Professional Documents
Culture Documents
Pavement Design For NR-1
Pavement Design For NR-1
PAVEMENT DESIGN
FOR
G - 42
PAVEMENT DESIGN
Pavement of the Study Road is designed following the procedures stipulated in AASHTO’S
Guide for Design of Pavement Structures. Also, Asphalt Pavement Manual of Japan Road
Association and Road Design Standard; Part II “Pavement” of Cambodia are referred as
appropriate.
The strength of pavement, denoted as SNB (structure number), is determined with the following
equation.
-------(Eq. 1)
Where
W18 = predicted number of 18-kip equivalent single axle load
applications,
ZR = standard normal deviate,
S0 = combined standard error of the traffic prediction
and performance prediction,
⊿PSI = difference between the initial design serviceability index, p0,
and the design terminal serviceability index, pt, and
MR = resilient modulus (psi) (of subgrade); calcualoted from CBR.
Design CBR
G - 43
The following sections describe the procedures to determine the factors used in designing of
pavement.
1. Design CBR
Laboratory CBR tests were conducted on the samples taken from the test pits excavated after
the field CBR tests had been completed. The laboratory CBR tests were conducted on 4-day
soaked samples.
The locations of the test-pitting and field CBR tests are as follows:
Table 1-1 Location of Test Pitting, Field CBR and Laboratory CBR Values
CBR Value
No. Location(KP)
Field* Laboratory
1 1+184 R 15.0 7.4
2 7+050 L 14.6 3.2
3 11+381 R 45.7 2.7
4 16+000 R 9.1 8.8
5 23+002 L 16.9 3.3
6 30+000 R 8.0 2.5
7 34+980 L 7.9 2.2
8 39+900 L 14.0 2.0
9 44+600 R 11.7 3.3
10 45+290 L 7.4 1.5
11 51+132 R 5.0 2.1
As can be seen in the above, the field CBR values vary from 5.0 to 45.7, while laboratory CBR
values vary from 0.8 to 16.2. There are large differences between the filed CBR values and
laboratory CBR values. In general, field CBR values are larger than laboratory CBR values.
G - 44
However, there is no apparently consistent relation between the field CBR values and laboratory
CBR values.
One way of interpreting the differences between the field CBR values and laboratory CBR
values may be that field CBR values represent the CBR during dry season while laboratory
CBR values represent CBR during high water level season. The field CBR tests were
conducted in June 2002 when the water level in Mekong River was still far below the road
surface, while the laboratory tests were conducted on the water-soaked specimens.
In DCPT, CBR values are estimated from the number of blow against the unit depth of
penetration (usually recorded every 10 cm). Because of this test procedure, DCPT yield
estimated CBR values at every 10 cm of penetration up to 1 m deep. Average CBR over 1 m
depth at each test locationwas obtained by the following formula:
Figure 1-1 shows the CBR values obtained by the DCPT. As seen in the figure, the CBR
values thus obtained considerably fluctuate, ranging from 3 to 20, which are similar values with
those of the conventional field CBT tests. It is difficult to find any tendency in distribution of
in longitudinal direction along the Study Road.
G - 45
1.1.3 CBR Values Obtained in the Previous Studies
In the past, there were two surveys on CBR of the Study Road; one by JICA Expert (Mr.
Kawamura) and another by ADB for the design of NR-1. (They are the result of laboratory CBR
tests.)
These values are slightly higher than the result of laboratory tests of this Study.
Selected Material
CBR = 30; T = 30 cm
Additional Embankment
100 cm
CBR = 5; T = 20 cm
Existing Subgrade
Dry Season: CBR = 7
High-water Season: CBR = 2
T = 50 cm
G - 47
following formula:
CBR values for dry season and high water season are obtained as the following.
From the result of the CBR tests, in-situ and in laboratory, showed that CBR of the existing
subgrade is 7 in dry season and 2 in high water season.
“AASHTO Guide for Design of Pavement Structure” (pp II-12 ~ 14) (AASHTO Guide) shows the
method to evaluate average CBR over a year where CBR fluctuates under certain climate, such as
freeze-thaw cycle. Using the CBR values of dry season and high water season, and following
the procedure described in AASHTO Guide, average CBR values over a year is estimated at
9.3 as shown in the following.
G - 48
Roadbed Relative
Month Soil Modulus Damage
CBR/MR Uf
Jan 12/18,000 0.016
Feb 12/18,000 0.016
Mar 12/18,000 0.016
Apr 12/18,000 0.016
May 12/18,000 0.016
Jun 12/18,000 0.016
Jul 12/18,000 0.016
Aug 7/10,500 0.055
Sep 7/10,500 0.055
Oct 7/10,500 0.055
Nov 7/10,500 0.055
Dec 12/18,000 0.016
Total Uf = 0.3848
Average Uf = 0.0290 à MR = 13,900 (psi) à CBR = 9.27
The table and chart in the following page shows the procedure of estimating average CBR
presented in AASHTO Guide.
G - 49
Figure 1-3 Chart for Calculating Average CBR over a Year (AASHTO)
G - 50
2. Estimation of Traffic Volume and Equivalent Single Axle Load (ESAL)
The values of ALEF have been determined using the axle load data obtained through the vehicle
weight survey. The process of determining ALEF is presented in a separate paper (Woking
Paper RD-1). ALEF values for light vehicles and heavy vehicles are as follws:
G - 51
Using these values of ALEF and the total traffic volume as described above, ESAL (W18) for each
section is calculated as the following:
In the urbanized section, 4-lane (2 directions) is proposed in the Study. In such case, the design
ESAL is to be determined by dividing the ESAL of 2-direction by 4. Howecer, theactual traffic
situation is that right lane is mostly used by motorcycles and moto-remorks, and 4-wheel vehicles
concentrate on the left (center) lane. Therefore, it is considered to be more reasonable to use
ESAL as half of the 2-direction ESAL.
As indicated in the above table, Sections D and E, Sections F and G are combined for the purpose
of pavement design with regard to ESAL. Thus, the section of pavement design are st as the
following:
G - 54
3. Calculation of Structure Number
Structure Number (SN) is an index to indicate strength of pavement. SN is calculated with the
following formula:
-------(Eq. 1)
Where
W18 = predicted number of 18-kip equivalent single axle load applications,
ZR = standard normal deviate,
S0 = combined standard error of the traffic prediction and performance prediction,
⊿PSI = difference between the initial design serviceability index, p0,
and the design terminal serviceability index, pt, and
MR = resilient modulus (psi) (of subgrade); calculated from CBR.
In this formula, W18, or ESAL has been determined as described in Section 2 above, while MR is
calculated from CBR. Design CBR has been described in Section 1 above. The formula to
calculate MR is given below:
MR = CBR x 1,500 (psi)
In case of the Study Road,
MR = 9 x 1,500 = 13,500 (psi)
ZR, S0 and ∆ PSI are assumed as follows:
Calculation of SN is made by trial-and error method in computer. The results are shown below:
Table 3-1 Required SN for Each Section
Section 1 2 3 4 5
Station Start – 3.5 3.5 - 7 7 -14 14 – 36 36 - End
Pk (MPWT) 5.6 – 9.1 9.1 – 12.6 12.6 – 19.6 19.6 – 41.6 41.6 - End
ESAL (W18) 6.56 5.27 4.15 2.71 2.22
CBR 9
Calculated SN 3.345 3.231 3.111 2.906 2.815
G - 55
4. Design of Pavement Structure
Examples of Structure Number of each layer for typical thickness are shown in the table below:
Table 4-2 Examples of Typical Thickness of Layers and Their Structure Numbers
Thickness (T) Layer Drain
Layer Coefficient T*a Factor T*a* Remarks
cm in (a) (D) D
Surface Course 5 1.969 0.42 0.83 1.0 0.83
(AC) 10 3.937 1.65 1.65
Base Course 10 3.947 0.13 0.51 0.8 0.41
(Crushed Stone) 15 5.906 (CBR=80) 0.77 0.62
20 7.874 1.02 0.82
25 9.843 1.28 1.02
Subbase Course 15 5.906 0.115 0.68 0.8 0.54
(Granular Material) 20 7.874 (CBR=30) 0.91 0.72
25 9.843 1.13 0.91
30 11.811 1.36 1.09
35 13.779 1.58 1.27
G - 56
4.2 Minimum Thickness of Each Layer
Design of pavement is done by combining these thicknesses to make the total of structural
numbers of the layers equal to, or lager than, the required SN, with minimum cost. However, it
is usual practice to decide the minimum thickness of layers. AASHTO Design Guide stipulates
the following thicknesses for asphalt concrete and aggregate base course.
In the case of theStudy Road, ESAL of the entire section fall in the category of “2,000,001 –
7,000,000”. Accordingly, the minimum thickness of 3.5 inches (approximately 8.9 cm) is
recommended for surface course. Similarly, minimum thickness of 6 inches (approximately 15
cm) is recommended for base course.
Asphalt Pavement Manual of Japan Road Association (JRO) stipulates the following minimum
thicknesses for surface course (total of “wearing course” and “binder course”).
The classes of traffic volumes used in the above table are as defined in the following table.
G - 57
Table 4-5 Class of Traffic Volume
Traffic Volume of Heavy Vehicles
Class of Design Traffic Volume (Vehicle/day/direction)
L Less than 100
A 100 – 249
B 250 – 999
C 1,000 – 2,999
D 3,000 or more
When these criteria are applied, the traffic volumes of Sections 4 and 5 are classified as “Class A”
and those of other Sections are classified as “Class B”. Accordingly, minimum thickness of 5
cm recommended for Section 4 and 5, and 10 cm is recommended for other Sections. (Please note
that the traffic volumes of heavy vehicles shown in Table 2-1 are for 2-directions, while the traffic
volumes shown in Table 4-5 are for 1-direction.)
JRO’s Asphalt Pavement Manual also gives minimum thickness of base course and subbase
course as shown in the table below.
G - 58
Table 4-7 Alternatives of Pavement Structure
Start - St. St. 14 - St. 36 -
Section St. 3 - 7 St. 7 - 14
3 36 End
Required SN 3.345 3.231 3.111 2.906 2.815
Surface Thick. (cm) 10 10 10 5 5
SN 1.654 1.654 1.654 0.827 0.827
A Base Thick. (cm) 20 20 15 25 25
L SN 0.827 0.827 0.620 1.033 1.033
T Subbase Thick. (cm) 24 21 24 29 27
1 SN 0.869 0.761 0.869 1.050 0.978
Total SN 3.350 3.241 3.143 2.911 2.838
Total Thickness (cm) 54 51 49 59 57
Surface Thick. (cm) 10 10 10 5 5
SN 1.654 1.654 1.654 0.827 0.827
A Base Thick. (cm) 15 15 20 20 20
L SN 0.620 0.620 0.827 0.827 0.827
T Subbase Thick. (cm) 30 27 19 35 32
2 SN 1.087 0.978 0.688 1.268 1.159
Total SN 3.360 3.252 3.169 2.921 2.813
Total Thickness (cm) 55 52 49 60 57
Surface Thick. (cm) 10 5 10 10
SN 1.654 0.827 1.654 1.654
A Base Thick. (cm) 25 25 15 15
L SN 1.033 1.033 0.620 0.620
T Subbase Thick. (cm) 19 35 18 15
3 SN 0.688 1.268 0.652 0.543
Total SN 3.375 3.128 2.926 2.817
Total Thickness (cm) 54 65 43 40
G - 59
Start - St. St. 14 - St. 36 -
Section St. 3 - 7 St. 7 - 14
3 36 End
Surface Thick. (cm) 10 10 10 5 5
Cost 2.067 2.067 2.067 1.000 1.000
A Base Thick. (cm) 20 20 15 25 25
L Cost 0.766 0.766 0.544 0.926 0.926
T Subbase Thick. (cm) 24 21 24 29 27
1 Cost 0.813 0.727 0.813 0.956 0.898
Total Cost 3.646 3.560 3.423 2.882 2.824
Surface Thick. (cm) 10 10 10 5 5
Cost 2.067 2.067 2.067 1.000 1.000
A Base Thick. (cm) 15 15 20 20 20
L Cost 0.544 0.544 0.766 0.766 0.766
T Subbase Thick. (cm) 30 27 19 35 32
2 Cost 0.984 0.898 0.607 10128 1.041
Total Cost 3.595 3.509 3.440 2.894 2.808
Surface Thick. (cm) 10 5 10 10
Cost 2.067 1.000 2.067 2.067
A Base Thick. (cm) 25 25 15 15
L Cost 0.926 0.926 0.544 0.544
T Subbase Thick. (cm) 19 35 18 15
3 Cost 0.607 10128 0.578 0.493
Total Cost 3.600 3.054 3.190 3.104
As indicated by bold-face letters, the following alternatives are with the lowest costs.
Section 1: Alternative 2
Section 2: Alternative 2
Section 3: Alternative 1
Section 4: Alternative 1
Section 5: Alternative 2
In case of Section 3, the estimated cost of Alternative 3 is the lowest. However, the thickness of
surface course does not satisfy the recommended minimum thickness of AASHTO and JRO, and,
thus, this alternative is not recommended. The recommended pavement structures are
summarized in the table below.
G - 60
Table 4-9 Summary of Pavement Structure
Section 1 2 3 4 5
Station Start – 3.5 3.5 - 7 7 - 14 14 - 36 36 - End
Pk (MPWT) 5.6 – 9.1 9.1 – 12.6 12.6 – 19.6 19.6 – 41.6 41.6 - End
Pavement Type A B C D E
Surface Thick. (cm) 10 10 10 5 5
SN 1.654 1.654 1.654 0.827 0.827
Base Thick. (cm) 15 15 15 25 20
SN 0.620 0.620 0.620 1.033 0.827
Subbase Thick. (cm) 30 27 24 29 32
SN 1.087 0.978 0.869 1.050 1.159
Total SN 3.360 3.252 3.143 2.911 2.813
Total Thickness (cm) 55 52 49 59 57
Required SN 3.345 3.231 3.111 2.906 2.815
Surface 10 cm 10 cm 10 cm 5 cm 5 cm
Base 15 cm 15 cm 15 cm 25 cm 20 cm
Subbase
30 cm 27 cm 24 cm 29 cm 32 cm
Total Thickness 55 cm 52 cm 49 cm 59 cm 57 cm
G - 61
4.2.3 Comparison of Costs for Various Design Life Periods
Although design life period of pavement is set at 10 years in usual practice, life cycle cost (LCC)
of design life of 5, 10 and 15 years are compared to verify the justification of design life period.
Table 4-10 shows the design factors and price indices of pavement of Section 1 and 5 for design
life of 5, 10 and 15 years.
Section 1 5
Design Life (Year) 5 10 15 5 10 15
Total ESAL 3.07 6.56 10.89 1.03 2.22 3.72
Required SN 2.965 3.345 3.621 2.487 2.815 3.057
Surface Thck. (cm) 10 10 10 5 5 5
SN 1.654 1.654 1.654 0.827 0.827 0.827
Base Thck. (cm) 15 15 20 15 20 25
SN 0.620 0.620 0.827 0.620 0.827 1.033
Subbase Thck. (cm) 19 30 32 29 32 33
SN 0.688 1.087 1.159 1.050 1.159 1.195
Total SN 2.962 3.360 3.639 2.497 2.813 3.056
Total Thickness (cm) 44 55 62 49 57 63
Actual Design Life (Year)
Price Index as Surface (T = 5 cm) = 1.000
Surface 2.067 2.067 2.067 1.000 1.000 1.000
Base 0.544 0.544 0.544 0.544 0.766 0.926
Subbase 0.607 0.984 1.012 0.927 1.041 1.070
Total 3.218 3.595 3.845 2.471 2.807 2.996
Tables 4-11 and 4-12 show the comparison of LCC for these pavement designs.
G - 62
Table 4-11 Comparison of Life Cycle Cost for Section 1
Section 1
Design Life (Year) 5 10 15
Discount Cost
Year Rate Nominal Disc'td Nominal Disc'td Nominal Disc'td
0 1.00000 3.2180 3.2180 3.5950 3.5950 3.8450 3.8450
1 0.89286 0.0322 0.0287 0.0322 0.0287 0.0322 0.0287
2 0.79719 0.0322 0.0257 0.0322 0.0257 0.0322 0.0257
3 0.71178 0.0322 0.0229 0.0322 0.0229 0.0322 0.0229
4 0.63552 0.0322 0.0205 0.0322 0.0205 0.0322 0.0205
5 0.56743 0.0322 0.0183 0.0322 0.0183 0.0322 0.0183
6 0.50663 1.0000 0.5066 0.0322 0.0163 0.0322 0.0163
7 0.45235 0.0322 0.0146 0.0322 0.0146 0.0322 0.0146
8 0.40388 0.0322 0.0130 0.0322 0.0130 0.0322 0.0130
9 0.36061 0.0322 0.0116 0.0322 0.0116 0.0322 0.0116
10 0.32197 0.0322 0.0104 0.0322 0.0104 0.0322 0.0104
11 0.28748 1.0000 0.2875 1.0000 0.2875 0.0322 0.0093
12 0.25668 0.0322 0.0083 0.0322 0.0083 0.0322 0.0083
13 0.22917 0.0322 0.0074 0.0322 0.0074 0.0322 0.0074
14 0.20462 0.0322 0.0066 0.0322 0.0066 0.0322 0.0066
15 0.18270 0.0322 0.0059 0.0322 0.0059 0.0322 0.0059
16 0.16312 0.0322 0.0052 0.0322 0.0052 1.0000 0.1631
17 0.14564 1.0000 0.1456 0.0322 0.0047 0.0322 0.0047
18 0.13004 0.0322 0.0042 0.0322 0.0042 0.0322 0.0042
19 0.11611 0.0322 0.0037 0.0322 0.0037 0.0322 0.0037
20 0.10367 0.0322 0.0033 0.0322 0.0033 0.0322 0.0033
21 0.09256 0.0322 0.0030 0.0322 0.0030 0.0322 0.0030
22 0.08264 1.0000 0.0826 1.0000 0.0826 0.0322 0.0027
23 0.07379 0.0322 0.0024 0.0322 0.0024 0.0322 0.0024
24 0.06588 0.0322 0.0021 0.0322 0.0021 0.0322 0.0021
25 0.05882 0.0322 0.0019 0.0322 0.0019 0.0322 0.0019
Salvage value 0.05882 0.9804 0.0577 0.7000 0.0412 0.4000 0.0235
Total 6.8812 4.4022 5.6030 4.1644 5.1851 4.2317
G - 63
Table 4-12 Comparison of Life Cycle Cost for Section 5
Section 5
Design Life (Year) 5 10 15
Discount Cost
Year Rate Nominal Disc'td Nominal Disc'td Nominal Disc'td
0 1.00000 2.5850 2.5850 2.8070 2.8070 2.9100 2.9100
1 0.89286 0.0259 0.0231 0.0259 0.0231 0.0259 0.0231
2 0.79719 0.0259 0.0206 0.0259 0.0206 0.0259 0.0206
3 0.71178 0.0259 0.0184 0.0259 0.0184 0.0259 0.0184
4 0.63552 0.0259 0.0164 0.0259 0.0164 0.0259 0.0164
5 0.56743 0.0259 0.0147 0.0259 0.0147 0.0259 0.0147
6 0.50663 1.0000 0.5066 0.0259 0.0131 0.0259 0.0131
7 0.45235 0.0259 0.0117 0.0259 0.0117 0.0259 0.0117
8 0.40388 0.0259 0.0104 0.0259 0.0104 0.0259 0.0104
9 0.36061 0.0259 0.0093 0.0259 0.0093 0.0259 0.0093
10 0.32197 0.0259 0.0083 0.0259 0.0083 0.0259 0.0083
11 0.28748 1.0000 0.2875 1.0000 0.2875 0.0259 0.0074
12 0.25668 0.0259 0.0066 0.0259 0.0066 0.0259 0.0066
13 0.22917 0.0259 0.0059 0.0259 0.0059 0.0259 0.0059
14 0.20462 0.0259 0.0053 0.0259 0.0053 0.0259 0.0053
15 0.18270 0.0259 0.0047 0.0259 0.0047 0.0259 0.0047
16 0.16312 1.0000 0.1631 0.0259 0.0042 1.0000 0.1631
17 0.14564 0.0259 0.0038 0.0259 0.0038 0.0259 0.0038
18 0.13004 0.0259 0.0034 0.0259 0.0034 0.0259 0.0034
19 0.11611 0.0259 0.0030 0.0259 0.0030 0.0259 0.0030
20 0.10367 0.0259 0.0027 0.0259 0.0027 0.0259 0.0027
21 0.09256 1.0000 0.0926 1.0000 0.0926 0.0259 0.0024
22 0.08264 0.0259 0.0021 0.0259 0.0021 0.0259 0.0021
23 0.07379 0.0259 0.0019 0.0259 0.0019 0.0259 0.0019
24 0.06588 0.0259 0.0017 0.0259 0.0017 0.0259 0.0017
25 0.05882 0.0259 0.0015 0.0259 0.0015 0.0259 0.0015
Salvage value 0.05882 0.4000 0.0235 0.6000 0.0353 0.4000 0.0235
Total 7.5279 3.7869 6.0016 3.3447 4.9304 3.2481
G - 64
As can be seen in the tables, 10-year life period design is most economical for Section 1, and
15-year design is slightly more economical than 10-year design for Section 5. As stated before,
it is usual practice to set the design life period at 10 years. Considering that the difference
between the 10-year design and 15-year design foe Section 5 is small and that the 10-year design
is a little more economical for Section 1, it is considered to be reasonable to adopt wo years as the
design life period of the pavement for the Study Road.
5. Summary
Design traffic volume, ESAL, CBR and pavement type for each section are summarized in Figure
5-1.
G - 65
G-4.
NATINAL ROAD No.1 HORIZONTAL ALIGNMENT
Printed 21 Oct 2002
No. PI No. NORTHING EASTING A(angle) AZ(deg.) AZIMUTH DISTANCE R C r XM CURVE ELEMENTs e S
degree d m s m m A IA (d) IA (d,m,s) TL LS LC Es % m
21 28 1,271,138.786 508,942.459 89.3 89.3 89 20 58 862.278 700 250 0.474 44.637 9.4 9 21 42 101.991 89.286 25.089 2.819 3 50
22 29 1,271,141.237 509,158.273 -80.5 99.5 99 31 2 215.827 700 250 0.474 44.637 10.2 10 10 4 106.996 89.286 34.940 3.241 3 50
23 30 1,270,972.199 510,166.527 -63.6 116.4 116 26 11 1,022.326 1,270 - 16.9 16 55 9 188.887 375.025 13.970 3 50
24 31 1,270,588.415 510,938.419 -70.7 109.3 109 19 51 862.037 2,820 - 7.1 7 6 20 175.089 349.730 5.430 NC -
25 32 1,269,845.783 513,055.395 -70.9 109.1 109 8 34 2,243.455 0 - 0.2 0 11 17 0.000 0.000 0.000 NC -
26 33 1,269,634.200 513,664.937 -41.3 138.7 138 43 21 645.220 780 270 0.467 46.725 29.6 29 34 47 252.786 93.462 309.225 27.211 3 50
G - 67
27 34 1,269,023.665 514,200.878 -50.8 129.2 129 12 14 812.395 1,740 - 9.5 9 31 7 144.869 289.072 6.020 RC 40
28 36 1,268,326.813 515,055.184 -49.1 130.9 130 54 5 1,102.470 5,000 - 1.7 1 41 51 74.071 148.132 0.549 NC -
29 38 1,267,129.566 516,437.258 -53.5 126.5 126 27 57 1,828.532 2,030 - 4.4 4 26 8 78.616 157.154 1.522 RC 40
30 39 1,266,717.601 516,994.694 -68.8 111.2 111 12 12 693.145 1,450 - 15.3 15 15 44 194.274 386.248 12.957 3 50
31 40 1,266,465.153 517,645.427 -61.6 118.4 118 22 32 697.986 1,640 - 7.2 7 10 19 102.779 205.289 3.217 RC 40
32 41 1,266,094.073 518,332.428 -61.6 118.4 118 25 6 780.814 0 - 0.0 0 2 34 0.000 0.000 0.000 NC -
33 42 1,265,563.467 519,313.010 -40.6 139.4 139 26 21 1,114.937 1,170 - 21.0 21 1 15 217.067 429.253 19.966 3 50
34 44 1,264,378.847 520,326.944 -40.3 139.7 139 44 21 1,559.290 0 - 0.3 0 18 0 0.000 0.000 0.000 NC -
35 45 1,264,144.547 520,525.370 -50.0 130.0 129 58 28 307.033 2,040 - 9.8 9 45 53 174.257 347.670 7.429 RC 40
36 47 1,263,230.965 521,615.117 -59.3 120.7 120 44 19 1,422.034 2,000 - 9.2 9 14 9 161.545 322.390 6.514 RC 40
37 50 1,262,372.145 523,059.309 -70.7 109.3 109 17 40 1,680.256 1,290 - 11.4 11 26 39 129.263 257.666 6.460 3 50
38 53 1,262,060.637 523,949.112 -47.4 132.6 132 38 43 942.755 980 - 23.4 23 21 3 202.510 399.398 20.705 3 50
39 55 1,260,754.348 525,367.439 -33.2 146.8 146 45 6 1,928.223 1,420 - 14.1 14 6 23 175.691 349.605 10.828 3 50
40 56 1,259,406.868 526,250.833 -8.5 171.5 171 32 22 1,611.237 1,020 - 24.8 24 47 16 224.148 441.283 24.338 3 50
41 57 1,257,438.527 526,543.618 -8.6 171.4 171 22 2 1,989.997 0 - 0.2 0 10 20 0.000 0.000 0.000 NC -
42 58 1,256,524.459 526,682.392 5.5 185.5 185 32 16 924.542 1,370 - 14.2 14 10 14 170.284 338.831 10.542 3 50
43 63 1,252,690.469 526,310.673 5.5 185.5 185 27 52 3,851.968 0 - 0.1 0 4 24 0.000 0.000 0.000 NC -
44 64 1,251,942.520 526,239.122 -40.7 139.3 139 17 54 751.364 990 - 46.2 46 9 58 421.925 797.694 86.160 3 50
45 66 1,249,913.221 527,984.699 -11.1 168.9 168 56 2 2,676.769 980 - 29.6 29 38 8 259.253 506.894 33.712 3 50
46 68 1,247,633.666 528,430.529 -7.4 172.6 172 38 48 2,322.743 2,360 - 3.7 3 42 46 76.490 152.927 1.239 RC 40
47 69 1,246,784.897 528,540.062 -15.4 164.6 164 35 1 855.807 1,680 - 8.1 8 3 47 118.407 236.423 4.168 RC 40
48 70 1,245,358.113 528,933.505 -68.8 111.2 111 12 60 1,480.038 490 190 0.461 36.830 53.4 53 22 1 283.329 73.673 382.726 58.921 4 60
49 71 1,245,086.892 529,632.152 -88.5 91.5 91 27 13 749.446 530 - 19.8 19 45 47 92.324 182.813 7.981 4 60
50 72 1,245,080.105 529,899.633 267.567 91.5 91 27 13 0.000 0.000 0.000
0 0 0.000 0.000 0.000
G-5. General Consideration on Soft Ground
The Study Road traverses the marshy hinterland of Mekong River, and existence of soft ground
is strongly suspected. From viewpoint of highway embankment, problems and countermeasures
are briefly explained below.
G - 68
(ii) More uniform both vertically and horizontally than river/lake deposits.
(iii) Less strength than river/lake deposits because of rich clay content.
(iv) Longer time needed for consolidation (squeezing out of water in soil) when load is
applied: This is due to longer path of water squeezed out because of uniformity, or
“homogeneity” in the geotechnical terminology, in both horizontal and vertical
direction.
(v) As a result of (iv) above, longer time is needed to complete settlement.
(vi) Slow increase in strength due to slow consolidation speed
(vii) As a result of (vi) above, stability of embankment against the failure of ground is slow
to be improved.
All of these facts make marine deposits unfavorable for highway embankment.
Because of the characteristics as described above, river/lake deposits are less unfavorable for
highway embankment than marine deposits. On the other hand, properties of river deposits may
drastically change in horizontal and vertical direction. Therefore, it is necessary to conduct
appropriate sounding of ground condition and to take precaution in execution are indispensable
for river deposits.
G - 69
ground is very unfavorable for highway embankment because of the following characteristics.
(i) Very low strength and, thus, very low stability of embankment
(ii) Large amount of post-construction settlement
(iii) High water content which requires special preparatory works and equipment for
embankment.
Very fortunately, it is rather rare to encounter this type of soft ground with large scale in tropical
climate like Cambodia.
For example, even if there is a soft layer with N-value of one (1) at 10 m or more below the
ground surface, and the layers above this soft layer are relatively firm (say N-value 4 or more),
then, highway embankment is safely constructed without serious problem of stability, unless the
height of embankment is large (for example higher than 10 m). This is due to the fact that the
load of the embankment is distributed by the relatively firm layers above the soft layer and
becomes small enough when it reaches the soft layer.
G - 70
Decrease of Load
More than 10 m
N=5
N = 10
N=7
N = 1 (Soft Layer)
G - 71
G-6. Preliminary Analysis of Stability and Estimation of Settlement of
Embankment on Soft Ground
1. Estimation of Settlement
The conditions as shown in Figure 1-1 were assumed. Assumed e-log p curve is shown in
Figure 1-2.
3.6m
γt = 2.0 t/m3
3.0 m
γt = 2.0 t/m3
1.75 m
γt = 1.8 t/m3
3.5 m
Calculation of Settlement
Using the data of the consolidation tests on the samples obtained from the soft layer, settlement
due to consolidation is calculated with the following formula:
De
S= ´ HS
1 + e0
Where
S: Settlement (m)
∆e: change in void ratio of soil due to loading of embankment,
determined from the e-log p curve obtained by consolidation test
e0: void ratio of soft soil before construction of embankment
HS: thickness of soft layer (m).
G - 72
Pressure, p (kN/m2)
10 100 1000
1.00
0.475
0.95
Void Ratio, e
0.95
1.05
0.90
0.90
0.85
0.80
0.75
De
S= ´ HS
1 + e0
0.05
= ´ 300 (cm)
1 + 0.95
= 7.7 cm
Residual Settlement
According to the past experience, 70 to 90 % of the total settlement occurs during the
construction. Therefore, amount of residual settlement, SR, or post-construction settlement
(settlement occurring after completion of embankment) is estimated as follows.
Since the assumptions and calculation adopted in the estimation above is very simplified, the
result of calculation should be interpreted as to show only the overall magnitude of the problem.
Therefore, it can be said that the magnitudes of settlement and residual settlement are in the
order of 10 and 2 cm, respectively. These values are considered to be relatively small.
The calculation shown here is very preliminary and considers only one soft layer. The reason for
G - 73
this simple calculation is that soils of other layers are relatively firm and it can be assumed that
the settlement due to consolidation of other layers are relatively small. The purpose of the
estimation made here is to show the magnitude of settlement and degree of difficultness of
the problem. More detailed analysis needs to be made at design stage.
2. Analysis of Stability
For the analysis of stability, the conditions as shown in Figure 2-1 were assumed. Factor of
safety, Fs, against circular slip failure was calculated. Minimum Fs = 1.51 was obtained. This is
considered to indicate sufficient stability against failure. (Usually minimum Fs of 1.2 to 1.3 are
stipulated in the design manuals of highway. For example, Design Manual of Japan Highway
Public Corporation stipulates Fs = 1.25.)
Similarly to the estimation of settlement, this stability analysis is for the purpose of show the
degree of seriousness of stability problem. More detailed analysis is needed at design and
execution stages wherever soft ground is suspected or encountered.
14.00
Fs min = 1.51
.0 .0
1:2
3.60
C = 2.0 tf/m 2
φ = 20°
(0,0) Top Soil γt = 2.0 tf/m 3
3.00
C = 1.5 tf/m 2
φ = 0°
Sandy Silt γt = 2.0 tf/m 3
3.00
C = 2.0 tf/m 2
φ = 20°
G - 74
G-7. Life Cycle Cost Analysis of Pavement
To verify the economic justification of usage of AC pavement, Life Cycle Cost (LCC) analysis
was made for AC pavement and DBST. This paper describes outline of the LCC analysis.
G - 75
(i) Condition of SBST pavement becomes intolerable 5 to 7 years from the time of new
construction if no routine maintenance is done.
(ii) The cost of minimum repair at this stage is approximately 10 % of the cost of new
construction of DBST.
In 2002, severe pot holes are to be repaired as a part of ADB’s Emergency Flood Relief Project.
In the Bill of Quantity of the contract, total 2,000 m2 of repair of pot holes and 2,000 m2 of
repair of edge break are listed for the 36 km-long section (KM 24 – 60). This corresponds
approximately 2 % of the total area of pavement of this section. This figure was very
provisionally decided for the purpose of tendering, based on the visual evaluation by the
consultant for the Emergency Flood Relief Project. After the works were started, it was felt
that the method repair of pot holes is not sufficient and MPWT is currently reviewing the repair
method. Even after revision of repair method, this repair work is limited to very severe pot
holes, and other less severe pavement defection will be left untouched. Therefore, new necessity
of repair will arise from next year and afterwards. MPWT is planning to request the necessary
budget allocation for these maintenance works.
(i) One year after the minimum repair works, more than 2 % of the total pavement area needs to
be repaired.
G - 76
It should be emphasized that the above record of maintenance does not mean that MPWT is
satisfied with the situation of maintenance. MTWT had to accept this situation because of the
shortage in the fund for maintenance. Therefore, better maintenance would have been
implemented if appropriate fund had been available.
1.2. NR-4
This highway was rehabilitated under USAID program. Rehabilitation was implemented in
year 1994 – 1995. The type of pavement was AC. In year 2000, small “dents” were observed
on the pavement surface very sporadically. Some of them developed to pot holes and they
were repaired by MPWT. The total expenditure for this repair was Riel 68 million, or
approximately US$ 17,400. Compared to the total length of NR-4 (214 km), this amount of
repair cost is considered to be very small. This figure becomes more impressive when the fact,
that this highway is used by heavy trucks connecting Phnom Penh and Sihanoukville, is
considered. The cost of AC pavement for entire 214 km-long section is very approximately
estimated at US$ 21.7 million. The above-mentioned cost of repair represents less than 0.1 %
(0.08 %) of the estimated cost of new construction of AC pavement.
Overall condition of the pavement of NR-4 with these sporadic potholes was much better than
that of NR-1. The present condition of pavement of NR-4 is still in fairly good and very little
repair is observed to have been done up to today. Therefore, it is reasonable to assume that
pavement of NR-4 is still in much better condition than that of NR-1 even without any repair.
(Of course this will result in the necessity of earlier rehabilitation and larger amount of cost than
those expected under present maintenance practice.)
G - 77
From this fact, the following can be derived.
(i) Routine maintenance cost of AC pavement is less than 0.1 % 5 to 6 years after construction.
(ii) AC pavement is fairly intact under substantially heavy traffic
G - 78
(ii) Scenario 2: Acceptable Maintenance
Scenario 1 assumes almost what was actually implemented in the past for DBST. As for AC,
the scenario assumed less maintenance than actually done to balance the condition of AC
pavement with that of DBST, and worse than actually anticipated. In Scenario 2, maintenance
of AC is assumed to be same to actual condition in the past case of NR-4. To balance the
condition, better maintenance for DBST is assumed. It is usually agreed that practical life
period of DBST with ordinary maintenance is 5 to 7 years. Therefore, 7 years is assumed to be
life period of DBST here. As for practical life period of AC pavement, there are very limited
data. One literature in Japan indicates that repair works increases when application of axle
load in terms of ESAL exceeds 1 million. In case of Section 5 of the Study Road, estimated
ESAL for design life of 10 yeas is approximately 2. Therefore, it is assumed that with ordinary
maintenance, overlay becomes necessary 10 years after construction. Based on the above
assumptions, the following scenario is assumed.
3. Estimation of LCC
3.1 Assumed Conditions and Scenario
LCC analysis was made on Section 5 of the Study Road. The reason for this was that the
estimated traffic volume of Section 5 is the smallest among those of the five sections of the
Study Road, and, thus, Section 5 is considered to be most suitable for adopting DBST.
The conditions assumed and used in the analysis are summarized in the table below. Anayses
were made for “Minimum Maintenance Scenario” and “Acceptable Maintenance Scenario” as
G - 79
described in Section 3 above.
As can be seen in the table above, LCC of AC is higher than that of DBST by 14 % for
“Minimum Maintenance Scenario” and by 16 % for “Acceptable Maintenance Scenario”.
G - 80
Table 3-2 Comparison of LCC: Minimum Maintenance Scenario
(Unit: $ 1,000)
AC DBST
Constructio Constructio
Discount Discounte Discount Discounte
Year n& n&
Rate* d Cost Rate* d Cost
Maintenanc Maintenanc
0 2,984 1.00000 2,983.50 2,282 1.00000 2,281.50
1 0 0.89286 0.00 0 0.89286 0.00
2 0 0.79719 0.00 0 0.79719 0.00
3 0 0.71178 0.00 0 0.71178 0.00
4 0 0.63552 0.00 0 0.63552 0.00
5 0 0.56743 0.00 186 0.56743 105.33
6 0 0.50663 0.00 15 0.50663 7.52
7 0 0.45235 0.00 15 0.45235 6.72
8 0 0.40388 0.00 15 0.40388 6.00
9 0 0.36061 0.00 15 0.36061 5.36
10 0 0.32197 0.00 338 0.32197 108.67
11 15 0.28748 4.29 338 0.28748 97.02
12 0 0.25668 0.08 338 0.25668 86.63
13 0 0.22917 0.07 0 0.22917 0.00
14 0 0.20462 0.06 0 0.20462 0.00
15 405 0.18270 73.99 0 0.18270 0.00
16 405 0.16312 66.06 0 0.16312 0.00
17 405 0.14564 58.99 186 0.14564 27.04
18 0 0.13004 0.00 15 0.13004 1.93
19 0 0.11611 0.00 15 0.11611 1.72
20 0 0.10367 0.00 15 0.10367 1.54
Salvage value (729) 0.10367 -75.57 (74) 0.10367 -7.70
Total 3,111.46 2,729.27
*Discount rate: 12 % / Yr
G - 81
Table 3-3 Comparison of LCC: Acceptable Maintenance Scenario
(Unit: $ 1,000)
AC DBST
Constructio Constructio
Discount Discounte Discount Discounte
Year n& n&
Rate* d Cost Rate* d Cost
Maintenanc Maintenanc
0 2,984 1.00000 2,983.50 2,282 1.00000 2,281.50
1 0 0.89286 0.00 0 0.89286 0.00
2 0 0.79719 0.00 15 0.79719 11.84
3 0 0.71178 0.00 15 0.71178 10.57
4 0 0.63552 0.00 15 0.63552 9.44
5 0 0.56743 0.00 15 0.56743 8.43
6 3 0.50663 1.51 15 0.50663 7.52
7 3 0.45235 1.35 338 0.45235 152.67
8 3 0.40388 1.20 338 0.40388 136.31
9 3 0.36061 1.08 338 0.36061 121.71
10 3 0.32197 0.96 0 0.32197 0.00
11 1,215 0.28748 349.28 15 0.28748 4.27
12 0 0.25668 0.08 15 0.25668 3.81
13 0 0.22917 0.07 15 0.22917 3.40
14 0 0.20462 0.06 15 0.20462 3.04
15 0 0.18270 0.00 15 0.18270 2.71
16 0 0.16312 0.00 338 0.16312 55.05
17 3 0.14564 0.43 338 0.14564 49.15
18 3 0.13004 0.39 338 0.13004 43.89
19 3 0.11611 0.35 15 0.11611 1.72
20 3 0.10367 0.31 15 0.10367 1.54
Salvage value (122) 0.10367 -12.60 (405) 0.10367 -41.99
Total 3,327.97 2,866.59
*Discount rate: 12 % / Yr
G - 82
G-8. Further Study on Traffic Situation at Chbar Ampov Intersection
Chbar Ampov Intersection is located at the eastern end of Monivong Bridge. It exists
between National Road No.1 and National Road No.361, while at the western of the bridge,
there is Kbal Ntal Intersection that is between National Road No.1 and National Road No.2
& 3. Chbar Ampov Intersection is located on the National Road No. 1 (NR-1) in Mean
Chey District of Phnom Penh Municipality, and the name of road at this section is
Viyadapuda Road.
Old Monivong Bridge had been constructed in 1929 on the extending line of Chbar Ampov
Intersection, and it had collapsed due to scouring of western abutment. Since the existing
Monivong Bridge was constructed in 1960s about 50 m north from the position of old
bridge, Chbar Ampov Intersection becomes staggered.
300 m stretch of Viyadapuda Road at the Phnom Penh side is divided 6 lanes road, and
concrete buildings and permanent residences exist along the road. Densely developed
commercial and residential areas are spread in this district, and grid-pattern road network
comprising local narrow streets sustain the development of this built-up area.
View from Kbal Ntal Intersection to Monivong Br. Crowded and congested Chbar Ampov Market
Fig. G-8-1 shows the built-up area and road network in the vicinity of Chbar Ampov
Intersection.
G - 83
2. Problems related to Road Traffic
12 hrs (6:00 – 18:00) traffic volume on Monivong Bridge are of 168,000 vehicles
(Motorcycle: 87%, Light vehicles: 11%), that is equivalent to 64,000 pcu, while 12 hrs
traffic volume from all directions at Chbar Ampov Intersection is observed 128,000 vehicles
or 44,000 pcu. These figures account for the saturation of traffic capacity quantitatively,
and it incurs problems related to road traffic in this area where traffic congestion frequently
occurs.
From physical and qualitative viewpoints, public facilities such as Chbar Ampov Market,
bus terminal, taxi terminal, ferry terminal and pagoda are scattered in the vicinity of Chbar
Ampov Intersection. One of salient features related to road traffic in this area is found
many turning traffic. East-westward through traffic at this intersection is predominant at
Chbar Ampov Intersection, and it is considerably affected by turning traffic access to and
egress from such public facilities.
Under such circumstances, this intersection has many disadvantages in the traffic
engineering aspect as follows:
1) Unbalanced number of lane occurs between western entrance and eastern exit at Chbar
Ampov Intersection. NR-1 has 6 lanes at 300 m stretch of Viyadapuda Road, but it
reduces up to 2 lanes on Monivong Bridge.
G - 85
2) It is basically 4-leg intersection, but entrance traffic is generated from more than four
directions actually because there are additional local roads to connect to the
intersection.
Undivided 2-lane National Road No.361 Narrow local road in Mean Chey District
3) Bus terminal, taxi terminals, public market and pagoda encompass Chbar Ampov
Intersection, and accordingly many turning traffic are generated.
4) It is situated on the steep slope of approach section of the bridge, and moreover it is
staggered. This intersection consists of two 3-leg intersections in the short distance
theoretically.
Situated on the steep slope of bridge approach Congested bus terminal besides intersection
The improvement of Chbar Ampov Intersection has been studied in the past, namely the
feasibility study of “Ho Chi Minh City to Phnom Penh Highway Improvement Project”
funded by ADB. According to hearing from MPWT staff, some grade separation
structures were examined to maneuver traffic effectively in the course of the study and the
improvement by roundabout was proposed finally as shown in Fig. G-8-2. The study team
G - 86
examined the improvement plan of channelized intersection as shown in Fig. G-8-3.
However, it is obvious that the present traffic volume exceeds the traffic capacity at
intersection considerably, and common issues were discussed technically to identify the
following points:
1) The existing intersection is situated on the steep slope of approach section of the bridge
as well as staggered shape, and it is inevitable defect of intersection design, that is to say,
below standard.
2) Queue of waiting vehicles at entrance is long enough to cause traffic interlocking that is
the most serious congestion at intersection.
Congested Chbar Ampov Intersection is one of major traffic bottlenecks on National Road
No. 1 C-1 Section (Phnom Penh – Neak Loueng Section) together with Neak Loueng Ferry
and Kokir Market. Accordingly, it is desirable to improve it simultaneously if NR-1 C-1 is
improved a flood-free road to an all-weather standard. However, physical constraints such
as close location to the bridge, steep slope, staggered shape and lack of land availability in
the vicinity are so severe and complicated that it is difficult to solve the problems only by an
engineering design without the construction of 2nd Monivong Bridge. 2nd Monivong
Bridge is proposed in the Study on the Transport Master Plan of the Phnom Penh
Metropolitan Area conducted by JICA in 2001 to relieve traffic bottleneck and increase the
traffic capacity.
G - 87
4. Recommendation on Improvement of Chbar Ampov Intersection
It may conclude that the construction of 2nd Monivong Bridge is badly required to solve the
problems related to road traffic as shown in Fig. G-8-4 even though it is out of the scope of
work for the Study. However, the scheme of 2nd Monivong Bridge surely leads to the
drastic change of Kbal Ntal Intersection where National Roads No.2 & 3 connect to
National Road No. 1.
It is recommended that the in-depth investigations and more comprehensive study covering
Chbar Ampov Market, Kbal Ntal Intersection and its surroundings in Mean Chey District of
Phnom Penh Municipality should be conducted for the improvement plan at Chbar Ampov
Intersection.
G - 90