Professional Documents
Culture Documents
PP Aaa PP1 150
PP Aaa PP1 150
SKIKDA, ALGERIA
OPERATING MANUAL VOLUME IV, SECTION 5-3:
UNIT 59 SERVICE WATER
KBR
JOB NO.: J6404
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................... 3
2.0 SYSTEM DESCRIPTION ...................................................................................... 5
3.0 OPERATIONS....................................................................................................... 6
3.1 Normal Running ................................................................................................................6
3.1.1 Industrial Water Pumps, 59-MJ01/01-A .........................................................................6
3.1.2 Fresh Firewater/Industrial Water Tank, 63-MF01 ..........................................................6
3.1.3 Potable Water Plant, 59-ML02 .......................................................................................6
3.1.4 Potable Water Pumps, 59-MJ02/02-A............................................................................7
3.1.5 Potable Water Storage Tank, 59-MF02 .........................................................................7
3.2 Typical Operating Parameters ..........................................................................................7
3.3 Temporary Operation ........................................................................................................8
4.0 START-UP .......................................................................................................... 10
4.1 Service Water to Hose and Sample Stations..................................................................10
4.2 Service Water to the Potable Water Plant ......................................................................10
4.3 Treated Water to Safety Showers/Eyewash, Control and Lab Buildings .......................11
5.0 SHUTDOWN ....................................................................................................... 13
5.1 Normal Shutdown ...........................................................................................................13
5.2 Process Upsets and Production Loss .............................................................................13
6.0 SAFETY/EMERGENCY SHUTDOWN ................................................................ 14
6.1 Safety Critical Shutdown Systems ..................................................................................14
6.1.1 I-5910-59MJ01/01A Industrial Water Pumps Trip ........................................................14
6.1.2 I-5920-59-MJ02/02A Potable Water Pumps Trip .........................................................14
6.1.3 Potable Water Plant 59-ML02 Trips .............................................................................14
6.2 Pressure Safety Valve Summary ....................................................................................14
6.3 Fire Protection Equipment ..............................................................................................14
7.0 ATTACHMENTS ................................................................................................. 15
7.1 Attachment I: Equipment List ..........................................................................................16
7.2 Attachment II: Utility Consumption .................................................................................17
Page 2 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
1.0 INTRODUCTION
This operating manual relates to the facilities indicated on Process Flow Diagram
PR-59-PR32-001 and PR-63-PR32-001 and P&ID’s PR-00-SYPI-017 through PR-00-
SYPI-019B, PR-10-SYPI-001 through PR-10-SYPI-008, PR-59-SYPI-002, PR-59-
SYPI-004 through PR-59-SYPI-006A, PR-63-SYPI-001 and PR-64-SYPI-003.
The industrial water demand for the LNG complex is supplied by the GL1.K existing
desalination facilities and a Zone Service Water tie-in connection from existing Zone
Water piping header. Industrial water is stored in the Fresh Firewater/Industrial Water
Storage Tank 63-MF01.
The Service Water System supplies industrial water via Industrial water pumps 59-
MJ01/01-A to the Potable Water Plant and to the service water header. Service water
is used at various locations throughout the LNG complex. Examples of the service
water usage are: The CPI Separator Package, firefighting, hose stations and sample
coolers.
The Potable Water Plant treats the service water by filtration to remove the
suspended solids, odor and organic compounds. A sodium hypochlorite solution is
added for disinfection. The treated water is then used to supply safety showers and
eyewash baths inside and outside of the battery limits. It is also used in the
Laboratory and the Control Room buildings. Potable water is suitable for drinking.
Page 3 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
2.0
Page 4 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
SYSTEM DESCRIPTION
Expected delivery rate of service water from the GL1.K facilities to the Fresh
Firewater/ Industrial Water Tank (63-MF01) is 18 m3/hr indicated on 63-FI-1020. In
addition to this, the new Zone Service Water connection can deliver 65 m3/hr of
Water as indicated on 63-FI-2200 to the same tank.
Service water is used in the CPI Separator Package for the initial fill of the effluent
sump. To avoid effluent from escaping from the unit, the water needs to be free of
oils and grease, but does not have to be potable. If a contaminated fluid is used for
initial fill it would take a lot of time for the unit to purge itself clean. Service water is
also used for flushing out the sludge.
The service water enters the Potable Water Plant at rates up to 4.2 m3/hr indicated
on 59-FI-3000. The flow then passes across 2 x 100% Pre-filters (59-ML02-
ML03/ML03A). The pre-filter is designed to remove particles greater than 3 microns.
Each pre-filter has a differential pressure gauge (59-DPG-3021/3022) and has
bypass piping around it. The filters should be replaced when the differential pressure
reaches 0.7 bar. The flow then goes across 2 x 100% cartridge filters (59-ML02-
ML01/ML01A) and differential pressure gauges (59-DPG-3024/3025). The cartridge
filters are designed to remove particles greater than 1 micron. The filters should be
replaced when the differential pressure reaches 0.7 bar. The flow then goes across 2
x 100% carbon cartridge filters (59-ML02-ML02/ML02A) and differential pressure
gauges (59-DPG-3027/3028). The filters should be replaced when the differential
pressure reaches 0.7 bar. The carbon filters are designed to remove odor and taste.
After the flow exits all of the filters a portion of or all of the flow can be diverted to fill
the hypochlorite storage tank (59-ML02-CV01) with water. During normal operations
the water will be dosed by the hypochlorite dosing pumps to obtain a residual
chlorine level of 0.5 to 1.0 ppm and will exit the system via TP002. TP002 is the tie-in
point where the potable water line from Potable Water Plant 59-ML02 connects to
KBR supplied line to the Potable Water Tank 59-MF02. The hypochlorite is injected
into the water piping on-skid via an injection quill.
The potable water plant starts and stops based on the opening of the level control
valve for the potable water tank. The level depends on the consumption of the users.
The potable water tank is sized for 24 hour requirement. The total estimated
consumption is 0.2 m3/day/person. With the estimated personnel of 250 people, this
results in a daily demand of 50 m3/day.
Page 5 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
3.0 OPERATIONS
3.1 Normal Running
This section provides a description of the operating parameters for the Service Water
System. Refer to Section 3.2 for a list of typical operating variables for this system.
Page 6 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
The local control panel includes a control power ON/OFF switch, local ALARM
ACKNOWLEDGE button, hypochlorite tank level indication, hypochlorite pump
HAND/OFF/AUTO switches, hypochlorite mixer HAND/OFF/AUTO switch and HI and
LOW level alarm indicators.
One pump always operates and the other is a spare. DCS logic K-5925 will
automatically start the spare pump based on low discharge pressure alarm 59-PSL-
1043 as measured by pressure transmitter 59-PT-1043. If the spare pump is started
by this logic it will run until it is stopped manually.
59-FI-3000 Inlet Flow to the Potable Water Plant 2.1 to 4.2 m3/hr
Page 7 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
<0.7
59-PDG-3025 Differential Pressure Gauge for Filter bar
(Max 2.0)
<0.7
59-PDG-3027 Differential Pressure Gauge for Filter bar
(Max 2.0)
<0.7
59-PDG-3028 Differential Pressure Gauge for Filter bar
(Max 2.0)
Page 8 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
When any one of the filters reaches the maximum desirable differential pressure, the
spare filter should be put on line in parallel with the partially plugged filter. Then, the
plugged filter should be shut down and drained with the filters being replaced so that
a clean filter is available for standby operation when needed.
Page 9 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
4.0 START-UP
This section outlines the steps necessary to place the Service Water System in
service. For the purpose of this section of the operating manual, it is assumed that
the following conditions exist: plant air system is operating and system is ready for
start up. For a more detailed start up of the unit, refer to the latest revision of Service
Water Start up Manual PP-AAA-PP1-250.
1. Close all valves and isolation blinds surrounding tank 63-MF01. Begin to fill
service water from the GL1.K complex or Zone Service Water connection as
necessary to a workable tank volume of 610 m3. With the flow rate of service
water entering the facility at 18m3/hr it will take approximately 34 hours to fill the
tank. If the facility is filled using Zone Water Service connection at 65 m3/hr the
approximate fill time will be 9.5 hours.
2. Close valve and isolation blind upstream of TP001 Service Water Inlet to
Potable Water Plant.
3. Install temporary strainer on the suction side of the Industrial Water Pump 59-
MJ01. Make sure all valves on the recirculation line are open. Start driver with
59-HS-1017 and slowly open the discharge valve. Check for flow by using 59-
PG-1015 to see if pump reaches a discharge pressure of 4.5 barg.
4. There are 98 hose stations throughout the LNG Plant. The following step will
need to take place at each hose station. Open valve upstream of the hose
connection and verify that the service water is available at that particular
location. Once complete close valve and move to next station.
5. Also verify service water flow to the CPI Separator by opening valve to blow
down drain.
6. Verify flow to 11 sample stations. Open service water valve upstream of the
sample cooler and open drain valves to verify flow.
Page 10 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
4. Fill the hypochlorite tank as needed with a mix of filtered water from the
package and a hypochlorite solution manually pumped through TP005. The
capacity of the tank is 1000 Liters.
12.5% Solution: Mix 10 L of solution with 450L of water.
5% Solution: Mix 10L of solution with 175L of water.
5. To protect mixer from hypochlorite fumes allow air to enter the potable plant
from TP007 Air Purge inlet. Adjust the air regulator 59-PCV-3040 and needle
valve until the tank pressure is 0.07 bar and flow indicator 59-FI-3042 reads 0.9
SCFM.
6. Close ½” suction valve and the ½” discharge valve to spare pump MJ01A. Open
1” valve at the bottom of the hypochlorite tank to ensure water mixture in the
suction line, liquid end and the discharge cartridge are filled. Relieve back
pressure in the discharge line and hydraulic system to purge air. Purge air by
reducing the pressure on the relief valve.
7. Set the capacity to 30-40% of the max capacity of the pump which is
0.033L/min. Manually start the pump using switch 59-HOA-3006 for 10-20 sec
then stop for 20-30 seconds. Repeat step a few times to fill the diaphragm oil
cavity. Run pump for ½ to 1-½ hours to warm up oil. Check discharge line for
indication of flow by checking the pressure gauge 59-PI-3010.
8. Increase to 100% maximum capacity of pump and operate for 10-20 minutes,
reduce the capacity adjustment setting back to 30-40% of maximum capacity.
Repeat this step several times to insure that the air is bled from the pump
displacement chamber.
9. The pump is now ready for on-line service. Put the pump in automatic mode.
When the pumps are in automatic mode the injection rate will be controlled by
the flow of water through the package. The mixer will also be turned on/off in
conjunction with the hypochlorite pumps turning on/off.
10. Check the chlorine analyzer indicator 59-AI-3001 reads 0.5 to 1 ppm and the
conductivity analyzer 59-AI-3002 reads less than 750 µS/cm. If the readings are
approved by the laboratory, then the treated potable water is now ready to fill
the potable water storage tank.
Page 11 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
59-HS-1025 and slowly open the discharge valve. Check for flow by using 59-
PG-1023 to see if pump reaches a discharge pressure of 3.6 barg.
5. Open drain valve on potable water distribution header to purge any air in the
line. Close drain valve.
6. There are 11 safety shower and eye wash baths throughout the LNG Complex.
Verify that there is flow to each station and also verify that the temperature and
pressure is sustainable to human touch.
7. Open the valve to the control room and verify that the water still meets
specifications.
8. Open the valve to the Lab Building and verify that the water still meets
specifications.
Page 12 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
5.0 SHUTDOWN
5.1 Normal Shutdown
The service water system will usually stay online unless there is a leak or
maintenance activities need to be performed. In the case of a maintenance activity,
the part of the system that is being serviced should be drained of service water.
The following steps are based on a planned shutdown of the Service Water System.
1. Slowly close the discharge valve to the Potable Water Pump 59-MJ02/A (which
ever one that is in service). Shutdown and Lock the driver manually 59-HS-
1025/6 or remotely 59-HS-1025/6-A.
2. Slowly close the discharge valve to the Industrial Water Pump 59-MJ01/A
(which ever one that is in service). Shutdown and Lock the driver manually 59-
HS-1017/8 or remotely 59-HS-1017/8-A.
3. The potable water plant will shutdown due to the fact that there is no flow
through the system. If the potable plant is being run remotely, the lack of flow
through the system will shutoff the hypochlorite dosing pumps and the agitator.
Page 13 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
Set Pressure
Valve Number Description/Location
(barg)
Page 14 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
7.0 ATTACHMENTS
The following attachments are included in this section of the Operating Manual:
7.1 Attachment I: Equipment List
7.2 Attachment II: Utility Consumption
Page 15 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
Design Design
Equipment
Description Pressure Temp
No.
(barg) (ºC)
Page 16 of 17 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-150
OPERATING MANUAL VOLUME IV, SECTION REVISION 1
5-3: SERVICE WATER 24 September 2013
Available
Motor Load
Equipment No. Description (kW)
Page 17 of 17 KBR