Job No. Document No. Rev.

PROPOSAL PROP-BPK-CIV-001 00

SHEET 1 OF

SALAK BRINE HEAT RECOVERY BINARY POWER


PLAN

METHODOLOGY AND EXECUTION PLAN

CIVIL WORKS PROCEDURE

Issue Record

00 07 JAN 2021 Issued for Construction Nurul Huda


By Date
Rev Date Reason for Issue Prepared Checked Approved
No. Client
CONTENTS
1. FIELD CONSTRUCTIONS.....................................................................................................2

1.1 Coordinates Check and Marking Areas...................................................................................2

1.2 Excavation..................................................................................................................................2

1.3 Compacted..................................................................................................................................2

1.4 Elevation Check.........................................................................................................................3

1.5 Formwork Installation..............................................................................................................3

1.6 Geotextile....................................................................................................................................3

1.7 Geogrid.......................................................................................................................................3

1.8 Sub Base Course 300mm...........................................................................................................3

1.9 Base Course 200mm...................................................................................................................3

1.10 Wiremesh....................................................................................................................................3

1.11 Casting........................................................................................................................................3
1. FIELD CONSTRUCTIONS

1.1 Coordinates Check and Marking Areas


Coordinate and marking carried out to ensure that the foundation to be make in accordance with
the location determined by the drawing company accordance company benchmark. This
activity is carried out by people who are competent in using measuring instruments such as
theodolite and auto level to avoid errors in reading and using tools.

1.2 Excavation
Excavation is an activity carried out after coordinates check and marking area, this activity
aims to get an elevation and mention to match the approved drawing and design. Excavation
activities can be done manually or using heavy equipment.

1.3 Compacted
Compaction work of a surface layer of the design soil, whether subgrade, excavation or
embankment, so that the surface becomes solid and can support the filter of the building above
it. For this compaction, a Vibrator Roller is used

1.4 Elevation Check


Check the elevation using a spirit level tool and the top position of the soil with a theodolite

1.5 Formwork Installation


This work is the final stage before the concrete work is done. Support is needed to hold the
formwork so that is does not leak or get damaged when the concrete work is carried out.
Providing support to the formwork must also be done in accordance with approved drawing.

1.6 Geotextile
In the deployment stage the geotextile must be spread evenly without any waves or
wrinkles. As for. For the geotextile installation process using the manual method with field
workers.

1.7 Geogrid
Is a soil improvement method to increase the bearing capacity of the soil so that it can optimize
its function to support the construction on it.  After ensuring that the soil is flat, then the
geogrid is withdrawn to make the geogrid not warp when filled with aggregate.
1.8 Sub Base Course 300mm
Before the sub base material is spread, first the clamped concrete / stoper / channel that
functions as the clamped concrete must be installed. In its implementation, the slope of the road
must be achieved according to the plan drawings and checked in the field with a measuring
device / instrument.

1.9 Base Course 200mm


After the material is spread, it is compacted with a rolling machine and the results must be firm
with each other. Filling the ash screening must use a vibrating machine such as a vibro roller to
get a solid, sturdy and no longer rocking surface.

1.10 Wiremesh
In the installation of wiremesh, must really pay attention to the elevation of the wiremesh that
will be installed according to its needs

1.11 Casting
This work is critical civil work, Before pouring concrete please make sure the following point:

 Do defect occur in the formwork


 Make sure the drawing approve
 Dimension inspection before pouring concrete
 Elevation Inspection before Pouring concrete
 Support installation formwork.
 When poring, make sure that all surface of the foundation are evenly and densely filled
with concrete, this work can be do manually or using a concrete vibrator.
 Prove the sample of concrete for compressive specimen.