PROVISION CONDUCTOR DAILY REPORT

Well Name : M 141 OS Operator : Pertamina Hulu Sanga Sanga Report No. : 9
Location : Mutiara Field Contractor : Trimitra Manunggal Energi Report Date : 11-Mar-21
RKB (Ground level) :- Rig Power /Name : SR 80 C Spud Date :
Ground level : Latitude : Longitude :
PERSONNEL
Drilling Reps :- Company Man : - Field Supt :
Welllsite Geologist : Rig Superintendent : - Drilling Engineer :
EQUIPMENT
Auger :1 Crane : 1 Wellding Machine : 1
Jacro :1 Dump Truck : 1 ELF : 1
Batch Mixer :1 Water Truck : 1 LV : :1
Water Tank :1 Wheelloader : 1 Total Station : 1
DEPTH DAYS
Plan Depth (m) : 80 Present Depth ( m ) : - Avg. ROP (mtr/hrs) :
Previous Depth : - Progress Depth (m) : 22 Drill From Spud In :

Daily Cost: (USD) Prev. Cost : (USD) Cum. Cost : (USD) Expenditure :
MUD DATA
2
Mud Time MW MW Vis Gels (Lbs/100ft ) Filtrate Solids Sand Water
Temperature
PV YP Cake LGS Cl- K+ PH
Type (Hrs) In, ppg Out,ppg sec 10 sec 10 min Loss % % % In/Out (0F.)
Fresh Water 8.6 9.3 60 -/-
-/-
DRILLING PARAMETER & HYDRAULIC PUMP DATA
WOB Torque RPM SPM SPM SPM Annular Velocity Jet Vel Press Pump Ø.Liner L.Stroke % Eff.
Gallon/Stoke
GPM SPP
klbs klbft Min/M 1 3 4 DC-OH HWDP-OH DP-OH DP-CSG (FT/SEC) drop 1 5.5 12 87% 3.223
2 5.5 12 87% 3.223
20 15 3 5.5 12 77% 3.223
4 4 10 87% 2.219
OPERATION SUMMARY
Time Cum IADC
Hours DESCRIPTION
From (-) To Hours Code
11-Mar-21
7:00 9:00 2.00 Pembersihan Lokasi M 197 OS dan Pembuatan Temporery Pit untuk lokasi M 141 OS
9:00 11:00 2.00 Pengeboran Pilot Slim Hole 12 m Bit 3.4", untuk pemasangan Temporery Casing
11:00 11:30 0.50 Running Casing Temporery HQ 3.5"
11:30 13:00 1.50 Instalasi BOP unit dan Blowdown Line
13:00 14:00 1.00 Function Test BOP unit (open, close), dan Pemantik Blowdown
14:00 14:30 0.50 Mixing Lumpur pemboran dengan Viscositas 60 Sec dan berat 8.6 ppg
14:30 16:30 2.00 Lanjut Pengeboran Pilot Slim Hole 2.85" PDC Bit
16:30 18:00 1.50 Observasi Sumur dan Close BOP
18:00
0:00 0 0
0:00 0 0
0 0 Note :
Pembersihan Lokasi M 197 OS 100%
Pengoboran Pilot Slim Hole 22 m
Kedalaman +- 10 m Sudah di temukan Lvl Air
Total (Hrs) : 11.0
PERSONNEL ON BOARD

PIC PT. Trimitra Manunggal Energi : Fuji Khasbianto

No. Company People No. Company People


1 PHSS SA 1 9
2 Trimitra Manunggal Energi 24 10
3 11
4 12
5 13
6 14
7 15
8 16
TOTAL POB 25
WEATHER
Time : 10:00 Temperature : N/A deg C Weather : Drizzle Wind Direction : North to East
REMARKS

PT. Trimitra Manunggal Energi Site Authority P/L Engineer

FUJI KHASBIANTO SURATNO ANGGA PRADIPTA / SAFRY

GP
Alamat : Perkantoran Tiara Buncit Blok A1
Jl.Kemang Utara IX No.9, Duren Tiga Jakarta Selatan
(021) 79187083

Lampiran :