Professional Documents
Culture Documents
OM MCQ Quizlet
OM MCQ Quizlet
Both components must function for the product to function. To achieve an overall reliability
of at least 0.95 without changing the reliability of the first component, the reliability of the
second component would need to be
0.97 ---------------------- 0.90
a. at least 0.925 .
b. at least 0.95.
c. at least 0.97.
d. at least 0.98. d. at least 0.98.
16. A company produces a product consisting of two components arranged as follows:
R1 ----------- R2
If both components must function for the product to function, then the two components
would need individual reliabilities of _______ to achieve an overall reliability of 0.90.
a. R1 = 0.90 and R2 = 0.90
b. R1 = 0.95 and R2 = 0.95
c. R1 = 0.80 and R2 = 0.80
d. R1 = 0.85 and R2 = 0.85 b. R1 = 0.95 and R2 = 0.95
17. A product consists of three components arranged as follows:
If all three components must function for the product to function, then the product's overall
reliability is approximately
a. 0.812.
b. 0.90.
c. 0.933.
d. 0.95. a. 0.812.
18. The overall reliability of the following system is
0.90
|
0.95 - 0.95 - 0.95
0.85 0.89
||
0.90 - 0.94 - 0.93
a. 0.787.
b. 0.85.
c. 0.89.
d. 0.919.
Ans: D d. 0.919.
22. If a product fails 10 times in 500 hours of operation, then its mean time between failures
(MTBF) is
a. 0.02 hour.
b. 0.10 hour.
c. 20 hours.
d. 50 hours. d. 50 hours.
23. If a piece of equipment has a mean time between failures (MTBF) of 500 hours with a
mean time to repair (MTTR) of 10 hours, then its uptime or average availability would be
a. 0.020 or 2.00%
b. 0.980 or 98.00%
c. 0.500 or 50.00%
d. 1.000 or 100.00% b. 0.980 or 98.00%
24. The system availability for a system with a mean time between failures (MTBF) of 1000
hours and a mean time to repair (MTTR) of 50 hours would be
a. 100.00%
b. 97.50%
c. 95.24%
d. 4.76% c. 95.24%
25. Which of the following will not improve design for manufacture and assembly?
a. minimizing the number of parts and subassemblies
b. using standard parts when possible
c. designing parts for limited, unique uses
d. designing parts for many, varied uses c. designing parts for limited, unique uses
26. _____________________ involves taking into account the capabilities at each level of
the supply chain when designing a product.
a. Design for supplier
b. Design for manufacturer
c. Design for supply chain
d. Design for competitor c. Design for supply chain
27. Functional design includes all the following except
a. reliability.
b. usability.
c. form design.
d. maintainability. c. form design.
28. Simultaneously designing new products and the processes to produce them is known as
a. concurrent design.
b. functional design.
c. modular design.
d. standard design. a. concurrent design.
29. ____________________ is a software system that facilitates collaborative design and
development among trading partners.
a. Computer aided design
b. Collaborative product design
c. Computer aided engineering
d. None of these answer choices is correct. b. Collaborative product design
30. ____________________ is a software system that assists in the creation, modification
and analysis of design.
a. Computer aided design
b. Collaborative product design
c. Computer aided engineering
d. None of these answer choices is correct. a. Computer aided design
31. ____________________ is a software system that retrieves the description and geometry
of a design from a database, and tests and analyzes that design on a computer screen.
a. Computer aided design
b. Collaborative product design
c. Computer aided engineering
d. None of these answer choices is correct. c. Computer aided engineering
32. ____________________ is a software system that stores, retrieves and updates design
data through the lifecycle of a product.
a. Computer aided design
b. Collaborative product design
c. Computer aided engineering
d. None of these answer choices is correct. d. None of these answer choices is correct.
33. Product lifecycle management is a software system that
a. facilitates collaborative design and development among trading partners.
b. stores, retrieves and updates design data through the lifecycle of a product.
c. retrieves the description and geometry of a design from a database, and tests and analyzes
that design on a computer screen.
d. assists in the creation, modification and analysis of design. b. stores, retrieves and
updates design data through the lifecycle of a product.
34. Failure mode and effects analysis (FMEA) is
a. a software systems that uses computer graphics to assist in designing products.
b. a systematic approach to analyzing the causes and effects of product failures.
c. a visual method for analyzing the interrelationships among failures.
d. a structured process that translates the voice of the customer into technical design
requirements. b. a systematic approach to analyzing the causes and effects of product
failures.
35. Fault tree analysis (FTA) is
a. a software systems that uses computer graphics to assist in designing products.
b. a systematic approach to analyzing the causes and effects of product failures.
c. a visual method for analyzing the interrelationships among failures.
d. a structured process that translates the voice of the customer into technical design
requirements. c. a visual method for analyzing the interrelationships among failures.
36. __________________________is a procedure, used by multifunction design teams, to
eliminate unnecessary features and functions from a product design.
a. Failure mode and effects analysis
b. Value analysis
c. Fault tree analysis
d. All of these answer choices is correct. b. Value analysis
37. Which of the following techniques would most likely be used to systematically analyze
product failures?
a. concurrent design
b. quality function deployment
c. failure mode and effects analysis
d. value analysis c. failure mode and effects analysis
38. The ability to meet present needs without compromising those of future generations is a
concept in product design known as
a. reusability.
b. maintainability.
c. reliability.
d. sustainability. d. sustainability.
39. All of the following are principles of green product design except
a) use new materials.
b) use less materials.
c) involve the entire supply chain.
d) change the paradigm of design. a) use new materials.
40. ___________________ is a concept where companies are held responsible for their
product even after its useful life.
a. Design for disposal or reuse
b. Sustainability
c. Extended producer responsibility
d. Environmentally safe people c. Extended producer responsibility
41. With ___________________, consumers are encouraged to use the product efficiently,
repair it when possible and dispose of it responsibly.
a. green sourcing
b. green manufacture
c. recycling and reuse
d. green consumption d. green consumption
42. With ___________________, suppliers are encouraged to suggest more environmentally
friendly materials, methods and processes.
a. green sourcing
b. green manufacture
c. recycling and reuse
d. green consumption a. green sourcing
43. Design for the environment includes all the following concepts except
a. design for disposal or reuse.
b. sustainability.
c. extended producer responsibility.
d. environmentally safe people. d. environmentally safe people.
44. Quality function deployment (QFD) is
a. a software systems that uses computer graphics to assist in designing products.
b. a systematic approach to analyzing the causes and effects of product failures.
c. a visual method for analyzing the interrelationships among failures.
d. a structured process that translates the voice of the customer into technical design
requirements. d. a structured process that translates the voice of the customer into technical
design requirements.
45. A structured process that translates the voice of the customer into technical design
requirements is known as
a. quality function deployment (QFD).
b. failure mode and effects analysis (FMEA).
c. concurrent design.
d. robust product design. a. quality function deployment (QFD).
46. Which of the following is a quantitative measure of maintainability?
a. design for manufacture (DFM)
b. mean time to repair (MTTR)
c. mean time between failures (MTBF)
d. quality function deployment (QFD) b. mean time to repair (MTTR)
47. When a product is designed to withstand variations in environmental and operating
conditions, it is known as
a) robust design.
b) design for change.
c) design for modification.
d) design for tolerance. a) robust design.
48. The Taguchi Quality Loss Function implies that a
a. customer's dissatisfaction increases geometrically as the actual value deviates from the
target value.
b. customer's satisfaction increases geometrically as the actual value deviates from the target
value.
c. customer's dissatisfaction decreases geometrically as the actual value deviates from the
target value.
d. customer's preferences are strongly oriented towards conforming to specifications. a.
customer's dissatisfaction increases geometrically as the actual value deviates from the target
value.
49. As a part of design for robustness, Taguchi believes that
a. consistent errors can be more easily corrected than random errors.
b. parts within tolerance limits may produce assemblies that are not within limits.
c. consumers have a strong preference for product characteristics near their ideal value.
d. All of these answer choices are correct. d. All of these answer choices are correct.
True/False
Operations Management is only concerned with the day-to-day operations of a firm's
productive systems. False
The four primary functional areas of a firm are marketing, finance, operations, and legal.
False (Human relations)
Lean production refers to high-volume production of a standardized product. False
(Correct term is Mass Production)
Lean Production: An integrated management system that emphasizes the elimination of waste
and the continuous improvement of operations.
The most current era in the evolution of operations and supply chain management is
sustainability. True
Firms compete in the marketplace based on cost, speed, quality, and flexibility. True
The fundamental objective of Six Sigma is to focus on improvement by reducing process
variation. True
The Deming Wheel is also known as the plan-do-act (PDCA) cycle. True
The probability that a product will operate properly within an expected time frame is known
as quality of performance. False (Correct term is reliability)
The cost of measuring, testing, and analyzing are collectively known as appraisal costs.
True
One principle of total quality management (TQM) is that upper management is solely
responsible for providing the leadership of quality. False
Two team approaches to quality improvement are quality circles and process improvement
teams. True
Comparing a product or process against the best-in-class is known as reverse engineering.
False (correct term is benchmarking)
A product's reliability is a function of the reliabilities of its component parts, but not a
function of how those parts are arranged. False
Concurrent design may involve simultaneously designing products and their production
processes. True
Quality function deployment (QFD) consists of a series of matrix diagrams that define
product design changes and the ramifications of implementing those changes. True
Test Two T/F
Producing a high volume of a single product is a characteristic of batch production.
False
Companies that control the production of virtually all of the parts that go into a product are
said to be horizontally integrated. False (Vertical Integration)
Outsourcing occurs when a company cannot or will not make all the parts that go into a
product. True
One-of-a-kind production of a product based on a customer's unique specifications is a called
a project. True
Mass production is characterized by high volumes of a customized product for mass market
False (Standardized product)
Breakeven analysis examines the cost tradeoffs associated with demand volume when
selecting a process. True
(volume, cost, revenue, profit)
Profit sharing involves the distribution of a task's time equally to all workers. False
A process layout groups similar activities together according to the functions they perform.
True
Ergonomics as applied to the workplace is fitting the task to the person. True
Cycle time refers to the maximum amount of time a product is allowed to spend at each
workstation. True
Line balancing is constrained by precedence requirements and cycle time restrictions.
True
The center of gravity technique outlines a method for identifying and weighing important
location factors. False (Load distance)
Job rotation often requires cross training of employees True
Empowerment involves giving employees the authority and responsibility to innovate and act
on their own. True
While still an important issue, diversity issues in US companies is on the decline. False
Multiple Choice (Test 1)
Operations management is concerned with the__________of a firm's productive systems.
A) Design
B) Operation
C) Improvement
D) All of these answer choices are correct D) all of the above
Which of the following is not an event or concept associated with the quality revolution?
A) TQM (total quality management)
B) Internet
C) Six Sigma
D) JIT B) Internet (Look Up)
Dividing a job into a series of small tasks, each performed by a different worker, is known as:
A) Craft production
B) Scientific management
C) Division of labor
D) Interchangeable parts C) Division of labor
Mass production is well suited to all of the following except:
A) producing large volumes of goods quickly.
B) adapting quickly to changes in market demand.
C) producing standardized products for a large scale market.
D) All of these answers are correct. B) Adapting quickly to changes in market demand
Companies go global to:
A) take advantage of favorable costs
B) to keep abreast of trends and access new technologies
C) to build reliable sources of supply
D) all the above D) all the above
Companies that compete on________are able to produce a wide variety of products in
response to customer needs.
A) cost
B) speed
C) flexibility
D) quality C) flexibility
The balanced scorecard examines a firm's performance in all the following critical areas
except:
A) finances
B) customers
C) processes
D) all the above D) all the above
All of the following are parts of DMAIC except:
A) define
B) measure
C) analyze
D) improvise D) improvise
W. Edwards Deming's overall philosophy for achieving quality is embodied in:
A) his 14 points
B) his statement of purpose
C) his use of statistical control
D) none of these answer choices A) his 14 points
________failure costs include scrap, rework, and downtime.
A) external
B) internal
C) process
D) system B) internal
Which of the following quality tools display major causes of poor quality on a graph?
A) process flow chart
B) fishbone diagram
C) histogram
D) scatter diagram D) scatter diagram (Look Up)
The six sigma quality goal is 3.4 defects per___________opportunities
A) hundred
B) thousand
C) million
D) billion C) million
The Baldridge Award was created in 1987 to________in the US
A) stimulate growth of quality management
B) stimulate economic growth
C) recognize the best quality gurus
D) None of these are correct A) stimulate growth of quality management
Carefully dismantling and inspecting a competitor's product to look for design features that
can be incorperated into your own product is known as:
A) concurrent design
B) design for manufacturability
C) benchmarking
D) reverse enineering D) reverse engineering
Creating a preliminary design that can be quickly tested and then either discarded or further
refined is referred to as:
A) benchmarking
B) rapid prototyping
C) concurrent design
D) Perceptual mapping B) rapid prototyping
M/C Problems Test 1
Telco Inc, A manufacturing firm, is calculating its monthly productivity report.
Labor Rate: $20
Machine Rate: $15
Units produced: 50,000
Labor Hours: 4,000
Machine Hours: 2,000
Cost of materials: $20,000
Cost of energy $5,000
Stage 1: 0.95
Stage 2: 0.95
Stage 3: 0.93
Stage 4: 0.97
How many units must the company put into production each day to achieve a daily yield of
350 good units?
A) at least 1.00
B) at least 0.896
C) at least 0.736
D) at least 0.534 B) 0.896
M/C test two
Variable demand and small-to-moderate quantities produced to-order are characteristic
usually associated with which of the following:
A) mass production
B) continuous production
C) projects
D) batch production D) batch production
Process flowcharts document:
A) productive activities.
B) non-productive activities
C) both productive and nonproductive activities
D) none of these answers is correct C) both productive and nonproductive activities
Which type of facility is large and expensive?
A) light-industry facilities
B) retail and service facilities
C) heavy-manufacturing facilities
D) medium-site facilities C) heavy-manufacturing facilities
A graph that reflects the fact that repetition of tasks improves worker performance is referred
to as a:
A) process flow chart
B) a learning curve
C) man-machine chart
D) value chain flowchart B) a learning curve
Motion study, the study of the individual human motions used in a task, was developed by:
A) Henry Ford
B) F.W. Taylor
C) Frank and Lillian Gilbreth
D) Fredrick Herzberg C) Frank and Lillian Gilbreth
M/C Problems Test Two
A company is considering producing a product for a new market. The fixed cost required for
manufacturing and delivering the product is $50,000. Labor and material costs are estimated
to be approx $25 per product. If the product is sold for $35.00 each, the firm's breakeven
volume would be:
A) 50,000 units
B) 5,000 units
C) 2,500 units
D) 500 units
Process A:
Fixed Cost: $500,000
Variable Cost per unit: $25.00
Process B:
Fixed Cost: $750,000
Variable Cost per Unit: $23.00
For what level of volume (output) would the firm prefer Process A to Process B?
A) for all volume levels greater than 75,000
B) for all volume levels greater than 97,500
C) for all volume levels greater than 117,500
D) for all volume levels greater than 125,000 D) for all volume levels greater than
125,000
A company has a target output rate of 40 units every five (5) hours when its line is fully
operational. To achieve this target the firm must have a cycle time of:
A) more than 12.50 minutes
B) more than 10.00 minutes
C) 7.5 minutes or less
D) 8 minutes or less C) 7.5 minutes or less
An assembly line consists of three workstations (WS) with each station's activity time as
shown.
2:
X2=100
Y2=400
W2=205
3:
X3=500
Y3=300
W3=300
The coordinates for the new warehouse suggested by the center-of-gravity method are:
A) x=311.4 and y=309.4
B) x=309.4 and y=311.4
C) x=291.2 and y=198.9
D) x=193.2 and y=219.4 B) x=309.4 and y=311.4
A prospective equipment investment in your plant has a purchase cost of $50,000 and it will
produce $15,000 in annual savings. The yearly operating & maintenance costs are estimated
to be $7,000. After 5 years the project will end and the equipment sold for 10% of purchase
cost. If interest is 10% and using the net present worth method, which of the following is
correct:
(50,000+18,000)*(3.791)+5,000(0.6209) = -16,567.5
A cellular manufacturing layout is being proposed for a textile plant that incorporates non-
wovens, and machines for tufting, knitting, and weaving. In-all the equipment cost is
estimated to be $1.5 million. If the cell is invested in it is anticipated that there will be
reduced quality costs, improved manufacturing efficiencies, labor cost savings, and increased
profitability. Together these effects will result in an annual positive cash flow of $300,000 the
first year, and then will increase by $200,000 each year thereafter. If the firm uses a Payback
Period guideline of 5 years for such technology investments, what is the payback for the cell
investment; and should you invest?
0.95-0.93
If both components must function for the product to function, then the product's overall
reliability is:
A company produces a product consisting of two components arranged as follows:
R1-R2
If both components must function for the product to function, then the two components
would need individual reliabilities of _______ to achieve an overall reliability of 0.90. R1
= 0.95 and R2 = 0.95
The overall reliability of the following system is
0.85 0.89
0.90 0.94 0.93 0.919
A product consists of three components arranged as follows:
R1= ? R2= 0.94 R3=0.98
If all three components must function for the product to function, and the product's overall
reliability must be at least 0.92, then the reliability of the first component, R1, must be: at
least 0.999
The LawnPlus Fertilizer Company distributes fertilizer to various lawn and garden shops.
The company must base its quarterly production schedule on a forecast of how many tons of
fertilizer will be demanded from it. The company has gathered the following data for the past
three years from its sales records.
Select the correct graph for the above provided demand data.
An up and down movement in demand that repeats itself over a lengthy time span is a:
Cycle
If a company's product demand is 100 units in month 1, 75 units in month 2, 110 units in
month 3 and 50 units in month 4, its 4-month moving average for month 5 is: 83.75
If a company's product demand is 100 units in month 1, 75 units in month 2, 110 units in
month 3 and 50 units in month 4, and it weights the month 1 demand 0.10, month 2 demand
0.20, month 3 demand 0.30, and month 4 demand 0.40, its 4-month weighted moving average
for month 5 is:
Forecasting customer demand is often a key to providing good quality service. True
Given the following demand data for the past five months, the four-period moving average
forecast for June is
Period Demand
January 120
February 90
March 100
April 75
May 110 93.75
Given the demand and forecast values below, the naïve forecast for September is
Two things that contribute to a firm's becoming leaner are __________ and __________.
A) automation; push systems
B) modular design; standard parts
C) pull systems; automation
D) large supplier base; push systems
Suppose a firm gets one-fourth of its sales from product A, one-fourth from product B, and
the rest from product C. Rather than producing to this schedule - ABCC - a lean firm might
produce in this schedule - ACBC. This is an example of:
A) lean leveling
B) loaded sequencing
C) level loading
D) sequenced leveling
C) level loading
The term that relates to matching the output rate with customer demand in a lean system is:
A) fill rate.
B) takt time.
C) closed-loop JIT.
D) single-minute exchange of die. B) takt time.
Which one of these is a system of lights used to signal problems in a lean production system?
A) SMED
B) andon
C) kanban
D) jidoka
E) muda D) jidoka
Which of the following would you not expect to see in a lean production system?
A) a flexible system
B) frequent schedule changes
C) little waste
D) low setup times
E) low inventory B) frequent schedule changes
assembly line
a product layout where a sequence of operations and tasks is performed on the end item at
workstations strategically located at points along the length of the line.
automation
machinery that has sensing and control devices that enable it to operate automatically.
balance delay the percentage of idle time of a line.
batch processing
layouts for the production of a moderate variety of end items in batches.
cellular production
layouts in which machines are grouped into a cell that can process items that have
similar processing requirements.
cycle time
the maximum time allowed at each workstation to complete its set of tasks on a unit.
fixed-position layout
layout in which the product or project remains stationary and workers, materials and
equipment are moved about as needed.
group technology
grouping items that have similar design or processing characteristics into part families.
job shop
layouts for the production of a low volume of each of a large variety of goods (or services).
line balancing
the process of assigning tasks to workstations in such a way that the workstations have
approximately equal time requirements.
manufacturing cell
a group of workstations dedicated to production of a limited number of similar parts.
Muther grid
a chart that displays an index of closeness ratings for every pair of departments or work
centers. It is used to assign work centers to positions in a process layout.
operating time
clock time available in a day of production, after subtracting scheduled stops and breaks.
outsource
obtaining goods or services from an external provider.
precedence diagram
a diagram that shows the sequence of tasks to be performed on a unit of product in an
assembly line.
process layout a layout that can handle varied processing requirements.
product layout
a layout that uses standardized processing operations to achieve smooth, rapid, high-volume
flow.
product profiling
Linking key product or service requirements to process capabilities.
project
non-routine production or developmental planning and construction with relatively long task
times for a network of tasks requiring specialized skills and services.
robot
a machine consisting of a mechanical arm, a power supply, and a controller.
task time
the time required to perform a given task on a unit of product.
technology
the application of scientific discoveries to the development and improvement of products and
services and operations processes.
technological innovation
the discovery and development of new or improved products, services, or processes
for producing or providing them.
workstation
a location on an assembly line where a series of tasks is performed on units of a product.
work center a location in a process layout where a specified group of tasks is performed on
a unit or batch of material.
T or F: At an 80% learning rate, if the first unit requires 100 labor hours, the 8th unit will
require 64 hours. False
T or F: Predetermined time standards are advantageous since they avoid needing multiple
performance ratings. True
The outputs from a work measurement study leads to developing of labor and equipment
standards that are used for all of the following except:
D) Providing accurate information for scheduling and sequencing C) Fatigue and personal
needs allowances
Allowances include time for all of the following except:
A) Poor scheduling
B) Fatigue
C) Rest periods
A) The worker is working at a pace that is 15% faster than standard time.
B) The worker is working at a pace at a is 15% slower than normal.
D) The worker needs to add 15% to the standard time. C) The worker is working at a
pace that is 15% faster than normal.
T or F: The learning curve does not apply to supervisory personnel, some skilled craftspeople
or jobs that have non-repetitive job tasks. True
The _____ states that the cost of doing any repetitive task, work activity or project decreases
as the accumulated experience of doing the job increases.
A) Deming philosophy
B)Experience curve
C)Regression method
B) Complex intellectual learning will end quicker than learning simple tasks.
A) 80% learning curves exhibit a step initial decline and then level off.
D) Are affected by a ratio of manual to machine work. C) Not used for a pricing
strategy.
Work standards:
A) A time study.
C) Work Sampling.
a. design
b. operation
c. improvement
d. All of these answer choices are correct. d. all of these answer choices are correct
2. The transformation process associated with health care is best described as
a. locational
b. exchange
c. physiological
d. informational c. physiological
3. All of the following are transformation processes discussed in the text except
a. physiological.
b. locational.
c. exchange.
d. spiritual. d. spiritual
4. Which of the following is not one of the four primary functional areas of a firm?
a. human resources
b. legal
c. marketing
d. operations b. legal
5. All of the following are responsibilities of operations managers except
b. managing inventories
c. planning production
b. Internet
c. Six Sigma
d. JIT b. internet
7. Linear programming, waiting line, simulation, and PERT/CPM are all elements of which
era of operations and supply chain management?
a) Quality Research
b) Operations Research
c) Internet Revolution
a. craft production
b. scientific management
c. division of labor
d. All of these answer choices are correct. b. adapting quickly to changes in the market
demand
12. The major factors impacting globalization of the supply chain include all the following
except
b. the Internet.
d. All of these answer choices are correct. d. all of these answer choices are correct
14. A manager of a global supply chain is concerned with all the following except
a. timeliness.
b. quality.
c. social issues.
a. labor productivity.
b. capital productivity.
c. machine productivity.
a. mass production.
b. craft production.
c. lean production.
a. 0.370
b. 0.625
c. 1.500
d. 1.667 b. 0.625
18. Telco Inc., a manufacturing firm, is calculating its monthly productivity report. From the
following data calculate the machine productivity.
a. 0..370
b. 0.625
c. 1.500
d. 1.667 d. 1.667
19. Telco Inc., a manufacturing firm, is calculating its monthly productivity report. From the
following raw data calculate the multifactor productivity.
a. 0.370
b. 0.625
c. 1.500
d. 1.667 a. 0.370
20. Snacknow, a food service firm, is calculating its monthly productivity report. From the
following raw data calculate the labor productivity.
a. 0.220
b. 0.476
c. 0.800
d. 1.000 d. 1.000
21. Snacknow, a food service firm, is calculating its monthly productivity report. From the
following data calculate the energy productivity.
a. 0.220
b. 2
c. 10
d. 20 d. 20
22. Snacknow, a food service firm, is calculating its monthly productivity report. From the
following data calculate the multifactor productivity.
a. 0.220
b. 0.476
c. 0.800
d. 1.000 c. 0.800
23. _____________ is how the mission of a firm is accomplished.
68. Strategy
69. Design
70. Positioning
70. Positioning
70. Positioning
70. Positioning
68. cost
69. speed
70. flexibility
68. cost
69. speed
70. flexibility
68. cost
69. speed
70. flexibility
68. cost
69. speed
70. flexibility
68. finances
69. customers
70. processes
71. All of these answer choices are correct. d. all of these answer choices are correct
35. The ____________ function helps strategy evolve by creating new ways of delivering a
firm's competitive priorities.
68. finance
69. marketing
70. operations
68. finance
69. marketing
70. operations
a) define.
b) measure.
c) analyze.
d) improvise. d. improvise
2. Which of the following is not a dimension of quality for a manufactured good?
a. performance
b. reliability
c. courtesy
d. durability c. courtesy
3. All of the following are dimensions of quality for manufactured products, except
a. conformance.
b. reliability.
c. durability.
d. feasibility. d. feasibility
4. The probability that a product will operate properly within an expected timeframe is the
dimension of quality known as
a. durability.
b. reliability.
c. performance.
d. serviceability. b. reliability
5. The degree to which a product meets pre-established standards is known as
a. conformance.
b. performance.
c. reliability.
a. quality of design.
b. process capability.
d. both the employees and management of the firm. d. both the employees and management
of the firm
8. W. Edwards Deming's overall philosophy for achieving quality is embodied in
a. his 14 points.
a. Outsourcing.
b. vertical integration.
c. partnering.
d. conformance. c. partnering
10. Directly involving employees in the quality management process is referred to as
a. partnering.
b. a quality circle.
c. Six Sigma.
a) training costs.
b) design costs.
a) External
b) Internal
c) Process
d) System b. internal
13. Which of the following quality tools display major causes of poor quality on a graph?
b. Fishbone diagram
c. Histogram
a. Fishbone diagram
b. Histogram
c. Scatter diagram
b. Fishbone diagram
c. Histogram
b. Fishbone diagram
c. Histogram
d. Scatter diagram a. process flow chart
17. Total quality management (TQM) was originated in the 1980s as a _____________
management approach to improve quality.
a. Korean
b. American
c. Japanese
d. European c. Japanese
Which of the following is not a basic principle of total quality management (TQM)?
a. Quality must be measured.
b. The quality standard is no defects.
c. Quality can and must be managed.
d. The producer defines quality. d. The producer defines quality
18. A ____________________ is a system that achieves customer satisfaction and
complements other company systems.
a. quality management system
b. total quality system
c. quality productivity system
d. None of these answer choices is correct. a. quality management system
19. Research has shown that companies achieving high customer satisfaction ratings
a. attract new suppliers.
b. retain existing customers.
c. attract new employees.
d. None of these answer choices is correct. b. retain existing customers
20. A relationship between a company and a supplier based on mutual quality standards is
called
a. sourcing.
b. partnering.
c. sourcing and partnering
d. None of these answer choices is correct b. partnering
21. The primary means for gathering information from customers and measuring customer
satisfaction is
a. a sampling program.
b. a phone interview.
c. feedback from competitors.
d. a survey. d. a survey
22. A(n) ____________ is the best level of quality achievement in one company that others
seek to match or exceed.
a. attribute
b. target value
c. benchmark
d. variable c. benchmark
23. _____________________ is an important measure of service quality that is not difficult
to measure.
a. Timeliness
b. Benchmarking
c. Kaizen
d. Participative problem solving a. timeliness
24. The Six Sigma quality goal is 3.4 defects per ___________________ opportunities.
a. hundred
b. thousand
c. million
d. billion c. million
25. At the heart of Six Sigma is the ____________________ strategy, a five-step process
applied to improvement projects.
a. continuous improvement
b. breakthrough
c. champion
d. None of these answer choices is correct. b. breakthrough
26. Quality costs include the cost of _____________________.
a. achieving good quality
b. poor quality
c. both achieving good quality and generating poor quality
d. None of these answer choices is correct. c. both achieving good quality and generating
poor quality
27. The cost of achieving good quality includes
a. prevention costs.
b. internal failure costs.
c. external failure costs.
d. None of these answer choices is correct. a. prevention costs
28. The cost of achieving poor quality includes
a. prevention costs.
b. appraisal costs.
c. internal failure costs.
d. All of these answer choices are correct. b. appraisal costs
1. Design can provide a competitive edge by
d. All these answer choices are correct. d. all these answer choices are correct
2. Which of the following is not a characteristic of an effective product design process?
c. ensures that customer requirements are met in the least costly and simplest manner
d. reduces the time required to design a new product or service b. maximizes the
revisions necessary to make a design workable
3. All of the following are characteristics of an effective design process except
a. a feasibility study.
b. a form design.
d. pilot runs and final tests. c. understanding the customer and identifying customer needs
5. If a firm's design process is too lengthy
d. None of these answers is correct. a. a competitor may capture market share by being first
to market
6. Carefully dismantling and inspecting a competitor's product to look for design features that
can be incorporated into your own product is known as
a. concurrent design.
c. benchmarking.
a. a market analysis.
b. an economic analysis.
a. Performance specifications
b. Benchmarks
c. Perceptual maps
d. Reverse engineering a. performance specifications
9. Creating a preliminary design that can be quickly tested and then either discarded or
further refined is referred to as
a. Benchmarking.
b. rapid prototyping.
c. concurrent design.
a. benchmarking.
b. perceptual mapping.
c. Maintainability.
d. Reliability. d. reliability
11. All of the following can improve a product's reliability except
a. rapid prototyping.
b. robust design.
c. modular design.
a. reliability.
b. usability.
c. form design.
d. None of these answer choices is correct. d. none of these answer choices is correct
18. Product lifecycle management is a software system that
b. stores, retrieves and updates design data through the lifecycle of a product.
c. retrieves the description and geometry of a design from a database, and tests and analyzes
that design on a computer screen.
d. assists in the creation, modification and analysis of design. b. stores, retrieves and
updates design data through the lifecycle of a product
1. Which of the following is not a characteristic of a service?
a. Intangible
b. Variable output
c. Difficult to emulate
a. Tangible
b. Variable output
c. Difficult to emulate
d. Perishable a. tangible
3. A grocery store is an example of a
a. service factory.
b. mass service.
c. service shop.
a. service factory.
b. mass service.
c. service shop.
b. group participation.
d. None of these answer choices is correct. c. both team work and group participation
2. Which of the following is not a serious disadvantage of scientific management?
a. workers become bored
b. opportunities to acquire new skills sets is limited
c. workers are required to perform repetitive motions
d. worker output is increased d. worker output is increased
3. Motivation is a willingness to work hard because doing so
a. satisfies employer needs.
b. satisfies employee needs.
c. satisfies both employee and employer needs.
d. None of these answer choices is correct. b. satisfies employee needs
4. Which of the following elements has not been shown to improve motivation?
a. fair treatment of workers
b. negative feedback and punishment
c. empowerment
d. restructuring of jobs b. negative feedback and punishment
5.All of the following are advantages of task specialization except
a. increased output.
c. reduced boredom.
b.job rotation.
b.empowerment.
a. Cross training
b.Empowerment
c. Job rotation
b.higher productivity.
c. abuse of power.
a. responsibility
b. authority
c. both responsibility and authority
d. None of these answer choices is correct. c. both responsibility and authority
13. Advantages of telecommuting include all of the following except
a. reduced turnover.
a. task analysis.
b.worker analysis.
c. environmental analysis.
d.All of these answer choices are correct. d. all of these answer choices are correct
20. Determining how tasks fit together to form a job is referred to as
a. worker analysis.
b.task analysis.
c. environmental analysis.
a. Task analysis
b. Worker analysis
c. Methods analysis
a. Cross training
b.Empowerment
c. Alternative workplace
a. process flowchart.
b.worker analysis.
c. task analysis.
a. globalization.
b.quality management.
c. scientific management.
b.gainsharing.
c. profit sharing.
d.overtime. b. gainsharing
107. The two traditional forms of employee compensation include
a. hourly wage and individual incentive.
b. hourly wage and profit sharing.
c. salary and individual incentive.
d. hourly wage and gainsharing. a. hourly wage and individual incentive
108. In a piece-rate wage system a worker's pay is based on
a. total output.
b. job rating.
c. job classification.
a. motivation.
b.worker analysis.
c. ergonomics.
a. methods analysis
b technology analysis
c environmental analysis
a. Henry Ford.
b.F. W. Taylor.
a) Learning curves
b) Process curves
c) Learning charts
Which of the following are characteristics of an effective product design? match product
characteristics with customer requirements, ensure requirements are met in a costly manner,
and reduce time required to design new product or service
All of the following are characteristics of an effective design process meeting customer
requirements in the least costly manner, matching product or service characteristics with
customer requirements, minimizing the number of revisions needed to make the design
workable
The design process begins with understanding the customer and identifying customer
needs
Carefully dismantling and inspecting a competitor's product to look for design features that
can be
incorporated into your own product is known as reverse engineering
Creating a preliminary design that can be quickly tested and then either discarded or further
refined is referred to as rapid prototyping
The probability that a product will perform its intended function for a specified length of time
under normal
conditions is called realiabiltiy
Which of the following is a quantitative measure of maintainability? Mean time to
repair
Which of the following is a quantitative measure of reliability? Mean time between
failures
All of the following can improve a product's reliability simplifying product design,
improving individual component reliability, and adding redundant components
Simultaneously designing new products and the processes to produce them is known as
concurrent design
Combining standardized building blocks in different ways to create unique finished products
is known
as modular design
Failure mode and effects analysis (FMEA) isa systematic approach to analyzing the causes
and effects of product failures
Quality function deployment(QFD) is structured process that translates the voice of the
customer into technical design requirements
A structured process that translates the voice of the customer into technical design
requirements is known
as quality function deployment (QFD)
Fault tree analysis (FTA) is a visual method for analyzing the interrelationships among
failures
Which of the following will improve design for manufacture and assembly?
minimizing the number of parts and subassemblies, using standard parts when
possible, and designing parts for many, varied uses
As a part of design for robustness Taguchi believes that consistent errors can be more
easily corrected than random errors, parts within tolerance limits may produce assemblies
that are not within limits, and consumers have a strong preference for product characteristics
near their ideal value
The ability to meet present needs without compromising those of future generations is a.
concept in product
design known as: sustiainability
All of the following are principles of green product design Use less materials, involve the
entire supply chain, and change the paradigm of design
Feedback: It is used to show what parent items have generated the demand for a component.
With lot-for-lot ordering, planned order releases equal net requirements. True
Planned order releases and planned order receipts must be equal. True
Planned order releases differ from planned order receipts in terms of timing, but not in terms
of quantity. True
A bill of materials contains a listing of all the materials needed to produce an item.
True
Capacity requirements planning involves determining short-range capacity requirements.
True
A regenerative system updates MRP records continuously. False
Feedback: It refers to exploding an end items bill of materials to determine the quantities of
components that were used to assemble it.
The planned order releases at each level of MRP are one determinant of the gross
requirements at the next lower level. True
MRP is typically part of an ERP system. True
MRP is primarily used in this setting: batch
Which of these describes lot sizing? Determining how much to order
In MRP, planned order receipts must always equal planned order releases
Which is true about scheduled receipts? They are orders previously placed, and not yet
completed or received.
In MRP, the listing of all the subassemblies and components needed to produce a unit of an
end item is called the: bill of materials
Which one is not a primary report for MRP? Exceptions.