Professional Documents
Culture Documents
Motorpool Procedure: Procedures Manual
Motorpool Procedure: Procedures Manual
Motorpool Procedure: Procedures Manual
Date : 12-05-16
PROCEDURES MANUAL
Revision No. : 00 Pages : 1 of 5
MOTORPOOL PROCEDURE
I. OBJECTIVE
To ensure the maintenance and efficient operation of all equipments, motor vehicles,
machines, generator and other small equipment.
II. SCOPE
Preventive and corrective maintenance of all equipments, motor vehicles, machines,
generator and other small equipment.
End-users – refer to accountable officer who was assigned with equipment and motor
vehicle
PR – Purchase Requisition
JO – Job Order
V. REFERENCE DOCUMENTS
Annual Preventive Maintenance Schedule, Annual Procurement Plan
No. Process Flow Description of Activity Guidelines/Criteria/Policy Responsible Person Retained Information
1. Simultaneous in the preparation of the
START
Corporate Operating Budget/ Annual 1.1 Status Report of all
Procurement Plan the General Services vehicles and
Chief shall prepare also the Annual equipments
1 Preventive Maintenance Plan of all motor 1.2 Preventive
Annual Procurement Plan General Services Chief
Maintenace
vehicles and equipment of MKWD to Schedule
Annual Preventive include the budget of preventive 1.3 Annual Calendar of
Maintenance Plan maintenance of vehicles and equipment in Activities
the APP.
Preventive Maintenance
2.2 Excavator
A 2.2.1 Battery
2.2.1 Daily check-up before using
the heavy equipment
2.2.2 Lights
2.2.2 Engine Oil twice a year
2.2.3 Oil (Engine and Hydraulic Oil)
2.2.3 Hydraulic Oil four times a year
2.2.4 Water
2.3 Motorcycles
2.3.1 Battery 2.3.1 Daily check-up of motor before
2.3.2 Lights utilization
2.3.3 Oil (Engine Oil) 2.3.2 Change battery once a year
2.3.3 Engine oil once a year
2.3.4 Brakes
2.3.4 Brakes once a year
2.3.5 Gas 2.3.5 Tires once a year
2.3.6 Self (seats, tires, guages 2.3.6 Tune-up once a year
& mirror)
2.3.7 Horn
2.3.8 Emergency equipment
2.4 Equipments
2.4 Conduct pre-operation and check-
2.4.1 Compressor up
2.4.2 Welding machine 2.4.1 Compressor-Once a year
2.4.3 Generators 2.4.2 Welding machine-Once a year
2.4.4 Cleaning tools (Grass cutter & 2.4.3 Generators-Quarterly
hydrotesting machine) 2.4.4 Cleaning tools-once a year
2.2.5 Construction Equipment 2.4.5 Construction Equipment – once
a year
(Concrete cutter, concrete
2.4.6 Tools – once a year
vibrator and mixer, compactor)
2.2.6 Motorpool Tools
(Jack, grease gun & chain block)
2.5 Motor vehicle and equipment is
reviewed for preventive maintenance
B
YES
4.1 Identify list of needed materials for Documents Required for PR/JO:
replacement and repair 4.1 Pre-inspection report
Prepare necessary 4.2 Decide labor requirement by 4.2 Spot Report
documents outsourcing of qualified or accredited 4.3 Vehicle history of asset
service provider 4.4 Photos Pre-inspection report
4 4.2 Prepare spot report for GM approval 4.5 Justification General Services Chief Spot Report
4.3 Attached vehicle history ledger and 4.6 APP History ledger card
photos, 4.7 CAF
4.4 Prepare Job Order, PR and certified 4.8 Canvass
APP
4.5 Prepare request for schedule repair
C
C
5.1 Repair will be done at motor-pool
wherein needed materials will be provided
by the end-users
5.2 Corrective maintenance will be done at
qualified private shop if beyond the PR and JO must indicate terms and
5 capacity of motorpool conditions including warranty period.
General Services Chief Spot Report
Repair of equipment or 5.4 If on site, inform supervisors and
request the services of a certified
motor vehicle mechanic/technician
END