Assignment # 3 - Villanueva

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Assignment no.

CM 654
CONSTRUCTION QUALITY MANAGEMENT
Under the supervision of:

Engr. Joseph Raniel A. Bianes, RMP

Submitted by : Villanueva, Marcelino Alvin S.


Student no. : 2020-16526-MN-0
Section : MSCM-LOC-1-1-B

1|P a ge
Introduction to

METHOD STATEMENT

Installation of structural column for Ayala Triangle Gardens

Master of Science in Construction Management

Polytechnic University of the Philippines – Open University System

Polytechnic University of the Philippines

July 2021

2|P a ge
II. TABLE OF CONTENTS

1. INTRODUCTION 4
1.1. SCOPE AND PURPOSE 4
1.2. REFERENCES 4
2. QA, ENVIRONMENTAL & SAFETY CLASSIFICATION FOR SUBCONTRACTORS 5

3. CLASSIFICATION FOR THE MATERIALS 6


4. METHOD / CONSTRUCTION / INSTALLATION SEQUENCE 6

4.1. GENERAL 6
4.2. SEQUENCE OF WORK 6
4.3. ERECTION 8
5. REPAIR / REMEDIAL METHODS 9
5.1. MATERIAL 9
6. CONTROL / STORAGE / PROTECTION OF SPECIFIC MATERIALS 9

6.1. MATERIAL RECEIVING 9


6.2. MATERIAL HANDLING 10
6.3. MATERIAL STORAGE AND PROTECTION 10
7. SAFETY REQUIREMENTS AND JOB HAZARD ANALYSIS 10
7.1. ELEMENTS OF ENVIRONMENT SAFETY & HEALTH PLAN (ES & H) 10

7.2. MEDICAL 10
7.3. HAZARD MANAGEMENT 10
7.4. HAZARD NOTIFICATION 11

7.5. PERSONAL PROTECTIVE EQUIPMENT 11


7.6. JOB HAZARD ANALYSIS 11
8. INSPECTION, TEST & APPROVAL PLAN (ITAP) 11

8.1. QUALITY INSPECTION 11

3|P a ge
1. INTRODUCTION

This Method Statement refers to the installation of the Structural Steel Column for Hotel Tower
Crown at 24th Level Penthouse.

To guarantee that this Method Statement and the associated Inspection, Test, and Approval Plan
(ITAP) are implemented effectively by all parties involved, including Subcontractors, the
processes are covered during the task initiation meeting with the respective Subcontractors.
Additionally, non-conformities identified on-site are managed & controlled per MDBI project
procedure.

1.1. SCOPE AND PURPOSE


1.1.1. Fabricate and Installation of A36 Structural Steel Grade materials
1.1.2. Supply and Install A325 Anchor Bolts and Nuts
1.1.3. Supply and Application of Non-Shrink Grout
1.1.4. Surface Preparation for Application of Primer Paint
1.1.5. Delivery to Site
1.1.6. Erection/Installation
1.1.7. In-house Non-Destructive Testing (DPT and Torque Test)
1.1.8. Provide Personal Protective Equipment for personnel
1.1.9. Mobilization and Demobilization

1.2. REFERENCES
List of relevant referenced documents:
o ATG's Quality, Safety & Environmental Management System Documents
o Interfacing Method Statements
o General / Particular Specification as listed below.
o Construction Specification for structural steel Preparation and Fabrication
1.2.1. AWS D.1.1 Structural Welding Code 1990 Edition
1.2.2. General Welding procedure
1.2.3. AISC, 9th Edition
1.2.4. Steel Structure Painting Manual, Vol. 2
1.2.5. MDBI App 2.3 Structural Specification
o Other Codes and Specification
1.2.6. ASTM - American Standard for Testing Materials
1.2.7. AISC - American Institute of Steel Construction
1.2.8. AWS - American Welding Society

4|P a ge
1.2.9. ANSI - American National Standard Institute
1.2.10. SSPC - Steel Structure Painting Council
1.2.11. AISI - American Iron and Steel Institute

2. QA, ENVIRONMENTAL & SAFETY CLASSIFICATION FOR SUBCONTRACTORS

The following subcontractors carry out the works:

ATG's QSE Classification


Name of Subcontractor Scope of Works
QA Safety Env.

Structural Steel Crown for Hotel


@ 24th level to 25th level
New Bloc Construction Inc Class 1 Class 1 Class 1
Structural Steel Crown for Office

@ 40th level

Description of MDBI’s QSE Classification:

Subcontractor with a certified and documented management system and can


prepare method statements and inspection & test plans and provide a complete
Class 1 management team and supervision for the works. Able to implement QSE risk
assessments independently and carry out the management system independently
with some supervision by MDBI.

The subcontractor must prepare and assist in the preparation and implementing
method statements and inspection & test plans. Able to carry out QSE risk
Class 2
assessments and implement the relevant parts of the MDBI management system
with some assistance from MDBI.

The subcontractor who does not have a documented management system and
cannot prepare method statements or carry out QSE risk assessments cannot
Class 3
independently implement relevant parts of the MDBI management system.
Usually, Subcontractors who only supply labor belong to this classification.

5|P a ge
3. CLASSIFICATION FOR THE MATERIALS

The main material suppliers used in this works or package are as following:

MDBI's

Material Type of Material(s) Supplier


Classification

M1 Structural Steel AMADA Co

ACER Steel

M1 Anchor Bolts ACER Steel

M1 Welding Electrodes Electro weld Manufacturing Corp

M1 Paint Globesco Inc

4. METHOD / CONSTRUCTION / INSTALLATION SEQUENCE

4.1. GENERAL
The method presented in this statement will govern the guidelines for the Erection of ATG
Diamond Structural Steel Crowns at Hotel and Office Roof Deck from Delivery, Staging,
Preparation, Lay-out, and Erection.

4.2. SEQUENCE OF WORK


4.2.1. JOB SITE PLANNING
4.2.1.1. Survey of Installation, Storage area, Delivery Pathways, and Crane
Capacity. To ascertain that there is enough space and a firm pathway for
delivery trucks and establish an unloading area for delivery trucks. In addition,
the crane capacity must be clarified and documented to determine if an
adjustment is needed in delivered materials.
4.2.1.2. Decide staging area and material storage. Choose a firm and dry location.
Materials shall be stored in designated areas and can be identified for their
specific location. It is also necessary to determine the proper delivery window
and schedule to avoid conflict on equipment used on site.

6|P a ge
4.2.1.3. Secure all necessary documents and permits for unloading and use of
tower cranes.
4.2.1.4. Before delivery on-site, NEW BLOC shall inform MDBI at least 12 hours
earlier to prepare and check the availability of the tower crane.

4.2.2. AREA PREPARATION


4.2.2.1. The area will be clear before erection and preparation of the area to avoid
trip and injury during erection.
4.2.2.2. Reference lines and Gridlines will be reflected on the area by MDBI Survey
and will be double-checked by NEW BLOC
4.2.2.3. Final Checking of site Lay-out will be conducted during curing of the
pedestal to establish center lines of each pedestal with compliance to the
approved shop drawings.
4.2.2.4. Signages and barricades will be prepared before the actual start of erection
and will be supervised by the in-house safety officer.

4.2.3. ERECTION OF LIFT-ABLE SCAFFOLDINGS USING TOWER CRANE


4.2.3.1. Scaffoldings based on approved shop drawings and calculations will be
prepared and assembled in the staging area provided to NEW BLOC
4.2.3.2. Scaffoldings will be braced and fixed using tubes, and swivel clamps will be
as per approved designs.
4.2.3.3. All parts of the scaffoldings should be fixed and inspected before lifted and
used.
4.2.3.4. Before the scaffold is lifted and positioned, it must be checked and
inspected by a certified scaffolder, NEW BLOC Safety Officer, MDBI Safety
Officer, and Supervisor.

4.2.4. ASSEMBLY OF SAFETY CATCH


4.2.4.1. Safety catch based on approved Shop drawing and calculation will be
assembled in the staging area provided to NEW BLOC.
4.2.4.2. Safety catch will be issued to be approved by MDBI Methods.
4.2.4.3. Before Safety Catch in installed, it must be checked for standards and up
to approved design.
4.2.4.4. An erection will be supervised and checked by NEW BLOC Supervisor.

7|P a ge
4.3. ERECTION
4.3.1. ERECTION OF INTERIOR AND EXTERIOR COLUMN (FR)

4.3.1.1. ANCHOR BOLT SETTING


4.3.1.1.1. Survey and Lay-out by MDBI and NEW BLOC
4.3.1.1.2. Surveyor to make sure the lay-out for anchor bolt is based on the
approved design specification
4.3.1.1.3. The installation will take effect with proper coordination with MDBI
Hotel Operation Team
4.3.1.1.4. Fixing alignment of anchor bolt by tying it to horizontal bars and or
tack weld to tie wire for proper stability
4.3.1.1.5. Avoid any welding works for vertical rebars

4.3.1.2. DELIVERY AND UNLOADING


4.3.1.2.1. Materials will be delivered and Fabricated to the capacity of the
tower crane, which will be used for unloading and erection of the
members. Based on the Tower Crane Layout, Load Chart, and the Lifting
plan provided
4.3.1.2.2. Before unloading staging area will be sorted to prevent double
handling of materials and will be sorted based on the sequence of erection
and priority
4.3.1.2.3. Timber Base will be provided on-site for proper staging and storage
4.3.1.2.4. Proper stacking will be observed

4.3.1.3. ERECTION
4.3.1.3.1. Tower Crane will erect FR Columns; proper lifting analysis will be
done to ascertain which tower will be best used for the erection
4.3.1.3.2. Lifting radius will be appropriately considered with the crane
loadings provided by MDBI as reference for lifting
4.3.1.3.3. Leveling plate will be positioned on the RC Pedestal for leveling.
4.3.1.3.4. FR Columns will be lifted using the Tower crane. Proper Tagline and
Tension wire will be fixed on the frame before lifting.
4.3.1.3.5. The frame will be lowered slowly into position and will be aligned
with the centerlines of the pedestals.
4.3.1.3.6. The frame will be guided into position. Adjustments will be made
using the nut located at the bottom and the top of the base plate.

8|P a ge
4.3.1.3.7. Once in position, tension wires will be tightened to position to
secure it in position.
4.3.1.3.8. Check the plumbness of the column and tighten the bolt to
maintain the level of the columns.
4.3.1.3.9. Removal of crane sling with the use of scaffoldings used as access
4.3.1.3.10. Erect four columns at a time before proceeding with the
installation of horizontal braced members.

5. REPAIR / REMEDIAL METHODS

The Consultant must approve all Repairs and remedial methods presented herein.

5.1. MATERIAL

5.1.1. Verify that material defects or distortion, if any, are corrected with an approved
or suitable method.
5.1.2. Application of localized heat is permitted for straightening members; this must be
done carefully so as not to exceed temperature limitations that would adversely
affect the properties of the steel quenched, and tempered steels should not be
above 1100 degrees Fahrenheit because deterioration of mechanical properties may
result from an undesirable microstructure when cooled to room temperature. Other
steel should not be heated above 1200 degrees Fahrenheit to avoid the possibility
of unwanted transportation products or grain coarsening, or both.

6. CONTROL / STORAGE / PROTECTION OF SPECIFIC MATERIALS

6.1. MATERIAL RECEIVING


6.1.1. Upon the arrival of materials at the site staging area, the material controller will
match delivery notes and verify each material's shop mark. The material controller
then reports to the site supervisor the received materials list and quality condition.
6.1.2. The site supervisor for ant damages shall visually inspect all material received at
the site. Remedial works to the damaged area should be done immediately, if
possible, to avoid delay in the erection.
6.1.3. The material Delivery Inspection form is then produced and signed off by NEW
BLOC and QA-MDBI, respectively.

9|P a ge
6.2. MATERIAL HANDLING
6.2.1. The delivery note is always enclosed with the list of supplied materials with the
project's name, location, type grade of materials, quantity, and delivery date.
6.2.2. Unloading will be done with cranes. A lifting belt with a suitable SWL and proper
certificate shall be used for unloading the materials to minimize damage. Be sure to
hook belts to components with the right no. of points.
6.2.3. Attached necessary taglines and lifting lines to the lifting components at the
bottom.
6.2.4. Proper stacking and staging will be observed.

6.3. MATERIAL STORAGE AND PROTECTION


6.3.1. Choose Firm and Dry Staging area for materials storage.
6.3.2. Materials should be stored above ground and within range of Tower Crane.
6.3.3. Upon unloading materials, proper staging and stacking will be observed to prevent
damage and wearing of paints
6.3.4. Materials shall be kept free from dirt, grease, and other foreign materials and
protected from road splash.
6.3.5. Bolts, nuts, and washers shall be suitably packed, identified, and stored in a proper
warehouse.
6.3.6. Materials should be elevated above ground level to keep water out.

7. SAFETY REQUIREMENTS AND JOB HAZARD ANALYSIS


7.1. ELEMENTS OF ENVIRONMENT SAFETY & HEALTH PLAN (ES & H)
7.1.1. These listed plan elements cover minimum areas, assessed by Project in Charge
and by the Safety Engineer.

7.2. MEDICAL
7.2.1. This must include the basic plan providing On-the-Job First Aid and Instruction for
providing and obtaining emergency medical care.

7.3. HAZARD MANAGEMENT


7.3.1. New Bloc Construction Inc. will formulate a plan to deal with recognized hazards
by any method employed in the successful elimination of hazards, i.e., designate
employee Safety Observer. or describe as a part of the duties of the named
employee.

10 | P a g e
7.4. HAZARD NOTIFICATION
7.4.1. New Bloc Construction Inc. shall make every effort to inform project personnel o
the job site of all existing hazards. This notification can be part of a pre-job
orientation or toolbox session but must be covered each day until the hazard has
been eliminated.

7.5. PERSONAL PROTECTIVE EQUIPMENT


7.5.1. The company will provide and require the use of equipment necessary to protect
from hazards of the job. The specification, selection, issue, and use of the protective
equipment will be controlled by the safety or project in charge in line with good
construction practice.

7.6. JOB HAZARD ANALYSIS (JHA)


7.6.1. Job Hazard Analysis specifically addresses common hazards or work elements
required to complete a specific job. This method identifies key job steps, tools or
equipment, and personal protective equipment (PPE) for significant and repetitive
jobs.
7.6.2. A Job Hazard Analysis (JHA) addressing the safety and health hazard risk and
subsequent hazard assessment shall be prepared for project work tasks and
operations.
7.6.3. The JHA shall be prepared by the NEW BLOC project safety and health officer. The
requirements of the JHA shall be incorporated into hazardous work permits and
project and safety and health plans as appropriate.

8. INSPECTION, TEST & APPROVAL PLAN (ITAP)


8.1. QUALITY INSPECTION
8.1.1. BOLT TIGHTENING
8.1.1.1. TORQUE WRENCH
8.1.1.1.1. A wrench containing an adjustable mechanism for measuring and
controlling the torque of turning force to be exerted is used to tighten
nuts on high-strength bolts as follows in the table.

Tension force ( KN ) Tightening Torque (Nm)


Bolt nominal diameter
(mm)
4.6 8.8 4.6 8.8

12 16 38 38 91

11 | P a g e
14 22 52 62 146

16 30 70 96 224

918 37 86 133 310

20 47 110 188 440

22 58 136 255 598

24 68 158 326 758

27 88 206 475 1112

30 108 251 648 1506

8.1.2. WELDING INSPECTION


8.1.2.1. A widely applied and low-cost inspection method is used to locate
surface-breaking defects in all non-porous materials (metals).
8.1.2.1.1. The test surface is cleaned to remove any dirt, paint, oil, grease, or
any loose scale that could either keep penetrant out of a defect or cause
irrelevant or false indications
8.1.2.1.2. The penetrant is then applied to the surface of the item being
tested
8.1.2.1.3. The penetrant is allowed "dwell time" to soak into any flaws
8.1.2.1.4. Excess penetrant is then removed from the surface
8.1.2.1.5. After excess penetrant has been removed, a white developer is
applied to the sample. The developer draws penetrant from defects out
onto the surface to form a visible indication, commonly known as bleed-
out
8.1.2.1.6. The inspector will use visible light with adequate intensity for
visible dye penetrant

12 | P a g e

You might also like