Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 17

Document Type

Royal Commission for Jubail and Yanbu


Method Statement

METHOD STATEMENT TEMPLATE

METHOD STATEMENT
(Contractor)

(Area/Building)

POTABLE WATER SUPPLY LINES, TIE-IN POINT &


RE-ROUTING INSTALLATIONS

Method Statement No:

Issued by:

Rev. # Date Description Prepared Checked Approved


Document Type

Royal Commission for Jubail and Yanbu


Method Statement

TABLE OF CONTENTS

1. PURPOSE OF DOCUMENT

2. SCOPE OF WORK

3. REFERENCE

4. PREPARATION

5. LAYOUT & SURVEY

6. PERSONNEL’S DUTIES AND RESPONSIBILITIES

7. QUALITY CONTROL / QUALITY ASSURANCE

8. MATERIAL HANDLING & STORATE

9. WORK METHODOLOGY

10. EQUIPMENT REQUIREMENTS

11. TIE-IN POINT INSTALLATION

12. JOB SAFETY ANALYSIS

13. APPENDICES

Page 2 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

1 PURPOSE OF DOCUMENT

Page 3 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

This method statement is prepared to provide necessary procedures to carry out the
installations including testing & disinfection of potable water supply lines as per control
and approved shop drawings.

2 SCOPE OF WORK

The scope of work is applicable for the installations including testing and disinfection of
potable water supply as per contract and approved shop drawings.

3 REFERENCES

3.1 RC Specification Section 02085

3.2 RC Specification Section 02315

3.3 RC Specification Section 15055

3.4 RC Specification Section 15060

3.5 RC Specification Section 15075

3.6 RC Specification Section 15080

3.7 RC Specification Section 15140

3.8 RC Specification Section 15145

3.9 RC Specification Section 15195

4 PREPARATION

The EPC Contractor shall obtain the approval of shop drawing layout showing potable
water lines and its connections for all check points indicated at contract no. 204-C62. The
EPC Contractor shall obtain also the approval of all required materials of the above
installations from client and client representatives prior to start the work.

5 LAYOUT & SURVEY

The EPC Contractor shall set out the coordinates, elevations on all installations of potable
water lines as per contract and approved shop drawings.

6 PERSONNEL’S DUTIES AND RESPONSIBILITIES

6.1 Construction Manager – Manage and directs the construction activities performed
by construction team composed of personnel assigned by various functional
department. Ensure that construction activities are carried out as per project
quality plan, approved ITP’s and approved project safety procedures.

Page 4 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

6.2 QA/QC Manger – Directs project’s inspection and testing to prevent work
nonconformity from the RC standard and other governing codes and standards. In
pursuing this objective he manages his departments QA/QC staffs and interacts
with other department managers and workers. He will report to upper
management and RC representatives.

6.3 Mechanical Superintendent – Supervise the activities of field engineer, supervisor


and skilled work force. Ensure that the approved products being used and correct
allocation of manpower and equipment to complete the task successfully in
accordance with project specification and IFC drawings.

6.4 Mechanical Engineer In-charge – Execution of works according to IFC drawings,


he will be assisted by surveyor. Shall have RC code 1 as competent personnel
and in-charge in securing necessary permits and clearance prior to any activity.

6.5 QA/QC Engineer – All Quality activities, monitoring field workmanship and
organizing testing.

6.6 Surveyor In-charge – Will be in-charge of establishing of a specific locations and


elevation, Horizontal and Vertical alignment as per IFC drawings.

6.7 Safety Officer – Shall be assigned full time on site Co-ordinate and monitor the
implementation of the approved safety plan. Detect, identify, analyze, control
eliminate recognized hazardous acts. Investigate & report immediately in writing
all accidents, unsafe acts, near misses etc., to Project Manager and client safety
representative.

6.8 Mechanical Supervisor / Foreman

6.9 Work Force – Helpers, Technicians, Qualified operators with TUV & other certified
local government certification, craftsmen / laborers involved in this activity.

7 QUALITY CONTROL / QUALITY ASSURANCE

7.1 General

1 Method of Construction and testing such as to achieve the specified quality shall
be approved both by RC prior to any execution of work.
2 One (1) copy of the aforementioned document shall be maintained on project site.

7.2 Contractual Requirements

1 Quality Assurance Requirements as per Project Technical Specification (Section


01450):
a. Approved Quality Control Program.
b. Approved Method of Statement and ITP
c. Approved Drawings
d. Special care taken for handling, storage and preservation of materials

Page 5 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

7.3 Critical Works

1 Coordinates / Locate the points to be used or layout must be coordinated with RC.
2 Approved IFC drawings, PTS and other contract documents must be used as
reference.

7.4 Follow up & Evaluation

1 Site documentation shall be used to keep records on site.


2 Site inspection by QA/QC team will access to this documentation for auditing
purpose.
3 Test Materials Inspection and damage reports shall be documented, logged and
controlled for reference.

8 MATERIAL HANDLING AND STORAGE

1 Storage and handling should be in accordance with manufactures


recommendations.

2 All Plasticized pipes and fittings shall be unloaded, handled and stored properly by
means of lifting equipment to avoid damaging the pipes. Materials shall not be
dropped to the ground, but lowered carefully.

3 Use a Forklift (or front end loader with forks) to remove each top unit separately.
Remove the rear units first. Do not slide the equipment forks against the
underside of pipe in the pallet. This may damage the pipe by abrasion.

4 Units should be protected by dunnage/ padding (scrap wood) the same way they
were loaded on the truck. The dunnage must support the weight of all units so that
pipe lengths do not carry the weight of the unit loaded above them.

5 Materials shall be stored in proper manner; pipes shall be supported and placed
on level ground at the assigned lay down area. Individual lengths of pipe should
be stacked in piles no higher than 1.5 m (5ft).

6 Plasticized pipes which are not packed in bundles or pallets shall be stored fully
supported over the entire length to prevent bending.

7 Do not use steel cables or chains to lift or transport the pipe. Do not lift pipes by
passing a rope through the section end to end.
8 All plasticized pipes shall be stacked on a reasonably flat surface free from sharp
projections, stones or other protuberances likely to deform them. If necessary,
level the ground at the storage point by means of a vehicle fitted with a scraper
blade in order that pipe may be uniformly supported throughout their length.

9 Side supports in the form of wooden posts, not less than 75 mm square shall be
provided at no more than 1500 mm intervals along the pipe length. Stack widths
shall not exceed 2000 mm

Page 6 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

10 When socketed pipes are stacked, the sockets shall be placed at alternate ends of
the stack with the sockets protruding so pipes are evenly supported along their
entire length.

11 Plasticized pipes of different sizes or wall thickness shall be stacked separately, or


where this is not possible those with larger diameter and thicker walls shall be at
the bottom.

12 Plasticized pipes and fittings shall be protected from the direct rays of the sun at
all times by means of reflective covers sheets. The pipe shall be stored under a
protective tarpaulin or polyethylene sheet cover, which shall not leave any pipe
surface or pipe ends exposed. The cover shall be arranged to allow air circulation
within its volume of confinement by fixing tarpaulin or polyethylene sheet to
wooden supports.

13 Fittings shall be stored under shade conditions preferably in boxes or sacks that
allow a free passage of air.

9 METHODOLOGY

9.1 Trenching and backfilling

9. Excavations for trenches shall be made as narrow as practicable or to the


2. minimum widths specified on the shop drawings but shall nevertheless
1 provide sufficient room for the laying jointing and testing of pipe work and
utilities.

9. The bottom of the excavation shall be kept dry and free from water at all
2. times. In no case shall the earth be scraped or dug by machinery near to the
2 bottom of the bedding formation level so as to result in the disturbance of the
material below.

9. If the required depth of trench is attained, remove all debris then prepare the
2. trench with clean pipe sand bedding and use water compacting and /or plate
3 compactor as needed as possible.

9. Backfill material shall be deposited in 150 mm maximum layers over the


2. properly bedded utility pipe and carefully tamped until the utility service has a
4 minimum cover of:

(a 300 mm for all utility pipe mains.


)
(b 300 mm for all utility pipe laterals
)
9.1.1 700 Dia Re-routing PW line Installation

Trenching & Shoring

1 We will excavate trench of size: 2.5m width, Height (one side) – 11m, Height

Page 7 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

(opposite side) 4m, Total length of Trench – 130M, see attached drawing 00000

2 We will make trench for shoring length 40m and will use 25 ton crane for shoring
plate on one-side installation with diagonal support.

3 Bedding and compaction up to 40m length of trench

4 Pipe installation up to 40m will be done by using 25 ton crane.

5 Then backfilling

We will repeat the above for next 40m trench and cover up to the total 130m
length of trench in repeated steps.

9.2 Pipe Installations

9.2.1 Underground Piping

a) All pipes, fittings, valves and other materials shall be carefully lowered into the
trench.

b) Every precaution shall be taken to prevent foreign material from entering the pipe
while it is being placed. If the pipe cannot be placed into the trench, without
getting earth into it, a heavy, tightly woven canvas bag of suitable size shall be
placed over each end and left there until the connection is to be made to the
adjacent pipe or fitting. During laying operations, no debris, tools, clothing or other
materials shall be placed in the pipe.

c) The full length of each section of pipe and fittings shall rest solidly on the pipe bed
with recesses excavated to accommodate bels, joints and couplings. Anchors and
supports shall be provided where necessary and as indicated on the Contract
Drawings. Proper provision shall be made for expansion and contraction of pipe
lines.

d) Open ends of pipe at the end of each day’s work, shall be closed temporarily with
wood blocks or bulkheads. Pipe shall not be laid when the conditions of trench or
weather are unsuitable.

e) Wherever jointing is specified with cement mortar, six (6) or more lengths of pipe
shall be in place ahead of each joint before such joint is finished.

f) The cutting of pipe for inserting valves, fittings or closure pieces shall be done in a
neat and workmanlike manner without damage to the pipe or lining and so as to
leave a smooth end at right angles to the longitudinal axis of the pipe. When
machine cutting is not available for cutting pipe 500 mm in diameter or larger, the
electric-arc cutting method is permitted. Only qualified and experienced workmen
shall be used on this work. Flame cutting of pipe by mans of an oxyacetylene
torch shall not be allowed.

Page 8 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

g) The pipe shall be laid at the level and gradient stipulated, on a prepared bed 150
mm deep with special hollows made for the joints. The pipe shall be aligned
carefully in both the horizontal and vertical planes and at no point be laid more
than 10 mm from the theoretical and vertical planes and at no point be laid more
than 10 mm from the theoretical straight line; for plastic pipe 20 mm. Supports
must not be placed under the pipe.

h) Every precaution shall be taken to prevent foreign matter from entering the pipe or
fittings. During laying operations, no debris, tools, cloths or other materials are to
be allowed to enter the pipe. After placing a length of pipe with socket/ spigot
joints in the trench with the socket end up-streams, the spigot end shall be
centered in the socket (or similar) and the pipe forced home and brought to
correct line and grade. The angle between any piping and fittings shall not exceed
the manufactures recommendations. The pipe and fittings shall be secured in
place with approved backfill material temped under it except at the joints.

i) All pipe lines shall be inspected and approved by the Royal Commission before
they are backfilled.

j) Continuous adequate support shall be provided along the whole pipe to prevent
sagging and bending. The pipe shall be securely placed into thrust blocking,
leaving no space for pipe movement.

k) Proper insertion of spigot ends into the bell ends of the pipe is essential. Spigot
shall be stop-marked and pushed into the bell housing only up to the mark to
avoid over-insertion.

l) Pipe shall not be exposed to direct sunlight for periods longer than three (3) days
and provisions shall be made for shading any pipe which is left in the open or
uncovered in trenches. Piping shall not become excessively over-heated causing
deformation or permanent damage to pipe.

m) An expansion gap shall be left each joint of a UPVC piping system. This gap shall
meet the requirements of the UPVC piping manufactures installation instructions
for underground piping and is equal to 13 mm plus 1/3 of the pipe thickness for a
maximum of 25 mm total between of the pipe socket and the chamber of the
spigot.

9.2.2 Above ground Installation

a) All pipe work and valves shall be installed as shown on the Contract Drawings and
on the approved Shop Drawings.

b) Section service shut-off valves shall be provided for each grouping of three (3) or
more fixtures in any plumbing installation.

c) Dielectric unions or flanges shall be installed at all interfaces between copper or


bronze piping components and ferrous fittings, nipples or equipment or other
dissimilar metals.

Page 9 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

d) Gate valve shall be installed on each side of each water mater.

e) Water Hammer Arrestors to be install in water supply lines to plumbing fixtures as


required by PDI WH 201. Install in upright position, in locations and of size in
accordance with Standard PDI WH-201, and elsewhere as required.

9.3 Related piping accessories installations

a) Install sleeves for pipes passing through concrete and masonry walls, gypsum-
board partitions, concrete floors, road crossings and elsewhere except on beams
ribs, columns or any other structural carrying member. Install plastic or moisture
resistant fiber sleeves as an alternative to steel pipe sleeves. Sleeve through
floors, walls, partitions and beam flanges shall be 25 mm greater in diameter than
external diameter of pipe.

b) All piping shall be securely fastened to slabs, beams, joints, columns, walls and
other permanent elements of the building. Piping shall not be hung from other
piping or equipment. Every branch of piping over one (1) m long shall be
supported by hangers. Finishing of all pipe supports attachments rods, hangers,
channels etc., shall be hot-dipped galvanized. Hangers for pipe sizes 12.5 to 40
mm (1/2 to 1 1/2in) shall be malleable iron, adjustable swivel, and split ring. Install
hangers to provide minimum 12.5 mm (1/2 in) space between finished covering
and adjacent work.

c) Pipe identification shall comply with ASME A13.1, for lettering size, colors, length
of color field and installation. Marker shall indicate pipe working fluid and direction
of flow. The markings shall be applied after all painting and cleaning of the piping
and insulation is completed. Markers shall be maximum 10 m apart n centers.
Reduce spacing to 7 m in congested areas of piping and equipment.

d) Installation of above ground domestic hot water pipelines above 15.60C (600C)
with pipe size 50 mm below shall be of mineral fiber or flexible cellular with 25 mm
thickness.

e) Fixed brackets shall be used at changes in direction or piping size to prevent pipe
movement in response to thrust from internal pressure.

f) No underground or under slab water piping within building shall be permitted


unless specifically approved by the Royal Commission.

9.4 Horizontal Thrust Boring

The method of Statement required for horizontal thrust boring will be submitted
separately by third party working on this task.

9.5 Hydrostatic Testing


a) Potable water piping inside building shall be tested in accordance with the
requirements of the International Plumping Code (IPC). Utility piping systems,

Page 10 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

including irrigation piping and water distribution mains, shall be tested in


accordance with ANSI/ASME B31.3

b) New piping systems with pipe sizes up to 300 mm (12 in.) NPS shall be flushed
clean of loose scale and debris or scraped prior to commencement of pressure
testing. Care shall be exercised to ensure all pipe spools are internally clean
before installation.

c) Clean, fresh city water shall be used for hydrostatic testing. All Systems piping
while being hydrostatically tested, shall be protected from being over-pressured by
means of relief valves of adequate capacity set to relieve at 5% above the
hydrostatic test pressure. In addition to the pressure relieving devices a bleed
valve shall be provided to protect the piping from over pressure. The bleed valve
shall be readily accessible in case immediate depressurization is required. An
isolation valve shall be provided between the pressure testing manifold and the
system being tested. The isolation valve shall be rated for the manifold test
pressure when in the closed position.

d) All joints shall be left uninsulated and exposed for examination during the test.

e) Field testing of Piping

1) Vents shall be provided at all high points of the piping system in the position
in which the test is to be conducted to purge air pockets while the component
or system is filling. Venting during the filling of the system may be provided by
the loosening of flanges having a minimum of four (4) bolts or by the use of
equipment vents.

2) Where impractical to cover long, exposed high-pressure pipelines, secure


them to sturdy members at intervals to limit any whipping action that might
occur if a pipe failed. Strap pipe lines to strong supports close to fittings,
bends, and on either side of couplings.
Place a piece of rubber or neoprene gasket material between the strap and
the high-pressure pipe to help prevent failure from wear due to vibration or
hammer caused by motion of the high pressure fluid. Suggested support
intervals are given in table below.

(inch) ¾ 1 1¼ 1½ 2 2½ 3 3½ 4 5 6
Pipe size
(mm) 19 25 32 40 50 65 75 90 100 125 150

(ft) 10 10 15 15 15 20 20 25 25 25 30
Interval
(Maximum) (In.) 3 3 4.5 4.5 4.5 6 6 7.5 7.5 7.5 9

3) Piping shall be examined before pressure is applied to ensure that it is tightly


connected. All items not subject to the pressure test shall be disconnected or
isolated by valves, blanks, plugs or other suitable means.

4) The hydrostatic test pressure at any point in the piping system shall not be

Page 11 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

less than 1.5 times the design pressure, but shall not exceed the maximum
allowable test pressure of any non-isolated components such as vessels,
pumps or valves.

5) The temperature of the piping system during testing shall be above the
ductile-brittle transition temperature applicable only to cut sample portion of
the piping in the system.

6) The means used to furnish the test pressure shall have either a pressure
limiting device or a pressure reducing device and a pressure relief device and
gage on the outlet side. The pressure relief devise shall be set above the test
pressure, but low enough to prevent permanent deformation of any of the
system components.

7) Mechanical joints at which blanks or plugs are inserted to blank off or


facilitate removal of equipment during the pressure test need not be pressure
tested after removal of the blanks or plug provided the joint passes a
subsequent leak test.

8) Filling and pressurizing shall be done on the upstream side of the check valve
in the system. The test fluid shall be injected at the low point in the system to
minimize entrapped air. When filling at the lowest point is not practical, the
Royal Commission shall be consulted. All vents shall be open during filling.

9) After the test pressure is reached and before commencement of inspection of


the system the isolation valve between the temporary test manifold/ piping
and the piping / equipment under pressure test shall be closed and the test
pump disconnected.

10) After the pressure test is completed a leak test shall be performed.
Examination shall be made of all joints and connections. The piping system
shall shower no evidence of leaking. All leaking joints shall be repaired.

11) The system shall be tested at 1 ½ times normal working pressure, as


indicated in the table below:

Testing Minimum Test Minimum %


S No. System
Medium pressure Time Deviation
A Water Lines
Non-potable water and potable
Water 1210 kPa 2 Hrs 0%
water
Chilled Water Water 1210 kPa 2 Hrs 0%
B Fuel Oil Water 690 kPa 2 Hrs 0%
C Fire Protection
Sprinkler System Water 1380 kPa 2 Hrs 0%
Water Mains Water 1380 kPa 2 Hrs 1%
Column to 3000
Storm and Sanitary Drainage
D Water mm above high 2 Hrs 1%
and Associated Vent Lines
point

Page 12 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

Column to 3000
E Roof Drain Water Conductors Water mm above high 2 Hrs 2%
point
F Instrument Air or Tube Air Nitrogen 345 kPa 24 Hrs 3%
G Medical Gas System Air 1035 kPa 24 Hrs 0%

12) Unless prevailing conditions or regulations require full backfilling of the piping
prior to the hydrostatic test, underground piping shall be partially backfilled
with all joints exposed during the hydrostatic test. The exposed joints shall be
shaded from direct sunlight and the hydrostatic test shall be performed so
that the temperature of the thermoplastic piping material or the temperature of
the test water does not exceed 400C (1040F) during the test period.

13) No thermoplastic piping shall be pressurized until it has cured for 24 hours at
a surface temperature of 10 0C (500F) or higher or for 48 hours at a surface
temperature below 100C (500F)

14) The piping and equipment shall be protected from over-pressure by relief
valve(s) of adequate capacity set at 5% above the test pressure or a
maximum of 173 kPa (25 psi) above the test pressure for pressure piping
systems. The relief valve(s) shall be tested dated and tagged within one (1)
week prior to the test pump shall be placed in firm ground away from the
piping. The pump and the piping system.

15) After pressure testing has been successfully completed, release of pressure
and draining shall be done on the downstream side of the check valves. All
vents shall be opened before draining to facilities drainage and to prevent
formation of a vacuum. No test fluid shall remain in low spots. The test fluid
shall be disposed as directed by the Royal Commission.

9.6 Preliminary Flushing

a) Lines shall be filled with potable water at a maximum of 0.3 m/s while venting all
air. Precautions shall be taken to prevent entrapping air in the pipe lines.

b) After filling pipe lines shall be flushed at blow offs and dead ends at a minimum
velocity of 0.9 m/s.

c) A minimum of three changes of potable water shall be used for flushing operations.

d) Valves shall be discharged to natural drainage channels, storm water sewers or


proper reservoirs as approved by the Royal Commission. Such discharge of water
shall be in a manner that prevents properly damage, erosion or siltation.

9.7 Potable Water Lines Disinfection

a) Disinfection of water mains shall be done according to AWWA 651.

b) The third party involve in disinfection of potable water line will submit their separate

Page 13 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

method of disinfection with respect to AWWA 651 and shall be approved by the
Consultant & Royal Commission.

The Method of Disinfection as per Royal Commission standard specification:

“Continuous-Feed Method”

c) Place calcium hypochlorite granules in pipe section during installation to provide a


strong chlorine concentration in the first flow of flushing.

d) The flushing velocity shall be less than 0.76 m/s

e) After flushing the system or a part of the system or a pipe section shall be slowly
filled with potable water and chlorinated at a constant rate of chlorine such that the
water will have not less than 25 mg/L free chlorine. Table below gives the amount
of chlorine required for each 30 m pf pipe section of various diameters. Solutions of
1% chlorine may be prepared with sodium hypochlorite or calcium hypochlorite.
The latter solution requires 450 g calcium hypochlorite in 30 L of water.

CHLORINE REQUIRED TO PRODUCE 25 MG / LITER CONCENTRATION IN 30M OF PIPE

Pipe Diameter 100% Chlorine 1% Chlorine Solution


Inches mm Ib g Gallon Liter
4 100 0.013 5.9 0.16 0.6
6 150 0.030 13.6 0.36 1.4
8 200 0.054 24.5 0.65 2.5
10 250 0.085 38.6 1.02 3.9
12 300 0.120 54.4 1.44 5.4
16 400 0.217 98.4 2.60 9.8

f) The equipment for chlorinating shall be a solution feed, vacuum operated


chlorinator and a booster pump.

g) After 24 hours the treated water in all portions of the pipe section shall have a
residual of not less than 10 mg / L free chlorine.

h) During the 24 hour period all valves and appurtenances shall be operated to
ensure disinfection.

9.8 FINAL FLUSHING SAMPLING AND TESTING

9.8.1 Following chlorination thoroughly flush treated water in newly laid pipe line until
replacement water throughout new pipe line is provided by laboratory testing
comparable in quality to water served to public from existing water system. Prior to
sampling for laboratory testing, reduce residual chlorine throughout length of pipe
line to 1 ppm or less. Upon achieving required residual chlorine level in pipe line,
take samples as specified.

Page 14 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

a) Testing laboratory shall collect samples for testing of new water mains. To
initiate the sampling and testing, present to testing laboratory written request
for work no later than 24hours prior to time when samples are to be taken.

b) Take sample from tap and riser located and installed to prevent outside
contamination.

Number of Sampling Locations

 Waterlines up to but less than 45 m (150 ft) in length, take 1 sampling riser installed
as near the end as possible.
 Waterlines 45 to 90 m (150 to 300 ft) in length, take 2 sampling risers, one near each
end of line.
 Waterlines 90 to 900 m (300 to 3,000 ft.) in length, take minimum of 3 sampling
risers.
 Represent dead end on main lines with sampling riser.

9.8.2 The number of samples taken at each sampling location shall be determined by
testing laboratory based on one of the following methods:

a) One sample from each sampling location which is examined and analyzed in
the laboratory over a 3 day (72 hour) period.

b) Two samples taken on separate days from each sampling location.


Satisfactory water quality of new main shall continue for period of at least 48
hours as demonstrated by laboratory examination of samples.

9.8.3 Upon completion of laboratory testing, send results of tests by testing laboratory to
the Royal Commission. Results of laboratory analysis will be interpreted by the
Royal Commission and reported to the Contractor. Under no circumstances shall
the contractor contact the laboratory. If there is need for test results before written
reports are submitted, obtain information from the Royal Commission or its
authorized representative.

9.8.4 Repetition of Testing

Should initial treatment fail to result in acceptance conditions, repeat original


chlorination procedure until satisfactory result are obtained.

9.9 Warning Tape

After initial hydrostatic test is accepted by the Royal Commission, warning tapes
shall be installed at 300 mm above the top of the pipe. The following, as applicable
shall be printed on the tape in both Arabic and English in durable black letters of
50 mm height.

Page 15 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

“Caution – Portable water Line Below

9.9 Mechanical Identification

The color coding of below and above ground utility pipe line except seawater
supply and return pipe lines shall be accomplished by painting the base color or
color band pipe line or by color-coded longitudinal strip on the top surface of
installed pipe, upon approval by Royal Commission. The base colors or bands and
identifying color strips for different utility pipelines shall be as shown in Table.

Utility Services Base Color Identifying color stripes

Potable Water Blue Blue

10 EQUIPMENT REQUIREMENTS

The following equipment and tools are required to perform works:

Items Equipment Nos. Purpose

1 Backhoe JCB Excavator 1 Excavation & Backfilling

2 Boom Crane 1 Trench Box & Pipe Installation

3 Dewatering Pump 2 Dewatering water along pipe route

Water Tanker 2 For water compaction & Hydro


4
test purposes

5 Plate Compactor 1 Use for levelling of pipe bedding

6 Manual Excavation 4 Set Manual Excavation & Backfilling


Tools

7 Shaving Tools 1 Set Use foe pipe end preparation

8
Power Generator 2 Power and Lighting
9
Wrenches 2 Use for tightening of Bolts and

Page 16 of 17
Document Type

Royal Commission for Jubail and Yanbu


Method Statement

(Different sizes) sets Nuts

Torque Wrench 2 Bolt tightening where bolts has a


10
specific torque required

Chain Block 3 Tons 2 For rigging of equipment by chain


11 block at foundation

Hack saw & Disc 1 set For Pipe Cutting


12
Grinder

Note: Number of equipments and tools may be change subject to the


installation requirements and priorities.

11 INSTALLATION OF TIE-IN POINT

a) After the entire network has been completely done, tie-in shall proceed accordingly.
Coordinate and arranged to Royal Commission in advance or scheduling shutdown
of the existing isolation valve.

b) Secure a work permit with regards to approval schedule date, and then prepare all
necessary tools and equipment needed to execute the work properly.

c) Isolate the existing gate valves then drain the water towards the designated drain
valve.

d) Excavation of trial pits will be carried out to locate the exact location of existing tie-
in point until it will exposed.

e) Prior pipe laying, bedding shall be compacted firmly.

12 Job safety analysis (attached)

Please see the attached Appendixes

13 APPENDICES

13.1 Appendix – 1 (Risk Assessment)


13.2 Appendix – 2 (Safe Sequences of Work)
13.3 Appendix – 3 (Medical Evacuation / Injury Handling Procedure)

END OF DOCUMENT

Page 17 of 17

You might also like