11
Effective span:
= 4300 mm
=143.33mm~150mm
Load Calculation:
= 5.59 kN/m
Self-weight of steps= 1xRx25
2
1
= x 0.150 x25
2
=1.875 kN/m
Mu = Wu *l^2
8
= 12.96 x 4.3^2/8
= 29.95 kNm
Check for
depth:
d = √ (Mu/0.138 x fck x b)
= √(29.95x106/138x25)
= 93.17mm
Hence safe
=270 mm2
Vu = 27.864 kN
ﺡv = Vu/bd
= (27.864x1000)/ (1000x165)
= 0.17 N/mm2
% of Ast = (591.77)/(1000x165)x100
= 0.35%
ﺡc = 0.40
ﺡ ﺡ
N/mm2 c> v
Hence safe.
Result:
Tread = 300mm
Rise = 150mm
4.6.4 STRUCTURAL DRAWING OF STAIRCASE
8.1 DESIGN OF SEPTIC TANK
8.1.1 DEFINITION
By this project the objective of entertaining the people under one roof is met with the
inclusion of all the amenities and requirements.
The attempt of this project made us to understand concepts of design of slab, beam,
column and footing we gained knowledge in softwares like STAAD.Pro and AutoCADD
and some codal provisions.
CHAPTER 6
REFERENCES