Comments 19.07.2019

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

COLOMBO PORT CITY DEVELOPMENT PROJECT

INFRASTRUCTURE & LANDSCAPE WORK JAEQR/DR-071

Document Review
JAEQR
 
Submission Submission of spherical bearing for bridge system
 
Reference CPCC/CECB/MP/013997 Date 18th July, 2019
CPCC Received
Type/ RB02/RB04 Bridge pier
Structure
Review Document: RB02/RB04 Bridge pier bar bending schedule

Doc. No: Date/s Reviewed: 18th July, 2019


Our reviews and comments of the above proposal done as per the relevant technical specification document
and drawings.

1). Shear hooks (308) was used instead of rectangular shear links (307 &308) given by the designer. However,
shape of the link given in the designers drawing does not match with the geometry of the section D. Therefore,
JAEQR has no objection for changing the shape of link. Also, number of hooks provided in section D is more
than required amount. However, this link arrangement should be approved by the designer.

2). Bar no 302 (Short bar) in design drawing is missing.

3). Bar no 302 (Long bar) is needed to be staggered according to the designer.

4). No Starter bars were included for the bearing pads.

5). Check the number of bars for bar mark 302 and 350.

6). Check the shape of link 355, C and D parts should be curved.

Hence, provided technical details of Bridge pier bar bending schedule (Vehicular Bridge RB02) according to the
BS 8666:2000 are insufficient.
Please adhere the following Notes,

1. Please refer the Shop drawing no. CPCDP-CHEC-SBR-RB02-DR-C-0002/0003(14/06/2019) and


Construction drawing no. CPCDP-CHEC-SBR-RB00-DR-C-1012 Revision C2(22/04/2019).
2. Sample Reinforcement shall be fabricated in bulk for each batch and shall be checked for the actual site
measurement before fabricating.
3. Any irregularities appear in the bar schedule and the erection at the site shall be noticed to the designer
before review.
4. Provided bar bending schedule were checked according to Construction drawing no. CPCDP-CHEC-SBR-
RB00-DR-C-1012 Revision C2(22/04/2019) at site.

Consent without Consent with comments 1) No Consent 3)


comments X
2)
  Consent with comments  
1) Comments to be addressed in official response and/ or update of submission  
2) No official response and/or update of submission required  
3) Comments to be addressed in full resubmission  
                         
Reviewed by:   Checked by:
Eng. D.D. Wijesinghe Eng. G.H.L. Kumarasiri
Resident QR Engineer-Civil   Team Leader-JAEQR