Professional Documents
Culture Documents
18Aug20Operations Research Material
18Aug20Operations Research Material
18Aug20Operations Research Material
Note: The Objective Function, the set of Constraints and Non-negative constraints together
referred as LPP
Problem 1.
A company produces 2 different models M1 and M2. Each M1 requires 4 hrs. of grinding
and 2 hrs. of polishing and whereas each M 2 requires 2 hrs. of grinding and 5 hrs. of
polishing. The company has 2 grinders and 3 polishers. Each grinder works for 40 hrs.
and each polisher works for 60 hrs. a week. Profit on M1 is ₹ 3 and on M2 is ₹ 4.
How should the company allocate production capacity to the 2 types models so as to
make the Max. profit in a week?
Solution: Mathematical Formulation of the given problem is
Step 1. Identify the decision vars. Let
x1 number of units of M1 and
x2 number of units of M2
Step 2. formulation of Objective Function
Objective of the company is to determine the number of 2 types of models so
as to maximize the profit, viz.,
z = 3x1 + 4x2
Step 3. formulation of Constraints
For grinding each M1 requires -- 4 hrs. &
each M2 requires -- 2 hrs.
Therefore, total no. of grinders needed per week = 4x1 + 2x2
ll ly for polishing each M1 -- 2 hrs. & each M2 -- 5 hrs. is 2x1 + 5x2
Further, observe the company have 2 grinders & 3 polishers and
each grinder works for 40 hrs.;
each polisher works for 60 hrs
therefore, grinders work for not more than 2X40 = 80 hrs.
polishers work for not more than 3X60 = 180 hrs.
Hence, by considering the time constraints
4x1 + 2x2 ≤ 80
2x1 + 5x2 ≤ 180
Step 4. Adding non-negativity constraints since production of negative numbers of
models is meaningless
so, must have x1 ≥ 0 and x2 ≥ 0
Hence, the company’s allocation problem can be -- following mathematical form
for any 2 real numbers x1 and x2
4x1 + 2x2 ≤ 80
2x1 + 5x2 ≤ 180
x1 ≥ 0 and x2 ≥ 0
for which the objective function is
Max. z = 3x1 + 4x2
Problem 2
An oil refinery company should decide on the optimum mix of 2 possible blending process
of which the i/ps and o/ps production run as follows
Input Output
Process Pi
Crude A Crude B Gasoline X Gasoline Y
P1 6 4 6 9
P2 5 6 5 5
The maximum amounts available of crudes A & B are 250 and 200 units respectively.
Market demand shows that at least 150 units Gasoline X- and 130 units Gasoline Y must
be processed. The profits per production run from processes 1 and 2 are ₹ 4 and ₹ 5
respectively. Formulate the problem for maximizing the profit.
Solution:
Step 1. Identify the decision vars. Let
x1 no. of units of units of Gasoline from P1
x2 no. of units of units of Gasoline from P2
Step 2. formulation of Objective Function
Objective is to determine the Gasoline to produce from P 1and P2 so as to
maximize the profit, viz.,
z = 4x1 + 5x2
Step 3. formulation of Constraints
For crude A P1 = 6. & P2 = 5.
Therefore, for Crude A = 6x1 + 5x2
ll ly for Crude B = 4x1 + 6x2; for Gasoline X = 6x1 + 5x2;
for Gasoline Y = 9x1 + 5x2
Further, observe the available Crudes for A = 250 and B = 200;
Market demand (at least) for Gasolines for X = 150 and Y = 130
Therefore, by considering these constraints
6x1 + 5x2 ≥ 250; 4x1 + 6x2 ≥ 200;
6x1 + 5x2 ≤ 150; 9x1 + 5x2 ≤ 130
Step 4. Adding non-negativity constraints
since production of negative numbers models is meaningless
so, must have x1 ≥ 0 and x2 ≥ 0
Problem 3
A company owns 2 flour mills viz. A and B, with production capacities for high, medium
and low-quality flour. The company has entered a deal to supply flour to a store every
month with at least 8, 12 and 24 quintals of high, medium and low quality respectively. It
costs the company ₹ 2000 and ₹ 1500 per day to run mill A and B respectively. On a day,
Mill A produces 6, 2 and 4 quintals of high, medium and low-quality flour, Mill B produces
2, 4 and 12 quintals of high, medium and low-quality flour respectively. How many days
per month should each mill be operated in order to meet the contract order most
economically?
Solution:
Step 1. Identify the decision vars. Let
Let x1 and x2 are the mills A and B
Therefore, mill be operated in order to meet the contract order most economically
Minimize z = 2000x1 + 1500x2
S. t. Constraints 6x1 + 2x2 ≥ 8
2x1 + 4x2 ≥ 12
4x1 + 12x2 ≥ 24
x1 ≥ 0 and x2 ≥ 0