Professional Documents
Culture Documents
Lecture Note - Price Analysis
Lecture Note - Price Analysis
Lecture Note - Price Analysis
Name :
Student ID :
1
SLT
Topic
Face to Face Self Learning
Introduction
Estimating and tendering
Roles of estimator
Types of tender, i.e. open, selective and negotiated tenders
Tender procedure 2.0 2.0
Tutorial 1.0 1.0
SLT/Topic 6.0
Principles of Estimating
All-in rate for labour
All-in rate for material
All-in rate for plant
Wastage
Profit and overhead 4.0 4.0
Tutorial 2.0 2.0
SLT/Topic 12.0
Prepared by Ts Tan Lea Koon 3) maximise profit margin without jeopardies success
of tender
2
“Estimating is the process of pricing work based on the There are a number of different types of estimates in the building construction industry.
For example:
information / specification / drawing available in Feasibility Estimate - used to evaluate the numerous technical solutions
developed
preparation of submitting an offer to carry out the work
Preliminary Estimate - is the approximate cost of the project that is calculated at
for a specific sum of money.” the on conceptual stage of project. When the project drawings and specifications
are not available, a preliminary estimate is prepared. It forecasts the total
(Buchan, 2003) budgeted cost of the specific construction project.
Bill of Materials (BOM) - a bill of materials is an extensive list of raw materials,
components, and assemblies required to construct,
“Estimating is the preliminary assessment of the net Detailed Estimate - is a cost of all the activities and materials that would be used
cost of carrying out a specified amount of building work.” in finishing the project.
Budget Estimate – used for financing. Approximation of the cost of an activity,
(Smith, 1986) job, program or project, prepared for budgeting and planning purposes
Cost Control Estimate - monitoring the project during construction
3 4
1
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
3) Elemental method
Requires the calculation of element unit quantities and
element unit rates using the detailed rules of
measurement.
4) Interpolation
This technique used in the early stages of the design
sequence when information, drawn or otherwise, on the
proposed project is in short supply. Is the process of
using known data values to estimate unknown data
values. 12
2
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
9) Price levels
Performed by using index numbers; the differences in
price levels between cost analysis and cost plan data
are adjusted using building cost indices, location
indicates or tender price indices.
17
3
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Most estimators begin their career doing quantity takeoff; 2) Commercial awareness skills:
as they develop experience and judgment, they develop
Benchmarking by comparison
into estimators.
Mathematics/calculating rates
Successful estimators are in demand throughout the
construction industry. Their primary skills include: Communication
1) Technical knowledge: Integrity/teamwork
Establishing scope of works Sub-contacting
Evaluating risk Negotiating
Finding and investigating alternatives Managing risk
19 20
Ethical behaviour
Tendering is refers to the process whereby governments
4) Confidence: and clients invite bids for projects that must be submitted
within a finite deadline.
Accuracy
Reliable reporting
21 22
4
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
25 26
5
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Advantage of negotiation tendering Tender pricing is usually reserved for more complex
Safe time projects to eliminate risk
relationship from early stage-design stage The style of pricing is depend on method of tendering
Pricing for selective - design and build tendering
Disadvantage of negotiation tendering Contractor responsible for designing and
Too risky if appointed contractor unable to continue constructing
work - very rare Estimator of contractor is responsible for
measurement and pricing since no BQ and drawing
31 32
Pricing for open and selective - traditional tendering Pricing for negotiation tendering
Adequate detail drawings and specifications Usually contractor involve in early stage
Estimator to call quotations based on Bill of Pricing will be negotiated based on drawing
Quantities proposed by contractor
Estimator to identify the site condition and which Give the quotation to selected supplier
work to be subcontracted Estimator use his/her experience to pricing and give
Management will determine the profit and overhead the proposal
to mark-up from original price
The process can be repeated until both parties
Will receive a clear trade breakdown and be able to satisfied
compare the different tenderers across all of the
different trades 33 34
1) The arrival of the tender documents 3) The collection of information - Enquires to suppliers
2) The decision to tender The specification of the material
The nature, size and complexity of the work
The quantity of materials required
The principal parties involved
An indication of delivery date
The value of the main contractor’s own work, PC
sums etc. The terms upon which the price is required
The time allowed for tendering Discounts and pro-forma
Firm or fluctuating price required Address and details of access to the site
Contract details
The date by which the quotation is required and
Current workload period for which it is open for acceptance
35 36
6
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
3) The collection of information - Enquires to sub- 3) The collection of information - Visit to the site and
contractors architect’s office
The items to be priced Details of site ground conditions, spot items, etc.
The terms and conditions of the main contract Nearest available tip
4) The preparation of the estimate Basic estimating involved analysis of the work to be
performed, including the type and quantity of work, type and
5) The adjudication size of plant to be used during construction, production rates
of labour and plant to install the work and other job site
The workload condition that are unique to the project and that can impact
the time and cost of construction.
Market level of competition
Procedures and techniques used for estimating vary from
The project reports
company to company
The resources required for the project Costs of materials, labour, plants are various from one
location to another, and over time.
6) The submission of the tender
No book can dependably give costs that can be applied for
bidding purposes.
39 40
41 42
7
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
PRINCIPLES OF ESTIMATING
In Unit Rate Method Materials, Plant and Labour are the actual net costs
involve in directly and physically producing a building
Take into account methods of construction and all
circumstances which may affect the execution of team, and form the ESTIMATE.
work. Project overheads are the cost of on-site services
Consist of a prediction of the cost of the physical should be a separate consideration. The mark-up or
resources and a mark-up by management. margin for general overheads, profit and risk will be
considered by management
The physical resources of the total cost are material,
labour and plant. General Overheads and Profit are added to the
ESTIMATE to produce the TENDER.
The rate should be prepared net.
45 46
In some cases one or more of the five parts may not In Unit Rate method, the cost of each element should
apply. For example as in excavating where no raw be calculated in detail, and in every case is made up of
material has to be furnished and in some cases where two components.
the material or other parts are supplied by the owner.
47 48
8
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
All calculations should be carefully set down as Is the main cost and is about 40% to 60% from contract
necessary so that: sum
The calculations can be checked by another person; All-in material rate is a rate which includes the cost
of materials delivered to site, unloading, handling,
The calculations and assumptions made can be
readily explained to senior management; and conversion, waste, storage, protection and
preparing for use.
The information may be used by, say, buying or
Material element cost involve an all-in rate for the
production control.
material and the quantities required on site.
Materials = all-in rate x quantity of material required
49 50
The material cost should considered subsidiary fixing The factors involved in producing the cost are:
materials. For example
a) The cost/sum quoted by the supplier;
Nails: for fixing timber, plastered board, roof decking,
etc. b) Discounts (i.e. bulk quantity orders, trade discounts,
Screws including brass cups: for fixing joinery work, cash discounts) allowed by the supplier;
particularly hardwood c) Transport to site; and
Adhesives: for fixing floor & wall tiles
d) Site handling and storage.
Bolts: for fixing steel work, metalwork
The material unit cost should also take into an account
of all appropriate charges and discounts.
51 52
Material procurement
Quality
(based on
drawing &
specification)
Time
Quantity
(based on
anticipated
Material (based on
Delivery, handling and storage measurement)
delivery time)
53 54
9
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
During the unit rate built-up, it is important to account of: All-in labour rate is a compound rate which includes
payments to operatives and associated costs which
fixed price period, cash discount offered by suppliers
arise directly from the employment of labour
extra charges i.e. site delivery charges or unloading
costs quoted by supplier
Labour or plant involved in unloading and handling Labour element cost involve an all-in rate for the labour
the materials and the times required to execute the job
Site condition and avoid multi-handling Labour = cost per hour x time required
“All-in’ rate for labour cost is a total cost which covered Wages are paid according to gender, market,
both direct cost and indirect cost location, working condition, skills or responsibility,
and experiences.
57 58
10
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Other factors that influence labour constant All-in mechanical plant rate is a compounded rate
Human Variances External Conditions which includes the costs originating from the
ownership or hire of plant together with operating
Skill of operative Climate
cost.
Familiarity with operation Supervision
Equipment used Complexity of design Plant element cost involve an all-in rate for the material
Motivation Site layout and and the quantities required;
Human needs organisation Plant = hire rate x time required
Security
Job satisfaction
Physiology
61 62
Plant cost is highly capital intensive and very large Types of mechanical plant
sums of money are involved.
Operated plant such as excavators or cranes
More plant is being used on building site due to: include the cost of an operator and are hired at
RM??? per hour (excluding fuel costs) with a
a) Reduce costs – increased labour costs compared
minimum hire period, usually eight hours
with plant costs.
b) Speed – greater speed of completion required. Non-operated plant such as compressors, concrete
mixer, pumps and vibrators are hired by the week
c) Increased use of large components.
d) Increased size of contracts
63 64
Types of non-mechanical plant Only consider mechanical plant in unit rate built-up
Non-mechanical plant such as site offices, The estimated cost is allocated to
scaffolding, system formwork may be hired by the a) relevant units in the bill of quantities if the plant is
weekly or monthly period and usually charged under used on specific items of work, and where the time
general overhead in preliminary required is directly related to the quantities of works.
E.g. excavating plant
Small equipment such as wheelbarrows, shovels,
hammers usually charged on an “on and off” basic. b) project overheads if the plant is used on a number of
This method involves charging the contract with the different trades or operation. E.g. a crane being used
cost of the items when sent to the site, and giving a for concrete, formwork and reinforcement
credit when returned distribution
65 66
11
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
67 68
The lessee (the contractor) has full possession and use 4) Flexibility of operation - Fully usage by contractor for
different project and can be rented out to collect the rental.
of the specific asset (item of plant) on payment of
specified amounts over a period, while the lessor 5) Tax allowances, grants and subsidies - As an incentives to
encourage the contractor to embark on capital expenditure
retains ownership
6) Good company profile - Enhanced company image
69 70
Disadvantages of ownership The estimator must also recover the cost of the plant
1) Difficulties in keeping up to date with equipment - over its expected useful life, and allow for the cost of the
Advances in design and technology results the plant become capital invested.
out of date
The lost value of plant and equipment over a period
2) Capital ties up - Committing a large sums of money for the
purchase time is called depreciation.
3) The costs of maintaining plant - Depreciation and There are many possible depreciation methods i.e.
maintenance costs are high straight line method, sum-of-years digits, double-
4) The cost of plant when not in use - Not fully utilise will declining balance, accelerated depreciation method etc.
results lost in full cost of operating the machine
5) The cost of transporting plant to and from site - Need
hauling to and from the site on suitable vehicles 71 72
12
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Straight line method is the most commonly Written down value method is also known as
used method to calculate depreciation. It allows diminishing balance method, reducing balance method,
economics life-cycle and scrap value at end of life-cycle. or declining balance method. This method unchanged
Example: percentage value until end of life-cycle.
Assuming cost of plant is RM 20,000.00, life-cycle 5 years
and scrap value after 5 years is RM5,000.00 Example:
Assuming cost of plant is RM 20,000.00, life cycle 5 years
Cost of plant = RM 20,000.00 and depreciation percentage is 20%
Ddt scrap value = RM 5,000.00
Depreciation per year = RM 15,000.00/ 5 years
= RM 3,000.00
73 74
Calculation of written down value method The built-up of an hourly all-in rate must take into the
1st year, 20% x RM 20,000.00 = RM 4,000.00 full costs of ownership and operating costs.
RM 20,000.00 - RM 4,000.00 = RM 16,000.00 The owning cost include initial capital costs/purchase
price, depreciation, interest and service charges on the
2nd year, 20% x RM 16,000.00 = RM 3,200.00 investment, taxation allowances, plant department
RM 16,000.00 - RM 3,200.00 = RM 12,800.00 overhead, insurance premium, standing time and
maintenance and repair costs.
3rd year = RM 10,240.00
4th year = RM 8,192.00 Operating cost include operator’s cost, fuel, lubrication
5th year = RM 6,553.60 and other consumable items.
75 76
Example 1: Assumptions:
Calculate the all-in working cost per hour of a 20-tonne Cost of insurance = RM 2500.00 per annum
mobile crane, inclusive of operator's wages, fuel and oil. Cost of license = RM 300.00 per annum
Cost of diesel = RM 2.30 per litre
Assumptions: Cost of lubricating oil = RM 3.20 per litre
Cost of mobile crane = RM 600,000.00 Quantity of diesel consume = 30 litres per day
Life time limit of the mobile crane = 15 years Quantity of lubricating oil consume = 5 litres per day
Depreciation on average life condition = 3,000 hours per year Wage of an operator = RM 3,000.00 per month
Taxes = 5 % of basic plant cost Working days = 26 days per month
Repair and maintenance = 15 % of basic plant cost Working hours = 8 hours per day
77 78
13
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM/hr RM/hr
OWNING COST
Hired Plant
i) Mobile crane = (RM600,000/ 15 years/ 3000 hrs) = 13.33 Hiring from a specialist hire company
ii) Insurance = (RM2500 per annum/ 3000hrs) = 0.83
iii) License = (RM300 per annum/ 3000hrs) = 0.10 Normally apply when variation occurs.
iv) Taxes = (5% x RM13.33/hr) = 0.67
v) Repairs and maintenance = (15% x RM13.33/hr) = 2.00
Variation means alteration of the design, quality or
Total machine cost per hour = 16.93 quantity of works throughout the works. When variation
OPERATING COST occurs, original cost will be deducted and new work is
i) Operator = (RM3,000/ 26 days / 8 hrs) = 14.42 measured
ii) Diesel = (RM2.30/ litre) x (30 litre/ 8 hrs) = 8.63
iii) Lubricating oil = (RM3.20/ litre) x (5 litre/ 8 hrs) = 2.00
Total operating cost per hour = 25.05
Total Unit Rate (RM) / hour = 41.98
80
14
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM/ hr RM/ hr The source of the amount of material will be the finished
a) Machinery Cost
work measurements in the Bills of Quantities. The
i) Rental cost = (RM 20,000.00 / 26 days / 8 hrs) = 96.15
measured amounts given are those as fixed in position.
Total Excavator Cost per hour = 96.15
Wastage of materials shall be allowed.
b) Running Cost
i) Operator's cost = (RM 3,000 / 26 days / 8 hrs) = 14.42 The allowance for waste varies from firm to firm and it’s
ii) Fuel consomption = (RM 2.30/ litre x 10 litres/hr) = 23.00 depend on the skill of the buyer, the efficiency of site
iii) Lubrication Cost = (5% x RM 96.15) = 4.81 foremen and the firm in general.
iv) Maintenance Cost = (10% x RM 96.15) = 9.62
Total Running Cost per hour 51.85
Total Unit Rate (RM) / hour = 148.00
85 86
WASTAGE WASTAGE
Material waste is an allowance for additional quantity of Waste can be classified as:
material which is wasted during construction. 1) Stockpile waste;
Allowance for damages and protection should are 2) Deterioration;
applied to all stages of building process. 3) Transit waste / breakages;
Waste allowances can only be assessed from past 4) Cutting waste;
experience and observations an of waste should be 5) Residue waste;
constantly noted be the estimator. 6) Theft and vandalism;
7) Subsidiary fixing materials; and
8) Conversion.
87 88
Happened during unloading of materials from lorries. Results from the effect of dampness, rain, and etc. on
unprotected materials.
Includes loss of materials into the ground,
contamination of materials by soil, and surplus materials Applies to materials such as cement, plaster,
‘lost’. plasterboard and pre-finished component.
89 90
15
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Physical loss of material due to breakage and damages Many materials are not supplied to exact requirements
either at delivery stage or handling stage. or when sheet materials have to be cut as specified.
Is an effect of mishandling materials when they are E.g. some cutting on bricks is normal to maintain the
unloaded, being fixed, or when finally in position. bond. If a special bond is required or if the design does
not take into account the size of the bricks, then extra
Results from careless due fixing, dropping or transit.
cutting may required.
Applies to brittle materials such as sanitary ware, glass
Offcuts; e.g. plywood, board, timber, steel wire mesh,
and tiles.
bar reinforcement, etc.
91 92
A small amount of materials that remains after the main Theft of material form site.
part has been taken or used.
Some aspects of projects cannot be fully controlled by
Consists of materials that are surplus to requirements the contractors.
which are normally delivered in containers and never
completely used. The costs of theft and vandalism on a project are
difficult to predict as they are somewhat random
E.g. 4-litres of paint of a special colour used when the
occurrences, but projects that fall victim to such losses
container holds 5-litres. Such surplus materials may be
salvaged for use on future contract, the cost of can face major losses.
collection and removing to store must be taken into
account.
93 94
To secure the principal material in position. Happen during converting imperial (feet, inch) of matrix
system in large quantity of small decimals e.g.
Should be treated as main materials as they often form
(conversion from 1000 ft3 into m3)
an important proportion of the total cost of an item.
For example:
Needs of identify the waste factor involved per unit.
(i) 1000.00 x 0.283 = 283.00 m3
Examples of subsidiary fixing materials would be
mortar required for brickwork, nails for fixing woodwork, (ii) 1000.00 x 0.283168 = 283.168 m3
and bolts for fixing structural timber or metal works. Therefore, different = 0.168 m3
95 96
16
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Allowance for laps should always be included in the unit Defined as an additional costs over and above the
rates for many building materials, but such allowances basic cost of carrying out each individual operation
cannot be described as waste. described in the bill of quantities.
For example laps in damp-proof courses, roof tiles, Also know as cost of operating/managing the business.
BRC.
May be classified as ‘Direct’ or ‘Indirect’ costs.
97 98
Direct costs are directly associated with carrying out of Indirect (head office) costs involved in running the site
the builder’s contractual obligations on site. For and in producing the actual building itself. For example:-
example:- Directors salaries and expense, staff salaries
Cost of supervision
Stationary, postage
Temporary electricity, telephone, water supply
Temporary workers accommodation Company cars
Tools, hammer, nails Repayment on loans
These expenses providing site ‘back-up’ facilities and Office space-rent
services to the particular project and usually priced in
maintenance & renewal of defective items
‘Preliminaries’.
99 100
101 102
17
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
If overhead increase 10% to RM770,000 and estimate Defined as being that amount of income which
net turnover RM9,800,000. Then, overhead % to be remains after all production and other costs have
charged been deduction
= RM 770,000 x 100% Why profit must be earned?
RM 9,800,000 1) Investment-profit/return for shareholders
= 7.86% 2) Expand the business and increase its turnover
If overhead % can be reduced that mean company is 3) To cushion the effects of a recession (maintain the
more competitive business intact when the workload declines)
4) Maintain confidence for future projects
5) Attract external capital for new projects
103 104
PROFIT PROFIT
The most arbitrary item and is dependent on number of Management will determined the percentage of profit
different factors: according proposal from estimator/QS
1) Workload in hand - lower % of profit when there is Percentage of profit is depend on the experience &
no project in hand to ensure competitive tender, previous project
vice-versa
Therefore, management just not be too greedy to make
2) Market price - level of competition in that area
sure the price is still competitive
3) Risk - site condition, serious lack of info, so higher
profit
4) Resources - fully utilised
105 106
Where the work cannot be valued by measurement, it Normally apply when variation occurs
may be valued on a day work basis
Variation means alteration of the design, quality or
Day works is given in items/lump sum cost consist of quantity of works throughout the works
labour, material, plant, overhead & profit
When variation occurs, original cost will be deducted
Day work is different from provisional sum because it and new work is measured
occurs when construction is begin while provisional sum
is predicted at tender stage
107 108
18
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Analogue defines as similar, parallel in function but not Brook, M 2017, Estimating and Tendering for Construction
necessary in structure or position e.g. same material but Work, 5th edn, Routledge
different thickness-premix Cartlidge,D 2017, Quantity Surveyor’s Pocket Book, 3rd edn,
Routledge
Known as pro rata rate (proportionally)
Mudd, DR 1984, Estimating and Tendering for Construction
The rate is based on original rate because certain Work, Butterworths
element will be the same as original rates and others Peterson, SJ & Dagostino, FR 2015, Estimating in Building
will differ Construction, 8th edn, Pearson
For example change of cost for a 25mm thick cement Pratt, DJ 2019, Fundamentals of Construction Estimating, 4th
edn, Cengage
and sand (1:3) render to 20mm thick
109 110
NOTE NOTE
111 112
NOTE NOTE
113 114
19
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
CONCRETE WORK
The concrete work section of the Bill of Quantities falls into 4) Precast concrete (i.e. lintels, copping, sills, etc.)
6 categories for the purpose of pricing:
5) Prestressed concrete (including both precast and in-situ
1) In-situ concrete (covering both plain and reinforced work)
concrete)
6) In-situ and precast flooring (including composite
2) Reinforcement (covering various types of bar construction of in-situ and precast work and contractor-
reinforcement which is priced by weight, and fabric designed construction)
reinforcement measured and priced by area)
3) Formwork (to surface of the various types of in-situ
concrete)
117 118
119 120
20
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
21
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
IN-SITU CONCRETE
IN-SITU CONCRETE (SITE-MIXED)
(READY-MIXED CONCRETE)
RM RM/m3
When pricing for site-mixed concrete, the rate
Plant Cost
calculation involved:
i) Cost of concrete vibrating poker per hour 6.00
Cost of plant per m3 = (RM6.00 / 4 m3) = 1.50 1) Cost of the materials required to make the concrete
2) Cost of mixing involving both plant and labour
Cost per m3 of RMC Grade C25 = 226.01
3) Cost of transporting, placing and any surface
treatments which may be specified
127 128
129 130
22
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Sand Water
purchased by weight (tonne) or volume (m3) and clean water is required for the mixing process
delivered to site in tipper lorries.
normally priced in the Preliminary section of the bill.
the density may be taken as 1600kg/m3
Coarse Aggregate
purchased by weight (tonne) or volume (m3) and
delivered to site in tipper lorries.
the density may be taken as 1400kg/m3 vary
according to the particular material and moisture
content
133 134
Mechanical mixers
The number of men employed in the mixing
operation will vary according to the size of mixer
used. Mixer 5 / 3½ Mixer 7 / 5
23
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
141 142
24
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM RM/m3
SOLUTION 2 RM RM/m3
Labour Cost
Material Cost
Given 6 labourer at RM40.00 per day
a) 1 m3 Ordinary Portland Cement
Labour per hour = 6 persons x (RM40.00 per day / 8 hrs) = 30.00
Cement per 50 kg-bag = (RM18.00 + RM0.50) = 18.50
Cost to produce per hour = 3.25m3 at RM30.00 per hour
Cement per kg = (RM18.50/50kg) = 0.37
OPC = (1/10m3 x 1420 kg/m3) x RM0.37/ kg = 52.54 Cost of labour for 1 m3 of concrete = (RM30.00/ 3.25 m3) = 9.23
b) 3 m3 Sand
Plant Cost
= (3/10m3 x 1.600 tonne/m3) x RM30.00/ tonne = 14.40
a) Mixer per hour = (RM130.00 per day / 8 hrs) = 16.25
c) 6 m3 Aggregate b) Diesel per hour = (RM24.00 per day / 8 hrs) = 3.00
= (6/10m3 x 1.400 tonne/m3) x RM28.00/ tonne = 23.52 c) Lubricator / hour = (RM11.20 per day / 8 hrs) = 1.40
Total material cost (1:3:6) per m3 = 90.46 Cost to produce 3.25 m3 per hour = 20.65
Add shrinkage, consolidation and waste 33.33% = 30.15 Cost of plant for 1 m3 of concrete = (RM20.65 / 3.25m3) = 6.35
Cost of materials per m3 = 120.61 148
RM RM/m3 Example 3
Cost of material = 120.61 Calculate the unit rate per cubic metre of concrete Grade 25 in
Cost of labour = 9.23 ground beam (1:1:2) by using a 7/5 mixer running continuously.
Working continuously will produce approximately 2.25 m3 of mixed
Cost of plant = 6.35
concrete in an hour.
25
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM RM/m3 RM RM/m3
Material Cost Plant Cost
Total material cost (1:1:2) per m3 = 148.75 a) Cost of mixer per m3 = (RM 15.50 per hour / 2.25m3) 6.89
Add shrinkage, consolidation and wastage 33.33% = 49.58 b) Cost of vibrator per m3 6.00
Cost of materials per m3 = 198.33
Cost of plant for per m3 = 12.89
Labour Cost
Total unit rate (RM) per m3 = 231.45
Cost of labour = (5 persons x RM48.00/8 hours) / 2.25m3 = 13.33
Add: Add 10% OHP = 23.15
Hoisting & placing concrete= 0.60 hr x (RM48.00/ 8 hours) = 3.60
working around reinforcement = 0.55 hr x (RM48.00/ 8 hs) = 3.30 Cost per m3 for concrete (1:1:2) = 254.60
Cost of labour per m3 = 20.23
153 154
155 156
26
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
REINFORCEMENT
BTQS2013 PRICES ANALYSIS The following are the prices to be included in the cost of
FOR BUILDING WORKS reinforcement:
“cleaning, cutting, bending, fabricating, placing,
REINFORCEMENT WORKS 157
temporary fixings and support.”
158
Rolling Margin
Through wear of the rollers in the bar extrusion plant,
bars are produced with diameter larger than their
nominal size
159 160
Rolling Margin
Extrusion is a process used to create an objects of a
fixed cross-sectional profile. A material is pushed
through a die of the desired cross-section.
Ring Rolling is known as a thick-walled ring is
compressed, deformed metal elongates, causing
diameter of ring to enlarge.
161 162
27
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Rolling Margin
Reinforcement bars
163 164
Labour
Reinforcement is carried out by barbender or steel
fixer
Sub-contracting
Sub-contractors will perform this work either on a
labour only, or labour and material basis
Spacer block Plastic rebar Rebar chair
wheel spacer
167 168
28
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
169 170
SOLUTION 1 RM RM/kg
Wage of a barbender = RM 80.00 /day,
Material Cost
Wage of a general labourer = RM 48.00 /day
Working hours = 8 hours/day i) 16mm Diameter bar delivered to site per tonne = 3,300.00
Allow idle time of labourer gang = 5% ii) Rolling margin, 2.5% = (2.5% x RM3,300.00) = 82.50
Profit and overhead = 10% iii) Unloading and stacking of bar per tonne = 5.00
Cost of bar per tonne = 3,387.50
Assume the time analysis for labourer per 100kg of rebar: iv) Waste on cutting bar to length, 10% = 338.75
1) Select = 23 minutes v) Tie-wire = 0.66kg/100kg at RM3,500/ tonne
2) Cut = 45 minutes = (0.66kg / 100kg) x RM3,500.00 per tonne = 23.10
3) Bend = 30 minutes
vi) Cost of spacer block = 3.00
4) Fix = 23 minutes
Cost of materials per tonne = 3,752.35
5) Hoist = 8 minutes
Cost of materials per kg = 3.75
129 minutes
173 174
29
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM RM/kg
Steel wire square-mesh fabric
Labour Cost
i) Labourer gang (1:1) = (RM80 + RM48) / 8 hrs = 16.00 Can be bought in straight lengths, or cut to size and
ii) Idling time, 5% = (5% x RM16.00) = 0.80 bent to shape by the supplier
Cost of labour gang per hour = 16.80 The standard sheet is 6 m x 2.2 m
iii) Total labour cost per tonne
The standard roll is 60 m x 2.2 m
= (129 min / 60 min/100kg) x rate per hour
= (0.0215 hrs per kg x RM16.80 per hour) = 0.36 Allowance to material:
Cost of labour per kg = 4.11 1) 5% wastage
Add 10% OHP = 0.41 2) 10% for tying bar/ tie-wire and spacer block
Total unit rate of Y16 per kg = 4.52 3) 10% for laps
175 176
Labour output
Output for general worker, 0.15 hour per m2
Output for cutting, bending, placing
177 178
Example 2 Assumptions:
Cost of steel wire fabric A7 = RM 269.28 /piece
Calculate the unit rate per square metre of steel wire
Cost of tire-wire & spacer block incl. waste = RM 1.00 /m2
square-mesh fabric reinforced to comply with BS 4483 Ref
Two generals labourers to unload the
A193 (A7) size 6.0 m x 2.2 m, weighting 3.02 kg per sq.
steel wire fabric = 5 minutes per sheet
metre and laid in roof slabs with 150 mm minimum laps at
Wage of a barbender = RM 80.00 /day
all joints.
Wage of a general labourer = RM 48.00 /day
Assuming two barbender's take about 0.10 hour to lay and Working hours = 8 hours /day
fix 1 square metre of the fabric. Discount for steel wire fabric from supplier = 55%
Allowance for laps = 10%
Waste on materials = 5%
Profit and overhead = 10%
179 180
30
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
183 184
NOTE NOTE
185 186
31
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
FORMWORK
188
FORMWORK FORMWORK
189 190
FORMWORK FORMWORK
Formwork usually consists of sawn timber framing and The amount of strutting timber requires various
waterproof plywood lining according to the heights of the soffit above floor level.
Plywood is commonly used for forms and sheeting Location Strutting (m3)
giving 1 use to 20 uses (depending on position and Side of column 0.02
quality). Sides of foundation and wall 0.04
For example formworks for slab and wall giving 6 times Sides and soffit of beam 0.05
usage; whereas foundation, beam and column giving for Sides and soffit of slab 0.06
4 times usage.
191 192
32
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
FORMWORK FORMWORK
FORMWORK FORMWORK
FORMWORK FORMWORK
Labour
Formwork is carried out by carpenter or joiners
Labour erecting and dismantling are varies; is
depending on the nature of the work
Labour constants increased by 20% for thick floors
and vibrated work
Sub-contracting
Formwork is commonly subcontracted, frequently in
conjunction with the concrete work
Form Tie (http://www.richee.com.sg/formwork.htm)
197 198
33
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
An average general guide and the figures given are for Factors affecting cost of formwork:
initial construction
a) Amount of re-use, from 1 (e.g. stairs) up to perhaps
Situation Erection hours/m2 Striking and 10 (e.g. walls).
Removal hours/m2
b) Degree of standardisation i.e. repetition.
Carpenter Labourer Labourer
c) Complexity and difficulty of the work.
Slab, walls and 1.00 0.75 0.75
associated features d) Strength requirements i.e. loads – spacing for props,
Beam and column 1.50 0.75 0.75 ties, bracing increased
Walls and associated 0.75 0.75 0.75
features (metal forms)
199 200
Costing
The major principles of estimating costs of formwork
is to accurately determine the number of uses that
will occur
The initial preparation and fixing is the most costly. It
would reduce by 5% for each re-use
Cost of formwork will be higher if a single flight in-
situ concrete staircase is being constructed, it is very
likely that new timber will be used and thrown away
after one use
201 202
Example 1 Assumptions:
Calculate the unit rate per square metre of timber formwork for Carpenter making and fixing of floor soffit = 1.00 hour /m2
horizontal soffit of suspended floor slab not exceeding 3.50 m
Labour making and fixing of soffit = 0.75 hour erection /m2
high.
Labour dismantling of floor soffit = 0.75 hour removal /m2
Assumptions: Wage of a carpenter = RM 80.00/day
Cost of 4' x 8' x 12mm thick plywood = RM 47.00 /pc Wage of a general worker = RM 48.00/ day
Cost of timber in support = RM 700.00 /m3 Working hours = 8 hours/ day
Timber in support required for the floor soffit = 0.06m3 /m2
Allow for mould oil, nails & bolts = 15% of each timber use
Usage of formwork to floor soffit = 5 times uses cost /m2
Initial waste in cutting of timber formwork = 5%
Waste on materials for each use = 10%
Profit and overhead = 10%
203 204
34
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 2: Conversion:
1 tonne = 50 ft3
There are six number of timber formwork to horizontal
1 m3 = 35.32 ft3
suspended beam size 300 mm x 600 mm x 10m long. Assuming
1 tonne = 1.4156 m3
one carpenter was assisted by one general labourer and take
1 feet = 0.3048 metre
21.50 hours to erect and dismantle 1 member of this formwork to
a beam.
Assumptions:
Calculate the unit rate per square metre of timber formwork. Cost of 4’ x 8’ x 12mm thick plywood = RM 47.00 /piece
Cost of strutting timber in support = RM 650.00 /m3
Strutting timber required (inclusive cutting waste) = 0.05 m3 /m2
Usage of formwork to sides & soffit of beam = 5 times uses
207 208
Assumptions: SOLUTION 2
(A) Find Cost per m2 RM RM/m2
Cost of mould oil of each use = RM 0.30 /m2
Material Cost
Cost of nails = RM 4.50 /kg
i) 1 m2 of plywood = (RM47.00 /(1.22 x 2.44)) = 15.79
Allow for nails and bolts of each use = 0.20 kg /m2 ii) Allow for cutting for plywood,15%= (15%xRM15.79) = 2.37
Wage of a carpenter = RM 80.00 /day iii) Timber in support = (0.05m3 x RM650.00/m3) = 32.50
Wage of a general labourer = RM 48.00 /day Initial cost of timber per m2 per 5 uses = 50.66
Working hours = 8 hours /day iv) Cost of timber per m2 per use = 10.13
Allow for cutting of plywood = 15% v) Allow for nails and bolts= (0.20kg x RM4.50/kg) = 0.90
Waste on materials of each use = 10% vi) Allow for mould oil per use per m2 = 0.30
Profit and Overhead = 10% Total Cost per m2 = (RM10.13 + RM0.90 + RM0.30) = 11.33
vii) Material waste, 10% = (10% x RM11.33) = 1.13
Total Materials Cost per m2 = 12.46
209 210
35
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM RM/m2
Labour Cost
Brook, M. 2017 Estimating and Tendering for Construction
Area per beam = (0.60+0.30+0.60) x 10m = 15.0m2 Work, 5th edn, Routledge.
21.5 gang hour (1 carpenter + 1 labour) per beam = Peterson, SJ & Dagostino, FR, 2015 Estimating in Building
i) Labourer gang per hour= (RM80.00 + RM48.00) / 8hrs = 16.00 Construction 8th edn. Pearson
Labour cost per beam = 21.5 gang hours x RM16.00 = 344.00
Peurifoy, RL & Oberlender, GD, 2014 Estimating Construction
Total Labour Cost per m2 = (RM344.00 / 15m2) = 22.93 Costs 6th edn. McGraw Hill
Total cost per m2 = 35.39 Smith, RC 1986, Estimating and Tendering for Building Work.
London: Pearson Education Limited.
Add 10% OHP = 3.54
Cost of formwork per m2 = 38.93
211 212
NOTE NOTE
213 214
NOTE NOTE
215 216
36
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
218
Drop a plumb bob to find the location of the bottom Type of brick bonds (on wall)
plate as shown at the right. Move along the top plate, 1) Stretcher bond/running bond
mark the floor at the other end, and check it at the 2) Header bond
Type of brick paving (on floor) The cost of brickwork or blockwork per square metre in
any class of work will comprise:
221 222
37
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
MORTARS MORTARS
Brickwork and blockwork are normally built in cement or Mixing would required 6 hours per cubic metre labour
cement-lime mortar depending on the location of the for hand mixing due to small quantities
work
Mortar is commonly mixed by machine, which is faster
Mortars can be:
and produces a better mix compared to hand mixing
i) cement and sand (1:3) mix; or
ii) cement, lime and sand (1:1:6) mix. An allowance of 1.0 hour per cubic metre for machine
mixing (using a 100-litre mixer)
Mortar can be site mixed or ready-mixed
An allowance of 1/3 or 33.33% needs to be added to
the cost of dry materials before mixing to cover both
shrinkage and waste
223 224
MORTARS MORTARS
Example 1: Assumptions:
Calculate the unit rate per cubic metre of cement mortar Cost of cement = RM 0.32 per kg (inclusive unloading)
(1:3) mix by using a 5/3½ mixer. The mixer takes 5 cubic Cost of sand = RM 35.00 per tonne
feet of dry materials and produces 3½ cubic feet of Density of cement = 1420 kg per m3
concrete per mix (i.e. 0.099 m3) (1 cubic feet = 0.0283 Density of sand = 1600 kg per m3
cubic metre). Rent of concrete mixer = RM 80.00 per day
Cost of diesel for mixer = RM 16.40 per day
The mixer working continuously at the rate of 12 mixes per Wage of a labourer = RM 40.00 per day
hour, and produces approximately 1.20 cubic metre of Number of labourer = 3 persons (1 filler, 2 wheelers)
mixed concrete in an hour.
Working hours = 8 hours per day
Shrinkage and wastage = 33.33%
227 228
38
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
BRICKWORKS BRICKWORKS
Bricks are normally purchased by the thousand and the Bricks are staked on wooden pallet and unload by lorry
cost of bricks includes delivery to site. crane
The allowance for unloading and stacking must be
taken. Reasonable allowance for common bricks being
unloads and stacks approximately 400 pieces per hour
Bricks can be (a) tipped; (b) hand off-loaded; or (c)
crane off-loaded
Bricks are transported to the site from the stack by the
labourer attending the bricklayer
231 232
BRICKWORKS BRICKWORKS
39
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
BRICKWORKS BRICKWORKS
BRICKWORKS BRICKWORKS
Brick positions in a wall For standard brick, one square metre of half brickwall
consist of 59.26 pieces brick
237 238
BRICKWORKS BRICKWORKS
Quantity of ½ brick per sq. metre Quantity of ½ brick per sq. metre
= (1m x 1m) / (0.225mm x 0.075mm)
= (1m x 1m) / (0.225m x 0.075m) = 59.26pcs
= 59.26 pcs/m2
1m
Qty of 1B Header bond
= (1m x 1m) / ( ? mm x ? mm)
= 118.52 pcs/m2
1m
Qty of 75mm thk. wall (refer rowlock stretcher)
= (1m x 1m) / ( ? mm x ? mm)
65mm + 10mm = 39.51 pcs/m2
215mm + 10mm
239 240
40
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
BRICKWORKS BRICKWORKS
Common bricks per sq. metre Facing brick per sq. metre
Brickwork bond Brick sizes
Joints 10mm wide 215 x 102.5 x 65mm
215 x 102.5 x 65mm Bricks Mortar English bond 89
bricks with 10mm joints Number of No frog One frog Flemish bond 79
bricks Cu. m Cu. m
English garden wall bond 74
½ B wall per sq. m 59 0.02 0.03 (3 courses of stretchers – 1 of headers)
1 B wall per sq. m 118 0.05 0.07 Flemish garden wall bond 68
1½ B wall per sq. m 177 0.08 0.11 (3 stretchers & 1 header in the same course)
Stretcher bond 59
(Source: Howard Wainwright, W. & Wood A.A.B. 1978. Practical Builders’
Estimating, p.82) Header bond 118
(Source: Howard Wainwright, W. & Wood A.A.B. 1978. Practical Builders’
241 242
Estimating, p.82)
BRICKWORKS BRICKWORKS
Brick bonding output depends on: Brick bonding output depends on (cont’d):
1) Nature of work, i.e. thickness of wall, sizes of 5) Weather condition, i.e. hot, cold, wet.
isolated column.
6) Quality of work, i.e. below ground level, fairface,
2) Complexity of the work, i.e. large uncomplicated facing work.
areas, circular work.
7) Pointing, i.e. flush, recessed.
3) Type of bond, i.e. the more intricate, the lower the
output. 8) Height of the wall, i.e. 3.2 metre, 6 metre.
243 244
BRICKWORKS BRICKWORKS
Labour Labour
An all-in gang rate may be built up and the An allowance is paid to bricklayers for maintaining
production output based on the gang rather than their own tools
individual operatives
A bricklayer is not constantly laying bricks, but also
Normally carried out in gangs comprising 2 setting out, forming hole for plumbing, fixing lintels
bricklayers and 1 labourer. etc.
41
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
BRICKWORKS BRICKWORKS
Description Skilled hours Unskilled hours Include mason's hand tools, mortar boards, mortar
½ B wall in commons 1.00 per m2 0.35 per m2 boxes, a mortar mixer, hoes, shovels, wheelbarrows,
1 B wall in commons 1.75 per m2 0.70 per m2 and pails (usually inclusive in general overhead or
Extra for fair face and pointing 0.30 per m2 0.30 per m2
preliminary)
Form 50mm wide cavity 0.30 per m2 0.30 per m2 Some projects may require scaffolding, power hoists,
Close 50mm cavity at openings 0.30 per m2 0.30 per m2 and forklifts
Extra for eaves filling 0.30 per m2 0.30 per m2
Estimator should complete the analysis on the cost
Bonding ½ B wall to existing 0.30 per m2 0.30 per m2
of ownership versus rental cost of equipment in
(source: Smith, R.C. 1986. Estimating and Tendering for Building Work. p.283) order to determined cost per day of such equipment
247 248
Sub-contractors Example 2
Calculate the unit rate in square metre for one-brick thick of 215
Labour is usually subcontracted at a quoted rate per
x 65mm common bricks laid in English Bond for strip foundations
1000 bricks or per block or per floor. This rate will
with a 10 mm thick cement mortar (1:3).
usually include for fixing related items such as dpc’s,
lintols, etc.
Assumptions:
The labour rate must be checked to discover
Cost of brick = RM 0.45 /piece
whether scaffolding and/or mixing equipment is
included in the quote, or has to be provided by the Cost of cement mortar (1:3) = RM 230.00 /m3
contractor Number of brick required = 118 pieces /m2
Mortar required (inclusive waste) = 0.05 m3 /m2
Materials are usually supplied by the contractor
249 250
SOLUTION 2 RM RM/m2
Labourer gang (1:1) = 1 bricklayer & 1 labourer
Material Cost
Output of a bricklayer = 120 pieces /hour i) Brick = (118 pcs/ m2 x RM0.45/piece) = 53.10
Wage of a bricklayer = RM 60.00 /day ii) Waste of bricks = (3% x RM53.10) = 1.59
Wage of a labourer = RM 40.00 /day iii) Mortar incl. waste = (0.05m3 x RM230.00/m3) = 11.50
Cost of materials per m2 = 66.19
Working hours = 8 hours /day
Labour Cost
Waste of bricks = 3% i) Labourer gang per hour = (RM60 + RM40) / 8 hrs = 12.50
Profit and overhead = 10% Cost of labour per m2 = (118 pcs/120 pcs) x RM12.50 = 12.29
Total cost per m2 = 78.48
Add 10% OHP = 7.85
Total Unit Rate (RM) / m2 = 86.33
251
42
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
BLOCKWORKS BLOCKWORKS
Lightweight insulating blocks made of various materials Block thickness range from 60mm to 215mm (i.e. 60, 75,
including foamed slag, concrete, clay, etc. 100, 140, 190, and 215mm)
Lightweight concrete and hollow clay blocks are in
common use. Usual size is 150 mm x 225 mm and
Grey Hollow Block
thickness from 50 mm to 225 mm 9” x 4” x 3”
Cement Solid Block
9” x 3” x 2”
253 254
BLOCKWORKS BLOCKWORKS
255 256
BLOCKWORKS BLOCKWORKS
Type of wall Skilled hour per m2 Labour is usually subcontracted at a quoted rate per
100mm lightweight blockwork in walls or 0.50 1000 bricks or per block or per floor. This rate will
partitions usually include for fixing related items such as dpc’s,
140mm as above 0.65
lintols, etc.
215mm as above 0.90 The labour rate must be checked to discover
Allow approx. 30% extra labour for dense load- whether scaffolding and/or mixing equipment is
bearing concrete block included in the quote, or has to be provided by the
Fair face and pointing one side as work 0.20 contractor
proceeds
Material is usually supplied by the contractor
(source: Smith, R.C. 1986. Estimating and Tendering for Building Work. p.284)
257 258
43
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
259 260
44
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Labour output
(source: Smith, R.C. 1986. Estimating and Tendering for Building Work. p.285)
267 268
Labour output The price of stone varies and its dependent on the type
of material, size, shape and finishes of the stones,
Type of work Skilled hours Unskilled hours location of the quarry, and particularly the haulage costs
Prepare top of old 1 B thick wall 0.25 per m 0.12 per m
for raising Stone can be sold by weight (tonne) or volume (m3)
Bedding wood frame in mortar 0.05 per m 0.03 per m In hardscape construction, various types of masonry
Extra for pointing one side in 0.06 per m 0.03 per m walls are being used.
mortar
(source: Smith, R.C. 1986. Estimating and Tendering for Building Work. p.285)
269 270
45
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Cost of stone delivered site = RM 82.50 /tonne Working hours = 8 hours /day
Cost of gauged mortar (1:1:6) = RM 180.00 /m3 Waste of stone = 10%
Number of stone required = 0.33 tonne /m2 Profit and overhead = 10%
Gauges mortar required (inclusive wastage) = 0.06 m3 /m2
271 272
SOLUTION 4 RM RM/m2
Brook, M. 2017 Estimating and Tendering for Construction
Material Cost Work, 5th edn, Routledge.
i) Stone = (0.33 tonne x RM82.50/tonne) = 27.25
ii) Waste of stone = (10% x RM27.25) = 2.73 Peterson, SJ & Dagostino, FR, 2015 Estimating in Building
iii) Mortar incl. waste= (0.06m3 x RM180.00/m3) = 10.80 Construction 8th edn. Pearson
Cost of materials per m2 = 40.78
Peurifoy, RL & Oberlender, GD, 2014 Estimating Construction
Labour Cost Costs 6th edn. McGraw Hill
i) 1 mason = 3 hrs x (RM80.00 per day / 8 hours) = 30.00
ii) 1 labour = 1.5 hrs x (RM40.00 per day / 8 hours) = 7.50 Smith, RC 1986, Estimating and Tendering for Building Work.
Cost of labour per m2 = 37.50 London: Pearson Education Limited.
NOTE NOTE
275 276
46
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
ROOFING
278
ROOFING ROOFING
Tiles/ slates
Horizontal lap Batten
Tiles/ slates batten
between runs of
Roof Head/
sarking felt L Tile roofing construction
End lap
W Side
lap
Sarking felt
Rafter
Roof board
Ventilated air between rafter
space (50mm Wall Timber
minimum) under batten
rafter
Source: http://www.vogue-garage-conversion.co.uk/garage-conversion-pitched-roof-
insulation.html) 279 280
ROOFING ROOFING
Roofing work would not only include the roof finish but Pitched roof covering include:
also such items as battens, insulation, wire netting,
gutters, downpipes, etc. a) Concrete roof tiles (mixture of cement and sand),
b) Clay roof tile (clay soil and water),
c) Asbestos cement (Portland cement and asbestos),
and
d) Steel sheet (aluminium, zinc).
47
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
ROOFING ROOFING
283 284
Materials pricing
The build-up rate comprising of:-
a) Tile (depend on size of tile and lapping);
b) Batten (tile will be hang on batten with nail);
c) Nail (nailed only at certain tile’s layer and batten to
rafter); and
d) Wastage 5% add on material cost.
287 288
48
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
(source: Smith, R.C. 1986. Estimating and Tendering for Building Work.
p.283) 289 grinder drill driver 290
CONCRETE / CLAY ROOF TILES PRICING CONCRETE / CLAY ROOF TILES PRICING
Example 1 Assumptions:
Calculate the unit rate per square metre of concrete Cost of 50mm x 38mm timber batten = RM 0.60 /m
interlocking 430mm x 380mm, fixing every tile with tile clip Nail required for timber batten = 450 mm centres
to 75mm end lap and 35mm side lap; batten 38mm x Output of a roofer for tile = 3.50 m2 /hour
25mm grade B timber to slope 40 degree pitch. Output of a joiner for batten = 80 m /hour
Wage of a roofer = RM 10.00/ hour
Assumptions: Wage of a joiner = RM 12.00/ hour
Cost of roof tile delivered to site = RM 2,500.00 /1000 pcs Wage of a general labourer = RM 6.00/ hour
Delivery and stack required = 1.75 hour /1000 pcs Working hours = 8 hours /day
Cost of tile clip = RM 0.30 /no Waste on materials = 5%
Cost of nails (1000 pcs = 2.85 kg) = RM 3.50 /kg Profit and overhead = 10%
291 292
CONCRETE / CLAY ROOF TILES PRICING CONCRETE / CLAY ROOF TILES PRICING
293 294
49
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
CONCRETE / CLAY ROOF TILES PRICING CONCRETE / CLAY ROOF TILES PRICING
RM RM/m2 RM RM/m2
(B) Battens Labour Cost
i) Qty of batten used per m2 (A) Fixing Roof Tiles
= [8.16 nos x (0.380m – 0.035m)] = 2.82 m Roofer per m2 = (RM10.00 / 3.50m2 per hr.) = 2.86
Cost of batten per m2 = (2.82m x RM0.60 per m) = 1.69
ii) Qty of nails per m2 (B) Fixing Batten
= [(2.82m / 0.45m) +1] = 7.27 pcs Output of joiner = 80.00 m per hour
Cost of nails per m2 Batten = 2.82 m per m2
= 7.27pcs x (2.85kg/ 1000pcs) x RM3.50 per kg = 0.07 Joiner per m2 = 2.82m x (RM12.00 / 80m per hr.) = 0.42
Cost of batten and nail per m2 = 1.76 Total labour cost per m2 = 3.28
iii) Waste on materials = (RM1.76 x 5%) = 0.09 Total cost per m2 = 29.22
Cost of batten and nail per m2 = 1.85 Add 10% OHP = 2.92
Total material cost per m2 = (RM24.09 + RM1.85) = 25.94 Total Unit Rate (RM) / m2 = 32.14
CONCRETE / CLAY ROOF TILES PRICING CONCRETE / CLAY ROOF TILES PRICING
Example 2 Assumptions:
Calculate the total cost and unit rate per square metre of Unload battens = 2 labourers; 1 labourer at 0.50
Swiss Terra Cotta tiles size 345mm x 190mm (effective cover) to hour per 100 metres
slope exceeding 22.5 degree, nailed to 50mm x 38mm battens. Nails for fixing roof tiles (incl. waste) = 1.50 kg /100 m2 of roof tiles
Assumptions: Nails for fixing batten (incl. waste) = 1.50 kg /100 m of batten
Roof area (16.0m long x 5.5m) = 88.00 sq. metre Labour output fixing roof tiles = 1 gang hour /15 m2
Cost of roof tiles delivered to site = RM 1.80/ piece Labour output fixing battens = 1 gang hour /100 m
Cost of battens 50mm x 38mm = RM 3.40/ m at 345mm centres Slope more than 22.5 degree = Add 25% gang hour
Cost of nails = RM 3.50/ kg Gang at ratio 2 : 1 = Skilled worker at RM 10.00/ hour,
Unskilled worker at RM 4.00/ hour
Waste on battens and tiles = 5%
Working hours = 8 hours /day
Unload of roof tiles = 2 labourers; 1 labourer at 1
hour per 1000 pieces Profit and overhead = 10%
297 298
CONCRETE / CLAY ROOF TILES PRICING CONCRETE / CLAY ROOF TILES PRICING
SOLUTION RM RM RM RM
Material Cost (B) Battens
Length of batten for 88 m2
(A) Roof Tiles for 88 m2
= 16m x [(5.50m / 0.345m ) + 1]
i) Qty = [88m2 / (0.345 x 0.19)] + 5% waste = 1409.61 pcs = 271.07 m
Roof tiles = (1409.61 pcs x RM1.80 per piece) = 2,537.30
16 m
ii) Cost of unloading of roof tiles
1 person @ 1 hour/1000pcs; 2 persons @ 1 hour/2000pcs
= (1 hr x 2 x RM4.00) x (1409.61 pcs / (2000pcs) = 5.64
5.5 m
iii) Nails = 88 m2 x (1.50 kg/ 100 m2) x RM3.50 per kg = 4.62
50
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
CONCRETE / CLAY ROOF TILES PRICING CONCRETE / CLAY ROOF TILES PRICING
RM RM
RM RM
(B) Battens
Labour Cost
i) Cost of batten per m for 88 m2 roof coverage i) Fixing batten = 1 gang hour/ 100 m
= (271.07m x RM3.40 per m) = 921.64 Total batten = (271.07 m / 100 m) = 2.71 gang hr
ii) Cost of unload for 88 m2 battens by 2 labourer
1 person @ 0.5 hour/100m; 2 persons @ 0.5 hour/200m
ii) Fixing tiles = 1 gang hour /15 m2,
Total tiles = (88 m2 / 15 m2) = 5.86 gang hr
= 271.07m x [(0.5hrs x 2 x RM4.00) /200m] = 5.42
Labour gang hours = 8.57 gang hr
iii) Waste on batten = [5% x (RM921.64+5.42)] = 46.35
iii) Add gang hour for 25% slope = 2.14 gang hr
iv) Cost of nails for 88 m2 battens
Total labour gang hours = 10.71 gang hr
= 271.07m x (1.50kg/ 100 m) x RM3.50 per kg = 14.23
Cost of fixing 88m2 battens = 987.64
Total material cost for 88m2 = 3,535.20
301 302
RM RM
Labour Cost
iv) Total labour gang (2:1) hourly
= (2 x RM10.00 per hour) + (1 x RM4.00 per hour) = 24.00
v) Total labour cost
= (10.71 gang hour x RM24.00 / gang hour) = 257.04
305 306
51
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Material pricing
The build-up rate comprising of:-
a) Steel sheet (standard size from supplier according to
specification);
b) Bolts (nailed only at certain roof sheet’s layer and
batten to rafter);
c) Allow cutting waste 5%; and
d) Lapping.
311 312
52
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
313
sheet metal cutter hand seamer/ bender 314
Example 3 Assumptions:
Cost of roofing sheet = RM 12.00 /m2
Calculate the unit rate per square metre of 2400mm x Galvanised nails required = 3 nos /m2
1075mm x 6mm thick corrugated asbestos cement roofing Cost of galvanised nails = RM 3.50 /kg (1kg = 90nos)
sheet with 150mm head laps and 75mm side laps laid at 30 Output of labourer gang (1:1) = 0.16 hour /m2
º pitch, nailed to timber purlins at 1000mm centers. Wage of a skilled worker = RM 60.00/ day
Wage of an unskilled worker = RM 40.00/ day
Working hours = 8 hours /day
Cutting waste of roofing sheet = 5%
Waste of nails = 5%
Profit and overhead = 10%
315 316
53
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Lead or lead-based flashings are widely used in normal Flashings are measured in metre stating the width, lap
building work and method of fixing with the net length being taken
making no allowance for laps or seams in the running
Supplied in rolls of various thickness ranging from length
1.25mm and weighting 14.48 kg/m2 to 3.55mm and
weighting 40.26 kg/m2 Allowance of 7.5% for laps and cutting waste
The rolls are standard 6m long and available in eight Using gang labour at ratio of 1:1, approx. 3m metre per
different widths: 150, 210, 240 270, 300, 390, 450 and hour for cutting and fixing 225mm girth lead flashing;
600mm and 1.5m metre per hour for stepped flashing
Fixing operation is carried out by a gang comprising a
plumber and mate
319 320
Felts are measured in sq. metre stating the lapped at The labour of fixing the felt has been included with the
side and end joints as well the method of fixing battens in the slanting analysis. The cost of nails has
also been included in the slating
Allowance of 15% for laps and cutting waste should
added due to net area being taken
Various materials including reinforced sarking felt,
aluminium foil, metalised foil, etc.
Aluminium foils (paper/woven) are widely used in
roofing work and supplied in rolls. The rolls are various
in size: 1.22 x 40m, 1.22 x 50m, and 1.25 x 48m
321 322
54
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
4) Ridge End Cap - Used for capping horizontal ridge ends. It 8) Elbow - Used at the bend (135ºC) of a horizontal/main
overlaps on both Left and Right Verge Tiles to provide a ridge.
good finish.
9) Valley Tile - Laid over metal valley gutter to give better
5) Left Verge Tile - Same as Right Verge Tile but used beneath finish to roof valley. It allows proper seating and securing of
Double Tile on left hand side of roof. cut tiles with cement mortar. For roof pitch of 20º - 40º.
6) Right Verge Tile - Provide water-tightness to roof edge and 10) Eaves Double Tile - Same as Eaves Standard Tile but
lends a solid appearance. Fixed onto wooden fascia board used only at left roof edge to match Double Tile.
beneath Standard Tiles on right hand side of roof.
11) Eaves Standard Tile - Used at the bottom most row of roof
7) Double Tile - Used at left edge of a straight roof to give a i.e. eaves. It prevents vermin and bats from entering roof.
similar wave finish at left edge of roof. Besides, it provides a solid, elegant finish to roof eaves.
325 326
12) Ventilation Tile - Facilities air flow below the roof. It 15) Hip Tile - Used on inclined ridge i.e. Hip formed by 2
prevents water condensation and humidity on underside of adjoining sloped roofs. Taper shape with internal width
tiles. Installed across a roof slope at 5-feet spacing and at 140mm at head and 190mm at tail. 3 pieces/metre.
5th or 6th row from roof ridge. If used together with Ridge
Connecting Tiles and/or Ventilation Tape, it greatly improves 16) Standard Tile
roof ventilation and brings down roof temperature. 17) Hip End - Starter tile at eaves area of a roof hip. It gives
13) Ridge Tile - Used on horizontal/main ridge formed by 2 roof aesthetic finishes and water-tightness.
slopes. Internal width 220mm. Coverage 3 pieces/metre. 18) Eaves Joint - Used where 2 roof eaves join for Hip
End/Ridge End to rest on it. Provides better finishing and
14) 3-Way Apex - Used to cover a 3-way Intersection where
water-tightness.
roof ridge meets with 2 hips.
327 328
329 330
55
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
EXAMPLES OF WOODWORK
332
WOODWORK WOODWORK
333 334
Carcassing kitchen cabinet
WOODWORK WOODWORK
The following 6 main categories shows the Standard 4) Composite items – Factory-made standard items
Method arranges the woodwork on site: supplied ready for assembling and fixing on site.
1) Carcassing – Involved structural timbers forming the 5) Sundries – General labours in connection with
framework of roofs, floors, wall, etc. woodworking operations, together with the supply of
insulating materials and metalwork.
2) First fixing – Items fixed after the framework and
including roof and floor boarding together with grounds, 6) Ironmongery – involving all types of door, window
battens, bearers, etc. which form a base or backing ironmongery, etc.
3) Second fixing – Covering such as skirting, architraves,
window boards, ceiling lining, etc.
335 336
56
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Materials
Timber can be purchased in a sawn state, planed
and moulded.
The basic selling unit is based on tonne, cubic feet
or cubic metre.
Joinery rails i.e. handrailing it is normally quoted per
linear metre.
The prefabricated joinery components i.e. roof
trusses, doors and frames, window etc. reduces site
labour to a minimum
337 338
WOODWORK WOODWORK
Method of pricing
The following are the items which normally states that
prices are to included for;
Halving joint Mortise and Tenon
Bridle joint
“all labours in framing, drilling for bolts, fixing in
position complete with all nails.”
Dove tail
Finger
Cross having
341 342
57
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
WOODWORK WOODWORK
WOODWORK WOODWORK
Description Skilled operatives Labour output and nails for additional timber work
Structural members of roofs and floors 10 m / hour *
(wall plates, rafters, ceiling joists, etc.)
Type Nails (kg) Carpenter (hr/m)
Partitions 6 m / hour
Fascia and barge boards 8 m / hour Fascia board 0.02 0.20
Grounds generally 12 m / hour Skirting 0.03 0.10
Herringbone strutting 5 m / hour
Tongued and grooved flooring 12 m / hour
Chipboard flooring 10 m2 / hour
100mm Skirting, including mitres 12 m / hour
Door frame/ lining for single door 0.75 hr each
Hollow-cored single door 0.75 hr each
(source: Smith, R.C. 1986. Estimating and Tendering for Building Work. p.310) 346
WOODWORK WOODWORK
347 348
58
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 1: Example 1:
Calculate the unit rate per linear metre run for delivery of 100mm x Calculate the unit rate per linear metre run for delivery of 100mm x
75mm thick sawn pressure treated wall plate. A general labourer will 75mm thick sawn pressure treated wall plate. A general labourer will
take an hour to unload and stacking 1 cubic metre of timber. take an hour to unload and stacking 1 cubic metre of timber.
Assumptions:
Cost of timber = RM 650.00 /m3
Cost of nails = RM 4.50 /kg
Nails required = 1 kg /m3
Waste on timber and nails = 10%
Output of a joiner = 12 hours /m3
Wage of a joiner = RM 60.00 /day
Wage of a general labourer = RM 44.00 /day
Working hours = 8 hours /day
349
Profit and overhead = 10% 350
SOLUTION RM RM RM RM
Material Cost Labour Cost
i) Cost of timber per m3 = 650.00 i) Cost of joiner per hour = (RM60.00 / 8hrs) = 7.50
ii) Unload & stacking of timber = (1 hr x RM44/ 8hrs) = 5.50 Output of a joiner = 12 hours per m3
Total labour cost per m3= (12 hrs x RM7.50/ hr) = 90.00
Cost of timber per m3 = 655.50
Total cost per m3 = 816.00
iii) Waste on timber = (RM655.50 x 10%) = 65.55
Add 10% OHP = 81.60
iv) Cost of nail per m3 = (RM4.50 per kg x 1 kg) = 4.50 Total Unit Rate (RM) / m3 = 897.60
v) Waste on nail = (RM4.50 x 10%) = 0.45
Total material cost per m3 = 726.00 Cost per m= RM897.60/m3 x (0.10m x 0.075m) = 6.73
351 352
SOLUTION RM RM/m
Example 2: Double nails
Calculate the unit rate per linear metre of 150mm x 25mm thick Material Cost
fascia board fix to timber roof rafter. The joiner used 2 numbers of i) Cost of fascia board per m = 3.00
nails to nailed the fascia board at every 400mm centres of rafter. ii) Qty of nail= [(1m / 0.40m) + 1] x 2nos = 8 nos
One joiner required an hour for fixing 6m length fascia board. Cost of nail = [8 nos x (RM3.50/ 220 nos)] = 0.13
Assumptions: Cost of material = 3.13
Cost of fascia board = RM 3.00 /m (including off-load & stack) iii) Waste on nails = (10% x RM3.13) = 0.31
Cost of nail = RM 3.50 /kg Total material cost per m = 3.44
Number of nails = 220 nos /kg
Labour Cost
Wage of a joiner = RM 70.00 /day
i) Labour cost per m = (RM70.00/ 8 hours) / 6m = 1.46
Working hours = 8 hours /day
Total cost per m = 4.90
Waste on materials = 10%
Add 10% OHP = 0.49
Profit and overhead = 10%
Fascia board 353 Total Unit Rate (RM) / m = 5.39
59
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 3: Conversion:
Calculate the unit rate per linear metre of ceiling joist for UAC 1 tonne = 50 ft3
superflex flat sheet in 1200mm x 600mm panels.
1 m3 = 35.32 ft3
Assumptions: 1 tonne = 1.4156 m3
Cost of 50mm x 100mm tanalised ceiling joist = RM 850.00 /tonne
Cost of nails = RM 3.50 /kg
Nails required (inclusive wastage) = 0.022 kg /m
Cost of labour for ceiling joist = RM 2.50 /m
Working hours = 8 hours /day
Waste on materials = 5%
Profit and overhead = 10%
355 356
ii) Waste on material = (RM17.00/ft3 x 5%) = 0.85 ii) Waste on material = (RM600.45/m3 x 5%) = 30.02
Cost of ceiling joist per ft3 = 17.85 Cost of ceiling joist per m3 = 630.47
Cost per m3 = (RM17.85/ft3 x 35.32 ft3 per m3) = 630.46 Cost per m = (RM630.47/m3 x 0.05m x 0.10m) = 3.15
Cost per m = (RM630.46/m3 x 0.05m x 0.10m) = 3.15
iii) Cost of nails incl. waste = (0.022kg x RM3.50/kg) = 0.08
iii) Cost of nails incl. waste = (0.022kg x RM3.50/kg) = 0.08
Cost of material per m = (RM3.15 + RM0.08) = 3.23
Cost of material per m = (RM3.15 + RM0.08) = 3.23
357 358
RM RM/m Example 4:
Labour Cost Calculate the unit rate per square metre of 150mm tongued and
i) Cost of labour for ceiling joint per m = 2.50 grooved (T&G) timber flooring. After laying, the effective or ‘laid’
width of the board is 144mm.
Total cost per linear metre = 5.73
Add 10% OHP = 0.57 Note: The effective area is important when calculating the total
Total Unit Rate (RM) / m = 6.30 length of boards required per square metre of flooring
6mm 144mm
359 360
60
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Assumptions:
Cost of 150mm x 25mm T&G timber flooring = RM 635.00 /100m
Cost of nails (approx. 250 nos. per kg) = RM 4.50 /kg
Unloading of T&G timber flooring = 0.25 hour /100m
144mm Nails required = 5 nos /m
Output of a joiner = 15m /hour
144mm 150mm Wage of a joiner = RM 70.00 /day
Wage of a unskilled labourer = RM 40.00 /day
Working hours = 8 hours /day
Waste on materials = 5%
Profit and overhead = 10%
361 362
SOLUTION RM RM/m2 1m
Material Cost
i) Cost of T&G flooring per 100m = 635.00
ii) Unloading per 100m = (0.25 hr x RM40.00/8hrs) = 1.25 Qty of T&G timber flooring
iii) Nails = (5 nos x 100m) x (RM 4.50/250nos) = 9.00 = 1m x (1m/0.144)m
Cost of T&G flooring = 645.25 = 6.94m per m2 of floor
1m
iv) Waste on materials = (5% x RM645.25) = 32.26
Cost of material per 100m = 677.51
144mm 144mm 150mm
Qty of flooring = 1m x (1m / 0.144m )= 6.94m
Cost of per m2 = 6.94m x (RM677.51/100m) 47.02
363 364
365 366
61
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
368
369 370
62
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
373 374
Example 1:
Compute a quantity take-off of the structural steel
columns and beams of the one-storey building in the
following figure.
Profile Weight
Note:
1 lb = 0.4536 kg (shift conv 23)
Length
1’ = 12”
375 376
63
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Shop
drawings
381 382
64
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
389 390
65
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
66
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
397 398
399 400
NOTE NOTE
401 402
67
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
FLOOR, WALL & CEILING FINISHES FLOOR, WALL & CEILING FINISHES
The following are the items which normally states that Factors affecting labour output:
prices are to included for;
1) Nature of work, e.g. wall, isolated column, opening.
2) Complexity, e.g. large uncomplicated areas, circular
“Narrow widths, small quantities, internal angles, work.
cutting and making good around pipes, sanitary
fittings and the like” 3) Method statement e.g. applied in two coats.
4) Location, e.g. ground floor, high level, confined
space.
5) Weather, e.g. hot or rain
6) Available of raw material, e.g. cement, sand, lime.
405
7) Available of plant, e.g. tower crane, material hoist. 406
FLOOR, WALL & CEILING FINISHES FLOOR, WALL & CEILING FINISHES
Taken-off for wall and floor finishes Taken-off for ceiling finishes
Wall finishes measured in square metre. Window Ceiling finishes measured in area means in square
area, door area or void exceeding 0.50 m 2 will be metre. These should include sloping ceiling.
deducted
Ceiling opening /access units will be measured in
Floor finishes measured in area means in square number.
metre. Horizontal or sloping will be measured
separately. Architraves, mouldings, ceiling ribs and cornices and
will be measured in linear metre.
Drop and skirting will be measured in linear metre.
407 408
68
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
cement rendering pebble wash flooring 19~20 mm thick for backing screed to received wall
tiles
411 412
For in-situ plasterwork to ceilings: using mixture of For site-mixed, an allowance of 5%~10% should be
cement mortar (1:3) strong mix for concrete surface, made for shrinkage and consolidation during mixing an
and thickness of plaster is various. application and wastage of materials.
2~11 mm thick for ceiling plastering Modern plasters are manufactured from gypsum rock
For in-situ floor screeding: using mixture of cement and crushed to fine powder with various additives (setting
sand (1:3), and thickness of cement render is various. times, workability, lightweight, insulating or hard-
wearing characteristics).
12~25 mm thick for cement render
Most plaster can be used neat and required only to be
19~20 mm thick for backing screed to received floor
mixed with clean water on site.
tiles
413 414
69
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
415 416
Guide to average labour outputs for in-situ works Guide to average labour outputs for in-situ works
In-situ Wall & Ceiling Finishes Output in skilled In-situ Floor Finishes Output in skilled
hour per m2 hour per m2
6mm skim coat gypsum plaster on walls 0.35 25mm cement and sand screed (1:3) 0.30
6mm skim coat gypsum plaster on soffit 0.58 50mm cement and sand screed (1:3) 0.45
13mm two-coats lightweight plaster on walls 0.90 Steel trowelled finish 0.20
13mm two-coats lightweight plaster on soffit 1.15 Finishing to falls or crossfalls 0.25
Angle bead, incl. working around in two coats 0.15 per m Works to staircase areas and all work n.e. 300mm wide, additions
lightweight plaster of 30% added to the of labour cost
Works to staircase areas, ceilings and beams over 3.5m high and
in compartments n.e. 4m2 on plan, additions of 25% added to the (Source: Smith, R. C. 1986. Estimating and Tendering for Building Works.
of labour cost Pearson Education Limited, p.331)
418
Guide to average labour outputs for in-situ works Plant / equipment pricing
Plasterers are responsive on their hand tools and
Type of work Labour output
should be included in the project overheads
1 Skilled : 1 Unskilled
Plastered external angle to cornice 0.25 hour / m Mechanical plants would be included in the
preliminaries
Plastered internal angle to cornice 0.75 hour / m
Fixing plaster cornice to wall 0.20 hour / m
Fixing metal angle bead to wall 0.20 hour / m
(Source: Wainwright W.H. & Wood A.A.B. 1977. Practical Builders’ Estimating.
London, Hutchinson & Co Ltd, p.140)
70
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Solution: RM RM/m2
Assumptions:
Material Cost
Cost of cement and sand (1:4) mix = RM 212.00 / m3 i) Cost of cement & sand= (0.019m x RM212.00 m3) = 4.03
Output of a spreader = 3.0 m2 / hour Material waste = (5% x RM4.03) = 0.20
Total Cost of material per m2 = 4.23
Output of a plasterer = 2.5 m2 / hour
Wage of a plasterer / spreader = RM 80.00 / day Labour Cost
i) Laying a 19mm thick bed (2:1)
Wage of a labourer = RM 48.00 / day
Output of 1 spreader : ½ labour = 3m2 per hour
Working hours = 8 hours / day Output of 2 spreaders : 1 labour = 6m2 per hour
Waste on materials = 5%
Gang hourly = [ 2(RM80.00)+RM48.00 ] / 8 hours = 26.00
Profit and overhead = 10%
Cost of bed per m2 = (RM26.00/ 6 m2 ) = 4.17
423 424
RM RM/m2
Example 2
Labour Cost
ii) Screed trowelled finish (2:1) Calculate the unit rate per square metre of 3mm thick skim
Output of 1 plasterer : ½ labour = 2.5 m2 per hour
coating in accordance with the manufacturer’s instructions,
Output of 2 plasterers : 1 labour = 5 m2 per hour
steel-float finish to concrete ceilings.
Gang hourly = [ 2(RM80.00)+RM48.00 ] / 8 hours = 26.00 Two plasterers will be supplied with material by one
Cost of finish per m2 = (RM26.00/ 5 m2 ) = 5.20
labourer who will unload and mixing the materials (2:1).
Total cost of labour per m2 = 9.37
Total cost for 19mm thick cement & sand to wall = 13.60
Add 10% OHP = 1.36
Total Unit Rate (RM)/ m2 = 14.96
425 426
71
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Solution RM RM/m2
Assumptions:
Material Cost
Cost of skim coat plaster = RM 25.00 / 25kg bag
i) Cost of skim coat plaster = (RM25.00/ 8 m2 ) = 3.13
Coverage of skim coat = 8 m2 / bag
ii) Labour off-loading and stacking,
Labour off-loading and stacking = 2 minutes / bags
= [(2min/ 60min)/ 8m2] x (RM48.00/ 8 hours) = 0.03
Output of a plasterer = 10 minutes / m2 =
Cost of material per m2 3.16
Wage of a plasterer = RM 80.00 / day =
iii) Waste on materials = (5% x RM3.16) 0.16
Wage of a labour = RM 48.00 / day Total cost of material per m2 3.32
Working hours = 8 hours / day
Waste on materials = 5%
Profit and overhead = 10% 427 428
Solution RM RM/m2
Example 3
Labour Cost
Calculate the unit rate per linear metre of galvanised
Skim coated concrete ceiling (2:1)
perforated metal angle bead with 50mm returns to comply
Output of 1 plasterer : ½ labour = 10 min per m2
with BS1246, secured to brick arris with plaster dabs,
Output of 2 plasterers : 1 labour = 5 min per m2 including working plaster to bead both sides.
i) Gang hourly = [ 2(RM80.00)+RM48.00 ] / 8 hours = 26.00
ii) Cost of finish per m2 = (10min/ 60min) x RM26.00 = 2.17
Total cost of labour per m2 = 2.17
Total cost of 3mm thick skim coating = 5.49
Add 10% OHP = 0.55
Total Unit Rate (RM) / m2 = 6.04
429 430
Generally room heights are about 2.3m, and a plaster will Assumptions:
fix about five lengths to walls in one hour. As these beads Cost of metal angle bead = RM 5.00 per 2.5 m length
are fixed during the general plastering working with a 3:2 Cost of neat plaster for fixing = RM 0.60 / m
gang, 0.67 hour must be included for attendant labourer.
Wage of a plasterer = RM 80.00 / day
Wage of a labourer = RM 40.00 / day
Tips:
Labourer gang (3:2) = 3 plasterer + 2 labourer, OR Working hours = 8 hours / day
= 1 plasterer + 2/3 labourer
= 1 plasterer + 0.67 labourer Waste on materials = 10%
If 1 plasterer take 1 hour Profit and overhead = 10%
= 1 hr plasterer + 0.67 hr labourer
431 432
72
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Solution: RM RM/m
Example of tiles finishes
Material Cost
i) Cost of metal angle bead per m = (RM5.00 / 2.5m) = 2.00
ii) Cost of neat plaster per m = 0.60
iii) Waste on materials = (10% x RM2.60/m) = 0.26
Total cost of material per m = 2.86
Labour Cost
i) 1 Plasterer = (1 hr x RM80.00/ 8 hrs) / (5 x 2.5m) = 0.80
ii) 1 Labourer = (0.67 hr x RM40.00/ 8 hrs) / (5 x 2.5m) = 0.27
Total cost of labour per m = 1.07
Total cost of metal angle bead = 3.93
Add 10% OHP = 0.39 wall tiles ceramic floor tiles
Total Unit Rate (RM) / m = 4.32
433 434
Tiles are purchased by pieces. Allowance of cement paste to received tiles finishes
The size of the tile and the thickness of the joint must 0.002m3 for one square metre of wall / floor tiles
be known so that the number required per square metre 0.0012m3 for linear metre of finish skirting
can be determined.
An allowance of 5% should be made for cutting and
The unit rate must include cost for bedding and jointing waste.
material which may include cement and sand, coloured
mortar or adhesives recommended by the supplier and The work involved in tiling is normally undertaken by
‘gangs’ comprising 2 tilers and 1 labourer.
specified in the bill description.
435 436
Guide to average labour output for tiles finishes. Plant / equipment pricing
Tilers are responsive on their hand tools and should be
Tiles Finishes Output in
1 skilled : 1 unskilled included in the project overheads
Laying wall tiles ≥ 150mm x 150mm 1.00 hour / m2 Mechanical plants e.g. material hoists would be
Laying wall tiles < 150mm x 150mm 1.25 hour / m2 included in the preliminaries
Laying floor tiles ≥ 150mm x 150mm 0.75 hour / m2
Laying floor tiles < 150mm x 150mm 1.90 hour / m2
Laying tiles finish skirting, 75mm high 0.20 hour / m
Laying tiles finish skirting, 100mm high 0.23 hour / m
Laying tiles finish skirting, 125mm high 0.26 hour / m
Laying tiles finish skirting, 150mm high 0.30 hour / m
437 tile cutter hand tools 438
73
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 4
Calculate the unit rate per square metre of 152mm x
152mm x 6mm thick mosaic tile paving in tile adhesive and
pointed with 3mm wide white cement mortar joints on
screeded backing (measured separately) to required
pattern.
Two tilers will be supplied with materials by one labourer,
who will unload the materials (2:1). Assume one tiler will
takes 0.75 hours to bed and lay one square metre of
mosaic tiles.
439 440
RM RM/m2
Example 5
Labour Cost
Laying tiles finishes (2:1) Calculate the unit rate per linear metre of 50mm high drop
Output of 1 tiler : ½ labour = 0.75 hour per m2 for 250mm x 250mm x 6mm thick ceramic tiles paving in
Output of 2 tilers : 1 labour = 0.375 hour per m2 tile adhesive and pointed with 3mm wide white cement
i) Gang hourly = [(2 x RM90.00) + RM48.00] / 8 hrs = 28.50 mortar joints on screeded backing (measured separately)
Labour per m2 = (0.375 hour x RM28.50) = 10.69 to required pattern.
ii) Wage of labour pointing per m2 = 3.00
Two tilers will be supplied with materials by one labourer,
Total cost of labour per m2 = 13.69
who will unload the materials (2:1). Assume one tiler will
Total cost of mosaic tile per m2 = 52.95
takes 0.20 hours to bed and lay 1 linear metre of 50mm
Add 10% OHP = 5.30
high drop ceramic tiles.
Total Unit Rate (RM) / m2 = 58.25
443 444
74
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM RM/m
Sheet finishes are popular material for wall and ceiling
Labour Cost
works
Laying tile skirting finishes (2:1)
Output of 1 tiler : ½ labour = 0.20 hour per m The kind, quality and thickness of the material is to be
Output of 2 tilers : 1 labour = 0.10 hour per m stated, together with the method of fixing and treatment
i) Gang hourly = [(2 x RM90.00 + RM40.00) / 8 hrs)] = 27.50
of the joints
Labour per m = (0.10 hr. x RM27.50) = 2.75
ii) Wage of a labour pointing per m = 1.50 The unit of measurement is the square metre with work
Total cost of labour per m = 4.25 not exceeding 300mm wide being so described
Total cost of 50mm high drop ceramic tiles per m = 6.27
Add 10% OHP = 0.63
Total Unit Rate (RM) / m = 6.90
448
Type of sheet finishes for wall and ceiling include: Example of sheet ceiling finishes
Ceiling tile system (asbestos free)
Suspended ceiling grid system (mineral fibre,
acoustic etc.)
Plastered board ceiling/ partition work
Plastered board are fixed to wall and ceiling,
subsequent finish with a skim coat of plaster or direct
decoration with paint
Two operatives should be involved with the installation
of suspended ceilings system. Suspended ceiling Asbestos free ceiling
449 450
75
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example of sheet ceiling and wall finishes Type of sheet finishes for floor include:
Carpet
Rubber flooring
Sheet vinyl flooring
carpet tile sheet vinyl flooring rubber flooring raised floor tiles system
453 454
455 456
76
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Assumptions: Assumptions:
Cost of 914mm x 1200mm Wage of a plasterer = RM 80.00 per day
gypsum plaster baseboard sheet = RM 3.50 per m2 Wage of a labourer = RM 40.00 per day
Cost of nail = RM 4.50 per kg Labourer gang to board & scrim (1:1) = 1 plasterer & 1 labourer
Cost of scrim cloth = RM 8.00 per 100m roll Labourer gang to skim (2:1) = 2 plasterer & 1 labourer
Cost of board finish plaster delivered to site = RM 285.00 per m3 Output of 1 plasterer to board & scrim = 1.5 hours per 10 m2
One labour to offload & stack the board = 5 minutes per 10 m2 Output of 1 plasterer to skim = 3 hours per 10 m2
Quantity of nails = 500 nos per kg Working hours = 8 hours per day
Number of nails required = 12 nos per m2 Cutting waste on sheet material = 5%
Usage of scrim cloth = 2m per m2 Waste on nails, scrim cloth and plaster = 10%
Coverage of skim coat = 165 m2 per m3 Profit and overhead = 10%
457 458
461 462
77
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example of strip finishes Approximately 10% for cutting and wastage factor on in-
situ strip finishes
For aluminium strip ceiling, an allowance of 10% for
nails wastage
For parquet, strip timber flooring and timber skirting:
5 nails per metre
0.25 litre per m2 of adhesive material
0.12 litre per m2 of floor dressing material
timber wall paneling
463 464
The work involved undertaken by gang comprising 2 Table below shows the labour output for timber floor
finishes.
skilled and 1 unskilled operatives
Works to staircase areas, ceilings and beams over 3.5 Floor Finishes Labour output
1 skilled : 1 unskilled
m high and in compartments n.e. 4 m2 on plan,
Parquet 0.50 hour / m2
additions of 25% added to the of labour cost
Strip 0.45 hour / m2
Works to staircase areas and all work n.e. 300mm wide, Laying timber skirting 0.20 hour / m
additions of 30% added to the of labour cost
465 466
Plant / equipment pricing Brook, M. 2017 Estimating and Tendering for Construction
Work, 5th edn, Routledge.
Using a trowel machine to make smooth surface for
floor after works completed. Peterson, SJ & Dagostino, FR, 2015 Estimating in Building
Construction 8th edn. Pearson
Peurifoy, RL & Oberlender, GD, 2014 Estimating Construction
Costs 6th edn. McGraw Hill
Smith, RC 1986, Estimating and Tendering for Building Work.
London: Pearson Education Limited.
78
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
470
DOORS DOORS
Material The doors are counted and classified by size and type.
Most of the items contained are taken off by the unit and Metal doors (hollow metal, hollow metal doors &
categorised by type and size. frames, aluminium frames, aluminium doors &
frames)
Usually priced by the unit.
Wood and plastic doors (wood frames, wood doors
The cutting and wastage factor on in-situ joinery is & frames)
about 10%. Allow a nominal 2.5% wastage on Special doors (cold storage, counter doors, glass
prefabricated joinery components (damage, lost or swing, hanger doors, jalousie, roll up grill, sliding,
stolen). swing, vertical lift)
Allowance for unloading must take into account for both Entrance and storefronts (revolving doors, sliding
frames and leaves. entrance, sliding panel, stainless steel, swing doors.)
471 472
DOORS DOORS
Door and door frame has many technical It’s easy to call Most of the door frames and door leaves are supply by
them ‘door’ and ‘door frame’. In general, the different respective door suppliers and installed by the general
parts of a door frame are called: contractors.
1) Head Door frame should support with temporary stay and trim
2) Sill or Threshold when was completed.
3) Door Stop The estimator may use the unit price method as a basis
4) Jamb for the labour calculations, or develop a labour hour per
5) Lining or Casing unit.
6) Architrave The time required to set door frames and jambs will
vary with the size of the opening, the type of frame or
jambs set, and the grade of workmanship.
473 474
79
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
DOORS DOORS
Units which are furnishes by a mill, may require some Table 1: labour productivity for setting a wood door frame, jambs, and trim
fitting before they are set, plumbed, and fastened in Operation Max size of Carpenter Helper
position. opening, ft (hr/ unit) (hr/unit)
Set frame for exterior door 3x7 1.0-1.5 0.2-0.3
The trim is installed after the walls are finished. 6x7 1.5-2.0 0.3-0.4
Table 1 shows the labour-hours required to set door 8x8 1.5-2.0 0.3-0.4
frames, jambs, and trim. Use the lower rates for Set frame for interior door 3x7 0.5-1.0 0.1-0.2
ordinary workmanship and the higher rates for first- 6x7 1.5-2.0 0.3-0.4
grade workmanship. Install interior trim, two sides:
Single casing 3x7 1.0-2.0 0.2-0.4
6x7 1.5-2.5 0.3-0.5
Two-member trim 3x7 1.5-2.5 0.3-0.5
475 6x7 2.0-3.0 0.4-0.6
DOORS DOORS
Table 2: labour productivity for setting the frame or jambs, install stops &
hardware, and fit & hang a door
Table 2 shows the labour-hours required to set the Operation Max size of Carpenter Helper
frame or jambs; install the stop, casing, butt; and lock, opening, ft (hr/ unit) (hr/unit)
and fit and hang one door. Exterior, single casing 3x7 3.0-6.0 0.6-1.0
6x7 5.0-10.0 1.0-2.0
The rates are based on using hand tools.
Exterior, two-member trim 3x7 3.5-6.5 0.7-1.3
If power tools are used to fit, route, and mortise, then 6x7 6.0-10.5 1.2-2.1
the rates should reduce by 10%. Interior, single casing 3x7 2.5-5.0 0.5-1.0
6x7 4.5-9.0 0.9-1.8
Interior, two-member trim 3x7 3.0-6.0 0.6-1.2
6x7 5.5-10.0 1.1-2.0
Sliding doors (track, double doors) 5x8 6.0-8.0 1.2-1.6
Screen doors 3x7 1.0-1.5 0.2-0.3
477 6x7 1.5-2.5 0.3-0.5
Example 1:
Estimate the unit rate per linear metre of 100 mm x 75 mm door
frame in softwood, moulded, rebated and plugged to brickwalls.
Assume a machine man take about 0.25 hour for cutting out
frame, mortising and tenoning; and a joiner take about 0.25 hour
for knocking up frame and jointing.
Note: door frame is attached to the door, holds the door upright,
Door frame should support Door leaf was fit and hang provides support, and allows the door to move on its hinges.
with temporary stay on the frame with all
necessary hinges and lock
479 480
80
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 1: Assumptions:
Cost of 100 x 75mm wrought joinery timber
(including unloading) = RM 7.20 /m
Cost of rebating by machine labour = RM 0.20 /m
Cost of 150mm nails (36 nos per kg) = RM 4.50 / kg
Number of nails required = 3 nos / m
Wage of a machine man = RM 80.00 /day
Wage of a joiner = RM 70.00 /day
Working hours = 8 hours /day
Waste on machine frame = 15%
Waste on nails = 10%
481 Profit and overhead = 10% 482
483 484
Example 2: Example 2:
Estimate the unit rate per linear metre of 150 mm x 38 mm
softwood door lining, rebated, plugged to brickwork, and tongues
at angles.
Assume one machine man was using 0.25 hour for cutting out
lining and tongueing and grooving; and 0.75 hour for knocking
up lining on site and fixing in operation.
81
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Solution RM RM/m
Assumptions:
Material Cost
Cost of 150 x 38mm wrought joinery timber
i) Cost of 150 x 38mm wrought joinery timber = 5.20
(including unloading) = RM 5.20 /m
Cost of rebating by machine labour = RM 0.20 /m ii) Cost of rebating by machine = 0.20
Cost of 100mm nails (66 nos per kg) = RM 4.50 / kg Cost of rebated timber = 5.40
Number of nails required = 3 nos / m iii) Waste on machined lining = (15% x RM5.40) = 0.81
Wage of a machine man = RM 80.00 /day iv) Cost of nails = (3 / 66nos x RM4.50 per kg) = 0.20
Wage of a joiner = RM 70.00 /day v) Waste on nails = (10% x RM0.20) = 0.02
Working hours = 8 hours /day Total material cost per m = 6.43
Waste on machine lining = 15%
Waste on nails = 10%
Profit and overhead = 10% 487 488
RM RM/m
Example 3:
Material Cost
Total material cost per m = 6.43 Estimate the unit rate per number for 38mm thick Group 'B'
skeleton timber frame flush single leaf door panel overall
Labour Cost size 900mm wide x 2100mm high, covered on both sides
i) Machine man = 0.25 hours x (RM80.00/ 8 hrs) = 2.50 with 6mm thick WBF plywood and hanging on butt hinges
ii) Joiner for fixing = 0.75 hours x (RM70.00/ 8 hrs) = 6.56 to a timber door frame.
Total labour cost per m = 9.06
Assume one joiner was assisted by one semi-skilled joiner
Total cost per m = 15.49
to set the frame, install stops, hardware, and fit and hang a
Add 10% OHP = 1.55
door.
Total Unit Rate (RM) / m = 17.04
489 490
82
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
WINDOWS WINDOWS
The cutting and wastage factor on in-situ joinery is Wood windows (wood sash, wood screens, wood
about 10%. Allow a nominal 2.5% wastage on windows)
prefabricated joinery components (damage, lost or
stolen). Windows and curtain walls (curtain walls, window
walls)
Allowance for unloading must take into account for both
frames and sash.
495 496
WINDOWS WINDOWS
Most of the window frames and sash are supply by Prefabricated windows frames may be shipped from the
respective window suppliers and installed by the mill unassembled, or completed assembled with the
general contractors. exception of the interior casing.
Window frames are rest on bed of concrete. Estimator Setting window frames involves carrying them to the
must consider cost of concrete bed during installation of opening, installing, plumbing, and bracing them in
the frame. position.
The estimator may use the unit price method as a basis The interior trim for window frames usually is installed
for the labour calculations, or develop a labour hour per after the plaster walls are completed.
unit.
497 498
83
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
WINDOWS WINDOWS
Table 3: Labour productivity for installing a wood window frame Table 4: Labour productivity for fitting and hanging a pair of wood
sash windows
Operation Carpenter Helper
(hr/unit) (hr/unit) Operation Carpenter Helper
Assembling frame, single opening 1.0-1.5 0.2-0.3 (hr/unit) (hr/unit)
Assembling frame, double opening 1.5-2.0 0.2-0.3 Fitting double-hung sash 0.5-0.8 0.1-0.2
Assembling frame, triple opening 2.0-2.5 0.3-0.4 Hanging double-hung sash 0.6-0.8 0.1-0.2
Setting frame, single opening 0.8-1.0 0.2-0.3 Fitting casement sash 0.6-1.0 0.1-0.2
Setting frame, double opening 0.9-1.1 0.3-0.4 Hanging casement sash 0.8-1.2 0.2-0.3
Setting frame, triple opening 1.0-1.2 0.4-0.5 (source: Peurifoy & Oberlender, 2002, p.295)
Installing interior trim 1.0-2.0 0.2-0.4
(Source: Peurifoy & Oberlender, 2002, p.295) 499 500
Example 5:
Estimate the total cost per unit for furnishing, assembling,
and setting double-casement wood window frames overall
dimension 1200mm wide x 1200 mm high divided into 2-
equal panel. The glazed sash was complete with 5mm thick
clear glass, glazing beads, ironmongery and accessories
including fixing to concrete or brickwork, grouting and
pointing.
84
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 6: Assumptions:
Cost of window frame c/w necessary fittings = RM 280.00 /no
Cost of anchors, nails & wedges to frame = 5%
Gang output for plumb, position and install (1:1) = 3 hour per no
Wage of a fitter = RM 80.00 /day
Wage of a labourer = RM 40.00 /day
Working hours = 8 hours /day
Waste on materials = 5%
Profit and overhead = 10%
507 508
85
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
GLAZING
512
GLAZING GLAZING
GLAZING GLAZING
86
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
GLAZING GLAZING
Price of glass can be very considerably, Normally panes would be cut to size by the supplier
which reduces the risks of breakages
1) Glass type, quality, thickness and sizes of sheets
2) Type of frame to receive glazing i.e. wood, An allowance of 5% waste is for pre-cut panes, whereas
aluminium or steel 10% waste is for cutting performed on site
3) Glazing compounds i.e. putty and sprigs Method of glazing and securing the glass in position
(i.e. putty and sprigs, pinned or screwed beads clips,
rubber gasket, etc.) must measured and priced in the
The smaller the panes, the greater the cost per square cost of glass
metre
517 518
GLAZING GLAZING
Type of Per sq. metre of pane size shown Per linear Glazing executed by skilled labour and may be
rebate metre of performed by specialist glazier
n.e. 0.1 Over 0.1 n.e. Over 0.5 Over 1 rebate
sq. m 0.5 sq.m n.e. 1 sq.m sq.m For extra large and heavy panes of glass, two or more
Wood sash 3.2 kg 2 kg 1 kg 0.5 kg 0.20 kg operatives may be required to manhandle and fix the
Metal sash 4 kg 2.5 kg 1.25 kg 0.75 kg 0.25 kg
glass in position
The location of glazing work may affect the cost where
(Source: Wainwright , W.H. & Wood, A.A.B. 1977. Practical Builders’ access is difficult or work is carried out in confined
Estimating. Hutchinson of London, p.159)
spaces
519 520
GLAZING GLAZING
Guide to labour outputs Add 25% labour time when the glazing is done during
Type of Output for glazing 4mm glass by size of panes cold weather
rebate
n.e. 0.1 sq. m Over 0.1 n.e. Over 0.5 n.e. Over 1 sq.m Add 20% labour time when the glazing is done from the
0.5 sq.m 1 sq.m
outside of a building
Wood with 0.60 skilled 0.55 skilled 0.50 skilled 0.45 skilled
putty and hours per m2 hours per m2 hours per m2 hours per m2
sprigs
Metal - - - -
a) For 6mm glass, increase outputs by 7.5%
b) Allow in addition of 50% of the above output where glass is cut on site
c) Allow an extra 10% for glazing with pinned beads
d) Allow an extra 20% for glazing with screwed beads
(Source: Smith, R.C. 1986. Estimating and Tendering for Building Work.
Pearson Education Limited, p.344) 521 522
87
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 2 Assumptions:
Cost of prefabricate alum. frame = RM 125.00 per no
Supply and install 1200mm x 2400mm x 10mm thick tempered
Cost of glass delivered to site = RM 40.00 per m2
glass fixed to aluminium frame glass panel and including rubber
Cost of rubber gasket for glazing = RM 0.50 per m
gasket, sealant and all necessary accessories.
Cost of sealant to glass panel = 5% of glazing
Calculate the unit rate per number. Labourer gang (1:1) = 1 glazier and 1 labourer
Gang output to glazing = 1.5 hours per no
Wage of a glazier = RM 60.00 per day
Wage of a general labourer = RM 40.00 per day
Working hours = 8 hours per day
Waste on materials = 10%
Profit and overhead = 10%
525 526
Solution RM RM/no
Brook, M. 2017 Estimating and Tendering for Construction
Material Cost
Work, 5th edn, Routledge.
i) Cost of prefabricated frame per no = 125.00
ii) Tempered glass per no= (1.2 x 2.4) x RM40.00/m2 = 115.20 Peterson, SJ & Dagostino, FR, 2015 Estimating in Building
iii) Sealant to glazing = 5.76 Construction 8th edn. Pearson
iv) Rubber gasket = [2 x (1.2 + 2.4) x RM 0.50/m] = 3.60
Cost of materials = 249.56 Peurifoy, RL & Oberlender, GD, 2014 Estimating Construction
iv) Waste on materials = 24.96 Costs 6th edn. McGraw Hill
Total material cost per no = 274.52
Labour Cost Smith, RC 1986, Estimating and Tendering for Building Work.
i) Labour = (1.5 hrs x (RM60.00+RM40.00)/ 8hrs) = 18.75 London: Pearson Education Limited.
Total labour cost per no = 18.75
Total cost per no = 293.27
Add 10% OHP = 29.33
Total Unit Rate (RM) / no = 322.60 528
88
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
530
Paints can be applied in one, two, three, or more coats, There are varies type of paints materials available in the
with sufficient time allowed between successive coats to market and the most common are:
permit the prior coat to dry thoroughly
a) Primer;
There are 4 general types of paint coating:
b) Undercoat / base coat; and
a) Interior wall coating,
c) Finish / final coat.
b) Exterior wall coating,
c) Wood and metal coating, and
d) Roof and tile coating.
533 534
89
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
90
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Guide to output for skilled labour (hours/100m2) Guide to output for skilled labour (hours/100m2)
Operation Gen. wood Glazed windows & Operation Gen. wood Glazed windows &
surf. Doors (wood) surf. Doors (wood)
Prepare, knotting 2 undercoats, 59 Small panes 67 Knotting only on wood surface 16 - -
1 finish coat oil paint Med. panes 64 before fixing
Large panes 61 Prepare 2 coats polyurethane 21 Small panes 24
varnish Med. panes 23
Touch up primer, 1 undercoats , 38 Small panes 44
1 finish coat oil paint Med. panes 42 Large panes 22
Large panes 40
(Source: Smith, R.C. 1986. Estimating and Tendering for Building Works. (Source: Smith, R.C. 1986. Estimating and Tendering for Building Works.
Pearson Education Ltd. p.349) Pearson Education Ltd. p.349)
541 542
Guide to output for skilled labour (hours/100m2) Guide to output for skilled labour (hours/100m2)
Operation Gen. metal Glazed windows & Operation Rendered/ Rendered/
surf. Doors (metal) conc. walls conc. floor
Prepare and prime only 20 Small panes 24 Prepare 2 coats cement based paint 29 -
Med. panes 23 Prepare and 1 coat bituminous paint 15 -
Large panes 21 Note:
Prepare 1 coat red lead primer, 62 Small panes 83 Labour outputs increased for conversion per sq. metre to liner metre
2 undercoats, 1 finish coat • n.e. 150mm girth Add 50%
Med. panes 80
• 150 - 300mm girth Add 33.33%
Large panes 76
(Source: Smith, R.C. 1986. Estimating and Tendering for Building Works. (Source: Smith, R.C. 1986. Estimating and Tendering for Building Works.
Pearson Education Ltd. p.349) Pearson Education Ltd. p.349)
543 544
The outputs shown in ‘Guide to output for skilled labour The cost of providing dustsheets, ladders and
(hours/100m2) are based on work over 300mm wide scaffolding would normally be prices as a lump sum and
and measured in sq. metre. included in the Preliminary
91
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
RM RM/m2
Example 4:
Labour Cost
Knot, prime, stop and paint two flat oil undercoats and one coat
i) Labour cost of priming, undercoating & oil gloss finish paint on general surface of woodwork externally,
finishing not exceeding 100 mm girth. Calculate per square metre.
= [16.90 hours x (RM60.00/ 8 hrs)] / 100m2 = 1.27
ii) Allow for preparation & replacement brushes Assume the following time analysis for labourer to painting of
= (5% x RM1.27 /m2) = 0.06 woodwork
Total labour cost per m2 = 1.33 a) 1 coat of primer = 15 hours / 100 m2
Total cost per m2 = 4.71 b) 1 coat of flat oil undercoat = 14 hours / 100 m2
Add 10% OHP = 0.47 c) 1 coat of gloss-finish paint = 17 hours / 100 m2
Total Unit Rate / m2 = 5.18
551 552
92
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Assumptions: Assumptions:
Cost of knotting = RM 6.00 / litre Wage of a painter = RM 60.00 per day
Cost of alabastine stopping = RM 3.00 / kg Working hours = 8 hours per day
Cost of primer = RM 21.00 / 5-litres Add brush waste = 5% of labour cost
Cost of flat oil undercoat = RM 105.00 / 5-litres Residue waste and sundry materials = 10%
Cost of gloss-finish paint = RM 112.00 / 5-litres Profit and overhead = 10%
Coverage of knotting = 0.75 litres / 100 m2
Coverage of alabastine stopping = 2.5 kg / 100 m2
Coverage of primer = 50 m2 / 5-litres
Coverage of flat oil undercoat = 60 m2 / 5-litres
Coverage of gloss-finish paint = 60 m2 / 5-litres
553 554
557 558
93
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Solution RM RM/m2
Brook, M. 2017 Estimating and Tendering for Construction
Material Cost Work, 5th edn, Routledge.
i) Wallpaper = [RM250.00 / (0.60 x 10m] = 41.67
ii) Pattern waste = (20% x RM41.67) = 8.33 Peterson, SJ & Dagostino, FR, 2015 Estimating in Building
iii) Cellulose paste = RM1.50 / (5 rolls x 0.6m x 10m) = 0.05 Construction 8th edn. Pearson
Total material cost per m2 = 50.05
Peurifoy, RL & Oberlender, GD, 2014 Estimating Construction
Labour Cost Costs 6th edn. McGraw Hill
i) Paperhanger Smith, RC 1986, Estimating and Tendering for Building Work.
= (1.25 x RM80.00/ 8 hrs) / (0.6m x 10m) = 2.08 London: Pearson Education Limited.
Total labour cost per m2 = 2.08
Total cost per m2 = 52.13
Add 10% OHP = 5.21
Total Unit Rate / m2 = 57.34 562
NOTE NOTE
563 564
94
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
SUB-CONTRACTING WORKS
566
The principal differences between DSC and NSC are: It is common practice for general or main contractors to
sub-let significant portions of the work to DSC or NSC.
(a) The tender process is organised and run by the
contract administrator who invites suitable sub- Sub-contracting allow the work can be carried out at
contractors to submit a tender lowest cost or due to it is at a specialised nature, which
the main contractor cannot attempt to carry out using
(b) The contract administrator selects the preferred
his own labour force.
tender and then instructs the main contractor to
enter into a contract with the subcontractors.
567 568
ADVANTAGES OF DISADVANTAGES OF
SUB-CONTRACTING WORKS SUB-CONTRACTING WORKS
(a) Minimised of risk borne by the main contractor as the sub- However, sub-contracting work might go into:
contractor will give a fixed price for the sub-let work and
(a) disputes,
saving in estimator’s time.
(b) liquidation,
(b) Main contractor able to concentrate on other trades of
work which give more efficient in the construction (c) unacceptable by project consultant,
management.
(d) delaying of works and causing main-contractor incurred
(c) Providing the client with good value for money, where a additional expenses
high level of competition for the work may be achieved, as
the main contractor eligible to compared varies quotations
by sub-contractors. This include the material and plant
available, and specialised workmanship provided.
569 570
95
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
The quotation from sub-contractors are important A sub-contractor system for work expects to sub-
element in the compilation of a project estimate. contract should be performed by the main contractor.
Quotation have made ‘apple to apple’ comparison to
For each sub-contracted component the quantity of a
ensure the fairness on valuation.
key element is taken off and all other elements are
The estimator will need an approximate price to listed.
evaluate the sub-bids and must be acknowledgeable
A unit price for the key element is then applied to derive
about the scope of the sub-contractors’ bids and be able
the approximate sub-contractor bid.
to evaluate the capability of the sub-contractors.
573 574
575 576
96
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
P.C sum is included within the main contractor’s tender Profit and Attendance on P.C sum
document. The main contractor to take responsibility for a) Add profit and establishment charges:
executing the work using NSC for an element of work. In percentage, say 2.5 % from P.C sum
P.C sum is fixed amount, estimator should not add-in
any profit required and/or attendance to NSC’s work. b) Add attendance:
But, provision can be made as an addition.
Additional facilities (included within preliminaries
Main contractor is required to price overhead profit and section of the BQ) which is provided by main
any items of attendance it has to provide, such as the contractor on behalf nominated sub-contractor to
use of site facilities, provision of a secure storage, execute the work
protecting the finished work until the project is
completed. 579 580
97
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Example 2: Calculation for P.C sum Peterson, SJ & Dagostino, FR, 2015 Estimating in Building
Construction 8th edn. Pearson
Allow prime cost sum for steelwork RM 100,000.00
Peurifoy, RL & Oberlender, GD, 2014 Estimating Construction
to be fabricated, supplied, erected Costs 6th edn. McGraw Hill
by nominated sub-contractor.
Harlow, PA 1981, The Practice of Estimating. UK: The Charted
Add profit: 5% of P.C sum RM 5,000.00 Institution of Building, p.70-79
Schuette, SD & Liska, RW 1994, Building Construction
Add attendance: Allow 5-tonne lorry Estimating. Singapore: McGraw-Hill International Editions,
@ RM300/day and operator for p.105-107
10 days @ RM50/day RM 3,500.00
RM 108,500.00
583 584
NOTE NOTE
585 586
NOTE NOTE
587 588
98
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
590
Checklists act as reminders to the estimator by A list of information required to prepared an estimate in
progress include type of unit, feed capacity, and project
Listing information required to prepared the early
duration.
estimate
For projects in the building sector, a listing of
Listing miscellaneous costs that may be required in
information to prepare an estimate may include type of
the estimate
building, function use of building, number of occupants,
Listing work items that may be required to build the building location, and project location.
project in accordance with the plans and
For typical miscellaneous cost item may include spare
specifications.
parts, permits, training, and other items.
591 592
Typical scope items that may required, but are not Table 1: Checklist for detailed estimate for concrete work
identified in the definition provided for the estimate, may 1) Are anchor bolts included?
2) Is reinforcing steel included?
include certain utility and auxiliary systems.
3) Is insulation of the slab included?
Table 1 is an example checklist for a detailed estimate 4) Is cost of pumping concrete included?
for concrete work. 5) Is the lifting crane included?
6) Are shop drawings for tilt-up panels included?
7) Is grouting under the wall panels included?
8) Is waste included in the concrete?
9) Are architectural finishes included?
10) Are concrete curing compounds included?
11) Is the portable compressor included?
593 594
99
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Before completing an estimate, one should check the Table 2: Building construction project bid summary
list to be sure that no operations have been omitted. Item Division Material Labour Sub- Total
contract
Table 2 illustrate the cost summary of an estimate. 1 Concrete works 97,176.00 51,524.00 - 148,700.00
2 Brickworks - - 212,724.00 212,724.00
3 Roofing - - 45,729.00 45,729.00
4 Door & windows 36,821.00 32,115.00 - 68,936.00
5 Finishes 172,587.00 187,922.00 - 360,509.00
Total direct costs 306,584.00 271,561.00 258,453.00 836,598.00
Material tax (5%) 15,329.00 851,927.00
Labour tax (12%) 32,587.00 884,514.00
Contingency (2%) 17,690.00 902,204.00
Profit (10%) 90,220.00 992,424.00
595
Bid price = RM992,424.00
ESTABLISH
ESTIMATE REVIEWS
ESTIMATING PROGRAMME
Final review Implementation of the computer has been one of the
Conducted at or near completion of the estimate greatest advancements in the estimating process.
Review is more structured process, depth of the The computer can be used to organise, store, and
review depends on the type or class of estimate that retrieve information and perform many calculations
is being prepared necessary to prepare an estimate.
Lead estimator, experience field personnel, a It is an effective tool for decreasing the preparation time
representative of upper management are involved and increasing the accuracy of cost estimating.
Aim to validate assumptions used in preparing the
estimate, i.e. construction sequence, supplier
selection, and owner’s cost
599 600
100
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
ESTABLISH ESTABLISH
ESTIMATING PROGRAMME ESTIMATING PROGRAMME
The computer is used for estimating in at least 5 Computer application for cost estimating
different applications: (1) quantities take-off, (2) price
a) Spreadsheet, i.e. MS Excel
extensions and bid summary, (3) historical cost
database, (4) labour and equipment productivity b) Estimating software, i.e. CostX, Glodon, BinaLink,
database, and (5) supplier database. Buildsoft, BuildSpace, WinQS, PriMus-DCF, etc.
The computer’s potential in construction estimating has
The changes in computer hardware and software are
progressed from its use as an adding machine to an
rapid and ongoing. The systems used today will be
integrated process of computer-aided design (CAD),
obsolete in a few years.
estimating software, job costing software, and project
scheduling systems.
601 602
ESTABLISH ESTABLISH
ESTIMATING PROGRAMME ESTIMATING PROGRAMME
The common elements of most estimating programme Database
are the Is used to set the estimating standard of the
database, company
Items entered into the database will be used in the
quantity takeoff, pricing of the estimate
cost calculations, and Information loaded in the database (labour
productivity, equipment costs, standard fomulas,
bid total. etc.) from past projects can be used for estimating
future projects
Each company must develop a numbering system
and items in the database to match their methods of
construction
603 604
ESTABLISH ESTABLISH
ESTIMATING PROGRAMME ESTIMATING PROGRAMME
Quantity takeoff Cost calculations
Involves the selection of database codes that will be This is done by the computer software after the
used on the project being estimated quantities are entered
Estimator need to enter the quantities for each item By using the database within the software, the cost
selected or enter the variables that calculate the of labour, material, and equipment is calculated by
quantities the computer
Bid total
In Building Information Modelling (BIM) system,
quantities information will transfer directly from The bid total calculates the overhead and requires
advanced Computer Aided Design (CAD) the estimator to enter the desired markup
605 606
101
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Before preparing an estimate, the estimator should visit Before preparing … (cont’d)
the site to ascertain any local condition that would affect
5) Local material supply and delivery cost
the cost of construction, such as
6) Local cost of drayage (transporting goods over short
1) The availability of storage space on site
distance)
2) The cost of off-the-site storage if required
7) Availability of electric power, water, etc.
3) Site conditions
8) Local ordinances and regulations
4) Local labour conditions (i.e. wage rates, labour
supply, availability of skilled and common labour)
607 608
The environment that surrounds the construction cost Ways to identify risks associated with the project
estimate is very risky. 1) Study all documents associated with the project
thoroughly
The estimator should try to identify those risks areas.
2) Make a site visitation before the bid
Risk can be decreased by making as few assumptions
as possible, doing estimate in a methodical manner, 3) Develop a construction schedule before the bid
and making logical decisions. 4) Investigate the financial capabilities of the owners
and their ethical business relations
The risks can be divided into two:
5) Identify responsibly subcontractors and material
Risks associated with the project suppliers that can meet the demands of the project
Risks associated with the process of estimating 6) Attend the prebid meetings
609 610
7) Be certain the resources are available to build the 12) Identify clauses in the supplementary or special
project conditions of the specifications that transfer additional
8) Develop a fact sheet about the project risk to the construction firm
9) Develop a strategy for getting the project 13) Identify government permit and other requirements
10) Investigate the reputation of the architect and the 14) Identify environment hazards associated with the
architect’s ethical working relationships with project
construction firms
15) Identify any adverse public reaction to the project
11) Identify clauses in the specification that have open-
ended or would transfer risk to the construction firm 16) Identify the availability of local labour and whether or
not unions are involved
611 612
102
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
17) Review the historical weather patterns for the area 22) An analysis should be done for each area that is
subcontracted to ensure that all items in the scope of
18) Identify disposal sites
work are included
19) Review the soil report for unusual soil conditions on
the site
20) Review the project and construction methods for
unsafe conditions
21) Review the proposed construction method to identify
activities that will have small quantities of materials
and thus lower the expected production rate of labour
613 614
Ways to identify risks associated with the process of 5) Review the system for receiving and distributing
estimating addenda
1) Develop a procedure for checking mathematical 6) Review the estimating sheets for unnecessary
errors calculations
2) Review for illegible handwritting 7) Review procedures for rounding off numbers
3) Review the labour production, material, and 8) Avoid scaling drawing
equipment standards of the historical data
9) Review the procedure for adding waste
4) Review the system for distribution of drawings and
10) Review the checklists and update as necessary to
specifications to subcontractors and material
include areas that are no evident from project
suppliers. Only complete sets should be made documents, i.e. transportation costs, storage costs
available
615 616
11) Make sure items are taken off from the correct 16) Review the standardised forms used in the estimating
drawings process to eliminate any procedure problems
12) Review procedures for receiving bids from 17) Review the detail systems associated with estimating
subcontractors and material supplier by computer. As the computer estimating can have
additional risks associated with the estimating
13) Review the consistency of detail in the estimate process (training should provided to ensure estimator
14) Avoid the use of percentage thoroughly understand all aspects of the software
before a computerise estimate is submitted)
15) Review the system for carrying the bid to the bid
receiving station
617 618
103
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
The purpose of the pricing notes is to point out that the The estimator is advised to make some comparison or
rates may be estimated from data. adjustment to the rates prior to apply the price book
data in cost estimate.
Historical data i.e. historical costs from past similar work
are excellent pricing sources. Factors need to be considered when using price book
cost data include size of project, location, fluctuations,
Estimators will refer to a published source of data, i.e.
labour costs, material costs, market conditions, and
pricing book when his/her own data are not available.
overheads and profit.
The price book is for guidance only. It included data on
the market prices of materials and measured rates for
both large and small projects.
619 620
(a) Size of project: Smaller sized projects on the whole tend (d) Labour costs: Take some adjustment i.e. labour
to cost more per unit than larger jobs of a similar type availability, and standard of workmanship required
and construction
(e) Material costs: Material prices often depend on
(b) Location: Some adjustment may need to be considered contractor, location, quantity and discount offer
in respect of projects in city centers or the country areas
(f) Market conditions: Aware the market condition, able to
(c) Fluctuations: In periods of high inflation the prices in the predict and submit a competitive bid price
price book can very quickly become out of date
(g) Overhead and profit: The percentage included in the
published rates vary considerably
621 622
Bills of quantities are a major source of cost information Bills from different contractors for other projects can
but must be used with a great care. show variation in excess of figures.
Comparison of rates between two bills of quantities for When examining bill rates, it is important that the
the same project will show a considerable variation for estimator should has some idea of the rate expected in
many of the items. order that a bill rate will not be used erroneously.
Although tenders may vary by only 10%, individual The estimator in attempting to make use of rates from
trades may differ by as much as 40% and individual prices bills, should be confidentiality, and should not
items by up to 200%. disclose their source to third parties.
623 624
104
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Data from bills of quantities can be summarised as When checking bills of quantities, variations in rates
follows: may due to the following project factors:
a) Individual rates for measured items. a) The size of the project;
b) The type of the project;
b) Overall costs for use with the single price methods c) The regional location of the project;
of approximate estimating, e.g. unit, square meter,
cubic metre. d) The contract conditions applicable to the project;
e) The market conditions happening at the time of
c) Elemental format analysis. tender for the project; and
d) Basic price list of materials, if available. f) The contract implications, particularly those affecting
the contract period and the account to be taken for
inflation.
625 626
The common reasons for unusual bid price in a tender 3. Deliberate distortion
1. Distribution of preliminary items The estimator may deliberately distort the bill rates
either because they are anticipating variations or in
The extent of preliminary items have been discovered
and price within this section order to obtain all the profit at an easy stage in an
attempt to finance the remainder of the work.
627 628
629 630
105
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
631 632
13. Local conditions Peurifoy, RL & Oberlender, GD, 2014 Estimating Construction
Costs 6th edn. McGraw Hill
Affecting the amount of work available and degree of
competition which may distort the overall situation. Schuette, SD & Liska, RW 1994, Building Construction
Estimating. Singapore: McGraw Hill, p.1-44
633 634
NOTE NOTE
635 636
106
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
COMPANY OBJECTIVES IN
TENDERING
The primary objective of tendering is to select a
qualified main contractor with necessary capacity to
undertake the construction phase of the project.
BTQS2013 PRICES ANALYSIS The bidding process must be to obtain best value and
FOR BUILDING WORKS not purely lowest price.
BIDDING STRATEGY 637
638
639 640
Type of tendering versus competitive environment The factors are considered in determining which
projects to bid include
Open tendering: high/maximum level of competition
a) Skills and availability of their labour and equipment
and is open for all contractors
will match the requirement of the job
Selective tendering: multiple stages tender b) Experience in building projects similar to the one
processes, while maintaining appropriate levels of being considered for bidding
competition. Contractors with known reputation are c) Current workload and amount of available bonding
selected usually 6 or 8 contractors credit for bidding additional work
Negotiated tendering: one contractor is approached • Amount of work in progress
and preserve very low level of competition • Available bonding capacity
641
• Size of the current project 642
107
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
The factors are considered in determining which Prior to starting the estimating process, upper
projects to bid include management must assess the desirability to bid the job.
d) Geographic location A contractor has to consider the
e) Size and complexity of the project to be bid investment to the probability of winning the bid,
f) Owner and designer’s reputation risks that may occur during construction, and
g) Available working capital potential of making a profit after the project is
h) How much the contractor wants to expand their completed.
construction operation
643 644
The decision to bid is based on the facts gathered by After the decision has been made to bid the project, the
the estimator, the analysis of the risk, and whether the estimating process can be started.
project fits the strategic plan of the company.
Management assigns the project to a estimator who will
The decision not to bid the project may happen at handle the estimating process.
anytime during the bidding process, but rarely change
All information must be assembled, evaluated,
after the initial decision.
documented, and managed in an organised manner
during the estimating process.
645 646
The quality of the estimate is depend on: Effective communications among the estimating team
are essential to ensure:
Quality and amount of information available for
preparing the estimate Desired level of accuracy
Collecting project data & confirming historical cost
Time allocated to prepare the estimate
information
Proficiency of the estimator and the estimating team
Organised the estimate into the desired format
Tools and techniques used in preparing the estimate Reviewing and checking the estimate
(i.e. cost per functional unit, cost per square metre of
Documenting the estimate
floor area, and approximate quantities)
647 648
108
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
Every bidding opportunity is a game for trying to Table 1 is an example of bidding strategy report. It lists
outguess and outsmart the opposition. the strength, risk, recommended strategies, and value
of each strategy.
The bidding techniques can include better construction
methods, knowledge of competitors, knowledge of the
owner’s needs, success on similar project, and a history
of building of an empirical strategy for being awarded
the bid.
649 650
BIDDING STRATEGY
PROFIT MARGIN OR MARKUP
CONSIDERATIONS
Table 1: Bid strategy report Is defined as
Strategy Strength Risk Value Recommended
number 1-10 (low-high)
“the amount of money, if any, which a contractor retains
1 Unique electrical Company has RM15,000 3
sub bid – said they been in better bid
after he/she has completed a project and has paid all
were bidding only business for 3% low costs for materials, equipment, labour, overhead, taxes,
our company one year insurance, etc.”
2 Our company has None +RM5,000 10 (Peurifoy & Oberlender, 1989, p.16)
a better scaffold
system
3
Notes:
652
The estimator’s objective when selecting a profit is to The amount of profit will vary with the
include the maximum possible profit, yet keep the bid at
size of the contract,
a competitive level.
type of work,
It can be defined as the return for taking the risk.
time required for completion,
The owner of the construction company or top
extent of competition
management will usually determine the amount of profit
that should be added to the estimate. extend of risk/hazard involved,
current workload, and
desire of the contractor.
653 654
109
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
655 656
657
4) Pricing of labour productivity 658
659 660
110
BTQS2013 PRICES ANALYSIS FOR BUILDING 6/20/2021
WORKS
661 662
NOTE NOTE
663 664
NOTE NOTE
665 666
111