FIR No:

Bureau Veritas FIELD INSPECTION REPORT JSL/KAN/OGC/92091/FIR/014


(India) Private Limited
BVIL REF: IND.A.4.20.0177 R1 BVIL Date: 17/06/2021

ti@Project: Central 48’’ Rich and Lean Gas Segregation


Manufacturer: M/s. Jindal Saw Ltd.
Pipe Line Project
Supply Intended For: OQ Gas Network (OGC) Order No/ LOA No: OGC-21-2019-LOA-92091
Inspection Ordered By: M/s. Jindal Saw Ltd. Place with: OQ Gas Network (OGC) to Jindal Saw Ltd.
Supplier: M/s. Jindal Saw Ltd. Supply / Item: Bare LSAW Pipes
Performing Office (PO): BV – Gandhidham Contracting Office (CO): BV – Ahmedabad
Drawing No: -N.A.- Rev.: -N.A.- ITP No. : Q-OGC-2020NS Rev. : C Dated : 07/07/2020

A] Measuring Instruments Used (including satisfactory verification of suitability)


 Please refer Plant Calibration Record Report No. JSLM/ICR/J3/21/016 Dated 25.04.2021
 Please refer Lab Calibration Record Report No. JSLM/LAB/CALIBRATION LIST/2021/08 Rev.00 Provided Dated 25.04.2021
 Please refer NDT Equipment Calibration Record updated on Dated 23.04.2021

Quantity Offered: Quantity Accepted: Quantity Rejected:


As per “Today’s Qty” of Table – 1 As per “Today’s Qty” of Table – 1 Nil

TABLE – 1: LOA Status (Cumulative Qty is accepted qty from Final Visual & Dimensional Inspection)
Ordered
Ordered Previous Today’s Cumulative Balance
Qty
Qty Qty Qty Qty Qty
Sr. combined %
Item Description
No. In Meters In Meters In Meters Completed
In In
(No's of (No's of (No's of In Meters
Meters Meters
Pipe) Pipe) Pipe)
48" Pipe, 20.6 mm WT, API 5L
1 4200 0.000 0.000 0.000 0.000 0.00%
Gr. X70MS / L485MS, PSL2, SAWL
26700
48" Pipe, 20.6 mm WT, API 5L
2 22500 0.000 0.000 0.000 0.000 0.00%
Gr. X70MS / L485MS, PSL2, SAWL
48" Pipe, 23.8 mm WT, API 5L
*** 3 39000
Gr. X70MS / L485MS, PSL2, SAWL
48" Pipe, 23.8 mm WT, API 5L 39670 39638.124 85.181 39723.305 0.000 100.00 %
*** 4 300
Gr. X70MS / L485MS, PSL2, SAWL
48" Pipe, 23.8 mm WT, API 5L
*** 9 370
Gr. X70MS / L485MS, PSL2, SAWL
48" Pipe, 27.0 mm WT, API 5L
*** 5 60
Gr. X70MS / L485MS, PSL2, SAWL
338 261.120 0.000 261.120 76.880 77.25 %
48" Pipe, 27.0 mm WT, API 5L
*** 8 278
Gr. X70MS / L485MS, PSL2, SAWL
52" Pipe, 28.6 mm WT, API 5L
6 72 72 73.555 0.000 73.555 -1.555 100 %
Gr. X70MS / L485MS, PSL2, SAWL
48" Pipe, 34.0 mm WT, API 5L
*** 7 36 36 60.725 0.000 60.725 NIL 100.00 %
Gr. X70MS / L485MS, PSL2, SAWL
16" Pipe, 10.0 mm WT, API 5L
10 60 60 0.000 0.000 0.000 0.000 0.00%
Gr. X70MS / L485MS, PSL2, SAWL
*** - Total Completed % acceptable subject to test results of Mechanical test results of MPQT and RP.

Production Status - For Production status please see on Daily Production report.

B] Details of Inspection Carried out :


For Regular Production Pipe Size: 48” OD X 23.80 MM WT,
 Random witnessed product chemical analysis for weld metal as per ITP Sr.No.15.A.2 - Found within acceptable
limit.
 Random witnessed tensile test (Longitudinal & Transverse) for product base metal as per ITP Sr.No.15.A.3-
Found meeting the requirements.
 Random witnessed transverse tensile test for weld metal as per ITP Sr.No.15.A.4- Found meeting the
requirements.
 Random witnessed Charpy V- notch impact test for Pipe Base, Weld and HAZ (FL, FL+2, FL+5) as per ITP
Sr.No.15.A.5- Found meeting the requirements.
 Random witnessed DWTT test at 0 ‘C as per ITP Sr.No.15.A.6- Found meeting the requirements.
 Random witnessed Guided bend test as per ITP Sr.No.15.A.7- Found satisfactory.

Format FIR r5 – 19th Aug 2015 Page 1 of 2


FIR No:
Bureau Veritas FIELD INSPECTION REPORT JSL/KAN/OGC/92091/FIR/014
(India) Private Limited
BVIL REF: IND.A.4.20.0177 R1 BVIL Date: 17/06/2021

B] Details of Inspection Carried out :


 Random witnessed Hardness test as per ITP Sr.No.15.A.8- Found meeting the requirements.
 Random witnessed Macrograph examination as per ITP Sr.No.15.A.9- Found meeting the requirement.
Note: - 34mm WT weldability testing completed.
Identification: Nil
Remark: Photographs not attached due to USB access not permitted to JSL premises.

Attending Inspectors: Kaushikkumar Patel & Nimesh Patel (Day Shift) & Mohit Solanki (Night Shift)
Category: (1) Accepted, (2) Conditionally Accepted, (3) Re-Inspection Required, (4) Rejected, (5) Advice / Instruction from Client Required.
Inspection Date(s):
ANY NON Yes
05/06/2021 to
CONFORMITY
16/06/2021
FOUND? No

Complete
Inspection Place(s):
ORDER
JCO – III, Jindal Saw Kaushikkumar Patel
STATUS
Ltd, Nanakapaya, Balance Supplier’s Signature & Date Date: 17.06.2021
Mundra Telephone No. Mobile No. +91-9687000073

Format FIR r5 – 19th Aug 2015 Page 2 of 2