Professional Documents
Culture Documents
Chapter 2 Route Selection
Chapter 2 Route Selection
Projects are planned and carried out using a sequence of activities known as the “project
Cycle.”
The cycle is composed of the following steps: identification, feasibility, design commitment
and negotiation, operation, and evaluation. Route corridor selection comprises of portion of
the first three of these activities.
2.1.1 Identification
The first stage of the cycle is to find potential projects. This is sometimes known as the
“prefeasibility” stage. There are many sources from which suggestions may come, including well-
informed technical specialists, local leaders, proposals to extend existing programs or projects, and
from operating agencies responsible for project implementation. The decision to proceed to the
feasibility stage arouses expectations for the project. Dubious projects shall therefore be rejected at
the identification stage. It becomes increasingly difficult to stop a project at the later stages of the
cycle.
2.1.2 Feasibility
The feasibility study will provide sufficient information to decide whether to proceed to a more
advanced stage of planning. The level of detail of this study will depend on the complexity of the
project and how much is already known about the proposal. The feasibility study shall define the
objectives of the project. It shall consider alternative ways of achieving these and eliminating poor
alternatives. The study provides the opportunity to mould the project to fit its physical and social
environment to maximize the return on the investment. Once the feasibility study has indicated
which project is likely to be the most worthwhile, detailed planning and analysis can begin. Less
promising projects will have been eliminated by this time, and the selected project may be redefined
and modified as more detailed information becomes available. At this stage, studies of traffic,
geotechnics and design will be carried out to refine the prediction of costs and benefits and to enable
an economic analysis to be carried out.
1
Highway engineering I chapter 2 ,Route Selection
2.1.3 Design
Preliminary design and feasibility are often simultaneous, but detailed design, which can be very
costly (up to 15 percent of project costs), usually follows a provisional commitment to the project.
Numerous decisions, which will affect economic performance, are taken throughout design; and
economic appraisal often results in redesign.
Commitment of funds often takes place is a series of stages. This is followed by invitation to tender
and negotiations with contractors, potential financiers and suppliers. At this stage, there are still
considerable uncertainties.
2.1.5 Implementation
Several aspects of the earlier stages in the project cycle will affect the success of the implementation.
The better and more realistic plan, the more likely it is that the plan can actually be carried out and
the full benefits realized. A flexible implementation plan shall be sought. It is almost inevitable that
some circumstances will change during the implementation. Technical changes may be required as
more detailed soils information becomes available or as the relative prices of construction materials
change. Project managers may need to change and re-plan parts of the project to take account of such
variations. The more innovative and novel the project is, the greater is the likelihood that changes
will have to be made during implementation.
2.1.6 Operation
This refers to the actual use of the road by traffic; it is during this phase that benefits are realized and
maintenance is undertaken.
2.1.7 Evaluation
The final phase of the project cycle is evaluation. This consists of looking back systematically at the
successful and unsuccessful elements of the project experience to learn how planning can be
improved in the future. For evaluation to be successful, it is important that data about the project is
collected and recorded in a systematic way throughout all stages of the project cycle. Without this, it
is usually impossible to determine details of events and information that were available during
periods leading up to the taking of important decisions. Many different people may carry out
evaluation. For each stage of the project, data shall be collected for identifying problems that need to
2
Highway engineering I chapter 2 ,Route Selection
be brought to the attention of the project’s management. The evaluation shall result in specific
recommendations about improving aspects of the project design, which can be used to improve on-
going and future planning.
2.2. Alignment
Definition: The position or the layout of the centre line of the highway on the ground is
called the alignment.
• Improper alignment of a road facility implies capital loss initially in construction as
well as loss in costs of maintenance and vehicle operation
• Once the road is aligned and constructed, it is not easy to change the alignment due
to increase in cost of adjoining land and construction of costly structures by the road
side.
• Hence careful considerations while finalising the alignment of a new road need not
be over-emphasised.
2.2.1 Requirements of an ideal alignment
• Requirements of an ideal alignment between two terminals include:
Short
• A straight alignment would be the shortest, though there may be
several practical considerations which would cause a deviation from
the shortest path
Easy
• Easy to construction
• Easy to maintain
• Easy for operation with easy grades and curves
Economical
• Design should consider initial capital cost, maintenance cost, and
operation cost
Safe
• Safe enough for construction and maintenance from the view point of
stability of natural slopes, embankments, cut slopes, and foundations
• Safe for traffic operations with easy geometric features such as
sharpness of curves, grades, side slopes and etc.
3
Highway engineering I chapter 2 ,Route Selection
In general, the aim of alignment selection process is to find a location for the new road that
will result in the lowest total construction, land, traffic and environmental costs. Before an
attempt can be made at selecting a physical location for a highway improvement, data must
be available regarding traffic desires and needs the planning intentions within the area to be
traversed, and estimates or the future physical characteristics of the highway itself: Location
surveys involving geologic and photogrammetric skills provide the basic information for
structural design, as well as the economic analysis that have a considerable influence on the
final location of the highway.
4
Highway engineering I chapter 2 ,Route Selection
There are certain guidelines that must be borne in mind in selecting the alignment and
locating the route. They are:
The route of the highway should be so selected that it can handle the traffic most
efficiently and serve the inhabited localities.
A direct alignment usually results in overall economy.
The gradients and curvature should be kept to the minimum necessary for the terrain.
Excess of both may result in economy of initial cost, but will involve high operation
costs, time costs and accident costs.
The location should minimize the use of agricultural land. If a road already exists, it may
be advisable to make use of the land already available to the maximum extent.
The location should involve the least impact on the environment.
Obstructions such as cemeteries, places of worship, archaeological and historical
monuments should be steered through.
Proximity to schools, playgrounds and hospitals should be avoided.
Interference with utility services like electric overhead transmission lines, water supply
mains, sewers, pipelines, etc should be avoided as far as possible.
Frequent crossing and re-crossing of railway lines should be avoided.
Locate the highway close to sources of embankment materials and pavement materials.
5
Highway engineering I chapter 2 ,Route Selection
The purpose of the reconnaissance survey is to evaluate the feasibility of one or more
corridor routes for a highway between specific points that may be many kilometers away.
Mostly a desk study, good reconnaissance survey can be the greatest single money-saving
phase in the construction of a new road. Hence the engineer should make ample provision in
both time and finance for this stage of highway location study. The following is a useful
checklist of the general information required in the first phase of the reconnaissance study
for a major highway, irrespective of whether it is in a rural or in a urban area.
6
Highway engineering I chapter 2 ,Route Selection
Upon completion of the reconnaissance survey, the engineer should be at least in a position
to design the more detailed geotechnical investigations which are likely to follow, and
should also have sufficient information available which, when taken in combination with the
social, ecology, traffic, economic, and political inputs, will enable the selection of one or
more apparently feasible corridor routes. If the reconnaissance survey has been very
thorough, and the necessary data are readily available, it may be possible immediately to
carry out the necessary economic and environmental comparisons to aid in the determination
of the best route.
The results of these studies are presented in a reconnaissance report. In its barest essentials,
this report should state the service and geometric criteria to be satisfied by the project,
describe the preferred route(s), and present tentative estimates of the cost.
7
Highway engineering I chapter 2 ,Route Selection
8
Highway engineering I chapter 2 ,Route Selection
After evaluating the alternative routes proposed, one or more routes will be
recommended. If more than one routes passed the reconnaissance survey detail study is
made to choose one best route in the preliminary survey.
The preliminary survey is a large-scale study of one or more feasible corridor routes. It
results in a paper location and alignment that defines the line for the subsequent final
location survey. This paper location and alignment should show enough ties to existing
topography to permit a location party to peg the centerline. In many cases field details for
final design may also be obtained economically during the preliminary survey phase.
The preliminary survey is made for the purpose of collecting the additional physical
information that may affect the location of the highway within a given corridor area, the
shape of the ground, any potential ground subsidence problems, the limits of the catchment
areas, the positions and invert levels of streams and ditches, and the positions of trees, banks
and hedges, bridges, culverts, existing roads, power lines and pipe lines, houses and
monuments are determined and noted. These are then translated into maps, profiles and
(frequently) cross sections that can assist the engineer in the determination of preliminary
grades and alignments and the preparation of cost estimates for alternative centerlines.
Two approaches are available for preliminary survey mapping: aerial surveys and ground
surveys, either separately or in various combinations.
The ground method is best used in the situation where then corridor is closely defined,
narrow right-of-way are contemplated, and the problems of man-made culture are clear.
Ground surveys, beginning with a traverse baseline, will probably furnish necessary data
9
Highway engineering I chapter 2 ,Route Selection
quite economically. Additional operations that can be quite easily included are the profile
levels and cross-sections, and the ties to land lines and cultural objects.
The aerial survey is likely to be more suitable and economical in the following instances:
Where the reconnaissance was unable to approximate closely the final alignment
Where a wide right-of-way is necessitated
Where it is desired to prevent the premature or erroneous disclosure of the details of
probable location (preventing any land speculation or the premature awakening of
local public concerns).
The choice of method should be an educated one, based on an advanced cost analysis that
takes into account the overall project schedule and the time and need requirements of
various techniques. The following discussion is primarily with the carrying out of the
traditional type of ground survey.
The first step is the carrying out of a baseline traverse – a series of connecting
straight lines and tangents stationed continuously from the beginning to the end of
the survey.
The degree of accuracy commensurate with the importance of the project and the
nature of the topography being traversed.
Angles between connecting lines should be measured in accordance with accepted
highway surveying procedures and every single point should be carefully referenced
to at least two points established well outside the area that might be occupied by the
highway construction.
To furnish date for a profile of the baseline, levels should be taken at all marked
stations, as well as at all important breaks in the ground. Elevations should also be
noted at all cross roads, streams, and other critical points on the line.
After the baseline has been pegged and levels run over it, the topography elevations
may be taken by one of the several methods, i.e. cross sectional leveling. These are
done at the same time as the profile levels. Observations are made at right angles
from each station as far as is considered necessary to cover the expected construction
area for a given centerline.
At the same time locations of all trees, fences, building and important elements are
noted so that they can be shown on the preliminary map
This survey, much of which is very often carried out as part of the preliminary survey,
serves the dual purpose of fixing the centerline of the road, while at the same time
collecting physical data which are necessary for the preparation of plans for construction
purposes.
10
Highway engineering I chapter 2 ,Route Selection
11
Highway engineering I chapter 2 ,Route Selection
12