PROBLEM 1

Determine the Following using the Job Data in the Table:

a. Current contract price

b. Credit or debit to date

c. Contract value of uncompleted


work

d. Credit or debit to come

e. Estimated final gross profit

f. Estimated total project costs

g. Estimated Profit to date

Status of Jobs
Job 5 ($) Job 6 ($)
Underway
Original Contact
3800 5630
price
Contract Changes 600 -300
Total Cost to Date 1710 620
Payments received
1830 340
or due to date
Estimated cost to
2300 5000
complete

SOLUTION FOR JOB 5


CEM 303 1
Construction Cost Accounting 7
CCE
J
o
Status of Jobs
b
Underway

5
3
8
Original Contact price
0
0
6
Contract Changes 0
0
1
7
Total Cost to Date
1
0
1
Payments received or 8
due to date 3
0
2
Estimated cost to 3
complete 0
0

a. CURRENT CONTRACT PRICE


Current Contract Price=Original Contract Price+ Contract Changes

Current Contract Price=$ 3,800+ $ 600=$ 4,400

b. CREDIT OR DEBIT TO DATE


CEM 303
CONSTRUCTION COST ACCOUNTING 2
CCE 7
d. CREDIT OR DEBIT TO COME

Credit ∨Debit ¿ come=Contract Value of Uncompleted Work−Estimated Cost ¿ Complete

Credit ∨Debit ¿ Come=$ 2,570−$ 2,300=$ 2 70

e. ESTIMATED FINAL GROSS PROFIT

Estimated Final Gross Profit=Credit ∨Debit ¿ date+Credit ∨Debit ¿ come

Estimated Final Gross Profit=−$ 120+ $ 270=$ 1 50

f. ESTIMATED TOTAL PROJECT COST

Estiamted Total Project Cost =Contract Price−Gross Profit

Estimated Total Project Cost =$ 4,400−$ 150=$ 4 , 250

g. ESTIMATED PROFIT TO DATE

Estiamted Profit ¿ date=Estimated final gross profit × Proportion of work completed

Estimated Total Project Cost =$ 150 × ( $$ 1,4 ,710


250 )
=$ 60.353

CEM 303 3
CONSTRUCTION COST ACCOUNTING 7
CCE
SUMMARY OF ANSWERS FOR JOB 5

Variable Value ($)


Current Contract Price 4,400
Credit or Debit to date -120
Contract Value of 2,570
Uncompleted Work
Credit or Debit co come 270
Estimated Final Gross Profit 150
Estimated Total Project Costs 4,250
Estimated Profit to date 60.353

CEM 303 4
CONSTRUCTION COST ACCOUNTING 7
CCE
SOLUTION FOR JOB 6

Status of Jobs Underway Job 6


Original Contact price 5630
Contract Changes -300
Total Cost to Date 620
Payments received or due to
340
date
Estimated cost to complete 5000

a. CURRENT CONTRACT PRICE


Current Contract Price=Original Contract Price+ Contract Changes

Current Contract Price=$ 5,630+ (−$ 3 00 ) =$ 5,330

b. CREDIT OR DEBIT TO DATE

Credit ∨Debit ¿ date=Total costs ¿ date−Payments received ∨due

Credit ∨Debit ¿ date=$ 620−$ 340=$ 280

c. CONTRACT VALUE OF UNCOMPLETED WORK

Contract Value of Uncompleted Work =Current Contract Price−Payments received ∨due

Contract Value of Uncompleted Work =$ 5,330−$ 340=$ 4990

d. CREDIT OR DEBIT TO COME

Credit ∨Debit ¿ come=Contract Value of Uncompleted Work−Estimated Cost ¿ Complete

Credit ∨Debit ¿ Come=$ 4,990−$ 5,000=−$ 10

CEM 303 5
CONSTRUCTION COST ACCOUNTING 7
CCE
e. ESTIMATED FINAL GROSS PROFIT

Estimated Final Gross Profit=Credit ∨Debit ¿ date+Credit ∨Debit ¿ come

Estimated Final Gross Profit=$ 280+(−$ 10)=$ 270

f. ESTIMATED TOTAL PROJECT COST

Estiamted Total Project Cost =Contract Price−Gross Profit

Estimated Total Project Cost =$ 5,330−$ 270=$ 5,060

g. ESTIMATED PROFIT TO DATE

Estiamted Profit ¿ date=Estimated final gross profit × Proportion of work completed

Estimated Total Project Cost =$ 27 0 × ( $$5,060


620
)=$ 33.083

SUMMARY OF ANSWERS FOR JOB 6

Variable Value ($)


Current Contract Price 5,330
CEM 303 6
CONSTRUCTION COST ACCOUNTING 7
CCE
Credit or Debit to date 280
Contract Value of 4,990
Uncompleted Work
Credit or Debit co come -10
Estimated Final Gross Profit 270
Estimated Total Project Costs 5,060
Estimated Profit to date 33.083

I affirm that I shall not give or receive any unauthorized help on this assignment and
that all work shall be my own

PLATOON N. BEJER

CEM 303 7
CONSTRUCTION COST ACCOUNTING 7
CCE
CEM 303 8
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 9
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 10
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 11
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 12
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 13
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 14
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 15
CONSTRUCTION COST ACCOUNTING 8
CCE
CEM 303 16
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 17
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 18
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 19
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 20
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
CONSTRUCTION COST ACCOUNTING 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1
IMPORTANCE OF PROJECT MANAGEMENT INFORMATION SYSTEM 8
CCE
As a future construction project manager, why is it important to understand the
Project Management Information System? Specify at least (3) reasons. Defend your
answer.

CEM 303 1