Professional Documents
Culture Documents
2018 Vimy Dfs Executive Summary Capital Cost Estimate
2018 Vimy Dfs Executive Summary Capital Cost Estimate
ESTIMATE
p76-p85
Mining »» Excavator, shovel and truck fleet sizes derived from »» Mobile equipment budget pricing
mine schedule from multiple contractors
»» Ancillary equipment fleet sizes derived from review
of active open pit areas across mine schedule
Mining Infrastructure »» Advanced pit dewatering requirements designed and »» Pit dewatering equipment budget
estimated by industry specialist (Advisian) pricing from multiple vendors
»» Preliminary general arrangement and layout drawings »» Multiple quotations for earthworks,
»» Preliminary design and material take-offs by concrete and structural scope items
experienced civil engineer »» Multiple vendor prices for equipment
and buildings
Earthworks »» Detailed Light Detection and Ranging (LIDAR) survey »» Budget pricing from multiple
»» Soil and foundation geotechnical assessment contractors
»» Preliminary 3D modelling to determine bill of quantities
Concrete »» Preliminary general arrangement and layout drawings »» Sole source quotation for all-in
»» Preliminary design and material take-offs by experienced unit rate to supply and install,
civil engineer including mobilisation and demob
costs of the batching plant
Structural »» Preliminary general arrangement and layout drawings »» Multiple quotations for all-in rates to
of major steel structures to determine bill of quantities supply, fabricate, paint and deliver
Equipment »» Equipment sizing based on project mass balance »» Multiple vendor budget prices for
derived from process design criteria major equipment (>$50k)
»» Specifications and data sheets developed for all »» In-house database for minor
major equipment and packages equipment (<$50k)
Continued...
Platework »» Fabricated platework component list (covering tanks, »» Multiple quotations for supply,
bins, chutes and launders) developed from project fabrication, surface preparation
mass balance and painting
»» Preliminary general arrangement and layout drawings »» Leach and RIP tank datasheets
to determine bill of quantities issued for multiple quotations
»» Materials of construction determined from corrosion to supply, fabricate, transport to
coupon testing site and erect
Piping »» Preliminary line and valve lists developed »» Supply rates from multiple piping
from piping and instrumentation diagrams suppliers for various specification
»» Piping quantities and pipe supports calculated from pipes, valves and fittings
layout drawings
»» Overland piping quantities calculated from
layout drawings
Electrical & »» Electrical, instrumentation and control quantities »» Budget pricing for major electrical
Instrumentation compiled from single line diagrams, instrument components including transformers,
list, piping and instrumentation diagrams, layouts, switchrooms, motor control centres,
equipment list and electrical load list and variable speed drives
»» Switchroom requirements based on substation »» Budget pricing for supply and
general arrangements installation of overhead powerlines
»» In-house database used for
electrical cabling, cable ladders,
instrumentation and instrument
control cabling
Buildings »» Floor plans developed for all buildings and workshops »» Multiple budget quotes including
»» Accommodation village building specification developed supply, installation and freight
Installation Labour »» I nstallation man-hours estimated for each equipment »» GRES construction labour rates
and fabrication item to be installed used for civil, structural, mechanical
and piping
»» GRES site installation rates used
for electrical, instrumentation and
control system
Project Indirect Costs »» EPCM estimate based on man-hours required for »» GRES commercial rates used for
engineering and project delivery team EPCM disciplines required
»» EPC allowance estimated by applying a margin to all »» Multiple quotations for flights, meals
costs identified as EPC associated costs and accommodation services
Growth Allowance »» Growth allowance commensurate with level of »» Overall growth allowance estimated
engineering completed and estimating confidence for for pre-production, process plant
each item within capital estimate and infrastructure is 6.7% of direct
capital cost
Contingency & »» Owner’s contingency is provision for unforeseen costs »» Owner’s contingency estimated
Owner’s Costs associated with project execution risk based on Monte Carlo analysis for all
»» Owner’s costs include allowances for owner’s project major components of the project
team, insurances, approvals, computing system, home »» Owner’s cost developed from
office costs, systems development and training quotations and first principles
7%
7%
11%
MINING
PRE-PRODUCTION CAPITAL Table 11.3: Pre-production Capital Estimate
Costs associated with the pre-production mining
prior to Year 1, Month 1 were developed by Mining Capital
Plus and are summarised in Table 11.3. These operating Expenditure Year -1 Year 0 Total
costs include a full complement of management and Area (A$M) (A$M) (A$M)
supervision to support the mining operation as soon as Labour 3.7 15.1 18.8
it commences. The costs also include the maintenance
personnel which are mobilised in line with the delivery Fuel 0.6 9.2 9.8
of the mining fleet. Other (variable) 0.6 5.4 6.0
»» SAG milling;
»» Leach feed thickener;
»» 6-stage uranium leach circuit;
»» 8-stage RIP circuit;
»» Resin elution;
»» Resin elution reagents make-up;
»» UF/NF plant;
»» 4-stage Uranyl peroxide precipitation circuit; and
»» Uranyl peroxide thickening, washing, drying
and packaging.
+11 -15
+4
+11 -9
Capital Cost (A$M)
-13
504 -21 +22
493
S
us
rip
ce
S
an
an
ct
st
ur
PF
DF
eo
an
st
Co
re
Pl
Pl
ct
e-
an
w
di
ru
als
id
Pr
r’s
lo
In
st
ell
Ac
Al
et
ne
ra
&
isc
M
nf
th
w
ng
M
tI
w
se
O
ini
an
ro
Ba
G
Pl