Pbq-1
Pbq-1
Pbq-1
The amounts inserted against the items in this section shall be in respect of the whole of the works.
Measurement
(a) In the first interim payment, the contractor shall be paid either the actual premium
upon submission of receipts or the amount entered in this item whichever is lesser.
The receipts of Premium paid must be from an approved bank issuing bank
guarantee.
(b) The remaining sum (if any) shall be paid in each subsequent payment in proportion
to the progress of works.
Item coverage
(a) Performance bond in form of bank guarantee from an approved bank for duration
of coverage as stipulated in the Contract;
1.02 INSURANCES
Measurement
(a) In the first interim payment, the Contractor shall be paid either the actual premium
upon submission of receipt or the amount entered in this item whichever is lesser.
The receipts of premiums paid must be from an approved insurance company
issuing the policies or the authorised underwriter or bank;
(b) The remaining sum (if any) shall be paid in each subsequent payment in proportion
to the progress of works.
Item coverage
1.03 SIGNBOARD
a:/d4.0143/B1 PBQ 1/1
Unit - number
Measurement
(b) 20 % on removal
Item coverage
(a) excavation in any material including rock and reinforced concrete and loading into
transport, upholding the sides and keep the earthworks free of water;
(c) support;
(d) formwork;
(k) pay all charges including obtaining permission, licences and fees, etc.
Measurement
(b) 20% for maintenance which shall be made in each interim payment in proportion to
the progress of work; and,
Item coverage
(c) Application for permit from Authority including all charges, deposits and fees;
Measurement
Item coverage
Measurement
Item coverage
(e) dismantling;
(f) transport from Site including loading and unloading at ports, and;
Measurement
Payment shall be made in each interim payment in proportion to the progress of work.
Item coverage
(b) comply with all safety regulations and statutes in connection therewith;
Measurement
Payment shall be made in each interim payment in proportion to the progress of work.
Item coverage
(b) comply with all safety regulations and statutes in connection therewith;
(c) provide and maintain temporary water storage with distribution piping, and ;
Measurement
(b) 20% for maintenance which shall be made in each interim payment in proportion
to the progress of work and,
Item coverage
(b) all necessary fences, notices and direction boards, vehicle access, parking areas and
foot paths;
(c) provision of water, sanitation, power, lighting and air-conditioning and telephone
including all fees and charges levied by the respective authorities;
(e) depreciation;
(g) disconnecting and removal of services and sealing off disused services;
(k) maintenance of buildings, furniture, fittings and all other facilities and services
including all necessary rental charges;
(o) charges for water, electricity, sewerage disposal and telephone calls;
(p) maintain all accesses for use under all weather conditions; and,
Measurement
Payment shall be made upon submission by the contractor and approval by the S.O.
Item coverage
(a) preparation of drawings and details of completed works by licensed surveyor to the
size and format directed by the S.O. including storing all information in ACAD
(Release 14 );
(b) providing labour, tools and equipment necessary to take measurement and
obtaining such information on site as are required by the S.O. for the preparation of
as-built drawings;
(d) printing and delivery of all approved as-built drawings in hardcopies and softcopies
(CD disc) to the S.O.
Measurement
Item coverage
(a) Temporary works required during the course of construction of permanent works;
For example, struting for trenches, cofferdams,temporary track, gantries, structures
for concrete mixing plant, block yard equipment, work yard sites,temporary sheet
piling, bunds and dewatering to keep work free of water etc;
(b) Temporary works required during the course of construction of permanent works in
order to prevent from causing damages to existing properties; For example,
temporary crossing over existing drain, temporary culvert or earth drain for
channelising existing water course etc;
(i) Indemnities to the employer against any claim by owner of neighbouring lots for
losses or damages arising from accidental flooding, siltation etc.; and,
Measurement
Item coverage
(b) making arrangements with owners and occupiers of land temporarily acquired and
costs arising therefrom;
(c) Preparing, amending and submitting to the S.O. and other relevant bodies,
drawings showing proposals and programme including liaison;
(f) Ramps, structures, footways, kerbs, fencing and road marking etc. where
necessary;
(l) Providing of approved electrically operated signals for traffic control as may be
directed;
(n) Provision of alternative access for other contractors if their accesses are hindered
by the works in the contract.
1.13 SURVEY
Measurement
Item coverage
(a) Survey for setting out of work, original ground levels and verifying survey data
provided by other licensed surveyor before commencement of works;
(c) Provision of survey instrument and chainmen for the use of S.O. and his
representatives;
(d) Any other survey related to the works as directed by the S.O.
Measurement
Item coverage
(a) Preparation and submission of progress report to PKNS MS ISO 9002 format and
at interval as directed by the S.O;
(b) Preparation and submission of progress photographs (3R size) in hard and soft
copies to format and at interval as directed by the S.O.
Measurement
Item coverage
Measurement
Item coverage
(a) Liaison with the Authorities in order to obtaining necessary information and
document relating to the works;
(b) Compliance with the contemporary laws and regulations of the Authorities
including all report, photographs, test etc required by the Authorities;
(d) Arrangement for site inspection (including preparation, arrangement for the
client’s/Engineer’s endorsement on letter/ document and submission of the same )
by the Authorities and all cost incurred ;
(e) Obtaining all necessary approval and hand over to local authorities on behalf of the
Employer (with Employer’s consent); and,
(f) Keeping completed works clean for the purpose of inspection by the Authorities.
Measurement
(a) In the first interim payment, the contractor shall be paid either the actual premium
upon submission of receipt or the amount entered in this item whichever is lesser;
(b) The remaining sum (if any) shall be paid in each subsequent payment in proportion
to the progress of works.
Item coverage
Measurement
Payment shall be made in each interim payment in proportion to the progress of work.
Item coverage
(a) the wages and other emoluments paid to the site agent inclusive of overtime
payment;
(b) the site agent working outside the contractor's normal working hours if so required
by the S.O.;
(c) costs and expenses incurred consequent upon the employment or hiring of the site
agent including payment of employee provident fund, insurances, medical and
hospitalisation;
(e) substitution of site agent when the appointed site agent is absent or on leave.
Measurement
To be paid full in the final payment if this item in the opinion of the S.O. is fulfilled.
Item coverage
(a) clearing and removal of all constructional debris and surplus material from
site;
(b) clearing and removal of the same above outside works limit if in the opinion of
S.O. is due to the Contractor of this works;
(c) cleaning and desilting of drain, pavement surface, road shoulder and sewers to the
satisfaction of the S.O; and,
Item coverage
(b) fortnightly inspection and control on site by the appointed pest control specialist
for prevention of mosquito related desease;
(e) Payment for penalty by the Authority due to the infringement of law related to
breeding of dangerous mosquito species.
Measurement
(b) 40 % shall be made in each interim payment in proportion to the progress of work.
Item coverage
(f) removal.
(b) 40% shall be made in each interim payment in proportion to the progress of work.
Item coverage
(a) arrangement for and cost of licenses, wave lengths and channels levied by Syarikat
Telekom Malaysia Berhad / other agencies
(e) Replacement of equipment when the regular equipment is unserviceable for more
than 24 hours;
(j) Depreciation.
Measurement
(b) 40% shall be made in each interim payment in proportion to the progress of work.
Item coverage
(d) depreciation;and,
(e) removal.
(D) PRINTER
Measurement
(b) 40% shall be made in each interim payment in proportion to the progress of work.
Item coverage
(d) removal.
Unit - Set
Measurement
It shall be the number of complete set of safety boot and helmet as accepted by the S.O.
Item coverage
(a) supply and delivery of safety boots and helmets to Site’s office; and,
Unit - number
a:/d4.0143/B1 PBQ 1/13
Measurement
Item coverage
(g) depreciation;
(h) provision of a suitable replacement when the regular vehicle is unavailable for
more than 24 hours, failing which the S.O. has the right to rent a replacement
vehicle and all expenses incurred shall be borne by the contractor;
(j) the motorcycle to be reverted back to the contractor on completion of works; and,
Measurement
Item coverage
(a) submission of road cleanliness and dust control programme for approval by the S.O
for existing roads within the limit of works or the limit in the opinion of the S.O
ought to be included ;
a:/d4.0143/B1 PBQ 1/14
(b) conducting road cleanliness and dust control programme for the whole duration of
works by an appointed personnel ;
(c) cleaning and removal of all constructional debris, accidental earth lumps, concrete
spillage , silting brought about by rain water etc, from road pavement and
shoulders ; and
(e) cleaning and removal of all silt, constructional debris, chokage etc from roadside
drain, sumps and culverts.
Measurement
Item coverage
(a) Search for all records to identify th nature, location and details of all underground
services.
(b) GPR scanning, ampping services and pilot trenching to accertain location and details of
underground services; and,
Measurement
Item coverage
(a) Support and proction of existing services including design and endorsement by
Professional Engineer on temporary works; and,
Measurement
The measurement for payment for the occupational safety and health officer shall be in
proportion to the progress of works.
Item Coverage
The cost for the occupational safety and health officer shall be for the duration of the
Contract and shall include:-
(a) The wages and other enumerations paid to the site staff inclusive of overtime
payments.
(b) Cost and expenses incurred consequent upon the employment for hiring of the site
staff including payment of employee provident fund, insurance, medical and
hospitalization.
(d) Substitution of site staff when the appointed traffic management staff is absent or on
leave.
Measurement
The measurement for payment for the health and safety report shall be the acceptance of the
health and safety report in accordance to the format and copies as stipulated in the
guideline / specification, bill of quantities and employer’s requirement.
Item Coverage
The item for health and safety report shall be in accordance with the Preambles to the Bill of
Quantities General Directions and shall include:-
(a) the costs of literatures, references and consultation in the production of the health
and safety report.
Measurement
a:/d4.0143/B1 PBQ 1/16
Payment shall be made in each interim payment in proportion to the progress of work.
Item coverage
(a) prevention of the deposition of any debris, rubbish, silt, waste materials, foul water,
chemicals etc. arising from the carrying out of the works into the existing
streams/waterways;
(b) diverting existing drains, waterways etc. encountered during the progress of the
Works without disrupting its flow system and subsequently reinstate the same if the
diversion is temporary;
(c) ensuring tyres of all vehicles leaving the site are free of mud;
(f) and carrying out of the works so as to cause minimum interference to the
environment as well as existing properties;
(h) providing, maintaining and removing all necessary temporary ways of access to and
within the site, as well as those from the site to public roads;