Professional Documents
Culture Documents
Chamber Pmamp Dadeldhura
Chamber Pmamp Dadeldhura
Abstract of Cost
72
Ministry of Agriculture and Livestok Development
Priminister Agriculture Modernization Project
Project Implementation Unit (Potato Super Zone), Dadeldhura
2 Stone Soiling
For Chamber 1.00 1.30 1.3 0.10
For canal 3.00 5.00 0.6 0.10
Y ESTIMATE
1.80
2.03
0.15
3.98 m3 430.50 1712.52
1.69
9.00 m3
10.69 m3 2486.65 26582.29
0.45
0.02
0.17
0.64 m3 11251.25 7167.04
77.38
65.10
6.70
5.21
9.30 3.6
8.93
0.99
1.12
174.72 kg 107.83 18839.62
14.40
2.88
17.28 m2 558.65 9653.47
0.90
1.80
0.04
0.14
0.86
Materials Rate at Site based on Approved District and Ex-factory rates for FY 2077/078
PMAMP Office Dadeldhura
1 SAND Referance Item No. 3-1, 21.1 Table 2
S.No Particulars Unit Quantity Rate Amount Remarks
a Labour for collection, stacking & screening
Unskilled labour nos. 1.43 615.00 879.45 ref:-3-1d
b Transportation charge upto site by Truck(5.38m3)
Time required for one trip
metalled road1*2km @ 40km per hour = 0.05 hrs. hrs. 0.050 ref:-21.1
rough road 4*2km @ 20km per hour =0.4 hrs. hrs. 0.400
Total hrs. 0.450 1490.34 670.65
Total Idel hour
loading & unloading time hrs. 0.750 ref:-21.1-3
idle hour hrs. 0.214 Table2
Total 0.964 626.75 604.18
Transportation charge per m3 up to site 236.96
c loading & unloading per trip (5.38m3) for labour
For gravel road 1st 5km = 0.204*1.5 nos. nos. 0.562 Table2
for next (-1) km =(0.043*-1*1.5+0.043) nos. nos. -0.06 Table2
for next (1) km =(0.043*1) nos. nos. 0.04 Table2
Total nos. 0 615.00 0.00
loading & unloading per m3 0.00
d Royalties m3 5.38 75 403.50 Dadeldhura dist rate
Total 403.50
royalties per m3 75.00
Total cost of sand per cum at site (a+b+c+d) Rs. 1191.41
3 AGGREGATE size 20mm to 40mm Referance Item No. 3-2-b, Table 2 Remarks
S.No Particulars Unit Quantity Rate Amount
a Collection of aggregates including stacking and screening at quarry site
Unskilled labour nos. 4.00 615.00 2460.00 ref:-3-2-b
b Transportation charge upto site by Truck (4.69 m3)
time required for one trip
metalled road1*2km @ 40km per hour = 0.05 hrs. hrs. 0.050 ref:-21.1
rough road 4*2km @ 20km per hour =0.4 hrs. hrs. 0.400
Total hrs. 0.450 1490.34 670.65
Total Idel hour
loading & unloading time hrs. 0.750 0.00 ref:-21.1-3
idle hour hrs. 0.232 0.00 Table2
Total 0.982 626.75 615.46
Transportation charge per m3 up to site 274.22
c loading & unloading per trip 4.69 m3)
for 1st 5km = 0.406*1.5 nos. nos. 0.609 Table2
for next (-1) km =(0.046*-1*1.5) nos. nos. -0.06 Table2
for next (-1+1) km =(0.046*-1*1.5+0.046*1) nos. nos. 0.04 Table2
Total nos. 0 615.00 0.00
loading & unloading per m3 0.00
d Royalties m3 Dadeldhura dist rate
Total 0.00
royalties & tax per m3 75.00
Toal cost of aggregate per m3 at site (a+b+c+d) Rs. 2809.22
5 CEMENT
S.No Particulars Unit Quantity Rate Amount Remarks
a Cost of 50kg bag at Dadeldhura (NS 43/53 grade) OPC bag 1.00 1025.00 1025.00 ref:-s.n5.2
b transportation charge from Dadeldhura to site by Truck(120bag)
time required for one trip
metalled road6*2km @ 40km per hour = 0.3 hrs. hrs. 0.300
rough road 0*2km @ 20km per hour =0 hrs. hrs. 0.000
total hrs. 0.300 1490.34 447.10
loading & unloading time hrs. 0.750 ref:-21.1-3
total 0.750 626.75 470.06
917.16
transportation charge per bag up to site 7.64
bag 1.00 0.00 0.00
c
loading & unloading per bag of cement @ Rs. 23 ( as per district rate ) ref:-s.n33.02
Total cost of cement per bag at site (a+b+c) Rs. 1032.64
c loading & unloading per kg of steel ( as per district rate )=85per Quental 0.00 ref:-s.n33.01
toal cost of steel per kg at site (a+b+c) Rs. 84.15
7 GI WIRE
S.No Particulars Unit Quantity Rate Amount
a Cost at Dadeldhura per kg of Heavy Coated kg 1.00 124.00 124.00 ref:-s.n12.030
b transportation charge from Dadeldhura to site by Truck(6mt.)
time required for one trip
metalled road6*2km @ 40km per hour = 0.3 hrs. hrs. 0.300
rough road 0*2km @ 15km per hour =0 hrs. hrs. 0.000
total hrs. 0.300 1490.34 447.10
loading & unloading time hrs. 0.750 ref:-21.1-3
idle hour hrs. 0.750 626.75 470.06
917.16
transportation charge per kg up to site 0.15
c loading & unloading per kg of steel ( as per district rate ) 0.46 ref:-s.n33.01
Toal cost of steel per kg at site (a+b+c) Rs. 124.61
9 Supply & spreading of river bed material at site transporting from river quarry site (Ref 21.1)
Unit- per cum
Particulars. Unit Qty. Rate Amount
a excavation by Hydraulic Machine JCB Bucket capicity 0.40
ref:-analysis
hydraulic
for excavation and Loading m 3
1 #REF! #REF! machine
Sub- Total #REF!
Rough road 10 Km, metalled road 20 Km
a Transportation Charge upto site by 6MT Truck per trip (4.69m3)
time required for one trip
Rough road 4*2 Km @ 20 Km per hour hr 0.4 ref:-21.1
Metalled road 0*2 Km @ 40 Km per hour hr 0
Sub- Total 0.4 1490.34 596.14
Loading & Unloading hr 0.75 ref:-21.1-3
Ideal hour hr 0.232 Table2
0.982 626.75 615.47
596.14
transportation charge per m3 127.11
b Loading & unloading charge
for 1st 5Km, 0.406 *1.5 nos no 0.609 Table2
for next (-1) km =(0.046*-1*1.5) nos. no -0.060 Table2
for next (1) km =(0.046*1) nos. 0.040 Table2
0.589 615.00 362.24
Loading & unloading per m3 77.24
c Royalties cum 4.69 65 304.85
304.85
Royalties 65.00
Cost of river bed material per m3 at site=a+b+c+d #REF!
d spreading of dupped material at site per m3 unit -1m2
20 cm solid depth
Unskilled labour md 0.21 615.00 129.15 ref:-15-9-d
River bed material sqm 0.256 #REF! #REF!
#REF!
e Raod roller Charge hr 0.018 #REF! #REF! ref:-15-9-d
Cost per Sqm of 20 cm solid depth #REF!
Add Contractor's Overhead @ 15% #REF!
Cost per Sqm of 20 cm solid depth #REF!
#REF! #REF!
Distance Calculation
A Agreegate ( Khola) Rough Metalled
i Average distance from 4.00 1.00
B Cement, GI wire & Reinforcement Bar Dadeldhura Rough Metalled
i Average distance 0.00 6.00
C Sand RBM Rough Metalled
i Average distance from Quarry To site 4.00 1.00
D Boulder (Khola) Rough Metalled
i Average distance from Quarry To site 4.00 1.00
E Gravel Rough Metalled
i Average distance from Quarry To site 4.00 0.00
2 Box cutting in soft soils including disposal up to 10 m lead and 1.5 m lift. (Ref:-2-17a)
Unit- per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
UnSkill (for excavation) m. d 0.78 615.00 479.70
479.70
Adding T & P 3% 14.39
494.09
Add Contractor's Overhead @ 15% 74.11
Rate per cu m Nrs 568.20
3 Earthwork excavation in soft soils including disposal up to 10 m lead and 1.5 m lift. (Ref:-2-1)
Unit- per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
UnSkill (for excavation) m. d 0.70 615.00 430.50
430.50
Adding T & P 3% -
430.50
Add Contractor's Overhead @ 15% 64.58
Rate per cu m Nrs 495.07
4 Ditch Cutting in Hard Soilsm Disposal up to 10 m head and 1.5 lift Ref:2.12
Unit- per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
UnSkill (for excavation) m. d 1.25 615.00 768.75
768.75
Adding T & P 3% 23.06
791.81
Add Contractor's Overhead @ 15% 118.77
Rate per cu m Nrs 910.58
5 Demolishing cement Mortar Masonary wall and removing demolished materials 10 m away from site.
Unit- per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
UnSkill m. d 2.12 615.00 1,303.80
1,303.80
1,303.80
Add Contractor's Overhead @ 15% 195.57
Rate per cu m Nrs 1,499.37
Concreting (1:1.5:3) work for foundation ,vert.faces,walls (cement concrete) including supply of materials
8
& hauling etc.all complete.
(ref:- 7-2c) Unit - per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
Skilled m. d 0.80 910.00 728.00
Un Skilled m. d 7.00 615.00 4,305.00
Materials:-
Cement mt 0.40 20652.80 8,261.12
Sand cu. m 0.43 1191.41 506.34
Aggregate (5-20mm) cu. m 0.86 3965.40 3,410.24
17,210.70
Add Contractor's Overhead @ 15% 2,581.61
Rate per cu m Nrs 19,792.30
Concreting (1:3:6) work for foundation ,vert.faces,walls (cement concrete) including supply of materials
9
& hauling etc.all complete.
(ref:- 7-2c) Unit - per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
Skilled m. d 1.00 910.00 910.00
Un Skilled m. d 4.00 615.00 2,460.00
Materials:-
Cement bag 4.40 1032.64 4,543.61
Sand cu. m 0.47 1191.41 559.96
Aggregate (20-40mm) cu. m 0.65 2809.22 1,825.99
Aggregate (5-20mm) cu. m 0.24 3965.40 951.69
11,251.25
Add Contractor's Overhead @ 15% 1,687.69
Rate per cu m Nrs 12,938.93
9 Supply, cutting bending binding & placing of 10 mm dia & above Reinforcement bar
including all the materals required For it all complete. (ref:- 7-2c) Unit -- Mt.
Particulars. Unit Qty. Rate Amount
Labour :-
Skilled m. d 12.00 910.00 10,920.00
Un Skilled m. d 12.00 615.00 7,380.00
Materials:-
M.S Bar Mt 1.05 84150.00 88,357.50
Binding wire. Kg 10.00 118.00 1,180.00
total 107,837.50
107.83
Add Contractor's Overhead @ 15% 16.17
Rate per Kg Nrs 124.00
10 Making wooden forms incl. supply and selection of material fixing nailing according
to drawing in position placing separator dismelting forms and hauling up to 30 m.
For flooring and slab works ( ref. 8-2a ) Unit -- per 10 sq.m
Particulars. Unit Qty. Rate Amount
Labour :-
Skilled m. d 1.72 910.00 1,565.20
Un Skilled m. d 2.57 615.00 1,580.55
Materials:-
Kukath (6 time use = ( 0.526/6 ) cu. m 0.087 33000.00 2,871.00
Deduct scrap values 25% (-) 717.75
2,153.25
Nails kg 2.500 115.00 287.50
total 5,586.50
558.65
Add Contractor's Overhead @ 15% 83.80
Rate per sq.m Nrs 642.44
13 Earthwork in filling by transported soil with lead 4 Km and Spreading at required slope
(Ref:-1-9, 2-25a) Unit- per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
Spreading soil at required slope m. d 0.04 615.00 24.60
T&P3% 0.03 0.73
Materials:-
soil cu m 1.00 662.69 662.68
Total 688.01
Add contractor over head 15 % 103.20
Rate per cu m Nrs 791.21
14 Making rectangular gabion box ( 3.0*1.5*0.75 ) with two way knots including supply
of 10 gauge of medium coated GI wire having mess size 10cm x 10 cm .
(ref:- 16-9b) Unit- per 15.75 sq m
Particulars. Unit Qty. Rate Amount
Labour :-
Skilled m. d 0.70 910.00 637.00
unskill 0.44 615.00 270.60
Materials:-
GI wire ( 10 gauge ) kg 33.00 124.61 4,112.13
Total 5,019.73
Add contractor over head 15 % 752.95
5,772.68
Rate per sq.m Nrs 366.52
19 Filling with Excavated ordinary soils in 15cm thick layers and hand compaction , with sprinkling water.
(Ref:-2-25) Lead - 10m Unit- per cu.m
Particulars. Unit Qty. Rate Amount
Labour :-
Un Skilled m. d 0.50 615.00 307.50
307.50
T&P3% 9.22
316.72
Add Contractor's Overhead @ 15% 47.51
Rate per cu m Nrs 364.22
2 Stone Soiling
For canal 1.00 300.00 0.45 0.10
Y ESTIMATE
60.75
60.75 m3 430.50 26152.88
135.00 m3
135.00 m3 2486.65 335697.75
6.75
6.75 m3 11251.25 75945.94
651.43
930.00
1581.43 kg 107.83 170526.03
14.40
14.40 m2 558.65 8044.56
12.00
12.00
24.00 m3 13278.43 318682.32
Total 935049.47
c
Ministry of Agriculture and Livestok Development
Priminister Agriculture Modernization Project
Project Implementation Unit (Potato Super Zone), Dadeldhura
Abstract of Cost
72
Government of Nepal
Ministry of Agriculture and Livestok Development
Priminister Agriculture Modernization Project
F.Y. 077/078
Truck Analysis
Name of Project:- PMAMP,Dadeldhura
Name of work :-Chamber Box
Truck Hire Charge
Transportation cost of construction materials by 6 MT capacity truck (Ref Gon Norms 21.2)
Cost of truck (NRs ) (C) = 3200000.00 Daily wages of Driver (NRs. = 795.00
Total working period in hrs (T) = 10000.00 Daily wages of Helper (NRs. = 635.00
Rate of Tyre (R) = 21000.00 Life of tyre (hr) = 2000.00
Yearly working period in hrs (t) = 2000.00 Diesel Mobil Gear oil Grease
82.30 661.00 661.00 661.00
1. Ownership cost per Hr.
Description Formula Value Remarks
a. Depreciation cost per hr. C/T 320.00
b. Insurance cost per hr. C*0.02/t 32.00
c. Intrest per hr. C*0.01/t 16.00
Sub-Total (1) = 368.00 NRs
2. Operation cost (maintenance &consumable cost)
2.1 Maintenance cost (per hour)
a. Over hauling expense per hr. C*0.55/T 176.00
b. Operation & maintenance
cost per hr. C*0.23/T 73.60
Sub-Total (2.1) = 249.60 NRs
2.2 Consumable cost (per hour)
Materials
Description Remarks
Quantity Rate/Unit Amount
(A) Oil & lubricants cost per hr.
Diesel (lit) 5.50 82.30 452.65
Mobil (lit) 0.10 661.00 66.10
Gear oil (lit) 0.03 661.00 19.83
Grease (Kg) 0.015 661.00 9.92
Sub-Total 548.50
(B) Spare Parts
Life of tyre (hrs) (L) 2000.00
Cost of tyre (of 6 nos) 6*R 126000.00
Cost per hr Cost of tyres/L 63.00
Miscellaneous L/S 0.75
Extra L/S 0.25
Sub-Total 64.00
(C) Salaries (per hr)
Driver daily wages/8 99.375 wage/working
Helper daily wages/8 79.375 hours = 8 hrs
Loading & unloading expenses L/S 0
Sub-Total 178.75