Professional Documents
Culture Documents
HPE - NonStop I NS2300 and NS2400 Site Planning Guide
HPE - NonStop I NS2300 and NS2400 Site Planning Guide
Acknowledgments
Intel®, Itanium®, Pentium®, Intel Inside®, and the Intel Inside logo are trademarks of Intel Corporation in
the United States and other countries.
Contents 3
Space for receiving and unpacking NonStop i Systems............................................................. 26
Operational space for NonStop i Systems.................................................................................. 27
Cables.................................................................................................... 53
Cable types and connectors....................................................................................................... 53
4 Contents
NonStop i System with a Rack-Mounted UPS................................................................. 59
SAS Disk Enclosures with a rack-mounted UPS............................................................. 60
Non-Supported UPS Configurations................................................................................ 61
NonStop i System With a Data Center UPS, Single Power Rail........................... 62
NonStop i System With Data Center UPS, Both Power Rails............................... 64
NonStop i System With Rack-Mounted UPS and Data Center UPS in Parallel.... 66
NonStop i System With Two Rack-Mounted UPS in Parallel................................ 67
NonStop i System with Cascading Rack-Mounted UPS and Data Center UPS....68
Contents 5
About This Document
This guide provides specifications for planning system installation and is intended for authorized service
providers who have completed HPE training on NonStop i system support.
Publishing history
Part Number Product Version Publication Date
Maximum SAS disk enclosures per A Storage CLIM pair supports a maximum of 4 SAS disk
Storage CLIM pair enclosures (applies to all Storage CLIMs)
Maximum Hard Disk Drives (HDDs) 100 HDDs per Storage CLIM pair
Maximum Solid State Drives (SSDs) SSDs are supported on J06.13 and later. As of J06.17 and
later, a maximum of 20 SSDs is supported per Storage
CLIM pair.
• Rack included with the system and each enclosure installed in the rack
• Rack U location at the bottom edge of each enclosure
• Each cable with source, destination, connector type, cable part number, and connection labels
NOTE: NS2300 blade elements and NS2400 blade elements cannot coexist in the same system.
For details about the rx2800 i4 server, see the HPE Integrity rx2800 i4 Server User Service Guide.
1 IMPORTANT: Requires installation of supported SPRs. See the CLuster I/O Module (CLIM) Software Compatibility
Guide.
Slot 1 ServerNet PCIe interface card provides the ServerNet fabric connections
iLO, Eth0 iLO port and Eth0 reserved for maintenance support
Item Characteristics of NonStop i 3C/2F IP and Telco CLIMs (Gen8 and Gen9)
Slot 1 ServerNet PCIe interface card provides the ServerNet fabric connections
iLO, Eth0 iLO port and Eth0 reserved for maintenance support
HBA in Slot Characteristics of NonStop i Storage CLIMs (Gen10, Gen9, and Gen8)
NOTE:
• Gen10 and Gen9 Storage CLIMs have two 12 Gbps SAS ports or two FC 16 Gbps
ports (ordered).
• Gen 8 Storage CLIM has two 6Gbps SAS ports or two FC 8 Gbps ports (ordered).
3 Optional order of SAS HBA with two SAS ports or FC HBA with FC ports.
Storage CLIM 13
SAS Disk Enclosures
NOTE: Solid state drives are supported as of J06.13.
SAS disk enclosures provide the storage capacity for the Storage CLIM and support SAS HDDs and SAS
SSDs.
The D3700/D3710 enclosure holds 25 2.5” SAS Smart Carrier HDDs and SSDs with redundant power
and cooling.
The following illustration shows the D3700 SAS disk enclosure.
NOTE: The D3710 SAS disk enclosure uses the same firmware file, IO modules, drive locations, and
hardware FRUs as the D3700 but has a different bezel.
The D2700 SAS disk enclosure holds 25 2.5” SAS universal carrier HDDs and SSDs with redundant
power and cooling.
NOTE: If you have ordered $OSS, you need a 4 pair disk configuration.
• The maximum number of logical unit numbers (LUNs) for each Storage CLIM, including SAS disks,
ESS and tapes is 512. Each primary, backup, mirror and mirror backup path is counted in this
maximum.
• G6 and later Storage CLIMs do not support daisy-chaining.
NOTE: For information on using OSM to manage a site UPS, AC power monitoring, or for power fail
support, see the OSM Configuration Guide.
HPE supports these rack-mounted UPS modules which support up to two HPE ERMs per UPS; no mixing
of UPS and ERM types.
More information
AC input power for NS2300 and NS2400 Systems
UPS’s and ERMs are in the lowest portion of the system to avoid tipping and stability issues.
No more than two HPE ERMs are used per UPS; no mixing of UPS or ERM types.
The manufacturing default setting ride-through time for the optional HPE-supported UPS has been
changed to an appropriate value for the system. Service providers can refer to the NonStop
NS2100 and NS2300 Hardware Installation Manual for these instructions
Your UPS configuration is supported. See UPS and Data Center power configurations.
Maintenance Switch 17
Enterprise Storage System — ESS (Optional)
An Enterprise Storage System (ESS) is a collection of magnetic disks, their controllers, and a disk cache
in one or more standalone racks. ESS connects to the NonStop i system either directly via Fibre Channel
ports on the Storage CLIM (direct connect) or through a separate storage area network (SAN) using a
Fibre Channel SAN switch (switched connect). For more information about these connection types, see
your Hewlett Packard Enterprise service provider.
NOTE: The Fibre Channel SAN switch power cords might not be compatible with the modular rack PDU.
Contact your Hewlett Packard Enterprise service provider to order replacement power cords for the SAN
switch that are compatible with the modular rack PDU.
Cables and switches vary, depending on whether the connection is direct, switched, or a combination:
For fault tolerance, the primary and backup paths to an ESS logical device (LDEV) must go through
different Fibre Channel switches.
Some storage area procedures, such as reconfiguration, can cause the affected switches to pause. If the
pause is long enough, I/O failure occurs on all paths connected to that switch. If both the primary and the
backup paths are connected to the same switch, the LDEV goes down.
For more information, see the documentation that accompanies the ESS.
The following topics provide the terminology and group-module-slot numbering for NS2300 and NS2400
system components to assist you in identifying and locating components.
Term Definition
Slot (or Bay or Position) A subset of a module that is the logical or physical
location of a component within that module.
• Group-Module-Slot-Port (GMSP)
Table Continued
On NS2300 and NS2400 systems, locations of the modular components are identified by:
• Physical location:
◦ Rack number
◦ Rack offset
• Logical location:
◦ Group, module, and slot (GMS) notation as defined by their position on the ServerNet rather than
the physical location
OSM uses GMS notation in many places, including the Tree view and Attributes window, and it uses rack
and offset information to create displays of the server and its components. For example, in the Tree view,
OSM displays the location of a power supply in a VIO enclosure in group 100, module 2, slot 15 in this
form:
Power Supply (100.2.15)
NOTE: For a blade element group, OSM uses the term Blade Complex in OSM displays.
Blade Processor
Element
0 400 100 1
1 400 101 1
2 400 102 1
3 400 103 1
This illustration shows the physical GMS numbering for the rear view of a blade element:
The X fabric connects to ports BX and AX. The Y fabric connects to ports BY and AY.
X Y Displayed Displayed
Fabric Fabric by OSM on Chassis
2 2 Not supported -
4 4 IP CLIM 1-2
5 5 Not supported -
7 7c Not supported -
• Top: Power and I/O cables are routed from above the rack.
• Bottom: Power and I/O cables are routed from below the rack.
Power quality
This equipment is designed to operate reliably over a wide range of voltages and frequencies, described
in Enclosure AC Input. Damage can occur if ranges are exceeded and severe electrical disturbances
can exceed the design specifications of the equipment. Common sources of such disturbances are:
To protect the system from electrical disturbances, use a dedicated power distribution system, power
conditioning equipment, and lightning arresters on power cables. For assistance, consult with your HP
site preparation specialist or power engineer.
Grounding Systems
The site building must provide a power distribution safety ground/protective earth for each AC service
entrance to all NonStop server equipment. This safety grounding system must comply with local codes
and any other applicable regulations for the installation locale.
For proper grounding/protective earth connection, consult with your Hewlett Packard Enterprise site
preparation specialist or power engineer.
Power consumption
In a NonStop i system, the inrush currents per connection can vary because of the unique combination of
enclosures housed in the rack. Thus, the total power consumption for the hardware installed in the rack
should be calculated as described in Enclosure power loads for NS2300 and NS2400 Systems on
page 40.
NOTE: Failure of site cooling with the system continuing to run can cause rapid heat buildup and
excessive temperatures within the hardware. Excessive internal temperatures can result in full or partial
system shutdown. Ensure that the site’s cooling system remains fully operational when the system is
running.
Weight
Total weight must be calculated based on what is in the specific rack, as described in Rack and
Enclosure Weights With Worksheet.
Flooring
NonStop i systems can be installed either on the site’s floor with the cables entering from above the
equipment or on raised flooring with power and I/O cables entering from underneath. Because cooling
airflow through each enclosure in the racks is front-to-back, raised flooring is not required for system
cooling.
The site floor structure and any raised flooring (if used) must be able to support the weight of the installed
system, individual racks, and enclosures as they are moved into position. To determine the total weight of
the installation, refer to Rack and enclosure weights with worksheet on page 44.
For your site’s floor system, consult with your HPE site preparation specialist or an appropriate floor
system engineer. If raised flooring is to be used, the rack is optimized for placement on 24‑inch floor
panels.
Zinc Particulates
Over time, fine whiskers of pure metal can form on electroplated zinc, cadmium, or tin surfaces such as
aged raised flooring panels and supports. If these whiskers are disturbed, they can break off and become
airborne, possibly causing computer failures or operational interruptions. This metallic particulate
contamination is a relatively rare but possible threat. Kits are available to test for metallic particulate
contamination, or you can request that your site preparation specialist or HVAC engineer test the site for
contamination before installing any electronic equipment.
26 Weight
√ Ensure:
There is adequate space to receive and unpack the system from shipping cartons and pallets and
to remove equipment using supplied ramps. For physical dimensions of the system equipment, see
Dimensions and Weights.
Enough personnel are present to remove and transport each rack to the installation site.
Tiled or carpeted pathways have temporary hard floor covering to facilitate moving the racks which
have small casters.
Door and hallway width and height, the floor and elevator loading, accommodate the system
equipment, personnel, and lifting or moving devices. If necessary, enlarge or remove any
obstructing doorway or wall.
NonStop i system site layout uses the equipment dimensions, door swing, and service clearances
listed in Dimensions and Weights and takes advantage of existing lighting and electrical outlets.
Airflow direction and current or future air conditioning ducts are not obstructed. Eliminate any
obstructions to equipment intake or exhaust air flow. See Cooling and Humidity Control.
Site layout plan includes provisions for things such as channels or fixtures used for cable routing,
cables, patch panels, and storage areas.
NOTE: For information about the G2 Advanced Series rack or using the HPE Rack Ground Bonding Kit
(P9L11A), refer your service provider to the Rack Options Installation Guide for the HPE Advanced G2
Series.
• The same PDU type, power phase, and power region must be used.
• For either top or bottom power feed cables, the PDU cores must be mounted at the bottom of the rack.
• PDU cores are mounted in the same 1U space.
◦ UPS does not change the number of PDU cores in the rack.
◦ PDU and UPS must have the same power input specification.
Example Intelligent PDU (iPDU) core connections for NS2300 and NS2400 Systems
The following illustrations show the connections between the PDU cores and the extension bars using a
42U rack as an example.
Example Intelligent PDU (iPDU) core connections for NS2300 and NS2400 Systems 29
Figure 3: Intelligent PDU connections (without UPS)
Example G2 Basic Modular PDU core connections for NS2300 and NS2400 Systems
• Single-phase G2 Basic modular PDU cores use six outlets: L1, L1, L1, L2, L2, L2.
• Three-phase G2 Basic modular PDU cores use six outlets: L1, L2, L3, L1, L2, L3.
• Racks with modular PDUs have three extension bars on each side.
The following illustrations show the connections between the PDU cores and the extension bars using a
42U rack as an example. The locations of the extension bars might not exactly match the installation.
32 Example G2 Basic Modular PDU core connections for NS2300 and NS2400 Systems
Figure 6: G2 Basic modular PDU connections (without UPS)
AC power feeds
NS2300 and NS2400 systems can be ordered with the AC power cords for the PDU installed either top or
bottom.
• Top: Power and I/O cables are routed from above the rack
• Bottom: Power and I/O cables are routed from below the rack
36 AC power feeds
Each PDU is wired to distribute the load segments to its receptacles.
CAUTION: If you are installing NonStop i system enclosures in a rack, balance the current load
among the available load segments. Using only one of the available load segments, especially for
larger systems, can cause unbalanced loading and might violate applicable electrical codes.
Connecting the two power plugs from an enclosure to the same load segment causes failure of the
hardware if that load segment fails.
CAUTION: Be sure the hardware configuration and resultant power loads of each enclosure within
the system do not exceed the capacity of the branch circuit according to applicable electrical codes
and regulations.
Select circuit breaker ratings according to local codes and any applicable regulations for the circuit
capacity. Note that circuit breaker ratings vary if your system includes an optional rack-mounted UPS.
Output Load 12 kW 24 A 24 A
Enclosure AC input
NOTE: For instructions on grounding the G2 Advanced Series rack using the HPE Rack Ground Bonding
Kit (P9L11A), refer your service provider to the Rack Options Installation Guide for the HPE Advanced G2
Series.
Specification Value
Number of phases 1
* Voltage range for the VIO enclosure is 100-240 V AC, and for the maintenance switch is 200-240 V
AC.
Each PDU is wired to distribute the load segments to its receptacles. For more information, see Power
distribution for NS2300 and NS2400 systems. Factory-installed enclosures are connected to the PDUs
for a balanced load among the load segments.
Enclosure AC input 39
CAUTION: If you are installing NS2300 or NS2400 system enclosures in a rack, balance the current
load among the available load segments. Using only one of the available load segments, especially
for larger systems, can cause unbalanced loading and might violate applicable electrical codes.
Connecting the two power plugs from an enclosure to the same load segment causes failure of the
hardware if that load segment fails.
Table Continued
Rack-mounted 1 36 36
keyboard and
monitor
Maintenance switch 1 9 15
(Ethernet) 2
1 One of the plugs for an enclosure must be connected to a left-side extension bar and the other must be connected to
a right-side extension bar. PDUs must be supplied from separate branch circuits.
2 Maintenance switch has only one plug. If a UPS is installed in the rack, the maintenance switch plug must be
connected to the extension bars on the right side of the rack.
Blade element 2
VIO enclosure 4
Storage CLIM 2
IP CLIM 2
Telco CLIM 2
42 Unit Sizes
42U G2 Advanced Series Rack physical specifications
Item Height Width Depth Weight
Enclosure dimensions
Enclosure Height Width Depth
Type
in cm in cm in cm
Table Continued
in cm in cm in cm
16GB CPU 52 23
32GB CPU 52 23
48GB CPU 52 23
Gen8 CLIM 55 24
Gen9 CLIM 45 20
Gen10 CLIM 33 15
SAS disk 38 17
enclosure, empty
Table Continued
Maintenance 6 2.7
switch (Ethernet)
Rack-mount 31 14
system console,
keyboard, and
display
Total -- --
1 iPDU=Intelligent PDU
For examples of calculating the weight for various enclosure combinations, see Calculating
specifications for enclosure combinations on page 49.
Rack Stability
Rack stabilizers are required when you have less than four racks bayed together.
NOTE: Rack stability is of special concern when equipment is routinely installed, removed, or accessed
within the rack. Stability is addressed through the use of leveling feet, baying kits, fixed stabilizers, and/or
ballast. Use baying kits to bay racks to racks of the same height. In all cases, a rack cannot be bayed with
another rack of a different height.
46 Rack Stability
For information about best practices for racks or grounding the racks using a rack ground bonding kit,
your service provider can refer to the Rack Options Installation Guide for the HPE Advanced G2 Series.
Environmental Specifications
Heat dissipation specifications and worksheet
Enclosure Type Number Installed Unit Heat (BTU/ Unit Heat (BTU/ Total (BTU/hour)
hour) Typical hour) Maximum
Table Continued
Environmental Specifications 47
Enclosure Type Number Installed Unit Heat (BTU/ Unit Heat (BTU/ Total (BTU/hour)
hour) Typical hour) Maximum
Maintenance switch 31 51
(Ethernet)1
1 Maintenance switch has only one plug. If a UPS is installed in the rack, the maintenance switch plug must be
connected to the extension bars on the right side of the rack.
Temperature (rack- 50° to 95° F (10° to 35° 68° to 77° F (20° to 25° 18° F (10° C) Repetitive
mounted system C) C)
36° F (20° C)
console and
Operating Range Nonrepetitive
maintenance switch)
1 Operating and recommended ranges refer to the ambient air temperature and humidity measured 19.7 in. (50 cm)
from the front of the air intake cooling vents.
2 For each 1000 feet (305 m) increase in altitude above 10,000 feet (up to a maximum of 15,000 feet), subtract 1.5× F
(0.83× C) from the upper limit of the operating and recommended temperature ranges.
For a total thermal load for a system with multiple racks, add the heat outputs for all the racks in the
system.
Information to collect
Accessing updates
• Some software products provide a mechanism for accessing software updates through the product
interface. Review your product documentation to identify the recommended software update method.
• To download product updates, go to either of the following:
◦ Hewlett Packard Enterprise Support Center Get connected with updates page:www.hpe.com/
support/e-updates
◦ Software Depot website:www.hpe.com/support/softwaredepot
• To view and update your entitlements, and to link your contracts and warranties with your profile, go to
the Hewlett Packard Enterprise Support Center More Information on Access to Support Materials
page:www.hpe.com/support/AccessToSupportMaterials
IMPORTANT: Access to some updates might require product entitlement when accessed
through the Hewlett Packard Enterprise Support Center. You must have an HP Passport set up
with relevant entitlements.
Remote support
Remote support is available with supported devices as part of your warranty or contractual support
agreement. It provides intelligent event diagnosis, and automatic, secure submission of hardware event
notifications to Hewlett Packard Enterprise, which will initiate a fast and accurate resolution based on your
product’s service level. Hewlett Packard Enterprise strongly recommends that you register your device for
remote support.
For more information and device support details, go to the following website:
www.hpe.com/info/insightremotesupport/docs
Documentation feedback
Hewlett Packard Enterprise is committed to providing documentation that meets your needs. To help us
improve the documentation, send any errors, suggestions, or comments to Documentation Feedback
(docsfeedback@hpe.com). When submitting your feedback, include the document title, part number,
edition, and publication date located on the front cover of the document. For online help content, include
the product name, product version, help edition, and publication date located on the legal notices page.
52 Websites
Cables
Table Continued
Cables 53
Connection From... Cable Type Connectors
*Customer-supplied cable
54 Cables
Default startup characteristics and naming
conventions
NS2300 and NS2400 systems use Default naming conventions on page 56 and ship with the
following default startup characteristics:
$SYSTEM disks residing in SAS disk enclosures:
SAS Disk Enclosures
• Systems with only two Storage CLIM and two SAS disk enclosures with the disks in these locations:
Primary 100 2 3 1 1
Backup 100 2 3 1 2
Mirror 100 2 3 2 3
Mirror-Backup 100 2 3 2 4
If the automatic system load is not successful, additional paths for loading are available in the boot task.
Using one load path, the system load task attempts to use another path and keeps trying until all possible
paths have been used or the system load is successful. These 16 paths are available for loading and are
listed in the order of their use by the system load task:
1 Primary $SYSTEM-P 0 X
2 Primary $SYSTEM-P 0 Y
3 Backup $SYSTEM-P 0 X
4 Backup $SYSTEM-P 0 Y
5 Mirror $SYSTEM-M 0 X
6 Mirror $SYSTEM-M 0 Y
Table Continued
9 Primary $SYSTEM-P 1 X
10 Primary $SYSTEM-P 1 Y
11 Backup $SYSTEM-P 1 X
12 Backup $SYSTEM-P 1 Y
13 Mirror $SYSTEM-M 1 X
14 Mirror $SYSTEM-M 1 Y
The command interpreter input file (CIIN) is automatically invoked after the first processor is loaded. The
CIIN file shipped with new systems contains the TACL RELOAD * command, which loads the remaining
processors.
Modular tape drive $TAPE number $TAPE01 First modular tape drive
in the system
IP CLIM N group module slot port N100241 IP CLIM which has the
X1 attachment point to
the VIO enclosure
located in group 100,
module 2, slot 4, port 1
Telco CLIM O group module slot O100243 Telco CLIM which has
port the X1 attachment point
to the VIO enclosure
located in group 100,
module 2, slot 4, port 3
Table Continued
Storage CLIM S group module slot port S100233 Storage CLIM which has
the X1 attachment point
to the VIO enclosure
located in group 100,
module 2, slot 3, port 3
Ethernet LIF object L group module slot PIF L10027B Logical interface (LIF)
for PIF B in slot 7 in
module 2 of the Group
100 VIO Enclosure
1 For more information about CLIM processes that use the CIP subsystem and the naming conventions for these
processes, refer to the Cluster I/O Protocols (CIP) Configuration and Management Manual.
On new NonStop systems, only one of each of these processes and names is configured:
• TCP6SAM - $ZTC0
• Telserv - $ZTCN0
• Listener - $LSN0
NOTE: Naming conventions or configurations for the dedicated service LAN TCP/IP are the same as the
TCP/IP conventions used with G-series and H-series RVUs. The names are $ZTCP0 and $ZTCP1.
Hewlett Packard Enterprise does not support changing the names of these processes.
OSM Service Connection provides the location of the resource by adding an identifying suffix to the
names of all the system resources. Other interfaces, such as SCF, also provide means to locate named
resources.
• Specifiy the UPS configurations supported on the NonStop system including the recommended UPS
configuration for when the disk drive write cache is enabled.
• Identify the non-supported UPS configurations that should not be used with the NonStop system when
the disk drive write cache is enabled.
• Explain why some configurations are not supported.
• Inform you of what you must do to prevent data loss.
NOTE: All example UPS configuration illustrations show NonStop i BladeSystem hardware, but these
configurations are supported on all NonStop i platforms and can be used with single-phase and three-
phase UPS.
IMPORTANT: You must change the ride-through time for a Hewlett Packard Enterprise-supported
UPS from the manufacturing default setting to an appropriate value for your system. During
installation of a NonStop i system or HPE UPS, your service provider can refer to the "Setting the
Ride-Through Time and Configuring for Maximized Runtime" procedure in the NonStop i NS2100
and NS2300 Hardware Installation Manual for these instructions.
IMPORTANT: With this configuration, you can guarantee that the data center never loses power.
When OSM detects that one power rail is running on UPS and the other power rail has lost power, OSM
logs an event indicating the beginning of the configured ride-through time period. OSM monitors if AC
power is restored before the ride-through period ends.
• If AC Power is restored before the ride-through period ends, the ride-through countdown terminates
and OSM does not take further steps to prepare for an outage.
• If AC Power is not restored before the ride-through periods ends, OSM broadcasts a PFAIL_SHOUT
command to all processors (the processor running OSM being the last one in the queue) to shut down
the system ServerNet routers and processors. The PFAIL_SHOUT command enables disk writes for
data that is in transit through controllers and disks to complete.
When the utility power fails, the NonStop system powers off without an OSM-initiated controlled shutdown
of the I/O operations and processors. Only the products in the rack with the rack-mounted UPS remain
powered on. All completed disk write transactions’ data are written to the disk drive media or the disk
drive write cache. The rack-mounted UPS provides the extended time for the disk drives to transfer the
data from their write cache to the media. The rack-mounted UPS provides extended time for the disk
drives to transfer the data from their write cache to the media preventing loss of data.
• NonStop i System With a Data Center UPS, Single Power Rail on page 62
• NonStop i System With Data Center UPS, Both Power Rails on page 64
• NonStop i System With Rack-Mounted UPS and Data Center UPS in Parallel on page 66
• NonStop i System With Two Rack-Mounted UPS in Parallel on page 67
• NonStop i System with Cascading Rack-Mounted UPS and Data Center UPS on page 68
When the utility power fails, OSM does not detect the data center UPS is running on battery and the UPS
has entered its battery runtime. OSM does not initiate the controlled shutdown of the I/O operations and
processors.
If the utility power is not restored before the data center UPS shuts down, any data in the NonStop
system disk drive write cache that has not been transferred to the disk drive media is lost.
To prevent data loss during a utility power failure, you must manually disable the Write Cache Enable
(WCE) option on all the disk drive volumes. For information on how to disable the WCE, see the SCF
Reference Manual for the Storage Subsystem (G06.28+, H06.05+, J06.03+).
IMPORTANT: If this configuration is used, there is no guarantee that your data center will never
lose power.
Figure 13: NonStop i System With Data Center UPS, Both Power Rails on page 65 shows an
example of a non-supported configuration in a NonStop system with the left and right PDUs connected to
the data center UPS. In this configuration, OSM does not manage or monitor the data center UPS.
When the utility power fails, OSM does not detect that the data center UPS is running on battery and the
UPS has entered its battery runtime. OSM does not initiate the controlled shutdown of the I/O operations
and processors.
If the utility power is not restored before the data center UPS shuts down, any data in the NonStop
system disk drive write cache that has not been transferred to the disk drive media is lost.
To prevent data loss during a utility power failure, you must manually disable the Write Cache Enable
(WCE) option on all the disk drive volumes. For information on how to disable the WCE, see the SCF
Reference Manual for the Storage Subsystem (G06.28+, H06.05+, J06.03+).
NonStop i System With Rack-Mounted UPS and Data Center UPS in Parallel
Figure 14: NonStop i System With Rack-Mounted UPS and Data Center UPS in Parallel on page
66 shows an example of a non-supported configuration in a NonStop i system with the left PDUs
connected to the rack-mounted UPS, and the right PDUs connected to the data center UPS. In this
configuration, OSM manages and monitors the rack-mounted UPS. However, OSM does not manage or
monitor the data center UPS.
Figure 14: NonStop i System With Rack-Mounted UPS and Data Center UPS in Parallel
When the utility power fails, OSM detects a UPS AC Input not Present event from the rack-
mounted UPS. OSM does not recognize the data center UPS. OSM does not detect that the data center
66 NonStop i System With Rack-Mounted UPS and Data Center UPS in Parallel
UPS is running on battery and the UPS battery runtime. OSM does not initiate the controlled shutdown of
the I/O operations and processors.
• The rack-mounted UPS shuts down before the data center UPS.
• If the utility power is not restored before the data center UPS shuts down, any data in the NonStop
system disk drive write cache that has not been transferred to the disk drive media is lost.
To prevent data loss during a utility power failure, you must manually disable the Write Cache Enable
(WCE) option on all the disk drive volumes. For information on how to disable the WCE, see the SCF
Reference Manual for the Storage Subsystem (G06.28+, H06.05+, J06.03+).
• When the utility power is restored, you can enable the WCE.
• During the utility power failure, the system can continue to run until the data center UPS runs out of
power or until it shuts down.
OSM has the capability to monitor both UPSs, but it does not have the logic to initiate the controlled
shutdown of the I/O operations and processors when utility power fails in this configuration.
If the utility power is not restored before both rack-mounted UPSs shut down, any data in the NonStop i
system disk drive write cache that has not been transferred to the disk drive media is lost.
If you want to extend the UPS battery runtime, Hewlett Packard Enterprise recommends adding the
Extended Runtime Modules (ERMs) to the UPS.
NonStop i System with Cascading Rack-Mounted UPS and Data Center UPS
Figure 16: NonStop System With Cascading UPS on page 69 shows an example of a non-supported
configuration in a NonStop i system with the left PDUs connected to the rack-mounted UPS, and the right
PDUs connected to a data center UPS. To create a cascading UPS configuration, the rack-mounted UPS
is connected to the data center UPS.
68 NonStop i System with Cascading Rack-Mounted UPS and Data Center UPS
Figure 16: NonStop System With Cascading UPS
A cascading UPS configuration presents potential problems. Problems attaining stability between the pair
of cascaded UPSs can cause unexpected and undesirable behavior. The control loops of each UPS can
interfere with the other.
A typical scenario where this behavior occurs is the failure of the smaller downstream UPS to recognize a
stable input from its upstream source. In the event of an upstream UPS failure or output disturbance, the
downstream UPS switches the load to battery. Once the upstream UPS regains full function, the
downstream UPS should recognize a stable input and switch to pass-through mode; but this does not
happen in all cases and some cases fail.
In a failing case, the downstream UPS fails to switch back to pass-through mode, instead running from
the battery until the battery set is drained. Once the battery is drained, the downstream UPS must attempt
to switch back up to pass-through mode. At the minimum, this leaves the downstream UPS with depleted
batteries.
Warranty information
HPE ProLiant and x86 Servers and Options
www.hpe.com/support/ProLiantServers-Warranties
HPE Enterprise Servers
www.hpe.com/support/EnterpriseServers-Warranties
HPE Storage Products
www.hpe.com/support/Storage-Warranties
HPE Networking Products
www.hpe.com/support/Networking-Warranties
Regulatory information
Belarus Kazakhstan Russia marking
Hewlett Packard Enterprise Company, 3000 Hanover Street, Palo Alto, CA 94304 U.S.
• Russia:
• Belarus:
• Kazakhstan:
• Russia
:
• Belarus:
• Kazakhstan:
Manufacturing date:
The manufacturing date is defined by the serial number.
CCSYWWZZZZ (serial number format for this product)
Valid date formats include:
• YWW, where Y indicates the year counting from within each new decade, with 2000 as the starting
point; for example, 238: 2 for 2002 and 38 for the week of September 9. In addition, 2010 is indicated
by 0, 2011 by 1, 2012 by 2, 2013 by 3, and so forth.
• YYWW, where YY indicates the year, using a base year of 2000; for example, 0238: 02 for 2002 and
38 for the week of September 9.