WEEKLY SCHEDULE REPORT


Plan % Area
PH-7 : New Projct PVC-5 Cata House
Actual 74.41 % PV-4

Almuzorin Ph-7 Team

No Job Description Detail Progress April May


Plan Actual (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Installation ACU A&B 100
a. Mobilization Tools and Material 100
b. Work Preparation 100
- Site Introduction 100
- Tools and Equipment Preparation 100
1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
c. Alignment ACU A&B 100
- Base Skid Installation 100
- Tighten Base skid bolt and nut to ACU 100
- Centering and Levelling ACU A&B 100
- Driling : Support Base Skid on Base Floor 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Installation Panel & Support Panel 100
a. Setting Panel Support and Marking Position 100
b. Drilling : Fixed Panel Support Position. 100
2
c. Setting Support JB Box and Marking Position 100
d. Drilling : Fixed Support JB Box Position 100
e. Install Panel 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Installation Ladder Tray Pipe and Cable Outdoor 100.0
a. Drilling Support Tray 100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
3
b. Cutting and Grinding Tray 100
c. Tightening Tray Bolt and Nut 100
d. Install Ladder Tray Pipe and Cable 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Installation Ceiling Indoor Insulation 100.0
a. Insulation Wall Indoor Material Mobilization DONE
b. Work Preparation DONE
4 c. Installation Ceiling Insulation 100.0
- Installation Support Hanger Ceiling 100
- Installation Hanger Ceiling 100
- Installation Ceiling PU (Skin 1 mm) 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Installation Swing Door 100.0
a. Inside Door Installation
5
- Install Sub Frame Inside Door 100
- Install Door 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Installation Wall Indoor Insulation 100.0
a. Wall Side 100.0
- North Side 100
- East Side 100
6 - South Side 100
- West Side 100
b. Partition ; Wall devide 100
b. Join Corner Corner Connection 100
c. Gluing Wall Connection 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
7 Floor Insulation Installation 100.0

8 Floor Cementing (ASC)

9 Make Pipe and Cable Access to Indoor 100.0

10 Make Drain Pipe Access to Indoor 100.0


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Pipe Installation 85.0
a. Outdoor Pipe Installation 100
- Setting Pipe Line 100
- Joint Piipe Line Connection (Brazing) 100
11

b. Indoor Pipe Instalation 70


- Setting Pipe Line 100
- Joint Pipe Line Connection Brazing 40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
FCU Installation 100.0
a. Install FCU Support 100
12 b. Install FCU :Alignment & Levelling 100
c. Pipe Line Joint Connection (Brazing) 100
d. Install Drain Pipe 100

Internal Test 40.0


a. Flushing Pipe Line 100
13
b. Leak Test 20
c. Vaccump Refrigeration Line Pipe
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Cable Installation 40.0
14 a. Setting Cable Position 50
b. Connecting Cable 30

Accessories Installation 0.0


a. JB Transit
15 b. Lamp Room
c. Alarm Room
d. JB TE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Commissioning 0.0
a. Charging refrigerant
16
b. Running System
c. Take Data System

17 Hand Over

: OFF
: Execution
: Planning