Subcontractor's Daily Report

Project : Subcontractor:
JCLDS Urdaneta Temple Philippines BGC Philbuilder, Inc.
Location: Date:
Urdaneta City, Pangasinan JUNE 11, 2021

MANPOWER
STAFF/TECHNICAL SKILLED/NON-SKILLED
ACTUAL ACTUAL
PRESENT PRESENT
DESIGNATION PRESENT DESIGNATION PRESENT
MANPOWER TO MANPOWER TO
ON SITE ON SITE
DATE DATE
PROJECT MANAGER 1 1 1 LEADMAN 1 1 1
PROJECT IN-CHARGE 1 1 0 MASON 0 0 0
QA/QC ENGINEER 1 1 0 GENERAL WORKER 2 2 2
SITE ARCHITECT 1 1 1
SAFETY OFFICER 1 1 1
FIRST AIDER 1 1 1

TOTAL 6 6 4 TOTAL 3 3 3

Safety Man-hour Staff/Technical: 32


Safety Man-hour Skilled/Non-Skilled: 24
Total Safety Man-hour: 56
Previous Safety Man-hour accumulative: 3256
To date Safety Man-hour accumulative: 3312

Prepared by: Checked by: Approved and Received by:

Jean Sambat Jonathan Mendoza Michael Manalo


BGCPI QA/QC Engineer BGCPI Project Manager HASKELL MEPF Superintendent
Subcontractor's Daily Report

ACTIVITIES ON CONSTUCTION OF TEMPORARY FACILITY


1. MANUAL LAYOUT AT AREA B & D
START: 7:30 AM END: 4:00 PM
Equipment: NONE
Hand Tool: HAMMER
Materials: STAKE WITH SAFETY END CAP, NYLON, ROPE
DETAILS