Civil Works Procedure: Job No. Proposal Document No. PROP-BPK-CIV-001 Rev. 00
Civil Works Procedure: Job No. Proposal Document No. PROP-BPK-CIV-001 Rev. 00
PROPOSAL PROP-BPK-CIV-001 00
SHEET 1 OF
Issue Record
1.2 Excavation..................................................................................................................................2
1.3 Compacted..................................................................................................................................2
1.6 Geotextile....................................................................................................................................3
1.7 Geogrid.......................................................................................................................................3
1.10 Wiremesh....................................................................................................................................3
1.11 Casting........................................................................................................................................3
1. FIELD CONSTRUCTIONS
1.2 Excavation
Excavation is an activity carried out after coordinates check and marking area, this activity
aims to get an elevation and mention to match the approved drawing and design. Excavation
activities can be done manually or using heavy equipment.
1.3 Compacted
Compaction work of a surface layer of the design soil, whether subgrade, excavation or
embankment, so that the surface becomes solid and can support the filter of the building above
it. For this compaction, a Vibrator Roller is used
1.6 Geotextile
In the deployment stage the geotextile must be spread evenly without any waves or
wrinkles. As for. For the geotextile installation process using the manual method with field
workers.
1.7 Geogrid
Is a soil improvement method to increase the bearing capacity of the soil so that it can optimize
its function to support the construction on it. After ensuring that the soil is flat, then the
geogrid is withdrawn to make the geogrid not warp when filled with aggregate.
1.8 Sub Base Course 300mm
Before the sub base material is spread, first the clamped concrete / stoper / channel that
functions as the clamped concrete must be installed. In its implementation, the slope of the road
must be achieved according to the plan drawings and checked in the field with a measuring
device / instrument.
1.10 Wiremesh
In the installation of wiremesh, must really pay attention to the elevation of the wiremesh that
will be installed according to its needs
1.11 Casting
This work is critical civil work, Before pouring concrete please make sure the following point: