Saudi Aramco Inspection Checklist
Saudi Aramco Inspection Checklist
Saudi Aramco Inspection Checklist
01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Fill, Select-Fill and Marl Cap Materials Receiving Inspection SAIC-A-1002 24-Mar-16 CIVIL-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Fill Materials
Delivered fill materials shall be free of frozen lumps, organic material, SAES-A-114
A2
trash, chunks of highly platic clay or other unsatisfactory materials. Sec. 6.1.1.2
Fill Material' shall be used for all fills except where 'Select Fill Material' is
specified. As a minimum, 'Select Fill Material' shall be used within 0.6 m
(2 ft) of the bottom elevation of foundations, spread footings, or slabs-on- SAES-A-114
A3
grade when fill is required to achieve final grade. 'Select Fill Material' Sec. 6.3.1
shall also be specified for backfill which will be in contact with concrete
or steel structures.
Maximum size of sand and gravel materials being received shall be SAES-A-114
B1
50mm diameter particles. Sec. 6.1
Select fill are composed only of inorganic materials and are free of SAES-A-114
B2
frozen lumps, trash, or other unsatisfactory materials. Sec. 6.1
Maximum size of marl materials being received shall be 75mm, and shall
have between 11-35% passing the No. 200 sieve. The capping material SAES-A-114
C1
shall have a maximum liquid limit of 35 and maximum plasticity index of Sec. 6.1.2
12, per D4318.