VIETNAM OIL AND GAS GROUP

BIEN DONG PETROLEUM OPERATING COMPANY


FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK

SECTION 3
SCOPE OF WORK

TABLE OF CONTENT

Form of Contract No.: BD-OPS-2021-008 Page 1 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
1. SCOPE OF WORK 3
2. REFERENCE COMPANY DOCUMENTS & STANDARDS 8
3. TECHNICAL REQUIREMENTS 9
4. PROJECT SCHEDULE REQUIREMENTS 10
5. CONTRACTOR’S REQUIREMENTS AND RESPONSIBILITIES 11
6. DOCUMENTATION REQUIREMENTS 13
7. ATTACHMENTS 14

Form of Contract No.: BD-OPS-2021-008 Page 2 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK

1. SCOPE OF WORK

1.1. Introduction
The Produced Water System consists of Hydrocyclone, Degasser and associated piping &
instrument. The purpose of the system is to treat the water produced from the 2 nd
Separation Stage to meet the regulatory requirement (Oil in Water ratio < 40mg/L), before
being discharged overboard through Dump Caisson.
The existing Produced Water Treatment (PWT) skid is designed for the capacity of 5,500
bwpd (barrel of water per day) which is equivalent to 36.36 m 3/hr with the following
specification:
 Design Capacity: 36 m3/hr (5,500BWPD)
 Operating Inlet Pressure: 16 – 24 barg
 Operating Inlet Temp.: 34 – 940C
 Maximum Free Oil Content: 2,500 ppm (at Package Feed)
 Maximum Oil in Water: 40 ppm (at Package Water Outlet)
Hydrocyclone pressure drops on oil side and water side are measured and transmitted to
a differential pressure ratio controller that will open/close the valve on the oil side to keep
the ratio of pressure drop constant. Hydrocyclone is protected against overpressure by
relief valves that are designed for fire case.
The liquid level at Degasser is controlled by two (02) sets of 100% LCV-3721A/B to
maintain liquid residence time at Degasser before being discharged to Dump Caisson.

Figure 1 – Produced Water Treatment System on PQP-HT


The current flowrate of Produced Water is around 3,500 bwpd. In order to control the level
of Degasser, the valve on-duty (in auto-mode) is opened around 60% and other standby
valve (in manual-mode) is kept opening around 50%. In case just one valve in operation,
the level of Degasser cannot be controlled even though the valve on-duty is 100%
opened. An investigation of the system has been carried out to find out that the operating
pressure at Degasser was almost at the atmospheric pressure as Degasser is directly

Form of Contract No.: BD-OPS-2021-008 Page 3 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
connected to the LP Flare through 4-in pipe and there is no pressure built-up inside the LP
Flare system.
As per the original design, Degasser was assumed to operate at 0.4 barg, the LCV-
3721A/B have been sized for the max case with the inlet pressure of 0.4 barg. Therefore,
the existing Degasser must be upgraded/ modified to achieve the operating pressure of
0.4 barg in order to maintain the vessel functioning as per its original design purpose.

1.2. General Information


This document is to define the Scope of Work (SOW) for engineering, procurement,
construction & installation services for modification/ upgrading of the Degasser system on
PQP-HT platform.
The service CONTRACT shall be awarded on an EPCI basis covering full SOW for
upgrading the Degasser system on PQP-HT platform, except procurement of valves which
shall be provided by COMPANY.
CONTRACTOR shall provide PERSONNEL, TOOLS/ EQUIPMENT, MATERIALS/
CONSUMABLES & other required RESOURCES to carry out the SOW as following, but
not necessarily limited to:
 Site survey, detailed engineering and design drawings (P&ID, Isometric, etc.) for
modification of the Degasser system on PQP-HT; liaise with Vietnam Register (VR) to
obtain VR’s approval & certification for the engineering design (if required);
 Procurement of piping components, fittings, materials & consumables for fabrication
and installation (process valves NOT included in this scope);
 Fabrication of process piping components as per approved Isometric drawings at
CONTRACTOR’s onshore workshop;
 Load-out & transportation of tools/equipment, fabricated piping components, fittings &
other consumables to COMPANY’s offshore facility;
 Installation/ hook-up of piping components, valves & fittings to the Degasser system;
 Leak-test, hydrotest & commissioning for the Degasser system upon modification as
per approved procedures;
 Submission of As-built Dossier upon completion of the WORK (Refer to Section 6 for
further details);
 Issuance of the warranty for the upgraded Degasser system for minimum of twelve (12)
months;
CONTRACTOR shall ensure that the modification work required on PQP-HT platform is
fully integrated into the existing facilities. CONTRACTOR shall plan and maintain
schedule such that installation work and testing/ commissioning of process piping and
control system are completed with the minimum interruption to the platform production.
CONTRACTOR shall, for the duration of the work, assign the necessary qualified and
experienced personnel, tools/ equipment, materials/ consumable and other resources
required to fulfill the objectives of this CONTRACT.

Form of Contract No.: BD-OPS-2021-008 Page 4 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK

Table 1 – General SOW for Modification of Degasser


Item
Description Unit Q.ty Rate Remark
No.
Modification of PQP Degasser
Site Survey, Engineering Work, Procurement &
I
Onshore Fabrication
1 Site survey LOT 01 Lump-sum
2 Project management LOT 01 Lump-sum
3 Engineering work LOT 01 Lump-sum
Procurement of materials/ consumables
4 LOT 01 Lump-sum
(process valves NOT included in this scope)
5 Onshore fabrication of process piping components LOT 01 Lump-sum
II Offshore Installation, Testing & Commissioning
6 Load-out, mobilization & transportation LOT 01 Lump-sum
Offshore installation of process piping
7 LOT 01 Lump-sum
components, valves & fittings, etc.
8 Testing & commissioning for the upgraded system LOT 01 Lump-sum
9 Submission of the As-built Dossier LOT 01 Lump-sum
1.3 WORK Description & RESPONSIBILITY Matrix
The further extent of SOW and the responsibility of COMPANY/ CONTRACTOR shall be
defined in more detail within the WORK Description & RESPONSIBILITY Matrix below.
Table 2 – WORK Description & RESPONSIBILITY Matrix
Item
WORK Description Company Contractor Location Remark
No.
Modification of PQP Degasser
To collect all the
necessary
1 Site Survey S X Offshore information/ data for
bidding &
engineering work
To meet the Project
Onshore/
2 Project Management S X Milestones approved
Offshore
by COMPANY
3 Engineering Work
Revise P&ID, issue Piping
3.1 S X Onshore
Isometric & shop drawings, MTO
Perform pipe-stress analysis and
3.2 X Onshore
relevant calculations
Documents to be
Prepare Work-pack for offshore submitted to
work (Method Statement, Project COMPANY for
3.3 X Onshore
Execution Plan, Risk-Assessment, review & approval
etc.) prior mobilization to
offshore
2nd site survey for detailed
If required by
3.4 engineering work and construction/ S X Offshore
CONTRACTOR
installation method
3.5 Prepare all necessary procedures X Onshore All procedures to be
required for onshore/ offshore work submitted to
(welding, blasting/ painting, bolt- COMPANY for
tensioning, testing, commissioning, review & approval
etc.) before

Form of Contract No.: BD-OPS-2021-008 Page 5 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
Item
WORK Description Company Contractor Location Remark
No.
Modification of PQP Degasser
commencement of
onshore/offshore
work
Liaise with Vietnam Register (VR)
If compulsory as per
3.6 to obtain VR’s approval & S X Onshore
regulation
certification (if required)
4 Procurement
Piping fabrication materials (pipes, To be made in
4.1 fittings & flanges) as per Piping X Onshore EU/G7 countries
Class Spec. A & A6 (Attachment 6) plus Korea
Piping erection materials (flanges,
To be made in
gaskets, bolts & nuts) as per
4.2 X Onshore EU/G7 countries
Piping Class Spec. A & A6
plus Korea
(Attachment 6)
Valves/ in-line items as per Valve To be provided by
4.3 X Onshore
Spec. (Attachments 2, 3, 4, 5) COMPANY
Other consumables required for
onshore fabrication, offshore
4.4 X Onshore
installation/ modification & testing/
commissioning work
5 Onshore Fabrication
CONTRACTOR to
Fabricate the process piping be responsible for
components/ spools and associate the accuracy/
5.1 X Onshore
pipe supports as per Piping adequacy of onshore
Isometric/ Shop-drawings fabricated
components
Apply external coating layers for
External coating to
process piping components/
5.2 X Onshore follow Paint Matrix
spools & pipe supports upon
for BD1 Project
fabrication
To follow
Hydrotesting/
Flushing &
Hydrotest for fabricated piping
Pneumatic
5.3 components/ spools & process X Onshore
Procedure
valves
Process valves to be
provided by
COMPANY
Wrap/ pack piping components/
To follow Temporary
spools, fittings, tools/ equipment &
5.4 X Onshore Equipment
consumables to containers/
Procedure
baskets prior to load-out
Load-out, Mobilization &
6
Transportation
Transfer the containers/ baskets of
piping components/ spools, fittings,
tools/ equipment & consumables
6.1 X Onshore
upon packing/ wrapping from
CONTRACTOR’s workshop to
PTSC Port
Load-out the containers/ baskets
of piping components/ spools,
6.2 X S Onshore
fittings, tools/ equipment &
consumables to vessel

Form of Contract No.: BD-OPS-2021-008 Page 6 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
Item
WORK Description Company Contractor Location Remark
No.
Modification of PQP Degasser
Transport the containers/ baskets
of piping components/ spools,
6.3 fittings, tools/ equipment & X S Onshore
consumables from PTSC Port to
COMPANY’s offshore facility
Process valves to be
Transport the process valves to
6.5 X Onshore provided by
COMPANY’s offshore facility
COMPANY
Mobilize the personnel for the
6.6 X S Onshore
offshore modification work
COMPANY to
Medevac service for emergency provide the medevac
6.7 X S Onshore
case in case of
emergency
Offshore Installation /
7
Modification Work
Provide Safety Induction, Permit-
to-Work (PTW) training for
7.1 X Offshore
Personnel on arrival to offshore
platform
Prepare all required paperwork
prior every offshore working
7.2 session (PTW, Job Safety Analysis S X Offshore
(JSA), Toolbox talk, hot-work
checklist, etc.)
Install the fabricated piping
components, valves & fittings as
7.3 X Offshore
per approved design and work
schedule
Modify existing process pipework,
7.5 pipe-supports as per approved X Offshore
design and work schedule
DPR/ WPR to be
Prepare the Daily Progress Report sent to COMPANY’s
7.6 (DPR)/ Weekly Progress Report X Offshore representatives for
(WPR) monitoring work
progress
8 Testing & Commissioning
To follow
Hydrotesting/
8.1 Leak-test S X Offshore Flushing &
Pneumatic
Procedure
8.2 Commissioning S X Offshore
9 Submission of As-built Dossier
As-built Dossier to
Submit the complete set of As-built be submitted within
9.1 Dossier as per requirements in X Onshore two (02) weeks upon
Section 6.2 the completion of
offshore work
Notes:
“X” = Main Responsibility “S” = Supporting

2. REFERENCE COMPANY DOCUMENTS & STANDARDS

Form of Contract No.: BD-OPS-2021-008 Page 7 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
CONTRACTOR shall carry out the service in accordance with the followings, but not
necessarily limited to:

2.1. Design Codes & Standards

 ASME B31.3–2020 Process Piping


 AWS B1.10 Guide for the Nondestructive Examination of Welds
 AWS B2.1 Specification for Welding Procedure & Performance
Qualification
 AWS D1.1 Structural Welding Code – Steel

2.2. COMPANY’s Specifications & Procedures

 BD-00-X-S-0002 Guideline for basic noise control requirement and procedures


 BD-00-X-S-0007 Specification for safety & firefighting equipment
 BD-00-X-S-0010 Specification for safety signs
 BD-OPS-MNR-P-2006 Piping Inspection Procedure
 BD-00-M-S-0331 Specification for Painting and Protective Coatings
 BD-00-M-S-0332 Specification for Welding for Piping & Equipment
 BD-00-M-S-0333 Specification for Insulation for Equipment & Piping
 BD-00-M-S-0335 Specification for vendor drawing & documentation
 BD-00-M-S-0380 Specification for Produced Water Treatment Package
 BD-00-P-S-0001 Piping Class Specification
 BD-00-P-S-0002 Specification for Piping Fabrication, Installation, Inspection &
Testing
 BD-00-P-A-0001 Piping design basis
 BD1-00-P-A-0002 Pipe Stress Analysis Design Basis
 BD-OPS-MNR-P-1009 Temporary Equipment Procedures
 BD-OPS-MNR-P-2001 Leak and Hydrostatic Test Procedure
 BD-OPS-MNR-P-1013 Corrosion Management Strategy
 BD-OPS-MNR-P-2012 Coating Maintenance & Repair Procedure
 E1001-00-Q-L-0001 Paint Matrix for Bien Dong 1 Project
 E1001-00-Q-L-0004 NDT Matrix for Bien Dong 1 Project
 E1001-00-Q-P-0020-2 Surface Preparation and Painting Procedure
 E1001-00-T-P-0002 Hydrotesting/ Flushing & Pneumatic Procedure
 VSP-BD1-00-Q-P-0018 Coating Application and Testing Procedure
The latest edition of the following codes and standards above shall be applicable.
CONTRACTOR may propose an equivalent alternative code compliance, in which case,
the CONTRACTOR shall clearly identify the propose alternate in the proposal. However,
any proposed alternate shall be subjected to COMPANY approval.

Form of Contract No.: BD-OPS-2021-008 Page 8 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
3. TECHNICAL REQUIREMENTS
CONTRACTOR is requested to upgrade/ modify the existing Degasser system to meet the
technical requirements as following, but not necessarily limited to:

3.1. Overall Project Objective


Degasser is assumed to operate at 0.4 barg, the LCV-3721A/B have been sized for the
max case with the inlet pressure of 0.4 barg as per the original design. Therefore, the
existing Degasser must be upgraded/ modified to achieve the operating pressure of
0.4 barg in order to maintain the vessel functioning as per its original design
purpose.

3.2. Process Pipework

 The additional process pipework shall be routed/ designed as per marked-up P&ID
drawing of the Produced Water Treatment Skid (Refer to Attachment 1);
 The pipe-stress analysis shall be performed for the designed process pipework to verify
if the design is NOT overstressed (Refer to BD1-00-P-A-0002);
 Piping Isometric drawings & detailed MTO shall be then prepared based on the
approved design of additional process pipework;
 The fabrication materials (pipes, fittings & flanges) and erection materials (flanges,
gaskets, bolts & nuts) must follow BD1 Project – Piping Class Specifications (Refer to
Attachment 6):
 Piping specification Class A for Nitrogen service line;
 Piping specification Cass A6 for other service lines (closed/ open drain, atmospheric
vent, HP flare, etc.);
 Pipe-support materials: ASTM A36 or JIS G3101 SS400;
 CO (copy), CQ (copy) & Mill Cert. must be submitted to COMPANY for review &
approval;
 Valves/ in-line items shall be provided by COMPANY.

3.3. Process Valves

 The process valves shall be provided by COMPANY;


 CONTRACTOR’s responsibility is only to install the process valves to the existing
Degasser system in according to approved P&ID and Piping Isometric drawings.

3.4. Welding Joints (for fabrication)

 All welding joints shall strictly follow Welding Procedure Specification (WPS) proposed
by CONTRACTOR which must been approved & certified by a well-known Certification
Authority (CA);
 All welding joints shall be tested and met requirements as per NDT Matrix (E1001-00-
Q-L-004).

Form of Contract No.: BD-OPS-2021-008 Page 9 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
3.5. Bolting Joints (for erection)

 All bolting connections shall be detailed based on the approved design of process
pipework;
 All required consumables (gaskets, stud bolts, nuts) and tension-forces shall follow BD1
Project – Piping Class Specifications (Refer to Attachment 6).

3.6. Surface Preparation & Painting

 External surface shall be prepared as per E1001-00-Q-P-0020-2 or equivalent


procedure proposed by CONTRACTOR;
 External painting system shall follow BD-01 Coating system (BD-00-M-S-0331) and
meet requirements as per Painting Matrix (E1001-00-Q-L-0001).

3.7. Testing & Commissioning

 The fabricated piping components shall be hydrotested as per E1001-00-T-P-0002 or


equivalent procedure proposed by CONTRACTOR;
 The upgraded Degasser system shall be leak-tested as per E1001-00-T-P-0002 or
equivalent procedure proposed by CONTRACTOR.

3.8. Warranty

 The offshore installation/ modification work shall have warranty for at least twelve (12)
months since the work completion certificate (WCC) is signed off by COMPANY’s
representative.

4. PROJECT SCHEDULE REQUIREMENTS


CONTRACTOR shall follow the project schedule as proposed below:
 Estimated start date of service: 15-April-2021
 Duration of engineering work: Three (03) weeks
 Duration of procurement of materials: Ten (10) weeks
 Duration of onshore fabrication: Four (04) weeks
 Duration of offshore installation: Four (04) weeks
 Location to perform the Service: COMPANY’s Offshore Facility (PQP-HT)

Form of Contract No.: BD-OPS-2021-008 Page 10 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK

5. CONTRACTOR’s REQUIREMENTS AND RESPONSIBILITIES

5.1. CONTRACTOR’s Capability & Experience Requirements


CONTRACTOR is requested to submit the company profile presenting the following
criteria, but not necessarily limited to:
 CONTRACTOR must have a valid business license for engineering, procurement,
construction & installation services in Oil & Gas industry;
 CONTRACTOR must have minimum three (03) similar projects/ service contracts in
offshore engineering & construction;
 CONTRACTOR must have minimum five (05) years of experience in Oil & Gas
industry;
 CONTRACTOR must have HSE policy & Quality management system.

5.2. CONTRACTOR’s Manpower Requirements


CONTRACTOR must submit the Project Organization Chart with a minimum list of
PERSONNEL as below for COMPANY’s review & approval.
CONTRACTOR must provide a list of competent and qualified PERSONNEL to carry out
the WORK with the minimum requirements as follows, but not necessarily limited to:
 At least one (01) Project Manager having minimum certifications & qualifications as
listed in Attachment 7 – Personnel’s Certifications & Qualifications;
 At least one (01) Process Engineer having minimum certifications & qualifications as
listed in Attachment 7 – Personnel’s Certifications & Qualifications;
 At least one (01) Piping Engineer having minimum certifications & qualifications as
listed in Attachment 7 – Personnel’s Certifications & Qualifications;
 At least one (01) Process/ Piping Draftsman having minimum certifications &
qualifications as listed in Attachment 7 – Personnel’s Certifications & Qualifications;
 At least one (01) Project Supervisor having minimum certifications & qualifications as
listed in Attachment 7 – Personnel’s Certifications & Qualifications;
 At least one (01) Welder 6G having minimum certifications & qualifications as listed in
Attachment 7 – Personnel’s Certifications & Qualifications;
 At least one (01) MT/PT Inspector (LV2) having minimum certifications & qualifications
as listed in Attachment 7 – Personnel’s Certifications & Qualifications;
 At least one (01) Scaffolding Supervisor (LV3) having minimum certifications &
qualifications as listed in Attachment 7 – Personnel’s Certifications & Qualifications;
 At least two (02) Mechanical Technician having minimum certifications & qualifications
as listed in Attachment 7 – Personnel’s Certifications & Qualifications;
All PERSONNEL provided by CONTRACTOR to carry out the WORK must have:
 Resume or relevant training certificate for required skill set (required for all personnel);

Form of Contract No.: BD-OPS-2021-008 Page 11 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
 Valid Medical certificate fit for offshore work (required for personnel working offshore
only);
 Valid T-BOSIET/BOSIET certificate approved by OPITO (required for personnel
working offshore only).

5.3. CONTRACTOR’s Tools/ Equipment Requirements


CONTRACTOR shall provide a list of TOOLS/ EQUIPMENT and its related validated
certificate to carry out the WORK with the minimum requirements as follows, but not
necessarily limited to:
 At least 200m3 of Scaffolding tower/hanging type meets BS 1139 (including tube, fixed
couple, swivel couple, sleeve couple, beam clamp, deck board, etc…);
 At least two (02) short baskets c/w slings & shackles set for scaffolding transportation;
 At least two (02) long baskets c/w slings & shackles set for materials transportation;
 At least two (02) 10ft-container c/w slings & shackles for materials transportation;
 At least one (01) Blasting equipment c/w completed accessories;
 At least one (01) Painting equipment c/w completed accessories (including airless
spray equipment);
 At least one (01) set of QC painting equipment (thickness gauge, surface temp. gauge);
 At least one (01) Set of Air Compressor, Max. Capacity 130 - 750 CFM;
 At least one (01) Set of RT equipment c/w all accessories and consumables;
 At least one (01) Set of UT equipment c/w all accessories and consumables;
 At least one (01) Set of MT/MPI equipment c/w all accessories and consumables;
 At least two (02) Tig welding machine c/w accessories;
 At least two (02) Milling machines;
 At least two (02) Stationary grinding machines;
 At least two (02) Magnetic drilling machines;
 At least two (02) Pneumatic drilling machine;
 At least two (02) Sets of Oxy and Acetylene cutting / heating outfit (torch handle, gas
hoses, pressure regulators etc.);
 At least one (01) Set of Semi-habitat equipment (complete set including air hose 30m,
air blower, ex. lamp, etc.)
 At least one (01) Set of Pressurized habitat equipment (size 2x2x2m) (completed set
including air hose 30m, air blower, ex. Lamp, etc.);
 At least one (01) Set of tools for bolt-tensioning;
 At least one (01) Set of tools for leak-test/ hydrotest.
Equipment used for performing WORK for COMPANY shall be in good condition, suitable
for use on site/ work-place and in hazardous areas (if any) and in compliance with
COMPANY’S requirements and specifications for portable and temporary equipment.

Form of Contract No.: BD-OPS-2021-008 Page 12 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK
CONTRACTOR shall refer to BD-OPS-MNR-P-1009 – Temporary Equipment Procedures
for detailed requirement.
The AC power suppliers are available on COMPANY’s offshore facilities:
 415V, 3P, 3P+N+E, 50Hz, 63A Max.
 240V, 1P, 1P+N+E, 50Hz, 13A Max.
There is no DC supply on COMPANY’s offshore facilities; therefore, CONTRACTOR must
provide its own DC service.

6. DOCUMENTATION REQUIREMENTS

6.1. Technical Evaluation Purpose (for all BIDDERs)


CONTRACTOR must submit a list of Attachments to Technical Proposal with the minimum
requirements as follows, but not necessarily limited to:
 Draft P&ID & Piping Isometric drawings (in A3 paper);
 Draft Pipe-stress analysis report (if possible);
 Draft Materials Take-off (MTO);
 Draft Method Statement and Project Execution plan to meet the project milestones as
mentioned in Section 4;
 Weld Procedure Specification (WPS) and list of Welders c/w valid certificates;
 NDT procedures and list of Inspectors c/w valid certificates;
 Blasting & painting procedure;
 Hydrotest & Leak-test procedures;
 Other information to prove BIDDER’ capacity & experience.

6.2. Final Documentation (for successful BIDDER)


CONTRACTOR shall submit the complete set of As-built Dossier with the minimum
requirements as follows, but not necessarily limited to:
 Revised P&ID drawings, Pipe-stress Analysis report, Piping Isometric drawings,
detailed MTO & shop-drawings with COMPANY’s final approval;
 Certificate of Origin (CO), Certificate of Quality (CQ) and Mill Certificates;
 Non-destructive testing (MPI) report;
 Hydrotest & Leak-test report;
 Commissioning report & Form of Acceptance;
 Warranty certificate for at least twelve (12) months from the Date of Completion;
 Work Completion Certificate (WCC).

Form of Contract No.: BD-OPS-2021-008 Page 13 of 14


VIETNAM OIL AND GAS GROUP
BIEN DONG PETROLEUM OPERATING COMPANY
FORM OF CONTRACT FOR PROVISION OF TECHNICAL SERVICE FOR MODIFICATION OF
DEGASSER SYSTEM ON PQP-HT PLATFORM
SECTION 3 – SCOPE OF WORK

7. ATTACHMENTS

7.1. Attachment 1 Mark-up P&ID


7.2. Attachment 2 Pressure Self-regulator Datasheet
7.3. Attachment 3 Rupture Disc Datasheet
7.4. Attachment 4 Ball Valve Datasheet
7.5. Attachment 5 Globe Valve Datasheet
7.6. Attachment 6 Piping Class Specification A, A6
7.7. Attachment 7 Personnel’s Certifications & Qualifications

Form of Contract No.: BD-OPS-2021-008 Page 14 of 14