Blasting and Painting Classic Schedule Layout

WBS Path Activity Name Original Duration Start Finish er 2019 November 2019 December 2019 January 2020
February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020
2 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 9
195 29-Oct-19 10-May-20 10-May-20, Blasting and Painting
Blasting a
and Painting
195 29-Oct-19 10-May-20 10-May-20, System A1 (Carbon steel)
System A1
A (Carbon steel)
60" Pipes 31 29-Oct-19 28-Nov-19 28-Nov-19, 60" Pipes
1.1 Blasting and Primer Layer 29 29-Oct-19* 26-Nov-19 Blasting and Primer Layer
1.1 Intermediate Layer 29 30-Oct-19 27-Nov-19 Intermediate Layer
1.1 Final Layer 29 31-Oct-19 28-Nov-19 Final Layer
48" Pipes 27 29-Nov-19 25-Dec-19 25-Dec-19, 48" Pipes
1.2 Blasting and Primer Layer 24 29-Nov-19 22-Dec-19 Blasting and Primer Layer
1.2 Intermediate Layer 25 30-Nov-19 24-Dec-19 Intermediate Layer
1.2 Final Layer 25 01-Dec-19 25-Dec-19 Final Layer
42" Pipes 15 26-Dec-19 09-Jan-20 09-Jan-20, 42" Pipes
1.3 Blasting and Primer Layer 12 26-Dec-19 06-Jan-20 Blasting and Primer Layer
1.3 Intermediate Layer 12 27-Dec-19 07-Jan-20 Intermediate Layer
1.3 Final Layer 13 28-Dec-19 09-Jan-20 Final Layer
36" Pipes 25 10-Jan-20 03-Feb-20 03-Feb-20, 36" Pipes
1.4 Blasting and Primer Layer 23 10-Jan-20 01-Feb-20 Blasting and Primer Layer
1.4 Intermediate Layer 23 11-Jan-20 02-Feb-20 Intermediate Layer
1.4 Final Layer 23 12-Jan-20 03-Feb-20 Final Layer
28" Pipes 7 04-Feb-20 10-Feb-20 10-Feb-20, 28" Pipes
1.5 Blasting and Primer Layer 5 04-Feb-20 08-Feb-20 Blasting and Primer Layer
1.5 Intermediate Layer 5 05-Feb-20 09-Feb-20 Intermediate Layer
1.5 Final Layer 5 06-Feb-20 10-Feb-20 Final Layer
24" Pipes 1 11-Feb-20 11-Feb-20 11-Feb-20, 24" Pipes
1.6 Blasting and Primer Layer 1 11-Feb-20 11-Feb-20 Blasting and Primer Layer
1.6 Intermediate Layer 1 11-Feb-20 11-Feb-20 Intermediate Layer
1.6 Final Layer 1 11-Feb-20 11-Feb-20 Final Layer
20" Pipes 5 12-Feb-20 16-Feb-20 16-Feb-20, 20" Pipes
1.7 Blasting and Primer Layer 3 12-Feb-20 14-Feb-20 Blasting and Primer Layer
1.7 Intermediate Layer 3 13-Feb-20 15-Feb-20 Intermediate Layer
1.7 Final Layer 3 14-Feb-20 16-Feb-20 Final Layer
16" Pipes 4 17-Feb-20 20-Feb-20 20-Feb-20, 16" Pipes
1.8 Blasting and Primer Layer 2 17-Feb-20 18-Feb-20 Blasting and Primer Layer
1.8 Intermediate Layer 2 18-Feb-20 19-Feb-20 Intermediate Layer
1.8 Final Layer 2 19-Feb-20 20-Feb-20 Final Layer
12" Pipes 4 17-Feb-20 20-Feb-20 20-Feb-20, 12" Pipes
1.9 Blasting and Primer Layer 2 17-Feb-20 18-Feb-20 Blasting and Primer Layer
1.9 Intermediate Layer 2 18-Feb-20 19-Feb-20 Intermediate Layer
1.9 Final Layer 2 19-Feb-20 20-Feb-20 Final Layer
10" , 8" , 6" , 4" and 3" Pipes 29 21-Feb-20 20-Mar-20 20-Mar-20, 10" , 8" , 6" , 4" and 3" Pipes
1.10 Blasting and Primer Layer 28 21-Feb-20 19-Mar-20 Blasting and Primer Layer
1.10 Intermediate Layer 28 22-Feb-20 20-Mar-20 Intermediate Layer
1.10 Final Layer 27 23-Feb-20 20-Mar-20 Final Layer
2" Pipes 16 21-Mar-20 05-Apr-20 05-Apr-20, 2" Pipes
1.15 Blasting and Primer Layer 14 21-Mar-20 03-Apr-20 Blasting and Primer Layer
1.15 Intermediate Layer 14 22-Mar-20 04-Apr-20 Intermediate Layer
1.15 Final Layer 14 23-Mar-20 05-Apr-20 Final Layer
1.5" , 1" a
and 0.75" Pipes 2 06-Apr-20 07-Apr-20 07-Apr-20, 1.5" , 1" and 0.75" Pipes

Actual Level of Effort Milestone Page 1 of 2 TASK filter: All Activities


Primary Baseline summary © Oracle Corporation
Actual Work
Remaining Work
Critical Remaining Work
Blasting and Painting Classic Schedule Layout
WBS Path Activity Name Original Duration Start Finish er 2019 November 2019 December 2019 January 2020
February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020
2 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 9
1.16 Blasting and Primer Layer 1 06-Apr-20 06-Apr-20 Blasting and Primer Layer
1.16 Intermediate Layer 1 07-Apr-20 07-Apr-20 Intermediate Layer
1.16 Final Layer 1 07-Apr-20 07-Apr-20 Final Layer
Fittings 8 03-May-20 10-May-20 10-May-20, Fittings
1.19 Blasting and Primer Layer 6 03-May-20 08-May-20 Blasting and Primer Layer
1.19 Intermediate Layer 6 04-May-20 09-May-20 Intermediate Layer
1.19 Final Layer 6 05-May-20 10-May-20 Final Layer
8 08-Apr-20 15-Apr-20 15-Apr-20, System A1 Plus (Carbon steel) - Underground
System A1
A Plus (Carbon steel) - Underground
12" and 3" Pipes 8 08-Apr-20 15-Apr-20 15-Apr-20, 10" , 8" , 6" , 4" , 3" and 2" Pipes
2.1 Blasting and Primer Layer 7 08-Apr-20 14-Apr-20 Blasting and Primer Layer
2.1 Final Layer 7 09-Apr-20 15-Apr-20 Final Layer
8 16-Apr-20 23-Apr-20 23-Apr-20, System G1 (Galvanized)
System G1
G (Galvanized)
2" ,1" and 0.75" Pipes 8 16-Apr-20 23-Apr-20 23-Apr-20, 2" , 1.5" , 1" and 0.75" Pipes
3.1 Blasting and Primer Layer 7 16-Apr-20 22-Apr-20 Blasting and Primer Layer
3.1 Final Layer 7 17-Apr-20 23-Apr-20 Final Layer
9 24-Apr-20 02-May-20 02-May-20, System D1 (Stainless steel)
System D1 (Stainless steel)
2" and 1" Pipes 9 24-Apr-20 02-May-20 02-May-20, 2" and 1" Pipes
4.1 Blasting and Primer Layer 3 24-Apr-20 26-Apr-20 Blasting and Primer Layer
4.1 Intermediate Layer 3 27-Apr-20 29-Apr-20 Intermediate Layer
4.1 Final Layer 3 30-Apr-20 02-May-20 Final Layer

Actual Level of Effort Milestone Page 2 of 2 TASK filter: All Activities


Primary Baseline summary © Oracle Corporation
Actual Work
Remaining Work
Critical Remaining Work