Name: Reg No: Description:: Saad Saleem BBA173065 Project Green Homes
Name: Reg No: Description:: Saad Saleem BBA173065 Project Green Homes
Name: Reg No: Description:: Saad Saleem BBA173065 Project Green Homes
1
Contents
Introduction:..................................................................................................................................3
Project Scope Statement of a Green House.............................................................................3
Project Objective........................................................................................................................3
Project Communication Plan:...................................................................................................3
Responsibility Matrix:...........................................................................................................4
Time and cost Estimation......................................................................................................4
2
ACKNOWLEDGMENT
3
Introduction:
The Green Homes project is a sustainable housing project introduced by UN-Habitat, Federation of
Nepalese Chambers of Commerce and Industry (FNCCI), CEN, ENPHO, IHS and SLTDC with support of
European Union to promote sustainable housing in Nepal. The project proposes to use green building
techniques such as green construction materials, passive solar design, energy efficiency, rooftop farming, and
effective waste and water management.
The objective of this project is to build a high-quality, Leadership in Energy and Environmental
Design (LEED)-certified, single family house in Colorado within 9 months. This initial estimate is
based on a modification to the average timeframes derived from the 2019 Survey of Construction as
reported by the National Association of Home Builders. The home will be built from sustainably
sourced material wherever possible and include features in the deliverable list to reduce the
occupants’ long-term carbon footprint. While the average construction price of a new home is
approximately $400,000, the home
Specification for this project calls for a larger finished area and significant sourcing of advanced
materials and systems. Therefore, the initial top-down estimate provided for a budget not to exceed
$1,000,000.
Additionally, the specifications of the number of rooms, and other structural attributes for this home
are based on a report from the National Association of Home Builders, which describe “what home
buyers really want. In keeping with the sustainability objectives, the home will not have luxury
amenities such as elevators, wine cooler, wet bar, or game room.
4
Responsibility Matrix:
Our Project Manager is Saad Saleem and there are other members whose are participants
are in this group, like Abdullah Hanif is handling three main departments which are
Finance, Technology, and Schedule Coordination Team.
Saad Saleem is Project Manager and he will only handle the main coming things which
will important for Project and handle out all the things.
Site analysis will cost $2000 owing to the fact that university volunteers will carry out most of
the analysis. The civil department will supply the project team with the resources and labor
needed to analysis the Land. Mechanical preparation of the site will entail harrowing equipment;
this will cost $ 4500. The purchase of Equipment cost will account for $ 120000. The purchase
5
of equipment needed to water and cement, Bricks, Iron sand will be $100000. Seedling
purchases will be the last purchase and they will account for the remainder of the budget. Other
care needs, such as watering, will still employ the same equipment that had been bought.
6
7
Gantt chart
8
Deliverables
1. A 3,500 square-foot finished home, with 4 bedrooms and 4 bathrooms.