Professional Documents
Culture Documents
Question Bank - SPM - KOE-068
Question Bank - SPM - KOE-068
Question Bank - SPM - KOE-068
Department of CSE
Multiple Choice Questions
Subject Name/ Subject Code: Software Project Management (KOE-068)
Year/Semester: VI
----------------------------------------------------------------------------------------------------
UNIT I - PROJECT EVALUATION AND PROJECT
PLANNING
Q1. In problem definition, the use of the project is
a. Clarified
b. Identified
c. Elaborated
d. Distinguished
Q2. The methods and regulation used to define goals, plan and monitor tasks and resources,
identify and resolve issues, and control costs and budgets for a specific project is known as
… a. project management.
b. Software
c. Process
d. Activities
Q5) You are working in Career Ride as a project manager. What will you do to minimize the
risk of software failure?
a. Request a large budget
b. You will increase the team size
c. Track progress
d. None of the above.
Q6) Boehm suggests an approach that addresses project objectives, milestones and schedules,
responsibilities, management and technical approaches and required resources, This principle is
called as ______.
a. W3HH principle
b. WHO principle
c. W5HH principle
d. None of the above.
Q7) Effective software project management focuses on the four P’s. What are those four
P’s? a. People, performance, payment, product
b. People, product, process, project
c. People, product, performance, project
d. All of the above.
Q8) For the best Software model suitable for the project, in which of the phase the developers
decide a roadmap for project plan?
a. Software Design
b. System Analysis
c. Coding
d. Testing
Q10)) Following are the phases of Project Management Life Cycle. Arrange them in correct
order
1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and
delivery a) 3-2-1-4
b) 1-2-3-4
c) 2-3-1-4
d) 4-3-2-1
16). ___ must plan, motivate, organize and control the practitioners who do software
work. a) Project Managers
b) Senior Managers
c) Customers
d) End Users
17) Risk the combination of both the possibility of occurrence of adverse event and the impact
of such bad event. (True / False)
a) False
b) True
18. A ___ is a discrepancy between how a requirement was mentioned and how the same
requirement is implemented. (Pick right option)
a) Defect
b) Change
c) Risk
d) None of the above
19 ___ can take place at any time during the project, though the sooner the better. (Pick right
option)
a) Risk assessment
b) Risk management planning
c) Risk resolution
d) Risk prioritization
21. The Mangers use the acronym SMART while goal setting.What does SMART stand
for? a. spectacular, measurable, actionable, resourced, timely
b. specific, measurable, achievable, relevant, timely
c. suitable, measurable, actionable, reviewed, timely
d. standardized, measurable, actionable, resourced, timely
22) A ___ is a discrepancy between how a requirement was mentioned and how the same
requirement is implemented. (Pick right option)
a) Defect
b) Change
c) Risk
d) None of the above
Q23) __ can take place at any time during the project, though the sooner the better. (Pick right
option)
a) Risk assessment
b) Risk management planning
c) Risk resolution
d) Risk prioritization
Q24) _ are the people involved in or affected by project activities and include the project
sponsor, project team, support staff, customers, users, suppliers, and even opponents of the
project.
a. Managers
b. Stakeholders
c. Directors
d. Citizens
Q25). Project ____ management involves defining and managing all the work required to
complete the project successfully.
a. scope
b. quality
c. time
d. cost
Q26). Project ____ management ensures that the project will satisfy the stated or implied needs
for which it was undertaken.
a. cost
b. time
c. scope
d. quality
Q27). Project ____ management is concerned with making effective use of the people involved
with the project.
a. human resource
b. risk
c. communications
d. procurement
Q28). Project ____ management involves generating, collecting, disseminating, and storing
project information.
a. risk
b. procurement
c. communications
d. resource
Q29). What works on one project may not work on another, so it is essential for project
managers to continue to develop their knowledge and ____ in managing projects. a.
time
b. resources
c. funding
d. skills
Q30) "All project leaders use a shared road map, focusing on key business aspects of their
projects while integrating goals across all parts of the organization" describes the ____ best
practice for project delivery.
a. Use an integrated toolbox
b. Grow project leaders
c. Develop a streamlined project delivery process
d. Measure project health using metrics
Q31. ____ project management software integrates information from multiple projects to show
the status of active, approved, and future projects across an entire organization. a. Investment
b. Active
c. Enterprise
d. Budget
Q32). A ____ can have many different job descriptions, which can vary tremendously based on
the organization and the project.
a. project supervisor
b. project manager
c. job coordinator
d. project coordinator
Q33) In an interview with two chief information officers (CIOs), both men agreed that the most
important project management skills seem to depend on ____.
Q34). Achieving high performance on projects requires ____, otherwise called human relations
skills.
a. capital skills
b. soft skills
c. light skills
d. hard skills
Q35) A(n) ____ focuses on long-term goals and big-picture objectives, while inspiring people
to reach those goals.
a. assistant
b. programmer
c. leader
d. manager
Q36) A(n) ____ often deals with the day-to-day details of meeting specific
goals. a. manager
b. leader
c. programmer
d. analyst
Q37). Some people say that ____ achieve the vision of a project.
a. leaders
b. managers
c. stakeholders
d. supervisors
Q38). Most people agree that the modern concept of project management began with the
____. a. Great Wall of China
b. first space shuttle
c. Egyptian pyramids
d. Manhattan Project
Q39). During the Cold War years of the 1950s and '60s, ____ continued to be key in refining
several project management techniques.
a. NASA
b. the military
c. steel manufacturing
d. marine biology
Q40). The longest path through a network diagram that determines the earliest completion of a
project is called the ____ path.
a. essential
b. important
c. critical
d. vital
Q41) What should a project manager do or follow to ensure clear boundaries for project
completion?
a. Scope verification
b. Completing a scope statement
c. Scope definition
d. Process Management in OS
Q) 42. An organization is certified to a stringent environmental standard and uses that as the
key differentiator with its competitors. Alternative method is available but involves lot of risk.
What should the project team do?
a. Drop the alternative approach
b.Work out a mitigation plan
c. Procure an insurance against the risk
d.Plan all precautions to avoid the risk
Q43): That is the objective of project manager behind the study of the work processes on a
project.
a. Quality control
b. Quality planning
c. Checking adherence to processes
d. Quality assurance
Q44) which of the following is NOT an input to project plan
execution? a)Work authorization system
b)Project plan
c)Corrective action
d)Preventive action
Q. (45) The model serves as the basis for the creation of ______ for the
Software. (a) Design
(b) Maintenance
(c) Testing
(d) Specifications
Q48). When you build a product or system, it’s important to go through a series of predictable
steps, the process which you follow to develop it is known as________
(a)Software design
(b)Software process
(c)Software schedule
(d)Framework
Q49__contains an analysis of what went wrong, what went right, and what you could have
done better in the software project.
Select correct option:
(a)Prepare closedown report
(b)Identify learning
(c)Identify reusable software components
(d)none
Q50) The three most important factors that influence project management are ___, ___and
___. a. Time, Cost, Scope
b. Money, time, budget
c. Time, staff, budget
d. None of them
Answer Keys:
Ans1 (a)
Ans2(a)
Ans3( d )
Ans4(c )
Ans5( c )
Ans6 (c)
Ans7 (b)
Ans8 (b)
Ans9 (a)
Ans 10 ( A )
Ans 11(B )
Ans12 ( c)
Ans13 (a)
Ans14 (D)
Answer15 : b
Ans 16 .( a)
Ans 17 (b)
Ans.18 (a)
Ans. 19(a)
Ans 20. a
Ans 21.(b)
Ans.22. a)
Ans.23 a)
Ans 24 : B
Ans25 : A
Ans26 : D
Ans 27 :A
Ans28 :D
Ans29 : D
Ans 30: C
Ans 31: D
Ans 32: B
Ans33: D
Ans34: B
Ans35: C
Ans 36: A
Ans 37: B
Ans 38: D
Ans 39: B
Ans 40: C
Ans 41(b)
Ans 42(a)
Ans 43.(d)
Ans 44. a
Ans 45(d)
Ans 46(b)
Ans 47(a)
Ans 48(b)
Ans49(a)
Ans 50. a
UNIT II - PROJECT LIFE CYCLE AND EFFORT ESTIMATION
Q3) The software life cycle can be said to consist of a series of phases. The classical model is referred
to as the waterfall model. Which phase may be defined as “The concept is explored and refined, and the
client’s requirements are elicited?”
(a) Requirements
(b) Specification
(c) Design
((d) Implementation
Q4) In Intermediate COCOMO the mode that represents complex products is referred to as
a) Embedded
b) Semidetached
c) Organic
d) Multiplicative
Q5) Which one of the following models is not suitable for accommodating any
change? a) Build & Fix Model
b) Prototyping Model
c) RAD Model
d) Waterfall Model
Q6. A simple way of looking at the spiral software life-cycle model is as a waterfall model with each
phase proceeded by
a) Build-and-fix
b) Freezing
c) Synchronization
d) Testing
e) Risk analysis
Q7) __ is the least flexible and most obsolete of the life cycle models.
a) Spiral model
b) Waterfall model
c) Throwaway prototyping model
d) Iterative / incremental development model
Q8) Before requirements can be analyzed, modeled, or specified they must be gathered through
a/an_______
(a) Elicitation process
(b) Interviewing
(c) Meeting
(d) None of given
Q10) Build & Fix Model is suitable for programming exercises of ___________ LOC (Line of
Code). a) 100-200
b) 200-400
c) 400-1000
d) above 1000
Q15). Which of the following statements regarding Build & Fix Model is
wrong? a) No room for structured design
b) Code soon becomes unfixable & unchangeable
c) Maintenance is practically not possible
d) It scales up well to large projects
Q17) Which model can be selected if user is involved in all the phases of
SDLC? a) Waterfall Model
b) Prototyping Model
c) RAD Model
d) both Prototyping Model & RAD Model
Q22. The process each manager follows during the life of a project is known
as a) Project Management
b) Manager life cycle
c) Project Management Life Cycle
d) All of the mentioned
Q23 Which of the following is/are main parameters that you should use when computing the costs of
a software development project?
a) travel and training costs
b) hardware and software costs
c) effort costs (the costs of paying software engineers and managers)
d) all of the mentioned
Q24 ___________is the least flexible and most obsolete of the life cycle models.
a) Spiral model
b) Waterfall model
c) Throwaway prototyping model
d) Iterative / incremental development model
a.person month
b.monthly cost
c.person cost
d.none of them
Q26.For normalization purposes, the productivity of a project is measured in terms of ___ per person
month.
a.functions
b.function point
c.cost
d.functional point
Q 27 Which of the following is not a metric for design model?
a) Interface design metrics
b) Component-level metrics
c) Architectural metrics
d) Complexity metrics
b) Use one or more empirical models for software cost and effort estimation
c) Use relatively simple decomposition techniques to generate project cost and effort estimates
d)The ability to translate the size estimate into human effort, calendar time, and dollar Q30)
What can be used to complement decomposition techniques and offer a potentially valuable
estimation approach in their own right Automated estimation tool
c) Size-related metrics
Q32 A ------------is developed using historical cost information that relates some metrics to the project
cost.
a) Algorithmic Cost Modeling
b) Expert Juggememt
c) Estimation by Anlogy
d) Parkison’a Law
Q38) Which of the options is correct for the prototyping model of software
development? a. For projects with large development teams.
b. When requirements are well defined.
c. When a customer cannot define requirements clearly.
d. both a & b
e. All of the above
f. None of the above
Q42. Which phase of the RUP is used to establish a business case for the
system ? a) Transition
b) Elaboration
c) Construction
d) Inception
Q44) In a university, students are asked to develop software. Which model would be
preferable? a. Waterfall model
b. Spiral model
c. Agile model
d. Code and fix model
Q46.which of the following testing strategy established during requirements analysis against
developed software?
a.Validation
b.Integration
c.Regression
d.System
Q1. The entire process of a project may be considered to be made up on number of sub process placed
in different stage called the
(A) Technical key resources
(B) Work key structure
(C) Work Breakdown Structure (WBS)
(D) None of the above
Q2) Each component of the software product is separately estimated and the results aggregated to
produce an estimate for the overall job.
(A) Algorithmic model
(B) Expert judgment
(C) Bottom-up
(D) Top down
Q3 Tool used for comparison of the proposed project to complete projects of a similar nature whose
costs are known.
(A) Algorithmic model
(B) Expert judgment
(C) Top down
(D) Analogy
Q4). Which of the following states that work expands to fill the time
available. a) CASE tools
b) Pricing to win
c) Parkinson’s Law
d) Expert judgement?
Q5) A is developed using historical cost information that relates some software metric to the project
cost.
a) Algorithmic cost modelling
b) Expert judgement
c) Estimation by analogy
d) Parkinson’s Law A
Q7) wo general notations used for scheduling are ___ charts and ___
charts. a.Pert, histogram
b.PERT, gantt
c.CPM,gantt
d.none of them
Q10) Which of the following can estimate size of project directly from problem
specification? A.LOC
B.Function Point Metric
C.Bothg
D.None
Q)11. In ____, Henry Gantt developed the famous Gantt chart as a tool for scheduling work in
factories.
a. 1897
b. 1917
c. 1927
d. 1957
Q12. A Gantt chart is a standard format for displaying project schedule information by listing project
activities and their corresponding start and finish dates in a ____ format.
a. pie chart
b. line graph
c. bar graph
d. calendar
Q13) _ is the sequence of processing steps that completely handles one business transaction or
customer request
Select one:
a. Model
b. Workflow
c. Prototype
d. Mock-up
Q19) Smith is a project manager for ABC Video games. He has produced a project network diagram
and has updated the activity list. Which process have he just finished?
Select one:
a. The Activity Sequencing process, which identifies all the activities dependences b. The Activity
Sequencing process, which identifies all the specific activities of the project c. The activity duration
Estimating process, which identifies all the dependent activities of the project d. The activity
duration Estimating process, which diagram project network time estimates
Q20) Which of the following is not the technique for network planning
model ? a) PERT
b)CPM
c) Monte Carlo simulation
d) Hybrid approach tecnique
Q21) Which of the following activity is undertaken immediately after feasibility study and before the
requirement analysis and specification phase?
A.Project Planning
B.Project Monitoring
C.Project Control
D.Project Scheduling
Q22)
The particular task performance in CPM is known as
a) Event
b)Activity
c) Task
d) contract
Q24) Which of the following activity is not the part of project planning?
A.project estimation
B.project scheduling
C.project monitoring
D.risk management
Explanation
Q25) In the project planning, which of the following is considered as the most basic parameter based
on which all other estimates are made?
A.project size
B.project effort
C.project duration
D.project schedule
Q27 ) Once project planning is complete, project managers document their plan
in A.SPMP document
B.SRS document
C.Detailed Design documet
D.Excel Sheet
Q28) Which of the following serves as metrics for project size estimation?
A.Lines of codes
B.function point
C.Number of persons
D.Only A & B
Q35) Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finishing time
for the three activities are 12, 15, and 10, then what will be the earliest starting time for Y? A. 10
B. 15
C. 12
D. Cannot be determined
Q36Activities P, Q, and R instantly follow activity M, and their current starting times are 12, 19, and
10. So, what is the latest finishing time for activity M?
A. 11
B. 10
C. 18
D. Cannot be determined
a) Red
b) Blue
c) Black
d) Green
Q45. Who introduced bar chart in
CPM?
a) Jane Gantt
b) Henry Gantt
c) Williams henry
d) Joseph henry
Ans Keys:
Ans1 c)
Ans2(C )
Ans 3(D)
Ans 4(c)
Ans5 (a)
Ans.6 a
Ans 7. b
Ans. 8(a)
Ans 9 d
Ans 10 (B)
Answe11(: B)
Answer:12( D)
Ans 13(b)
Ans 14(b)
Ans 15(c)
Ans16. a
Ans 17(c)
Ans 18(c)
Ans 19(b)
Ans 20(d)
Ans 21(A)
Ans 22(b)
Ans 23(b)
Ans 24(c)
Ans 25 (:A.)
Ans 26(D)
Ans 27(A)
.Ans 28(D)
Ans 29( D)
Ans 30(B)
Ans 31(c)
Ans 32(b)
Ans 33 c
Ans 34(D)
Ans 35(B)
Ans 36( A)
Ans 37(B)
Ans 38(D)
Ans 39(a)
Ans 40(a)
Ans 41(a)
Ans 42(c)
Ans 43(b)
Ans 44(d)
Ans 45(b)
Ans 46(d)
Ans 47(d)
Ans 48 (d)
Ans 49(c)
Ans 50(b)
a) True
b) False
2. ___ manage hardware/software requirements for development, testing, validation, and production
environments.
a) Logistics
b) Labour
c) staff
d) none
4. Project Management is the application of knowledge, skills, tools and techniques to project activities
to meet the project requirements.
a) True
b) False
a) Informal
b) Formal
c) adhoc
d) general
a) True
b) False
9. The ___ stage determines the nature and scope of the development.
a) Initiation
b) Implementation
c) Planning and Design
d) Maintenance
a) two
b) one
c) four
d) none
12. The purpose of a ___ is to detail the work requirements for projects and programs that have
deliverables and/or services performed.
a) Initiation
b) Statement of Work (SoW)
c) Planning and Design
d) Maintenance
14. The three most important factors that influence project management are ___, ___and ___.
17. The _____________ documented in 1970 by Royce was the first publicly documented life cycle
model.
a) RAD model
b) Spiral model
c) Waterfall model
d) None of the above
18. Most life cycle models can be derived as special cases of the ___.
a) RAD model
b) Spiral model
c) Waterfall model
d) None of the above
19. ___ is the least flexible and most obsolete of the life cycle models.
a) Spiral model
b) Waterfall model
c) Throwaway prototyping model
d) Iterative / incremental development model
21. Project scope, pros and cons are discussed in the ___________ phase.
a) Initiation
b) Implementation
c) Planning and Design
d) Maintenance
22. A semiformal way of breaking down the goal is called the ___.
a) RAD model
b) Spiral model
c) Waterfall model
d) Work Breakdown Structure
23. Two general notations used for scheduling are ___ charts and ___ charts.
a) bar, pert
b) PERT, Gantt
c) gantt, histogram
d) None
24. The purpose of planning a project is to identify the sequence of activities as per their complexities
and dependencies.
a) True
b) False
26. In ___ mode the project is characterized by tight, stringent constraints and interface
requirements. a) Organic
b) Embedded
c) Semidetached
d) None of the above
27. Budgeting in a business sense is the __________ allocation of available funds to each department
within a company.
a) Initiation
b) Implementation
c) Planning and Design
d) planned
31. A _____________ provides the idea about the start and finishes dates of key activities or terminal
elements of the project.
a) Schedule
b) Implementation
c) Design
d) plan
a) True
b) False
36. Accelerating the project schedule is often termed as ___ of the schedule. (Pick right
option) a) Breaking
b) Crashing
c) Speeding
d) None of the above
a) Person-Months
b) Plan-Months
c) Person-Years
d) None
a) True
b) False
40. If there is a certain probability that the objectives of the project will not be achieved, this risk should
not be reported to higher management.
a) True
b) False
41. Risk the combination of both the possibility of occurrence of adverse event and the impact of such
_____ event.
a) bad
b) good
c) average
d) planned
42. When there are disagreements between the project lead and overall project manager, the same can be
resolved through ___.
a) Change control board
b) Implementation
c) Planning
d) Design
43. A ___ is a discrepancy between how a requirement was mentioned and how the same requirement is
implemented. (Pick right option)
a) Defect
b) Change
c) Risk
d) None of the above
44. Tom DeMarco stated, “You can’t control what you can’t _________”.
a) Initiate
b) Implement
c) measure
d) plan
45. ___ is the statistics gathered over the course of the execution of the project.
a) Requirement
b) Software Metric
c) Software Plan
d) Cost
46. ___ is a software package used for preparing earned value analysis. (Pick right
option) a) MS Project
b) Primavera
c) Lotus Notes
d) None of the above
47. Status meetings and status reporting are required for a medium-size project.
a) True
b) False
48. ___ is a set of practices originally developed by Motorola to systematically improve processes by
eliminating defects.
a) Six Sigma
b) four sigma
c) SMART
d) none
49. Six Sigma is a registered service mark and trademark of ___. (Pick right
option) a) Microsoft
b) Sun Microsystems
c) Motorola
d) None of the above
50. ___ involves activities like typical strategies, processes, techniques, and tools involved in containing
the adverse impacts of risks on the software project.
ANSWER KEY
1. A
2. A
3. D
4. A
5. A
6. B
7. B
8. B
9. A
10.C
11.C
12.B
13.C
14.A
15.A
16.A
17.B
18.B
19.B
20.A
21.A
22.D
23.B
24.A
25.A
26.B
27.D
28.A
29.C
30.A
31.A
32.C
33.A
34.B
35.D
36.B
37.A
38.A
39.B
40.B
41.A
42.A
43.A
44.C
45.B
46.B
47.A
48.A
49.A
50.C
UNIT-V STAFFING IN SOFTWARE PROJECTS
2. Which of the following is not included in Hackman and Oldham’s job characteristics
model ofwork motivation?
a) Variety of
skill
b)Significance of
the taskc)Quality
of job life
d)Autonomy
3. Organizational
behavior is
a)A science
b)An art
c)A science as well as an art
d)None of the above
9.The is based on the environment. Though like thinking, expectations and perception do
exist, and they are not needed to manage or predict behaviou a)Behaviouristic approach,
Cognitive processes,
b)cognitive processes, behaviouristic approach
c) Social cognitive, behaviouristic
approachd)Cognitive processes, social
cognitive
10. Now a days a lot of stress is being put on the of the employee in theorganization
a)Character
b)improvemen
tc)Behaviour
d)Rewards
11. The purpose of job enrichment is to
a)expand the number of tasks an individual can do
b)increase job efficiency
c)increase job effectiveness
d)increase job satisfaction of middle management
13. theory emphasis that, Unsatisfied need can influence the behaviour satisfied one will not
act as a motivator.
a)Maslow Theory
b)Herzberg’s Theory
c) Expectancy theory
d)Alderfer’s ERG
theory
14. Among the following which is not a problem in changing the attitude of the
employeea)Insufficient Information
b)Resistant by
employeec)Cognitive
Dissonance
d)Cognitive
Dissonance
15. Motivation
includesa)job
enrichment
b)Job rotation
c)Job enlargement
d)all of the above
20. Which of the following best defines the type of rewards that are distributed
toindividuals fortheir unique contribution to the team?
a)functional team rewards
b)competitive team rewards
c)cooperative team rewards
d)non-competitive team
rewards
22. What is the ideal size of a team in order for it to be productive and
successful?a)2 to 4
b)9 to 12
c)5 to 8
d)8 to 11
23. Which of the following best defines an organization where decision making authority is at
thetop of the organization and employees have little freedom to make their own decisions?
a)decentralized organization
b)centralized
organizationc)virtual
organization d)functional
organization
29. On her work team Michelle develops detailed tasks lists and work flow charts to help
her team members understand the steps involved in each project. She also maintains
the project calendar and receives periodic updates from each team member to ensure
that projects are progressing on schedule.Which role does Michelle most likely fill
on her team?
a)assessorb)organizerc)maintainerd)creator
33. Project managers have to assess the risks that may affect a project.
a) True
b) False
35. The process each manager follows during the life of a project is known
as a) Project Management
b) Manager life cycle
c) Project Management Life Cycle
d) All of the mentioned
37. Which of the following is/are main parameters that you should use when computing the
costs of a software development project?
a) travel and training costs
b) hardware and software costs
c) effort costs (the costs of paying software engineers and managers)
d) all of the mentioned
39. Which of the following is incorrect activity for the configuration management of a software
system?
a) Internship management
b) Change management
c) Version management
d) System management
41. An independent relationship must exist between the attribute that can be measured and the
external quality attribute.
a) True
b) False
42. Project management involves the planning, monitoring, and control of the people, process,
and events that occur as software evolves from a preliminary concept to an operational
implementation.
a) True
b) False
46. A software ________ provides the framework from which a comprehensive plan for
software development can be established.
a) people
b) product
c) process
d) none of the mentioned
47. Who defines the business issues that often have significant influence on the
project? a) Practitioners
b) Project managers
c) Senior managers
d) None of the mentioned
48. Who delivers the technical skills that are necessary to engineer a product or an
application? a) Practitioners
b) Project managers
c) Senior managers
d) None of the mentioned
49. Which of the following paradigm attempts to structure a team in a manner that achieves
some of the controls associated with the closed paradigm but also much of the innovation that
occurs when using the random paradigm?
a) asynchronous paradigm
b) open paradigm
c) closed paradigm
d) synchronous paradigm
51. Which paradigm structures a team loosely and depends on individual initiative of the team
members?
a) random paradigm
b) open paradigm
c) closed paradigm
d) synchronous paradigm
53. ___ must plan, motivate, organize and control the practitioners who do software
work. a) Project Managers
b) Senior Managers
c) Customers
d) End Users
54. The realistic percentage for striving to work in Software Project Development is
___. a) 40%
b) 80%
c) 50%
d) 100%
55. ___ organizations take the networked structure one step further by combining IT with
traditional components to form new types of components.
a) Hierarchical
b) Flat
c) T-form (Technology-based)
d) Matrix
ANSWER KEY
1. D
2. C
3. C
4. A
5. D
6. D
7. A
8. B
9. C
10. C
11. B
12. C
13. A
14. B
15. D
16. D
17. B
18. A
19. C
20. B
21. B
22. C
23. B
24. C
25. D
26. B
27. A
28. C
29. B
30. C
31. E
32.
D
33. B
34. C
35. C
36.
D
37.
D
38. B
39.
A
40. B
41. B
42.
A
43. C
44.
A
45.
D
46. C
47. C
48.
A
49. B
50.
D
51.
D
52.
D
53.
A
54. B
55. C