Professional Documents
Culture Documents
Chapter 1-: Suresh Babu Adiandhra
Chapter 1-: Suresh Babu Adiandhra
Chapter 1-: Suresh Babu Adiandhra
1
Suresh Babu Adiandhra asbabueeemtu@gmail.com
Department of Electrical and Computer Engineering, MTU, Tepi. Introduction to Power Systems- ECEG-3154
Chapter 1- Fundamentals of power systems
Voltage levels can be easily transformed in AC
AC generators and motors are simple and cheaper than that of DC.
1st 3-phase line developed in 1883 in North America and 2300V, 12km in Southern California.
In early days frequency was- 25, 50, 60, 125 and 133 Hz; was standardized as 60Hz and 50Hz in
rest of the world.
In early days Voltages were- 12, 44 and 60kV; later raised to
165kV-1922
220kV-1923
287kV-1935
330kV-1953
500kV-1965
35kV-1966--- in US-1969
The industry has standardized the voltage levels to
115kV, 138kV,161 kV and 230kV- H.V.
345kV, 500kV and 765kV---E.H.V.
>735kV ----- U.H.V.
REASONS FOR INTERCONNECTION
Generating stations and distribution systems are connected through transmission lines
The transmission system of a particular area (e.g. state) is known as a grid
Different grids are interconnected through tie-lines to form a regional grid (also called power
pools)
Different regional grids are further connected to form a national grid
Interconnected operation is always economical and reliable
o Economic advantage of interconnection is to reduce the reserve generation capacity in
each area
o If there is a sudden increase of load or loss of generation in one area, it is possible to
borrow power from adjoining interconnected area
o To meet sudden increases in load, a certain amount of generating capacity ( in each
area) known as the “spinning reserve” is required. This consists of generators running at
normal speed and ready to supply power instantaneously
Cooperative assistance is one of the planned benefits of interconnected operation
Interconnected operation also gives the flexibility to meet unexpected emergency loads
Secondary transmission:
The primary transmission terminates at Receiving station where the voltage reduced to 33kV or
66kV (depends on the amount of power to be transmitted).
From this receiving station the transmitted to large consumers by 3-ph,3-wire overhead
transmission lines and this forms the secondary transmission.
Primary distribution:
The secondary transmission line terminates at the sub-station (SS)
where voltage is reduced from 33 kV to 11kV, 3-phase, 3-wire. The 11 kV lines run along the
important road sides of the city. This forms the primary distribution. It may be noted that big
consumers (having demand more than 50 kW) are generally supplied power at 11 kV for further
handling with their own sub-stations.
Secondary distribution:
The electric power from primary distribution line (11 kV) is delivered to distribution sub-
stations (DS). These sub-stations are located near the consumers’ localities and step down the
voltage to 400 V, 3-phase, 4-wire for secondary distribution.
The voltage between any two phases is 415 V and between any phase and neutral is 230 V.
The single-phase residential lighting load is connected between any one phase and neutral,
whereas 3-phase, 415 V motor load is connected across 3-phase lines directly.
The secondary distribution system consists of feeders, distributors and service mains.
Fig. shows the elements of low voltage
distribution system. Feeders (SC or SA)
radiating from the distribution sub-station (DS) supply power to the distributors (AB, BC, CD
and AD). No consumer is given direct connection from the feeders.
Instead, the consumers are connected to the distributors through their service mains.
3
Suresh Babu Adiandhra asbabueeemtu@gmail.com
Department of Electrical and Computer Engineering, MTU, Tepi. Introduction to Power Systems- ECEG-3154
Chapter 1- Fundamentals of power systems
4
Suresh Babu Adiandhra asbabueeemtu@gmail.com