Professional Documents
Culture Documents
Capital Budgeting and Risk Analysis: Chapter Orientation
Capital Budgeting and Risk Analysis: Chapter Orientation
Capital Budgeting and Risk Analysis: Chapter Orientation
Capital Budgeting
and Risk Analysis
CHAPTER ORIENTATION
The focus of this chapter will be on how to adjust for the riskiness of a given project or
combination of projects.
CHAPTER OUTLINE
275
B. Because of bankruptcy costs and the practical difficulties involved in
measuring a project’s level of systematic risk, we will give consideration to
the project’s contribution-to-firm risk and the project’s systematic risk.
III. Methods for incorporating risk into capital budgeting
A. The certainty equivalent approach involves a direct attempt to allow the
decision maker to incorporate his or her utility function into the analysis.
1. In effect, a riskless set of cash flows is substituted for the original set
of cash flows between which the financial manager is indifferent.
2. To simplify calculations certainty equivalent coefficients ( t's) are
defined as the ratio of the certain outcome to the risky outcome
between which the financial manager is indifferent.
3. Mathematically, certainty equivalent coefficients can be defined as
follows:
certain cash flow t
t =
risky cash flow t
4. The appropriate certainty equivalent coefficient is multiplied by the
original cash flow (which is the risky cash flow) with this product
being equal to the equivalent certain cash flow.
5. Once risk is taken out of the cash flows, those cash flows are
discounted back to present at the risk-free rate of interest and the
project's net present value or profitability index is determined.
6. If the internal rate of return is calculated, it is then compared with the
risk-free rate of interest rather than the firm's required rate of return.
7. Mathematically, the certainty equivalent can be summarized as
follows:
n
t ACFt
NPV = (1 i F ) t
- IO
t 1
276
B. The use of the risk-adjusted discount rate is based on the concept that
investors demand higher returns for more risky projects.
1. If the risk associated with the investment is greater than the risk
involved in a typical endeavor, then the discount rate is adjusted
upward to compensate for this risk.
2. The expected cash flows are then discounted back to present at the
risk-adjusted discount rate. Then the normal capital budgeting criteria
are applied, except in the case of the internal rate of return, in which
case the hurdle rate to which the project's internal rate of return is
compared now becomes the risk-adjusted discount rate.
3. Expressed mathematically the net present value using the risk-
adjusted discount rate becomes
n
ACFt
NPV = (1 i*) t
- IO
t 1
277
division's return on assets on the market index. The regression
coefficient from this equation would be the project's accounting beta
and serves as an approximation for the project's true beta.
2. The pure play method for estimating a project's beta: The pure play
method attempts to find a publicly traded firm in the same industry as
the capital-budgeting project. Once the proxy or pure-play firm is
identified, its systematic risk is determined and then used as a proxy
for the project's systematic risk.
V. Additional approaches for dealing with risk in capital budgeting
A. A simulation imitates the performance of the project being evaluated by
randomly selecting observations from each of the distributions that affect the
outcome of the project, combining those observations to determine the final
output of the final project, and continuing with this process until a
representative record of the project's probable outcome is assembled.
1. The firm's management then examines the resultant probability
distribution, and if management considers enough of the distribution
lies above the normal cutoff criterion, it will accept the project.
2. The use of a simulation approach to analyze investment proposals
offers two major advantages:
a. The financial managers are able to examine and base their
decisions on the whole range of possible outcomes rather than
just point estimates.
b. They can undertake subsequent sensitivity analysis of the
project.
B. A probability tree is a graphical exposition of the sequence of possible
outcomes; it presents the decision maker with a schematic representation of
the problem in which all possible outcomes are graphically displayed.
VI. Other sources and measures of risk
A. Many times, especially with the introduction of a new product, the cash flows
experienced in early years affect the size of the cash flows experienced in
later years. This is called time dependence of cash flows, and it has the effect
of increasing the riskiness of the project over time.
ANSWERS TO
END-OF-CHAPTER QUESTIONS
11-1. The payback period method is frequently used as a rough risk screening device to
eliminate projects whose returns do not materialize until later years. In this way, the
earliest returns are emphasized, which in all likelihood have less uncertainty
surrounding them.
278
11-2. The use of the risk-adjusted discount rate assumes that risk increases over time.
When using the risk-adjusted discount rate method, we are adjusting downward the
value of future cash flows that occur later in the future more severely than earlier
ones. This assumption can be justified because flows that are expected further out in
the future are more difficult to forecast and less certain than are flows that are
expected in the near future.
11-3. The primary difference between the certainty equivalent approach and the risk-
adjusted discount rate approach is where the adjustment for risk is incorporated into
the calculations. The certainty equivalent approach penalizes or adjust downwards
the value of the expected annual after-tax cash flows, while the risk-adjusted
discount rate leaves the cash flows at their expected value and adjusts the required
rate of return, i, upwards to compensate for added risk. In either case the net present
value of the project is being adjusted downwards to compensate for additional risk.
An additional difference between these methods is that the risk-adjusted discount
rate assumes that risk increases over time and that cash flows occurring later in the
future should be more severely penalized. The certainty equivalent method, on the
other hand, allows each cash flow to be treated individually.
11-4. A probability tree is a graphical exposition of the sequence of possible outcomes,
presenting the decision maker with a schematic representation of the problem in
which all possible outcomes are graphically displayed. Moreover, the computations
and results of the computations are shown directly on the tree, so that the
information can be easily understood. Thus the probability tree allows the manager
to quickly visualize the possible future events, their probabilities, and outcomes. In
addition, the calculation of the expected net present value and enumeration of the
distribution should aid the financial manager in his decision-making process.
11-5. The idea behind simulation is to imitate the performance of the project being
evaluated. This is done by randomly selecting observations from each of the
distributions that affect the outcome of the project, combining each of those
observations and determining the final outcome of the project, and continuing with
this process until a representative record of the project's probable outcome is
assembled. In effect, the output from a simulation is a probability distribution of net
present values or internal rates of return for the project. The decision maker then
bases his decision on the full range of possible outcomes.
11-6. The time dependence of cash flows refers to the fact that, many times, cash flows in
later periods are dependent upon the cash flows experienced in earlier periods. For
example, if a new product is introduced and the initial public reaction is poor,
resulting in low initial cash flows, then cash flows in future periods are likely to be
low also. Examples include the introduction of any new products, for example, the
Edsel on the negative side, and hopefully this book on the positive side.
279
SOLUTIONS TO
END-OF-CHAPTER PROBLEMS
= $5,000
= $6,000
N ACFt
(b) NPV = - I0
t 1 (1 i*) t
= $18,025 - $10,000
= $8,025
= $20,112 - $10,000
= $10,112
(c) One might also consider the potential diversification effect associated with
these projects. If the project's cash flow patterns are cyclically divergent
from those of the company, the overall risk of the company may be
significantly reduced.
280
N
11-2A. (a) X = Xi P(Xi)
i 1
N ACFt
(b) NPV = - IO
t 1 (1 i*) t
NPVA = $42,500 (3.605) - $100,000
= $153,212.50 - $100,000
= $53,212.50
NPVB = $45,000 (3.517) - $100,000
= $158,265 - $100,000
= $58,265
(c) One might also consider the potential diversification effect associated with
these projects. If the project's cash flow patterns are cyclically divergent
from those of the company, the overall risk of the company may be
significantly reduced.
11-3A.
Project A:
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) • (t) 5% Value
0 -$1,000,000 1.00 -$1,000,000 1.000 -$1,000,000
1 500,000 .95 475,000 .952 452,200
2 700,000 .90 630,000 .907 571,410
3 600,000 .80 480,000 .864 414,720
4 500,000 .70 350,000 .823 288,050
NPVA = $ 726,380
281
Project B:
(A) (B) (A x B)
Present Value
11-4A.
(A) (B) (A x B)
Present Value
Thus, this project should not be accepted because it has a negative NPV.
11-5A.
N ACFt
NPVA = - I0
t 1 (1 i*) t
= $30,000 (.893) + $40,000(.797) + $50,000(.712)
+ $90,000(.636) + $130,000(.567) - $250,000
= $26,790 + $31,880 + $35,600 + $57,240 + $73,710 - $250,000
= - $24,780
N ACF
NPVB = - I0
t 1 (1 i*) t
= $135,000(3.127) - $400,000
= $422,145 - $400,000
282
= $22,145
283
11-6A.
Project A:
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) • (t) 6% Value
0 -$ 50,000 1.00 -$ 50,000 1.000 -$ 50,000.00
1 15,000 .95 14,250 .943 13,437.75
2 15,000 .85 12,750 .890 11,347.50
3 15,000 .80 12,000 .840 10,080.00
4 45,000 .70 31,500 .792 24,948.00
NPVA = $ 9,813.25
Project B:
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) • (t) 6% Value
0 -$ 50,000 1.00 -$ 50,000 1.000 -$ 50,000.00
1 20,000 .90 18,000 .943 16,974.00
2 25,000 .85 21,250 .890 18,912.50
3 25,000 .80 20,000 .840 16,800.00
4 30,000 .75 22,500 .792 17,820.00
NPVB = $ 20,506.50
284
Internal Rate
11-7A. (a –c)
of Return for Joint
0 Year 1 Year 2 Years each Branch Probability (A)(B)
p=
- 0.3
p = 0.2
$850,000
$1,000,000 33.33% 0.06 2.00%]
p = 0.1
11-8A. (a –c)
of Return for Joint
0 Year 1 Year 2 Years each Branch Probability (A)(B)
p = 0.5
$180,000 124.68% 0.09 11.22%
$200,000
p=
0.3
p = 0.5 $205,000 121.09% 0.15 18.16%
p = 0.5
p = 0.5
$175,000 $155,000 114.96% 0.15 17.24%
285
p= $100,000
p = 0.2
p = 0.5 $180,000 111.30% 0.06 6.68%
$-100,000
p = 0.5
$150,000 $130,000 104.46% 0.06 6.27%]
p = 0.4 p= p = 1.0
0.6 $10,000 -42.44% 0.24 -10.19%
$10,000
p = 1.0
$10,000 $0 -90.007% 0.16 -14.40%
p = 0.4
$0 1.00
Expected internal rate of return = 46.70%
SOLUTIONS TO INTEGRATIVE PROBLEM
1. First there is the project standing alone risk, which is a project's risk ignoring the
fact that much of this risk will be diversified away as the project is combined with
the firm's other projects and assets. Second, we have the project's contribution-to-
firm risk, which is the amount of risk that the project contributes to the firm as a
whole; this measure considers the fact that some of the project's risk will be
diversified away as the project is combined with the firm's other projects and assets,
but ignores the effects of diversification of the firm's shareholders. Finally, there is
systematic risk, which is the risk of the project from the viewpoint of a well
diversified shareholder; this measure considers the fact that some of a project's risk
will be diversified away as the project is combined with the firm's other projects,
and, in addition, some of the remaining risk will be diversified away by the
shareholders as they combine this stock with other stocks in their portfolio.
2. According to the CAPM, systematic risk is the only relevant risk for capital
budgeting purposes; however, reality complicates this somewhat. In many instances
a firm will have undiversified shareholders; for them the relevant measure of risk is
the project's contribution to firm risk. The possibility of bankruptcy also affects our
view of what measure of risk is relevant. Because the project's contribution to firm
risk can affect the possibility of bankruptcy, this may be an appropriate measure of
risk since there are costs associated with bankruptcy.
3. The primary difference between the certainty equivalent approach and the risk-
adjusted discount rate approach is where the adjustment for risk is incorporated into
the calculations. The certainty equivalent approach penalizes or adjusted downwards
the value of the expected annual after-tax cash flows, while the risk-adjusted
discount rate leaves the cash flows at their expected value and adjusts the required
rate of return, i, upwards to compensate for added risk. In either case the net present
value of the project is being adjusted downwards to compensate for additional risk.
An additional difference between these methods is that the risk-adjusted discount
rate assumes that risk increases over time and that cash flows occurring later in the
future should be more severely penalized. The certainty equivalent method, on the
other hand, allows each cash flow to be treated individually.
4. A probability tree is a graphical exposition of the sequence of possible outcomes,
presenting the decision maker with a schematic representation of the problem in
which all possible outcomes are graphically displayed. Moreover, the computations
and results of the computations are shown directly on the tree, so that the
information can be easily understood. Thus the probability tree allows the manager
to quickly visualize the possible future events, their probabilities, and outcomes. In
addition, the calculation of the expected net present value and enumeration of the
distribution should aid the financial manager in his decision-making process.
5. The idea behind simulation is to imitate the performance of the project being
evaluated. This is done by randomly selecting observations from each of the
distributions that affect the outcome of the project, combining each of those
286
observations and determining the final outcome of the project, and continuing with
this process until a representative record of the project's probable outcome is
assembled. In effect, the output from a simulation is a probability distribution of net
present values or internal rates of return for the project. The decision maker then
bases his decision on the full range of possible outcomes.
6. Sensitivity analysis involves determining how the distribution of possible net present
values or internal rates of return for a particular project is affected by a change in
one particular input variable. This is done by changing the value of one input
variable while holding all other input variables constant.
7. The time dependence of cash flows refers to the fact that, many times, cash flows in
later periods are dependent upon the cash flows experienced in earlier periods. For
example, if a new product is introduced and the initial public reaction is poor,
resulting in low initial cash flows, then cash flows in future periods are likely to be
low also. Examples include the introduction of any new products, for example, the
Edsel on the negative side, and hopefully this book on the positive side.
8. Project A:
(A) (B) (A x B)
Present Value
Project B:
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) • (t) 7% Value
0 -$200,000 1.00 -$200,000 1.000 -$200,000
1 50,000 .95 47,500 .935 44,413
2 60,000 .85 51,000 .873 44,523
3 60,000 .80 48,000 .816 39,168
4 50,000 .75 37,500 .763 28,613
NPVB = - $ 43,283
Thus, neither project should be selected, as they both have negative NPVs..
287
Internal Rate
of Return for Joint
Part 9
0 Year 1 Year 2 Years each Branch Probability (A)(B)
p=
0.4 p = 0.2 $250,000 0.00% 0.08 0.00%
p = 0.5
p = 0.4 $450,000 20.55% 0.20 4.11%
288
-$600,000
p = 0.3
$350,000
$650,000 37.26% 0.12 4.47%
= $6,000
= $7,000
N ACFt
(b) NPV = - I0
t 1 (1 i*) t
= $21,102 - $10,000
= $11,102
= $21,889 - $10,000
= $11,889
(c) One might also consider the potential diversification effect associated with
these projects. If the project's cash flow patterns are cyclically divergent
from those of the company, the overall risk of the company may be
significantly reduced.
289
N
11-2B. (a) X = Xi P(Xi)
i 1
= $47,500
= $55,000
N ACFt
(b) NPV = - I0
t 1 (1 i*) t
= $175,560 - $125,000
= $50,560
= $193,435 - $125,000
= $68,435
(c) One might also consider the potential diversification effect associated with
these projects. If the project's cash flow patterns are cyclically divergent
from those of the company, the overall risk of the company may be
significantly reduced.
290
11-3B.
Project A:
(A) (B) (A x B)
Present Value
Project B:
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) x (t) 5% Value
0 -$1,000,000 1.00 -$1,000,000 1.000 -$1,000,000
1 600,000 .95 570,000 .952 542,640
2 650,000 .75 487,500 .907 442,162.50
3 700,000 .60 420,000 .864 362,880
4 750,000 .60 450,000 .823 370,350
NPVB = $ 718,032.50
11-4B.
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) .( t) 8% Value
0 -$100,000 1.00 -$100,000 1.000 -$100,000
1 30,000 0.95 28,500 .926 26,391
2 25,000 0.90 22,500 .857 19,283
3 30,000 0.83 24,900 .794 19,771
4 20,000 0.75 15,000 .735 11,025
5 25,000 0.65 16,250 .681 11,066
NPV = -$ 12,465
Thus, this project should not be accepted because it has a negative NPV.
291
11-5B.
N ACFt
NPVA = - IO
t 1 (1 i*) t
= $30,000 (.885) + $40,000(.783) + $50,000(.693)
+ $80,000(.613) + $120,000(.543) - $300,000
= $26,550 + $31,320 + $34,650 + $49,040
+ $65,160 - $300,000
= - $93,280
N ACF
NPVB = - IO
t 1 (1 i*) t
= $130,000(3.127) - $450,000
= $406,510 - $450,000
= -$43,490
11-6B.
Project A:
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) x (t) 7% Value
0 -$ 75,000 1.00 -$ 75,000 1.000 -$ 75,000.00
1 20,000 .95 19,000 .935 17,765.00
2 20,000 .85 17,000 .873 14,841.00
3 15,000 .80 12,000 .816 9,792.00
4 50,000 .70 35,000 .763 26,705.00
NPVA = ($ 5,897.00)
Project B:
(A) (B) (A x B)
Present Value
Expected (Expected Factor at Present
Year Cash Flow t Cash Flow ) x (t) 7% Value
0 -$ 75,000 1.00 -$ 75,000 1.000 -$ 75,000.00
1 25,000 .95 23,750 .935 22,206.25
2 30,000 .85 25,500 .873 22,261.50
3 30,000 .80 24,000 .816 19,584.00
4 25,000 .75 18,750 .763 14,306.25
NPVB = $ 3,358.00
292
Internal Rate
11-7B. (a –c)
of Return for Joint
0 Year 1 Year 2 Years each Branch Probability (A)(B)
p = 0.6
$400,000 0.00% 0.06 0.0000%
p = 0.2
p=
-$900,000 0.3
p = 0.2
$900,000 24.73% 0.06 1.4838%]
p = 0.1
$1,300,000 40.44% 0.03 1.2132%
p = 0.1
p=
0.6 $900,000 58.94% 0.06 3.5364%
$1,500,000
p = 0.1 $1,100,000 66.27% 0.01 0.6627%
1.00
Expected internal rate of return = 18.1230%
(d) The range of possible IRR’s from -15.12% to 66.27
Internal Rate
11-8B. (a –c)
of Return for Joint
0 Year 1 Year 2 Years each Branch Probability (A)(B)
p = 0.5
$225,000 $205,000 110.76% .105 11.6298%
p=
0.3
p = 0.5 $210,000 101.15% .175 17.7013%
p = 0.5
p = 0.5
$160,000 95.18% .175 16.6565%
p = 0.7 $180,000
p = 0.2
294
$100,000 p = 0.5
$170,000 86.57% .070 6.0599%
$-120,000
p = 0.5
$0 1.00
Expected internal rate of return = 50.3627%
(d) The range of possible IRR’s from –91.67% to 115.83%
MADE IN THE U. S. A., DUMPED IN BRAZIL, AFRICA, . . .
(Ethics in Capital Budgeting)
OBJECTIVE: To force the student to recognize the role ethical behavior plays in all
areas of Finance.
Case Solution:
With ethics cases there are no right or wrong answers - just opinions. Try to bring out
as many opinions as possible without being judgmental. In this case the question centers
around what to do when a product is no longer sellable.
295