Professional Documents
Culture Documents
Operations MGT Module #15
Operations MGT Module #15
LEARNING ACTIVITIES
I. ASSIGNMENT
1. Project planners have sought the judgment of various knowledgeable engineers,
vendors and foremen and have developed the time estimates for the plant construction
project as shown in the table below.
Activity Predecess Time Estimates
or (months)
Description Code a m b
Design plant A None 9 11 16
Select Site B A 2 8 35
Select Personnel C A 1 4 5
Select Vendor D A 2 3 4
Project site E B 9 12 20
Manufacture generator F C 15 18 28
Prepare manual G C 3 5 8
Install generator H E,F 2 4 8
Train operators I D,G 5 8 12
License J H,I 5 6 14
a. Construct the PERT network for the project.
b. Find the critical path and its standard deviation.
c. Determine the slack time of all activities of the project.