Professional Documents
Culture Documents
ST Methodist Boundary Wall - Revised
ST Methodist Boundary Wall - Revised
ST Methodist Boundary Wall - Revised
Excess Work & Work Not Done Div. Eng/Dist. Irrig.Eng Office………………………………. Approval
Name of Institution: C/St. methodist tamil Vidyalaya A
Work Description : Repairing of boundary wall and gate
Contract Amount(excluiding GST) Rs. Cts.
BOQ (as per contract agreement) Quantity Amount for
Item Actually Actual Work Work Not
No Short Description of Work Unit Qty. Rate In excess Not Done Excess Reasons
Done Done Done
1.00 2.00 3.00 4.00 5.00 6=5-3 7=3-5 8=4x5 9=4x6 10=4x7
1 demolishing 4 1/2" bk walls 550.00 0.19 913.00 104.50
Sqr. 1.85
1.66
2 demolishing bk piers 1,225.00 0.04 539.00 49.00
cube 0.40
0.44
3 demolishing bk foundation 1,470.00 0.00 0.00 279.30 0.00 0.00
cube 0.19
0.19
4 removing and refixing name board 3,000.00 1.00 0.00 3,000.00
item 1.00
0.00
5 removing gate 950.00 0.00 0.00 950.00 0.00 0.00
item 1.00
1.00
6 cleaning wall 2,950.00 1.00 0.00 2,950.00
item 1.00
0.00
7 excavation 2,055.00 0.11 1,335.75 226.05
cube 0.76
0.65
8 1: 3: 6 concrete 35,700.00 0.03 6,783.00 1,071.00
cube 0.22
0.19
9 g20 concrete 44,245.00 0.01 9,733.90 442.45
cube 0.21
0.22
10 rrm 26,940.00 0.09 13,739.40 2,424.60
cube 0.60
0.51
11 4 1/2" bk wall 13,670.00 0.04 22,692.20 546.80
Sqr. 1.70
1.66
12 stiffner columns 610.00 6.16 7,832.40 3,757.60
Lft. 19.00
12.84
13 copings 300.00 27.09 7,773.00 8,127.00
Lft. 53.00
25.91
14 semi rough plastering 5,045.00 0.07 20,533.15 353.15
Sqr. 4.00
4.07
15 plinth wall plastering 4,825.00 0.97 579.00 4,680.25
Sqr. 1.09
0.12
Form - A Comparative Statement FINAL
Excess Work & Work Not Done Div. Eng/Dist. Irrig.Eng Office………………………………. Approval
Name of Institution: C/St. methodist tamil Vidyalaya A
Work Description : Repairing of boundary wall and gate
Contract Amount(excluiding GST) Rs. Cts.
BOQ (as per contract agreement) Quantity Amount for
Item Actually Actual Work Work Not
No Short Description of Work Unit Qty. Rate In excess Not Done Excess Reasons
Done Done Done
1.00 2.00 3.00 4.00 5.00 6=5-3 7=3-5 8=4x5 9=4x6 10=4x7
16 tor steel 203.00 0.96 6,081.88 194.88
kg 29.00
29.96
17 mild steel 179.00 4.98 719.58 891.42
kg 9.00
4.02
18 wall primer 1,385.00 3.00 6,094.00 4,155.00
Sqr. 7.40
4.40
19 weathershield paint 2,480.00 3.00 10,912.00 7,440.00
Sqr. 7.40
4.40
20 fixing gate 5,000.00 1.00 0.00 5,000.00
Nr 1.00
0.00
21 clearing debris per 3,200.00 1.00 9,600.00 3,200.00
2.00
load 3.00
Grand Total 127,090.56 4,239.48 44,374.22
490.00 0.00
279.30 0.00
3,000.00 0.00
950.00 0.00
2,950.00 0.00
1,561.80 0.00
7,854.00 0.00
9,291.45 0.00
16,164.00 0.00
23,239.00 0.00
11,590.00 0.00
15,900.00 0.00
20,180.00 0.00
5,259.25 0.00
5,887.00 0.00
1,611.00 0.00
10,249.00 0.00
18,352.00 0.00
5,000.00 0.00
6,400.00 0.00
167,225.30
Form - B Comparative Statement FINAL
Extra Contractual Works Div. Eng/Dist. Irrig.Eng Office………………………………. Approval
Name of Institution: C/St. methodist tamil Vidyalaya B
Work Description : Repairing of boundary wall and gate
Contract Amount(excluiding GST) Rs. Cts.
Rate
Amount
Item No Description of Work Quantity Unit Recommende Recommended Reasons
Dept Contractor's d by the by the Engineer
Engineer
1 2 3 4 5 6 7 8=3x7 9
Ex-1 removing existing name 1.00 Item 7,150.00 7,150.00
board, repair and
refixing
Summary
As per Guidelines on Government Tender Procedure (Revised Edition - August 1997) & Public Finance Circular No. 352(11) of 09.02.2001
Note :- The GST values for rows 2 to 8 I certified that the details given above are true and correct
should be given only if the contractor is
registered for GST
………………………………………………..
Date:-……………………… Divisional Engineer/Dist .Irrig. Engineer
Variation To Contracts
Contingencies 2,707.66
Excess 4,239.48
Extra 31,250.00
177,341.43