Professional Documents
Culture Documents
SOP Canal Blocks 2019
SOP Canal Blocks 2019
2019
1
1. Scope of works
For rewetting of the project area a total of 199 compacted peat canal dams will be
constructed, as confirmed from the Field Surveys carried out in July-August 2019. The
coordinates of all 199 peat dams are given in Table 1 below.
The 199 peat dams have been divided into 9 Clusters as shown in Table 1 and in the Cluster
map Picture 1.
The size of the peat dams has been standardized in 3 design Types, depending on the
existing canal width.
The design Type (1-2-3) for each peat dam is shown in Table 1, and design drawings are
given in the following Section on Design Drawings.
The total number of each Peat dam Type is shown in the following Table:
2. Work Method
Mobilization and demobilization, making access roads, setting up and removing field camps,
safety procedures, preparing as-built drawings, reporting etc. must follow the methodology set
out in the General Specifications (Spesifikasi Umum) below.
The compacted peat dams will be constructed by hydraulic excavators of a type that are not
too heavy to travel on uncompacted peat using matting, with criteria as listed in the General
Specification Clause SU-10.
The material for constructing the peat dams will be obtained from borrow pits along the canals,
located not too close to the canals, with work method as shown in the Design Drawings No.1
to No.8.
Construction of the peat dams will commence from the most upstream dam in each Cluster,
as shown in the Maps for each Cluster (Pictures 2 to 11).
2
The recommended Work Method is for 10 excavators, working in 5 Sites, covering each
Cluster from upstream to downstream. Travelling fron dam to dam will require matting to
prevent the excavator tracks from sinking in the peat. The planned Sites are summarized as
follows:
Because construction of the peat dams will close the canals, it will not be possible to travel
along the canals by boat after construction. So it is important to make a joint inspection on
completion of each peat dam, to record the dimensions, take record photos, and make a
Berita Acara for each dam, to be signed by the Contractor and Field Supervisor, to facilitate
calculation of volume for payment. This is described in the Technical Specification
(Spesifikasi Teknis) Clause ST-2.4.2c.
3
SUPPORTING DATA
4
Table 1 – List of Canal Blocks, Design Types and Coordinates
TOTAL COMPACTED PEAT TO BE IMPLEMENTED ARE:
CLUSTER #1 18
CLUSTER #2 37
CLUSTER #3 15
CLUSTER #4 26
CLUSTER #5 15
CLUSTER #6 20
CLUSTER #7 22
CLUSTER #8 15
CLUSTER #9 31
199
CLUSTER #1
1 DAM_40 -1.9664700 104.1309967 Typical 1
2 DAM_65 -1.9670000 104.1340027 Typical 1
3 DAM_14 -1.9745100 104.1340027 Typical 1
4 DAM_34 -1.9726400 104.1389999 Typical 1
5 DAM_36 -1.9693900 104.1520004 Typical 1
6 DAM_35 -1.9772100 104.1460037 Typical 1
7 DAM_98 -1.9823600 104.1389999 Typical 1
8 DAM_15 -1.9898700 104.1399994 Typical 1
9 DAM_29 -1.9967600 104.1439972 Typical 1
10 DAM_28 -2.0019701 104.1510010 Typical 1
11 DAM_27 -2.0065801 104.1579971 Typical 1
12 DAM_83 -2.0087700 104.1579971 Typical 1
13 DAM_16 -2.0147800 104.1620026 Typical 1
14 DAM_76 -2.0204999 104.1699982 Typical 1
15 DAM_75 -2.0255201 104.1770020 Typical 1
16 DAM_73 -2.0343299 104.1770020 Typical 1
17 DAM_74 -2.0347500 104.1800003 Typical 1
18 DAM_80 -2.0282400 104.1829987 Typical 1
5
CLUSTER #2
6
1 DAM_82 -2.0166900 104.1480026 Typical 1
2 DAM_430 -2.0206800 104.1449966 Typical 1
3 DAM_190 -2.0220301 104.1370010 Typical 1
4 DAM_189 -2.0257699 104.1370010 Typical 1
5 DAM_100 -2.0288899 104.1320038 Typical 1
6 DAM_425 -2.0283699 104.1220016 Typical 1
7 DAM_426 -2.0274899 104.1139984 Typical 1
8 DAM_421 -2.0160699 104.1259995 Typical 1
9 DAM_420 -2.0162499 104.1179962 Typical 1
10 DAM_419 -2.0139999 104.1100006 Typical 1
11 DAM_418 -2.0108900 104.1019974 Typical 1
12 DAM_97 -2.0073900 104.0989990 Typical 1
13 DAM_427 -2.0084300 104.1159973 Typical 1
14 DAM_428 -2.0029299 104.1100006 Typical 1
15 DAM_413 -1.9953200 104.1070023 Typical 1
16 DAM_39 -1.9871000 104.1110001 Typical 1
17 DAM_20 -1.9729400 104.1029968 Typical 1
18 DAM_21 -1.9805700 104.1070023 Typical 1
19 DAM_414 -1.9854000 104.1119995 Typical 1
20 DAM_415 -1.9932600 104.1159973 Typical 1
21 DAM_416 -1.9996200 104.1220016 Typical 1
22 DAM_417 -2.0067999 104.1269989 Typical 1
23 DAM_92 -2.0021100 104.1320038 Typical 1
24 DAM_93 -1.9941100 104.1360016 Typical 1
25 DAM_26 -1.9862500 104.1350021 Typical 1
26 DAM_96 -1.9898000 104.1320038 Typical 1
27 DAM_95 -1.9956800 104.1299973 Typical 1
28 DAM_91 -1.9955900 104.1259995 Typical 1
29 DAM_90 -1.9889400 104.1220016 Typical 1
30 DAM_94 -1.9881800 104.1259995 Typical 1
31 DAM_1 -1.9786500 104.1240005 Typical 1
32 DAM_88 -1.9831800 104.1169968 Typical 1
33 DAM_4 -1.9768600 104.1139984 Typical 1
34 DAM_24 -1.9725800 104.1179962 Typical 1
35 DAM_25 -1.9673700 104.1110001 Typical 1
36 DAM_37 -1.9712200 104.1080017 Typical 1
37 DAM_2 -1.9628400 104.1050034 Typical 1
CLUSTER #3
7
1 DAM_52 -2.0373700 104.1709976 Typical 1
2 DAM_51 -2.0325201 104.1650009 Typical 1
3 DAM_50 -2.0253201 104.1620026 Typical 1
4 DAM_49 -2.0196600 104.1559982 Typical 1
5 DAM_431 -2.0236001 104.1480026 Typical 1
6 DAM_81 -2.0244801 104.1439972 Typical 1
7 DAM_429 -2.0285201 104.1409988 Typical 1
8 DAM_188 -2.0289800 104.1389999 Typical 1
9 DAM_187 -2.0329299 104.1399994 Typical 1
10 DAM_19 -2.0370800 104.1399994 Typical 1
11 DAM_186 -2.0356100 104.1360016 Typical 1
12 DAM_185 -2.0369101 104.1320038 Typical 1
13 DAM_184 -2.0376699 104.1279984 Typical 1
14 DAM_183 -2.0395899 104.1240005 Typical 1
15 DAM_182 -2.0418000 104.1200027 Typical 1
CLUSTER #4
1 DAM_212 -2.0305400 104.1979980 Typical 2
2 DAM_211 -2.0287800 104.1949997 Typical 2
3 DAM_210 -2.0309801 104.1910019 Typical 2
4 DAM_209 -2.0305700 104.1880035 Typical 2
5 DAM_79 -2.0355999 104.1920013 Typical 1
6 DAM_208 -2.0345600 104.1859970 Typical 2
7 DAM_207 -2.0376899 104.1829987 Typical 1
8 DAM_206 -2.0399699 104.1790009 Typical 1
9 DAM_77 -2.0401800 104.1839981 Typical 1
10 DAM_72 -2.0444100 104.1829987 Typical 1
11 DAM_78 -2.0431399 104.1760025 Typical 1
12 DAM_205 -2.0422299 104.1750031 Typical 1
13 DAM_204 -2.0427499 104.1699982 Typical 1
14 DAM_203 -2.0446801 104.1669998 Typical 1
15 DAM_202 -2.0448000 104.1630020 Typical 2
16 DAM_201 -2.0489600 104.1610031 Typical 2
17 DAM_200 -2.0496199 104.1579971 Typical 1
18 DAM_199 -2.0490601 104.1529999 Typical 2
19 DAM_198 -2.0481300 104.1490021 Typical 1
20 DAM_197 -2.0466499 104.1449966 Typical 2
21 DAM_196 -2.0453200 104.1409988 Typical 2
22 DAM_195 -2.0468299 104.1380005 Typical 2
23 DAM_194 -2.0493801 104.1340027 Typical 2
24 DAM_193 -2.0511301 104.1299973 Typical 2
25 DAM_192 -2.0535800 104.1269989 Typical 2
26 DAM_191 -2.0564101 104.1240005 Typical 2
CLUSTER #5
8
1 DAM_22 -1.9860700 104.0999985 Typical 1
2 DAM_38 -1.9932700 104.1039963 Typical 1
3 DAM_33 -1.9969200 104.1019974 Typical 1
4 DAM_32 -2.0033100 104.0979996 Typical 1
5 DAM_87 -1.9980500 104.0940018 Typical 1
6 DAM_86 -2.0056601 104.0920029 Typical 1
7 DAM_3 -2.0109301 104.0960007 Typical 1
8 DAM_283 -2.0165200 104.0960007 Typical 1
9 DAM_284 -2.0183101 104.0999985 Typical 1
10 DAM_85 -2.0237701 104.0970001 Typical 1
11 DAM_30 -2.0293100 104.1039963 Typical 1
12 DAM_31 -2.0374999 104.1100006 Typical 1
13 DAM_181 -2.0453501 104.1169968 Typical 1
14 DAM_180 -2.0492201 104.1169968 Typical 1
15 DAM_179 -2.0527301 104.1190033 Typical 2
CLUSTER #6
1 DAM_322 -2.0048599 104.0680008 Typical 1
2 DAM_321 -2.0067301 104.0690002 Typical 1
3 DAM_320 -2.0085199 104.0699997 Typical 1
4 DAM_319 -2.0103700 104.0719986 Typical 1
5 DAM_324 -2.0105400 104.0780029 Typical 1
6 DAM_323 -2.0107701 104.0739975 Typical 1
7 DAM_318 -2.0123100 104.0719986 Typical 1
8 DAM_317 -2.0136700 104.0699997 Typical 1
9 DAM_316 -2.0150599 104.0680008 Typical 1
10 DAM_302 -2.0156400 104.0650024 Typical 1
11 DAM_315 -2.0171199 104.0670013 Typical 1
12 DAM_301 -2.0193100 104.0670013 Typical 1
13 DAM_306 -2.0186801 104.0650024 Typical 1
14 DAM_307 -2.0206599 104.0640030 Typical 1
15 DAM_308 -2.0209401 104.0619965 Typical 1
16 DAM_309 -2.0211101 104.0599976 Typical 1
17 DAM_310 -2.0227001 104.0599976 Typical 1
18 DAM_311 -2.0241001 104.0630035 Typical 1
19 DAM_300 -2.0228100 104.0699997 Typical 1
20 DAM_299 -2.0266800 104.0699997 Typical 1
CLUSTER #7
1 DAM_293 -2.0282400 104.0759964 Typical 1
2 DAM_292 -2.0290000 104.0739975 Typical 1
9
3 DAM_291 -2.0299799 104.0719986 Typical 1
4 DAM_290 -2.0312099 104.0699997 Typical 1
5 DAM_289 -2.0319700 104.0680008 Typical 1
6 DAM_288 -2.0326700 104.0660019 Typical 1
7 DAM_287 -2.0335200 104.0640030 Typical 1
8 DAM_313 -2.0282600 104.0609970 Typical 1
9 DAM_312 -2.0323300 104.0619965 Typical 1
10 DAM_286 -2.0348799 104.0619965 Typical 1
11 DAM_276 -2.0367100 104.0810013 Typical 1
12 DAM_275 -2.0372701 104.0790024 Typical 1
13 DAM_274 -2.0373399 104.0759964 Typical 1
14 DAM_273 -2.0375700 104.0739975 Typical 1
15 DAM_272 -2.0378900 104.0719986 Typical 2
16 DAM_230 -2.0398700 104.0729980 Typical 3
17 DAM_271 -2.0382600 104.0699997 Typical 1
18 DAM_270 -2.0383699 104.0680008 Typical 2
19 DAM_269 -2.0377700 104.0660019 Typical 1
20 DAM_268 -2.0365300 104.0640030 Typical 1
21 DAM_267 -2.0361900 104.0619965 Typical 2
22 DAM_266 -2.0365701 104.0589981 Typical 3
CLUSTER #8
1 DAM_178 -2.0569501 104.1190033 Typical 2
2 DAM_177 -2.0612600 104.1179962 Typical 2
3 DAM_176 -2.0652800 104.1179962 Typical 2
4 DAM_175 -2.0694799 104.1169968 Typical 2
5 DAM_174 -2.0715599 104.1159973 Typical 2
6 DAM_173 -2.0730901 104.1149979 Typical 2
7 DAM_172 -2.0742700 104.1129990 Typical 2
8 DAM_171 -2.0760400 104.1110001 Typical 2
9 DAM_170 -2.0775101 104.1100006 Typical 2
10 DAM_169 -2.0781400 104.1080017 Typical 2
11 DAM_168 -2.0789700 104.1060028 Typical 2
12 DAM_167 -2.0795300 104.1039963 Typical 2
13 DAM_166 -2.0803900 104.1019974 Typical 1
14 DAM_165 -2.0810299 104.0999985 Typical 1
15 DAM_164 -2.0817001 104.0979996 Typical 1
CLUSTER #9
1 DAM_354 -1.9770200 104.2080002 Typical 1
10
2 DAM_353 -1.9790300 104.2089996 Typical 1
3 DAM_352 -1.9810200 104.2099991 Typical 1
4 DAM_351 -1.9821301 104.2119980 Typical 1
5 DAM_350 -1.9821700 104.2139969 Typical 1
6 DAM_349 -1.9819700 104.2170029 Typical 1
7 DAM_348 -1.9814900 104.2190018 Typical 1
8 DAM_346 -1.9781700 104.2149963 Typical 1
9 DAM_345 -1.9793500 104.2170029 Typical 1
10 DAM_344 -1.9803900 104.2190018 Typical 1
11 DAM_347 -1.9818600 104.2220001 Typical 1
12 DAM_122 -2.0090301 104.2080002 Typical 1
13 DAM_121 -2.0088401 104.2119980 Typical 1
14 DAM_120 -2.0085800 104.2160034 Typical 1
15 DAM_131 -2.0065999 104.2149963 Typical 1
16 DAM_119 -2.0081000 104.2210007 Typical 1
17 DAM_118 -2.0081201 104.2229996 Typical 1
18 DAM_117 -2.0081699 104.2249985 Typical 1
19 DAM_116 -2.0080500 104.2279968 Typical 1
20 DAM_115 -2.0081100 104.2300034 Typical 1
21 DAM_114 -2.0079801 104.2320023 Typical 1
22 DAM_113 -2.0080700 104.2340012 Typical 1
23 DAM_112 -2.0199599 104.2210007 Typical 1
24 DAM_111 -2.0206299 104.2259979 Typical 1
25 DAM_68 -2.0209799 104.2279968 Typical 1
26 DAM_110 -2.0214000 104.2300034 Typical 1
27 DAM_109 -2.0225599 104.2320023 Typical 1
28 DAM_108 -2.0243700 104.2330017 Typical 1
29 DAM_66 -2.0244901 104.2350006 Typical 1
30 DAM_104 -2.0246100 104.2369995 Typical 1
31 DAM_103 -2.0234699 104.2379990 Typical 1
11
DESIGN DRAWINGS
Drawing 1: Work Method, Excavation from Borrow Pits and Filling to Canal Dam
(Plan).
Drawing 2: Work Method, Excavation from Borrow Pits and Filling to Canal Dam
(Sections).
12
Drawing 1: Work Method, Excavation from Borrow Pits and Filling to Canal Dam (Plan)
13
Drawing 2: Work Method, Excavation from Borrow Pits and Filling to Canal Dam (Sections)
14
Drawing 3 : Design of Canal Dam Type 1 (Plan)
15
Drawing 4 : Design of Canal Dam Type 1 (Sections)
16
Drawing 5 : Design of Canal Dam Type 2 (Plan)
17
Drawing 6 : Design of Canal Dam Type 2 (Sections)
18
Drawing 7 : Design of Canal Dam Type 3 (Plan)
19
Drawing 8 : Design of Canal Dam Type 3 (Sections)
20
CLUSTERING of PEAT CANAL DAMS
Picture 1. All Clusters Showing Excavator Start Point for Each Cluster
Picture 2. Cluster #1
Picture 3. Cluster #4
Picture 4. Cluster #8
Picture 5. Cluster #2
Picture 6. Cluster #3
Picture 7. Cluster #5
Picture 8. Cluster #8 (Transit)
Picture 9. Cluster #9
Picture 10. Cluster #6
Picture 11. Cluster #7
21
ALL CLUSTERS
Picture 1. All Clusters Showing Excavator Start Point for Each Cluster
PROCEDURE SITE 1: 2 UNITS EXCAVATOR: Clusters No. 1, 4 and 8.
22
Stripping
Dig Volume (m3) BackFill Distance (m)
Fill Volume Volume (m3)
Typical (m3) Borrow Pit (Clean)
Compacted Stripping (Dirt)
Length Length
Width
NO CODE LAT_48S LONG_48S Design Code Width Length Depth Depth Volume Depth Volume One Side Two Side
CLUSTER #1
1 DAM_40 -1,9664700 104,1309967 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 13.573
2 DAM_65 -1,9670000 104,1340027 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 339
3 DAM_14 -1,9745100 104,1340027 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 835
4 DAM_34 -1,9726400 104,1389999 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 593
5 DAM_36 -1,9693900 104,1520004 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.488
6 DAM_35 -1,9772100 104,1460037 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.095
7 DAM_98 -1,9823600 104,1389999 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 966
8 DAM_15 -1,9898700 104,1399994 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 842
9 DAM_29 -1,9967600 104,1439972 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 885
10 DAM_28 -2,0019701 104,1510010 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 970
11 DAM_27 -2,0065801 104,1579971 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 931
12 DAM_83 -2,0087700 104,1579971 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 243
13 DAM_16 -2,0147800 104,1620026 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 802
14 DAM_76 -2,0204999 104,1699982 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.092
15 DAM_75 -2,0255201 104,1770020 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 957
16 DAM_73 -2,0343299 104,1770020 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 979
17 DAM_74 -2,0347500 104,1800003 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 336
18 DAM_80 -2,0282400 104,1829987 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 796
23
Picture 2. Cluster #1
CLUSTER #4
24
1 DAM_212 -2,0305400 104,1979980 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 1.685
2 DAM_211 -2,0287800 104,1949997 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 386
3 DAM_210 -2,0309801 104,1910019 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 507
4 DAM_209 -2,0305700 104,1880035 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 336
5 DAM_79 -2,0355999 104,1920013 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 714
6 DAM_208 -2,0345600 104,1859970 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 677
7 DAM_207 -2,0376899 104,1829987 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 481
8 DAM_206 -2,0399699 104,1790009 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 511
9 DAM_77 -2,0401800 104,1839981 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 555
10 DAM_72 -2,0444100 104,1829987 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 483
11 DAM_78 -2,0431399 104,1760025 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 790
12 DAM_205 -2,0422299 104,1750031 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 150
13 DAM_204 -2,0427499 104,1699982 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 559
14 DAM_203 -2,0446801 104,1669998 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 396
15 DAM_202 -2,0448000 104,1630020 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 444
16 DAM_201 -2,0489600 104,1610031 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 513
17 DAM_200 -2,0496199 104,1579971 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 342
18 DAM_199 -2,0490601 104,1529999 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 558
19 DAM_198 -2,0481300 104,1490021 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 456
20 DAM_197 -2,0466499 104,1449966 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 474
21 DAM_196 -2,0453200 104,1409988 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 468
22 DAM_195 -2,0468299 104,1380005 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 373
23 DAM_194 -2,0493801 104,1340027 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 527
24 DAM_193 -2,0511301 104,1299973 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 485
25 DAM_192 -2,0535800 104,1269989 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 430
26 DAM_191 -2,0564101 104,1240005 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 458
25
Picture 3. Cluster #4
CLUSTER #8
26
DROP SITE -2,0527301 104,1190033 Exca From #4 #5
1 DAM_178 -2,0569501 104,1190033 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 469
2 DAM_177 -2,0612600 104,1179962 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 492
3 DAM_176 -2,0652800 104,1179962 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 447
4 DAM_175 -2,0694799 104,1169968 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 480
5 DAM_174 -2,0715599 104,1159973 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 256
6 DAM_173 -2,0730901 104,1149979 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 203
7 DAM_172 -2,0742700 104,1129990 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 258
8 DAM_171 -2,0760400 104,1110001 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 297
9 DAM_170 -2,0775101 104,1100006 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 197
10 DAM_169 -2,0781400 104,1080017 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 233
11 DAM_168 -2,0789700 104,1060028 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 240
12 DAM_167 -2,0795300 104,1039963 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 231
13 DAM_166 -2,0803900 104,1019974 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 242
14 DAM_165 -2,0810299 104,0999985 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 233
15 DAM_164 -2,0817001 104,0979996 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 234
27
Picture 4. Cluster #8
CLUSTER #2
1 DAM_82 -2,0166900 104,1480026 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 9.388
2 DAM_430 -2,0206800 104,1449966 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 555
3 DAM_190 -2,0220301 104,1370010 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 900
4 DAM_189 -2,0257699 104,1370010 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 416
5 DAM_100 -2,0288899 104,1320038 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 654
6 DAM_425 -2,0283699 104,1220016 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.112
7 DAM_426 -2,0274899 104,1139984 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 894
8 DAM_421 -2,0160699 104,1259995 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.840
9 DAM_420 -2,0162499 104,1179962 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 889
10 DAM_419 -2,0139999 104,1100006 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 922
11 DAM_418 -2,0108900 104,1019974 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 954
12 DAM_97 -2,0073900 104,0989990 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 512
13 DAM_427 -2,0084300 104,1159973 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.891
14 DAM_428 -2,0029299 104,1100006 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 904
15 DAM_413 -1,9953200 104,1070023 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 909
16 DAM_39 -1,9871000 104,1110001 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.016
17 DAM_20 -1,9729400 104,1029968 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.807
18 DAM_21 -1,9805700 104,1070023 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 957
19 DAM_414 -1,9854000 104,1119995 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 772
20 DAM_415 -1,9932600 104,1159973 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 980
21 DAM_416 -1,9996200 104,1220016 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 972
22 DAM_417 -2,0067999 104,1269989 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 972
23 DAM_92 -2,0021100 104,1320038 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 762
24 DAM_93 -1,9941100 104,1360016 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 994
25 DAM_26 -1,9862500 104,1350021 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 880
26 DAM_96 -1,9898000 104,1320038 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 516
29
27 DAM_95 -1,9956800 104,1299973 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 690
28 DAM_91 -1,9955900 104,1259995 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 444
29 DAM_90 -1,9889400 104,1220016 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 862
30 DAM_94 -1,9881800 104,1259995 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 452
31 DAM_1 -1,9786500 104,1240005 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.082
32 DAM_88 -1,9831800 104,1169968 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 926
33 DAM_4 -1,9768600 104,1139984 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 777
34 DAM_24 -1,9725800 104,1179962 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 651
35 DAM_25 -1,9673700 104,1110001 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 969
36 DAM_37 -1,9712200 104,1080017 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 542
37 DAM_2 -1,9628400 104,1050034 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 989
30
Picture 5. Cluster #2
CLUSTER #3
1 DAM_52 -2,0373700 104,1709976 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 9.747
2 DAM_51 -2,0325201 104,1650009 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 857
3 DAM_50 -2,0253201 104,1620026 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 867
4 DAM_49 -2,0196600 104,1559982 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 917
5 DAM_431 -2,0236001 104,1480026 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 990
6 DAM_81 -2,0244801 104,1439972 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 455
7 DAM_429 -2,0285201 104,1409988 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 559
8 DAM_188 -2,0289800 104,1389999 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 228
9 DAM_187 -2,0329299 104,1399994 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 453
10 DAM_19 -2,0370800 104,1399994 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 461
11 DAM_186 -2,0356100 104,1360016 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 473
12 DAM_185 -2,0369101 104,1320038 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 467
13 DAM_184 -2,0376699 104,1279984 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 453
14 DAM_183 -2,0395899 104,1240005 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 493
15 DAM_182 -2,0418000 104,1200027 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 507
32
Picture 6. Cluster #3
CLUSTER #5
33
DROP SITE -2,0418000 104,1200027 Exca From #3
1 DAM_22 -1,9860700 104,0999985 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 6.579
2 DAM_38 -1,9932700 104,1039963 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 915
3 DAM_33 -1,9969200 104,1019974 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 462
4 DAM_32 -2,0033100 104,0979996 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 837
5 DAM_87 -1,9980500 104,0940018 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 734
6 DAM_86 -2,0056601 104,0920029 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 874
7 DAM_3 -2,0109301 104,0960007 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 735
8 DAM_283 -2,0165200 104,0960007 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 621
9 DAM_284 -2,0183101 104,0999985 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 486
10 DAM_85 -2,0237701 104,0970001 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 692
11 DAM_30 -2,0293100 104,1039963 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 991
12 DAM_31 -2,0374999 104,1100006 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.128
13 DAM_181 -2,0453501 104,1169968 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.168
14 DAM_180 -2,0492201 104,1169968 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 430
15 DAM_179 -2,0527301 104,1190033 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 449
34
Picture 7. Cluster #5
CLUSTER #8
35
DROP SITE -2,0527301 104,1190033 Exca From #4 #5
1 DAM_178 -2,0569501 104,1190033 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 469
2 DAM_177 -2,0612600 104,1179962 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 492
3 DAM_176 -2,0652800 104,1179962 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 447
4 DAM_175 -2,0694799 104,1169968 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 480
5 DAM_174 -2,0715599 104,1159973 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 256
6 DAM_173 -2,0730901 104,1149979 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 203
7 DAM_172 -2,0742700 104,1129990 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 258
8 DAM_171 -2,0760400 104,1110001 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 297
9 DAM_170 -2,0775101 104,1100006 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 197
10 DAM_169 -2,0781400 104,1080017 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 233
11 DAM_168 -2,0789700 104,1060028 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 240
12 DAM_167 -2,0795300 104,1039963 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 231
13 DAM_166 -2,0803900 104,1019974 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 242
14 DAM_165 -2,0810299 104,0999985 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 233
15 DAM_164 -2,0817001 104,0979996 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 234
36
Picture 8. Cluster #8 (Transit)
37
CLUSTER #9
38
DROP SITE -2,0836220 104,0964160 Main Camp
1 DAM_354 -1,9770200 104,2080002 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.356
2 DAM_353 -1,9790300 104,2089996 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 249
3 DAM_352 -1,9810200 104,2099991 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 247
4 DAM_351 -1,9821301 104,2119980 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 254
5 DAM_350 -1,9821700 104,2139969 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 222
6 DAM_349 -1,9819700 104,2170029 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 335
7 DAM_348 -1,9814900 104,2190018 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 228
8 DAM_346 -1,9781700 104,2149963 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 578
9 DAM_345 -1,9793500 104,2170029 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 259
10 DAM_344 -1,9803900 104,2190018 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 250
11 DAM_347 -1,9818600 104,2220001 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 371
12 DAM_122 -2,0090301 104,2080002 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 3.396
13 DAM_121 -2,0088401 104,2119980 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 444
14 DAM_120 -2,0085800 104,2160034 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 446
15 DAM_131 -2,0065999 104,2149963 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 247
16 DAM_119 -2,0081000 104,2210007 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 687
17 DAM_118 -2,0081201 104,2229996 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 222
18 DAM_117 -2,0081699 104,2249985 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 222
19 DAM_116 -2,0080500 104,2279968 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 333
20 DAM_115 -2,0081100 104,2300034 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 223
21 DAM_114 -2,0079801 104,2320023 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 222
22 DAM_113 -2,0080700 104,2340012 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 222
23 DAM_112 -2,0199599 104,2210007 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.957
24 DAM_111 -2,0206299 104,2259979 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 560
25 DAM_68 -2,0209799 104,2279968 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 225
26 DAM_110 -2,0214000 104,2300034 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 228
27 DAM_109 -2,0225599 104,2320023 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 257
28 DAM_108 -2,0243700 104,2330017 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 230
29 DAM_66 -2,0244901 104,2350006 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 222
30 DAM_104 -2,0246100 104,2369995 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 222
31 DAM_103 -2,0234699 104,2379990 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 168
39
DEMOB POINT -2,1451800 104,1618600 Pelabuhan WLMS 15.950
40
Picture 9. Cluster #9
42
18 DAM_311 - 104,063003 Typical 1 7,0 6,0 2,3
2,0241001 5 0 0 3
97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 368
19 DAM_300 - 104,069999 Typical 1 7,0 6,0 2,3
2,0228100 7 0 0 3
97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 790
20 DAM_299 - 104,069999 Typical 1 7,0 6,0 2,3
2,0266800 7 0 0 3
97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 430
DEMOB POINT - 104,161860 Pelabuhan
2,1451800 0 WLMS
16.657
TOTAL DISTANCE 6.248
43
Picture 10. Cluster #6
CLUSTER #7
1 DAM_293 -2,0282400 104,0759964 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 1.853
2 DAM_292 -2,0290000 104,0739975 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 238
3 DAM_291 -2,0299799 104,0719986 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 247
4 DAM_290 -2,0312099 104,0699997 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 261
5 DAM_289 -2,0319700 104,0680008 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 238
6 DAM_288 -2,0326700 104,0660019 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 235
7 DAM_287 -2,0335200 104,0640030 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 241
8 DAM_313 -2,0282600 104,0609970 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 673
9 DAM_312 -2,0323300 104,0619965 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 466
10 DAM_286 -2,0348799 104,0619965 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 283
11 DAM_276 -2,0367100 104,0810013 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 2.120
12 DAM_275 -2,0372701 104,0790024 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 231
13 DAM_274 -2,0373399 104,0759964 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 334
14 DAM_273 -2,0375700 104,0739975 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 223
15 DAM_272 -2,0378900 104,0719986 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 225
16 DAM_230 -2,0398700 104,0729980 Typical 3 11,00 6,00 2,33 153,45 1,00 230,18 0,40 92,07 4,00 41,10 20,55 92,07 246
17 DAM_271 -2,0382600 104,0699997 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 378
18 DAM_270 -2,0383699 104,0680008 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 222
19 DAM_269 -2,0377700 104,0660019 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 232
20 DAM_268 -2,0365300 104,0640030 Typical 1 7,00 6,00 2,33 97,65 1,00 146,48 0,40 58,59 4,00 26,16 13,08 58,59 261
21 DAM_267 -2,0361900 104,0619965 Typical 2 9,00 6,00 2,33 125,55 1,00 188,33 0,40 75,33 4,00 33,63 16,81 75,33 226
22 DAM_266 -2,0365701 104,0589981 Typical 3 11,00 6,00 2,33 153,45 1,00 230,18 0,40 92,07 4,00 41,10 20,55 92,07 336
45
TOTAL DISTANCE 7.916
46
Picture 11. Cluster #7
47
SPECIFICATIONS
General Specifications (Spesifikasi Umum)
48
SPESIFIKASI UMUM
SU - 1. LOKASI PEKERJAAN
Lokasi pekerjaan yang meliputi Pembangunan Canal Blocking Merang
menuju lokasi SMPP menggunakan jalur darat dari Jambi melalui jalan trans
Sumatra Jambi-Palembang, dan masuk ke lokasi SMPP melalui areal
Wahana Lestari Makmur Sukses (WLMS) atau Conoco-Phillips.
49
SU - 4. IKLIM, CURAH HUJAN DAN ELEVASI MUKA AIR KANAL
SU - 4.1 Umum
Untuk keperluan perencanaan konstruksi, informasi berikut memberikan
gambaran kondisi iklim dan hidrologi, berkaitan dengan lokasi pekerjaan,
yang terjadi sepanjang tahun, tetapi ini tidak membebaskan Kontraktor
dengan cara apapun dari kewajiban untuk mencari informasi tambahan
dengan semua data yang tersedia. Pemilik Pekerjaan dan Direksi tidak
bertanggung jawab apapun untuk keakuratan informasi, dan resiko ketidak
akuratan interpretasi ditanggung sepenuhnya oleh Kontraktor.
SU - 5. GEOLOGI
50
SU - 5.1. Material Konstruksi
Material penimbunan untuk canal boking menggunakan tanah setempat dari
bahan tanah gambut dengan menggunakan pemadatan dari alat excavator
SU - 6.1. Umum
Kontraktor harus membangun, melengkapi dan memelihara semua
pekerjaan, termasuk semua pekerjaan sementara, di bawah persyaratan
kontrak yang sesuai dengan Spesifikasi dan gambar, atau seperti yang
diarahkan atau disetujui oleh Direksi Pekerjaan. Kecuali jika ditentukan lain
dalam kontrak, Kontraktor wajib menyediakan semua bahan konstruksi,
pabrikasi dan personil, peralatan, tenaga kerja dan pengawasan, dan semua
persyaratan lainnya untuk membuat, menyelesaikan dan
memeliharapekerjaan.
SU - 6.3.1. Umum
Pekerjaan yang diperlukan mencakup penimbunan tanah pada dasar dasar
kanal harus diproteksi dengan batang batang yang ada apabila diperlukan
untuk penimbunan kemablai pada depan sekat kanal.
51
Sumatra Jambi-Palembang, dan masuk ke lokasi SMPP melalui areal
Wahana Lestari Makmur Sukses (WLMS) atau Conoco-Phillips.
Kontrator harus bertanggung jawab atas pemeliharaan jalan ini dalam
kondisi memuaskan, entah sepenuhnya atau sebagian selesai, sementara
digunakan selama pelaksanaan konstruksi, sampai dengan penyelesaian
proyek. Setelah menyelesaikan pekerjaan jalan ini harus diserahkan sesuai
dengan kondisi semula dan disetujui oleh Direksi Pekerjaan dan diserahkan
kepada pemilik proyek dalam kondisi baik.
52
jalan dan jembatan dapat diamati. Dalam hal itu menjadi perlu untuk
memindahkan setiap kelebihan beban dari peralatan atau komponen
konstruksi. Kontraktor harus memperoleh semua ijin yang diperlukan dan
persetujuan dari instansi terkait mengenai kelebihan beban yang luar biasa
seperti itu, dan harus memenuhi semua persyaratan yang sah lainnya.
Batas pengiriman melalui jalan nasional bervariasi sesuai dengan kondisi
jalan dan jembatan. Ini akan menjadi tanggung jawab Kontraktor untuk
diberitahu tentang pembatasan pada semua beban muatan jalan dengan
memasang marka jalan dan papan petunjuk yang diperlukan.
SU – 8. GAMBAR KONTRAK
Gambar desain yang terdapat dalam dokumen tender akan menjadi bagian
dari dokumen kontrak setelah kontrak perjanjian telah ditandatangani.
Selain gambar terlampir, desain gambar mengenai detail pekerjaan akan
diserahkan oleh Pengguna Jasa kepada Kontraktor pada saat SPMK, dan
gambar tersebut akan menjadi bagian dari dokumen kontrak.
Selama kemajuan pekerjaan gambar detail desain lebih lanjut akan
dikeluarkan oleh Pengguna Jasa sebagai kebutuhan yang muncul untuk
melengkapi, menggantikan, atau lebih detail seperti yang ditunjukkan pada
gambar di atas, dan gambar tambahan tersebut harus menjadi bagian atau
dokumen kontrak.
Kontraktor harus mengikuti ukuran dimensi seperti yang diberikan pada
gambar. Perubahan skala gambar untuk tujuan dimensi tidak diperbolehkan.
Dimana dimensi yang dibutuhkan tidak ditampilkan dalam gambar,
Kontraktor wajib mendapatkan dimensi tersebut dari Direksi sebelum
melaksanakan pembangunan bagian yang dikerjakan. Dalam semua kasus,
gambar yang lebih rinci harus didahulukan dari gambar umum.
Kontraktor wajib melakukan pemeriksaan rinci dari semua gambar yang
dikeluarkan kepadanya sebagai bagian dari kontrak. Jika ada kekurangan,
ambiguitas, perbedaan, atau kesalahan, yang ditemukan dalam gambar,
maka bersama sama Direksi meneruskan untuk meminta keputusan
Pengguna Jasaguna menyelesaikan kekurangan tersebut, perbedaan
ambiguitas, atau kesalahan, bersifat final.
53
Semua gambar-gambar yang disiapkan oleh Kontraktor haruslah gambar-
gambar yang telah ditandatangani oleh Direksi dan apabila ada
perubahan harus diserahkan kepada Direksi untuk mendapat
persetujuan sebelum program pelaksanaan dimulai.
b. Gambar-gambar pelaksanaan
Kontraktor harus menggunakan Gambar-gambar kontrak sebagai dasar
untuk mempersiapkan gambar-gambar pelaksanaan. Gambar-gambar itu
dibuat lebih detail untuk pekerjaan tetap dan dimana mungkin dapat
memperlihatkan penampang melintang dan memanjang bagian pekerjaan
yang akan dilaksanakan lebih detail, untuk gambar disain canal bloking.
c. Kontraktor harus menyediakan 1 (satu) set gambar lengkap di lapangan.
Apabila ada pekerjaan dilaksanakan sebelum ada persetujuan Direksi
adalah menjadi tanggungjawab Kontraktor. Persetujuan Direksi terhadap
gambar tersebut tidak mengurangi tanggungjawab Kontraktor atas
kebenaran gambar tersebut.
54
spesifikasi.Kontraktorjuga wajib menyerahkan semua gambar tersebut dalam
tiga (3) salinan kepada Pengguna Jasa untuk persetujuan kecuali dinyatakan
khusus. Gambar-gambar yang diserahkan oleh Kontraktor harus cukup rinci
untuk menunjukkan:
Pengaturan umum dan detail konstruksi untuk bagian dari pekerjaan
yang akan dibangun atau dibuat berdasarkan kontrak;
Dimensidan ukuran dari semua komponen bagian yang relevan dari
pekerjaan, dan
Bahan dari berbagai bagian atau komponen dari pekerjaan yang akan
dibangun atau dibuat.
Pabrikasi, manufaktur, atau konstruksi, dari setiap bagian dari pekerjaan
yang akan dilaksanakan, Kontraktor wajib menyampaikan gambar ke
Pengguna Jasa untuk disetujui, tidak akan dapat dimulai pekerjaan sampai
gambar tersebut telah disetujui secara tertulis oleh Direksi Pekerjaan.
Setelah itu jika ada perubahan harus dibuat untuk setiap gambar sehingga
disetujui Direksi.
Persetujuan oleh Direksi untuk semua gambar yang disampaikan oleh
Kontraktor tidak akan membebaskan Kontraktor dari setiap kewajiban atau
tanggung jawabnya sesuaikontrak.
Semua gambar disampaikan oleh Kontraktor dan telah disetujui oleh Direksi
Pekerjaan maka akan menjadi bagian dari kontrak.
55
Penyelesaian gambar purnalaksana paling lambat pada saat penyerahan
pertama pekerjaan (PHO).
Gambar purnalaksana yang akan diserahkan kepada Pengguna Jasa terdiri:
Satu (1) set gambar asli ukuran A3, termasuk file digital
(AutoCAD);
Tiga (3) set copy ukuran A3.
56
SU – 11.2. Laporan Kemajuan Pelaksanaan Bulanan
Sebelum tanggal dua puluh lima tiap bulan atau pada suatu waktu yang
ditentukan Direksi, Kontraktor harus menyerahkan 5 (lima) salinan laporan
kemajuan bulanan dalam bentuk yang bisa diterima oleh Direksi, yang
menggambarkan secara detail kemajuan pekerjaan selama bulan
sebelumnya. Laporan sekurang-kurangnya harus berisi hal-hal sebagai
berikut :
a. Prosentase realisasi kemajuan pekerjaan yang dicapai pada bulan
laporan maupun prosentase rencana yang diprogramkan pada bulan
berikutnya.
b. Prosentase dari tiap pekerjaan pokok yang diselesaikan maupun
prosentase rencana yang diprogramkan harus sesuai dengan kemajuan
yang dicapai pada bulan laporan.
c. Rencana kegiatan dalam waktu dua bulan berturut-turut dengan
ramalan tanggal permulaan dan penyelesaiannya.
d. Daftar tenaga kerja.
e. Daftar perlengkapan konstruksi, peralatan dan bahan di lapangan
yang digunakan untuk melaksanakan pekerjaan termasuk yang sudah
datang dan dipindahkan dari lapangan.
f. Jumlah volume pekerjaan yang merupakan bagian pekerjaan Utama
galian dan timbunan
g. Uraian pokok pekerjaan sementara yang dilaksanakan selama masa
laporan
h. Daftar besarnya pembayaran terakhir yang diterima dan kebutuhan
pembayaran yang diperlukan pada bulan berikutnya
i. Hal-hal yang diminta sesuai dengan kontrak dan masalah yang timbul
atau berhubungan dengan pelaksanaan pekerjaan selama bulan
laporan
j. Catatan mengenai kondisi cuaca termasuk jumlah curah hujan
k. Foto kegiatan yang sudah dilaksanakan.
57
pekerjaan, pengadaan bahan, pengangkutan bahan dan peralatan lain-lain
yang diminta Direksi.
Kontraktor harus menyerahkan 2 (dua) rangkap rencana kerja harian secara
tertulis semua kemajuan yang sudah disetujui oleh Direksi setiap hari
maupun untuk hari-hari berikutnya. Rencana kerja harus mencakup
pekerjaan tanah, pekerjaan konstruksi dan kegiatan lain yang berhubungan
dengan pelaksanaan pekerjaan.
Kontraktor harus menyediakan Rencana Kerja Bulanan dengan sistim bar-
chart pada akhir bulan dan untuk bulan-bulan berikutnya. Rencana Kerja
ini harus memperlihatkan tenggang waktu dari mulai sampai akhir kegiatan
utama dengan volume pekerjaannya, Rencana Kerja ini harus diserahkan
kepada Direksi pada hari ketiga tiap bulan untuk perbaikan dan perubahan.
SU - 12.1. Umum
Kontraktor harus menyediakan, membangun, dan memelihara semua
fasilitas sementara selama pelaksanaan kontruksi sesuai dengan yang
ditetapkan dalam Spesifikasi Teknik , dan setelah masa konstruksi,
58
Kontraktor harus membongkar semua fasilitas sementara sesuai dengan
persetujuan dari Direksi Pekerjaan.
Semua fasilitas konstruksi sementara tersebut harus sesuai persetujuan dari
Direksi Pekerjaan, dan dalam hubungannya dengan program pembangunan
sebagaimana diatur dalam Pasal SU-9 dari Spesifikasi Umum. Kontraktor
harus menyerahkan untuk persetujuan Direksi Pekerjaan dalam waktu tujuh
(7) hari, Kontraktor harus mengirim Surat Persetujuan yang menguraikan
dengan rincian dan rencana untuk semua fasilitas sementara tersebut.
Pembangunan fasilitas sementara tidak akan dimulai sampai rencana
disampaikan oleh Kontraktor telah sepenuhnya disetujui oleh Direksi
Pekerjaan.
Tidak kurang dari tujuh (7) hari kalender sebelum konstruksi atau
pemasangan setiap bagian dari fasilitas sementara diusulkan untuk dimulai,
Kontraktor harus menyerahkan kepada Direksi Pekerjaan surat
persetujuannya, rencana rinci dan program untuk bagian yang diusulkan
dari fasilitas untuk dibangun atau dipasang.
59
SU - 12.4. Suplai Listrik
Kontraktor harus menyediakan pasokan tenaga listrik ke dan di lokasi yang
diperlukan untuk pekerjaan konstruksi, termasuk kepada semua kantor,
perumahan staf, kamp kerja, bengkel, gudang, dan tempat-tempat kerja di
lokasi serta kantor dan perumahan Direksi Pekerjaan.
Kontraktor harus memasang, mengoperasikan dan memelihara, sampai akhir
masa pemeliharaan atau untuk periode yang lebih pendek seperti yang
disetujui oleh Direksi Pekerjaan, semua penghasil daya, peralatan, kabel dan
perlengkapan sebagaimana diperlukan untuk menjamin pasokan yang cukup
dan tidak terputus dari daya listrik. Pada saat awal konstruksi Kontraktor
harus menyediakan generator pembangkit listrik.
60
mengembalikan daerah lokasi ke kondisi semula sesuai dengan persetujuan
dari Direksi Pekerjaan dengan pengecualian bahwa, sesuai dengan pilihan
Direksi, Kontraktor dapat diarahkan untuk mempertahankan dan
memelihara bagian dari fasilitas sementara di lokasi sampai dengan
selesainya masa pemeliharaan di bawah syarat-syarat kontrak. Selain itu,
dan pada kebijaksanaan Direksi, Kontraktor dapat diminta untuk
menyerahkan kepada Direksi secara gratis, semua atau bagian dari
bangunan sementara dan fasilitas dalam kondisi operasi pada akhir kontrak.
Kontraktor harus selalu berkonsultasi dengan Direksi mengenai persyaratan
Direksi terhadap semua bangunan sementara dan fasilitas sebelum
dimulainya setiap pembongkaran bangunan tersebut, dan tidak akan
memulai pekerjaan tersebut tanpa persetujuan tertulis dari Direksi
Pekerjaan.
SU - 13.1. Umum
Kontraktor harus menyediakan semua bahan dan perlengkapan yang
diperlukan untuk penyelesaian pekerjaan. Semua bahan dan perlengkapan
yang merupakan bagian dari pekerjaan harus sesuai dengan standar yang
diberikan dalam Spesifikasi Teknik dan Spesifikasi Umum.
Bila Kontraktor dalam mengusulkan penyediaan bahan dan perlengkapan
tidak sesuai dengan standar seperti tersebut di atas, Kontraktor harus segera
memberitahukan kepada Direksi untuk mendapatkan persetujuan tertulis
dari Direksi.
61
c. Lapangan
Kontraktor agar supaya menyerahkan penjelasan yang menyangkut
perlengkapan dan bahan kepada Pengguna Jasa sesuai dengan permintaan,
untuk tujuan pemeriksaan, tetapi bagaimanapun juga tidak mengurangi
tanggungjawab Kontraktor untuk menyediakan perlengkapan dan bahan
sesuai dengan spesifikasi.
62
dan buruh untuk maksud tersebut di atas merupakan beban Kontraktor.
Dan semua biaya tersebut sudah termasuk dalam harga satuan di dalam
pekerjaan pada Daftar Kuantitas dan Harga.
SU - 15.1. Umum
Kontraktor akan bertanggungjawab terhadap perencanaan, spesifikasi,
pelaksanaan dan termasuk pemindahan semua pekerjaan sementara untuk
pelaksanaan pekerjaan dengan sebaik-baiknya. Detail dari pekerjaan
sementara yang akan dilaksanakan Kontraktor di lapangan, harus
diserahkan kepada Direksi untuk mendapat persetujuan sesuai dengan
prosedur dalam Spesifikasi Umum.
Apabila Kontraktor bermaksud mengajukan alternatif untuk pekerjaan
sementara di luar daerah lapangan seperti terlihat pada gambar, semua
biaya yang dibutuhkan untuk melaksanakan termasuk pembebasan tanah,
sewa tanah dan sebagainya, ditanggung oleh Kontraktor dan biayanya sudah
termasuk pada uraian pekerjaan pada daftar volume pekerjaan.
Keterlambatan menjadi tanggung jawab Kontraktor sesuai ketentuan dalam
Kontrak. Dalam hal tersebut tidak diberikan perpanjangan waktu bila terjadi
keterlambatan.
SU - 16.1. Umum
Keamanan dan pemeriksaan kesehatan yang perlu selama pelaksanaan
pekerjaan, antara lain pengaturan kesehatan, pembersihan lapangan, bahan
berbahaya dan bensin, pemagaran sementara, keamanan dan pencegahan
kebakaran, disiapkan dan dipelihara oleh Kontraktor atas biaya Kontraktor.
Kontraktor harus bertanggungjawab terhadap keamanan dan pemeriksaan
63
kesehatan, dan menyerahkan peraturan dan organisasi untuk mendapatkan
persetujuan Direksi. Tidak ada pembayaran tambahan, dan dalam hal ini
semua biaya sudah termasuk dalam harga kontrak.
64
harus berusaha keras memadamkan kebakaran yang terjadi di lokasi
pekerjaan.
Dalam hal ini, Kontraktor harus menyediakan perlengkapan yang diperlukan
dan melibatkan tenaga kerja di lapangan, termasuk peralatan dan tenaga
Sub Kontraktor.
SU - 17.1. Umum
Kegiatan mobilisasi dan demobilisasi dapat meliputi hal-hal sebagai berikut :
a. Penyiapan dan perataan lahan yang diperlukan untuk base camp
Kontraktor dan kegiatan pembangunannya.
b. Mobilisasi dan pemasangan konstruksi dari tempat perakitan/pabrik
yang ada sampai lokasi pekerjaan.
c. Penyediaan dan pemeliharaan Base Camp Kontraktor, meliputi kantor,
tempat tinggal, bengkel, gudang dan sebagainya.
d. Penyediaan dan pemeliharaan peralatan pengujian laboratorium
apabila diperlukan. Peralatan ini akan tetap menjadi hak milik
Kontraktor pada waktu penyelesaian proyek.
e. Mobilisasi semua alat-alat berat dan kendaraan yang akan dipakai
operasional kontraktor selama pengerjaan proyek, dan demobilisasi
setelah pekerjaan selesai.
f. Mobilisasi semua tenaga Kontraktor yang terlibat dalam pekerjaan
tersebut, dan demobilisasi setelah pekerjaan selesai.
65
SU.17.3 Program Demobilisasi
a. Setelah pelaksanaan proyek, Kontraktor harus mengajukan program
demobilisasi kepada Direksi.
b. Program demobilisasi yang ada harus menetapkan pengaturan
waktu dari semua kegiatan sebagaimana diterangkan dalam Pasal
SU-17 dan memasukkan informasi tambahan yang dapat ditetapkan,
antara lain:
1). Jadwal pengiriman peralatan, jumlah peralatan dan sarana
transportasi yang dipakai.
2). Daftar terinci yang menunjukkan struktur yang memerlukan
perkuatan untuk lintasan lalu-lintas yang aman, berikut dengan
metodologi pelaksanaan yang diusulkan, tanggal permulaan dan
akhir yang dijadwalkan untuk perkuatan setiap struktur.
66
SPESIFIKASI TEKNIS
ST – 1 PEKERJAAN PERSIAPAN
ST–1.1. UMUM
Kontraktor harus menyediakan, mengoperasikan, dan memelihara fasilitas
konstruksi sebagaimana tercantum dalam bagian yang relevan dari
Spesifikasi Umum sesuai dengan persyaratan sebagaimana diatur
selanjutnya dan diarahkan atau disetujui oleh Direksi Pekerjaan yang
dituangkan dalam Berita Acara Pemeriksaan Pekerjaan.
Semua fasilitas konstruksi yang disediakan oleh Kontraktor harus mendapat
persetujuan dari Direksi atau Pengguna Jasa serta aturan perundangan yang
berlaku.
Dalam waktu enam puluh (15) hari setelah menerima Surat Perintah Mulai
Kerja (SPMK), Kontraktor harus menyerahkan program kerja untuk
mendapat persetujuan Direksi sebagaimana diatur dalam Pasal SU-9 dari
Spesifikasi Umum, program rinci untuk pasokan (tenaga, bahan dan alat)
konstruksi, dan pemeliharaan semua fasilitas konstruksi yang akan
diberikan. Program tersebut harus mencakup penjelasan penuh dari semua
rincian yang berkaitan dengan fasilitas termasuk lingkup pekerjaan, lokasi
kegiatan, dan semua bagan alir/flow chart yang diperlukan, program
konstruksi, gambar, detail desain dan perhitungan, serta deskripsi tertulis
dari semua peralatan, bahan, dan hal yang tak terduga, sehingga
memungkinkan penilaian yang lengkap dan tepat dari semua pekerjaan
terkait yang harus dilakukan oleh Direksi Pekerjaan. Selain itu Kontraktor
wajib, pada saat yang sama, mengajukan semua izin yang diperlukan sesuai
dengan aturan yang berlaku dengan syarat bahwa Direksi akan memberikan
semua bantuan yang wajar dalam memperoleh semua izin yang diperlukan.
67
lainnya yang sudah ada, atau akan meningkatkan dan memperkuat fasilitas
yang ada, yang akan digunakan/diperlukan untuk akses ke lokasi pekerjaan.
Semua biaya yang dikeluarkan oleh Kontraktor dalam memenuhi
persyaratan Pasal SU- 6.2.1 dari Spesifikasi Umum sudah dianggap
termasuk dalam harga lump sum untuk Pemeliharaan Jalan Akses dalam
Daftar Kuantitas, yang akan mencakup semua biaya yang dikeluarkan oleh
Kontraktor dalam kompensasi atas penggunaan dari setiap daerah di luar
haknya yang disediakan oleh Pengguna Jasa untuk pekerjaan dan pekerjaan
sementara, yang mungkin diperlukan.
68
pengolahan semua limbah, dan limbah pembuangan serta memfasilitasi
monitoring dari Badan Pemantauan Lingkungan Hidup Daerah, dianggap
sudah dimasukkan dalam harga satuan pekerjaan dalam Daftar Kuantitas
dan Harga.
69
Spesifikasi Umum, harus dianggap termasuk dalam harga satuan pekerjaan
dalam Daftar Kuantitas dan Harga.
ST – 2.1. UMUM
70
ST – 2.1.2. Dimensi, Batas dan Ketinggian Pekerjaan Tanah
Semua pekerjaan tanah harus dilaksanakan menurut dimensi, batas dan
ketinggian sebagaimana ditunjukkan dalam gambar atau seperti ukuran dan
ketinggian lain sebagaimana ditentukan oleh Direksi. Dimensi dan batas
yang berdasarkan pada atau yang berhubungan dengan permukaan tanah,
harus ditunjukkan kepada Direksi sebelum dimulai pekerjaan tanah di suatu
lokasi.
Untuk keperluan spesifikasi tersebut, penentuan ketinggian permukaan
tanah asli harus mengikuti permukaan tanah atau permukaan dasar kanal
sebelum memulai pekerjaan tanah, sesuai dengan yang tercantum pada
pasal 14.2. dalam Spesifikasi Umum. Pengukuran elevasi muka tanah asli
harus mengikuti sistem grid yang tercantum pada gambar.
Kontraktor harus melengkapi dan bertanggungjawab penuh untuk penetapan
posisi pekerjaan-pekerjaan dan menetapkan dalam jumlah yang memadai
titik-titik tetap dan titik-titik ikat. Survey yang akan dilaksanakan oleh
Kontraktor digambarkan pada pasal 14 dalam Spesifikasi Umum. Posisi
galian dan pulau sebagai tempat pembuangan hasil galian harus ditentukan
sesuai koordinat seperti tercantum pada gambar.
ST – 2.4.1. Umum
Timbunan kanal blocking harus termasuk pengadaan material yang
memenuhi syarat yang didapatkan dari hasil sekitar lokasi saluran dari
kanal blocking. Kontraktor diperkenankan untuk menentukan lokasi galian
untuk penimbunan dengan persetujuan Direksi.
71
oleh Direksi. Pengukuran tidak akan dilakukan diluar batas timbunan
yang ditetapkan.
b. Pembayaran
Pembayaran untuk timbunan harus dilakukan berdasarkan harga satuan
seperti tercantum dalam Daftar Kuantitas Harga dan harus dianggap
termasuk seluruh kompensasi untuk penyediaan tenaga kerja, bahan
timbun, peralatan, alat bantu dan sebagainya untuk menyelesaikan
pekerjaan-pekerjaan dan dengan teknik pelaksanaan terbaik dan
sepenuhnya sesuai dengan semua persyaratan yang dijelaskan dalam
Spesifikasi.
ST – 3 PEKERJAAN LAIN-LAIN
ST – 3.1. UMUM
Pasal ini mencakup spesifikasi dan persyaratan-persyaratan untuk
pelaksanaan pekerjaan yang berbeda dari pekerjaan-pekerjaan dan
komponen pada pasal-pasal sebelumnya. Pekerjaan-pekerjaan yang tercakup
dalam spesifikasi teknik pada pasal ini, ini harus termasuk, tetapi tidak
terbatas dan semacamnya serta semua seperti yang tampak pada gambar
atau atas perintah dari Direksi.
72
ST – 3.2.2. Pengukuran dan Pembayaran
a. Pengukuran
Pengukuran untuk pembayaran Patok Bench Mark, harus didasarkan
pada jumlah yang dihitung dari gambar dan / atau yang diperintahkan
oleh Direksi.
b. Pembayaran
Pembayaran untuk Patok Bench Mark, dianggap sudah termasuk dalam
harga satuan pekerjaan yang ditenderkan pada Daftar Kuantitas dan
Harga.
73
74