Professional Documents
Culture Documents
RRU3804&RRU3801E&RRU3806 Installation Guide (V200 - 11)
RRU3804&RRU3801E&RRU3806 Installation Guide (V200 - 11)
U3806
V200
Installation Guide
Issue: 11
Date: 2011-02-15
R bb h
Rubber hammer C i ing
Crimp i pliers
li Wi stripper
Wire ti
Adjustable wrench
G
Guarded blade utility knife
f Wi e cutter
Wire tt (with the diameter of at least 32 mm)
Torque wrench
5mm
M
M3~M6 Combination wrench
(21mm~21mm) for pole installation
Level
Torque screwdriver (17mm~17mm) for wall installation
Markking pen
(with the diam
meter of no more
Multimeter Measuring tape
than 10 mm)
2
Installation Modes
On a metal pole (three On a metal poole (four On a metal pole (six centralized RRUs)
centralized RRUs) centralized RR
RUs)
3
Dimensions and Installation Clearance
a Dimensions of the RRU b Recommended Clearance for a
Single RRU
485 mm
≥500 mm
300 mm
To
op view Side view
A
Auxiliary metal pole
400 mm 280 mm
300 mm
Top view
100 mm 400 mm
280 mm
600 mm
Main metal Auxiliary
Main metal pole pole metal pole
4
Dimensions and Installation Clearance
e f
Recommended Clearance for Minimum Clearance for Multiple
Multiple Centralized RRUs Centralized RRUs
200 mm
≥300 mm
Top view
300 mm
300 mm
≥500 mm
300 mm
600 mm
i
Recommended Vertical Spacing for
Two RRUs Installed in Parallel j Minimum Vertical Spacing for Two
RRUs Installed in Parallel
≥300 mm 200 mm
≥500 mm 300 mm
≥500 mm 300 mm
5
Requirements for Installatio
on Support Structure
The following
g figure
g describes the specifications
p for the metal
m pole,, angle
p g steel,, and U-steel where the RRU is
installed.
60 mm to 114 mm
63 mm to 80 mm
0 mm to 50 mm
(The recommended value is 80 mm.)
30
50 mm to 100 mm
63 mm to 80
8 mm
Metal pole Angle ste
eel U-steel
z If the diameter of a pole ranges from 60 mm to 76 mm, a maximum of two RRUs can be installed on the pole
and the side-mounted installation is not recommended. Iff the diameter of a pole ranges from 60 mm to 76 mm,
a maximum of three RRUs can be installed on the pole and
a the side-mounted installation is recommended.
z It is recommended that only one RRU be installed on a U-steel or an angle steel.
z When installed on a tower, only one RRU can be installed in standard mode or reverse mode. Two RRUs
cannot be installed one a pole in back-to-back mode, and
d the brackets for more than two RRUs cannot be
combined.
z A single RRU can be bound and lifted to a tower. For details,
d see page 31 "Lifting the RRU and Installation
C
Components to the
h T Tower.""
RRU
The angle between
the vertical and the
angle steel or U-
Angle steel steel or angle steel
≤10° where the RRU is
or U-steel
installed must be
less than or equal to
10 degree.
The brackets cannot be
combined when the RRUss
are installed on the wall.
6
Installation Procedure
Dual-nut bolt
Main bracket
7
Installing the RRU on a Mettal Pole
a Installing a Single RRU on a Metal Pole
1200 mm~1600 mm
You may fit one end of the auxiliary bracket on one duual-nut bolt assembly and then the other end on the
other dual-nut bolt assembly during the installation.
3. Install the RRU on the main bracket. When you hear click sound, you can infer that
the RRU is in p position.
8
Installing the RRU on a Mettal Pole
b Installing Two RRUs Back-To-Back
k on a Metal Pole
1. Install an RRU. For details, see page 8 2. Install the main fixture for another RRU.
Installing a Single RRU on a Metal Pole.
M6X16
5N•m
Cabling cavity
9
Installing the RRU on a Mettal Pole
c Installing Multiple RRUs in Ceentralized Mode
1. Install the main fixture and the auxiliary fix
xture. For details, see page 8
Installing a Single RRU in Ordinary Mode.
M6X16
5N•m
5. Fit the tabs on the attachment plate of 6. Install the third RRU.
the second RRU into the anchor slots on
the second main fixture.
10
Installing the RRU on a Mettal Pole
c Installing Multiple RRUs in Ceentralized Mode
7. Install the fourth main fixture. 8. Fit the tabs on the attachment plate of
8
the fourth RRU into the anchor slots on
the fourth main fixture.
9. Four RRUs installed in centralized mode. 10. Six RRUs installed in centralized mode.
11
Installing the RRU on a U-S
Steel
Plan view
U-steel
Plan view
Angle steel
z The procedure for installing the RRU on an angle steel is the same as that for installing the RRU on a metal
pole.
z It is recommended that only one RRU be installed on an
a angle steel.
12
Installing the RRU on a Wall
1. Place the auxiliary bracket at the installatio
on position. Use a level to check that the
auxiliary
y bracket is p
placed horizontally.
y Then n, mark the anchor ppoints byy using
ga
marking pen.
128 mm
Auxiliary bracket
M10x65 bolt
Spring washer 10
Plastic tube
Ø14
Flat washer 10
Expansion tube
90°
55 mm to 60 mm
Do not hammer the bolt entirely into the
wall. Instead, leave 20 mm to 30 mm of
the bolt outside the wall.
20 mm to 30 mm
After the expa
ansion bolt is removed,
dispose of the
e plastic tube.
13
Installing the RRU on a Wall
3. Fit the auxiliary bracket on the expansion
n 4. Install the main bracket.
bolts downward, and then tighten the bolts
by using a combination wrench 17 mm.
M10
30N•m
14
Installing the RRU on a Wall
6. Install multiple RRUs.
Recommended Clearance :
≥760 mm ≥760 mm
Minimum Clearance:
560 mm 560 mm
≥70 mm ≥70 mm
15
Installing the Cables of the RRU
a Cable Connections of a Singlee RRU
PGND cable
DC RRU power cable
RRU RF jumper
Feeder
AISG multi
multi-wire
wire cable between the RRU and the RCU
AISG extended cable between the RRU and the RCU
CPRI optical cable Start
DC RRU alarm cable
Antenna
Install the PGND cable
IInstall
t ll the
th DC RRU
power cable
RCU
End
BBU
External
power supply
16
Installing the Cables of the RRU
b Connections of Two RRUs Caables
PGND cable
DC RRU power cable
RF cable between RRUs
CPRI optical cable
Antenna
Start
AISG multi-wire
multi wire cable
between the RRU and the
RCU(optional)
The above figure shows the scenario where the RRU uses the CPRI optical cable and interconnect jumper.
The CPRI optical cable is used for RRU cascading.
Determine the routing of CPRI optical cables accordin
ng to site requirements.
17
Installing the Cables of the RRU
c Cable List
Cable Connector Type Co
onnected to...
PGND cable OT or 2-hole terminal (M6) Gro
ounding bolt on the RRU
RRU RF DIN connector Porrts labeled ANT_TX/RXA and ANT_RXB at the bottom of
jumper the RRU
CPRI optical DLC connector Connnect the fiber tails labeled 1A and 1B to the CPRI_W
cable portt on the RRU.
Con
nnect the fiber tails labeled 2A and 2B to one of the
CPR
RI0 to CPRI2 ports on the WBBP.
18
Installing the Cables of the RRU
c Cable List
Cable Connector Type Connected to...
AISG multi- Waterproof DB9 Port labeled RET at the bottom of the RRU
wire cable connector
between the
Standard AISG female Standard AISG male connector of the AISG
RRU and the
connector extension cable or RCU
RCU
AISG extended Standard AISG male Standard AISG female connector of the AISG
cable between connector multi-wire cable
the RRU and
Standard AISG female Standard AISG male connector on the RCU
the RCU
connector
The figures are for illustration purposes only and mayy not reflect actual cables.
19
Installing the Cables of the RRU
d Opening the Cover Plate of th
he RRU Cabling Cavity
M4
20
Installing the Cables of the RRU
f Cable Connections on the RR
RU
CPRI optical
cable
Grounding bolt
OT terminal
PGND cable
Shielding layer of
the power cable
DC RRU
power cable
Waterproofing
filler
21
Installing the Cables of the RRU
h RRU+BBU Installed Against thhe Wall
z When connecting the DC RRU power cable to the DC CDU-03B you must add an OT terminal to the shielding
layer. Then, fix the OT terminal to the corresponding GND terminal of the DCDU-03B. For details on how to
add an OT terminal, see page 33 "Adding OT Terminals to the Shielding Layer of the DC RRU Power Cable."
z The DC RRU power cable is connected to one of the L
LOAD0 to LOAD5 terminals of the DCDU
DCDU-03B.
03B.
22
Installing the Cables of the RRU
i RRU+OMB
LOAD0
The DC RRU power cable is connected to one of the LOAD0 to LOAD5 terminals of the DCDU-03B.
DCDU 03B
23
Installing the Cables of the RRU
j RRU+APM30/APM30H (Ver.A))
LOAD4
z The DC RRU power cable is connected to one off the LOAD4 to LOAD9 terminals of the PDU.
z Strip the jacket of the DC RRU power cable for a small part, press the exposed shielding layer on the
strap, and then connect the PGND cable on the stra
ap to the nearest grounding bolt on the side in the
APM30/APM30H(Ver.A).
24
Installing the Cables of the RRU
k RRU+APM30(+24V) / APM30H
H(Ver.B, +24V)
LOAD0
25
Installing the Cables of the RRU
l RRU+APM30H (Ver.B)
RRU0
z The DC RRU power cable is connected to one off the RRU0 to RRU5 terminals of the EPS.
z Strip the jacket of the DC RRU power cable for a small part, press the exposed shielding layer on the
strap, and then connect the PGND cable on the stra
ap to the nearest grounding bolt on the side in the
APM30H(Ver.B).
26
Installing the Cables of the RRU
m RRU+TMC
LOAD0
27
Installing the Cables of the RRU
n RRU+TMC11H(Ver.A) / TMC11
1H(Ver.B)
LOAD0
28
Checking the RRU Hardwarre Installation
SN Item
3 The cover plate is securely insttalled on the cabling cavity of the RRU.
10 Labels are correct, legible, and complete on both ends of each cable.
29
Powering On the RRU
The power switch must be set to OFF. Then, check the input voltage and ensure that the voltage ranges
from -36 V DC to -57 V DC if -48 V DC power is supp
plied or 150 V AC to 300 V AC if AC power is supplied.
Start
Check whether
the status of the RUN LED
is 1s ON, 1s OFF and that of N
No
ALM LED is OFF.
Yes
End
30
Appendix
a Lifting the RRU and Installatioon Components to the Tower
1. Bind the RRU by leading the lifting rope along the lower part of the adapting piece and
through the handle, bind the main and auxilia ary brackets with the lifting rope, and then
bind the steering rope with the handle of the RRU, as shown in the following figures.
Liifting rope
Steering rope
Lowe
er part of the
adap
pting piece
z When lifting the RRU and installation components to the tower, Do not bind the lifting rope
prevent the RRU from colliding with the tower
tower. only on the handle when
z Lift the RRU to the tower before it is installed on the metal
m pole, lifting the RRU.
angle steel, or U-steel.
Pulley
z Installer A climbs onto the tower. Then, installer
A fixes the pulley to the support of the tower
platform and leads the lifting rope through the
pulley.
z Installer C uses a lifting rope to bind the RRU
and installation components as shown in the
preceding figure and then ties a knot in the steering
Steering rope rope at the
h h handle
dl off the
h RRU
RRU.
z Installer B pulls the lifting rope, and at the same
time, installer C pulls the steering rope away from
the tower to prevent the RRU and installation
Lifting rope components from colliding with the tower.
z Installer A holds the RRU and installation
components and untie the ropes.
z The procedure for hoisting the RRU and auxiliary
components onto the tower is for your reference
y
only.
31
Appendix
b Adding OT Terminals to the DC RRU power Cable of the RRU
Adding the OT terminals to the DC RRU po
ower cable involves adding OT terminals to
the RRU power cable and adding OT terminnals to the shielding layer of the DC RRU
power cable.
Label for preparing
-48V DC power cable NEG ( - ) the power cable
OT
T terminals
15 mm
32
Appendix
c Adding OT Terminals to the Shieldiing Layer of the DC RRU Power Cable
WARNING
Do not damage the shielding layer of the power cable when
w cutting around the jacket.
33
Appendix
d Waterproofing Outdoor Cables
tie
34
Appendix
f Pin Assignment for the Wires of the Alarm Cable
X1.2 X2 SWITCH_INPUT0+
+ White/Blue Twisted SWITCH_INPU
pair
p T0+
X1.6 X4 SWITCH_INPUT1+
+ White/Orange Twisted SWITCH_INPU
pair T1+
X.Shell - - - Shield -
35
Change History
This part describes the changes in the RRU3804&RRU3801E&RRU3806
R
I t ll ti G
Installation Guide.
id
z11 (2011-02-15)
This is the eleventh commercial release.
Compared with issue 10 (2010-12-30) , this issue modified some descriptions.
z10 (2010-12-30)
(2010 12 30)
This is the tenth commercial release.
Compared with issue 09 (2010-11-10) , this issu
ue modified some descriptions.
z09 (2010-11-10)
This is the ninth commercial release.
Compared with issue 08 (2010-07-15) of V200, the descriptions of the requirements for the
recommended diameter of the metal pole and the handling of the dustproof caps on the RF
ports are added.
z08 (2010-07-15)
This is the eighth commercial release.
Compared with issue 07 (2010-06-05) of V200, the figure of the minimum clearance for RRU
are optimized, and the minimum clearance for the
t RRU installed on a tower requirements is
added.
added
z07 (2010-06-05)
This is the seventh commercial release.
Compared with issue 06 (2010-03-05) of V200, the figure of the adapting piece for the RRU is
changed, and the description on the recommen
nded and minimum installation clearance
requirements is added.
z06 (2010-03-05)
This is the sixth commercial release.
Compared with issue 05 (2009-12-10) of V200, the description on the cross-section area of the
RRU power cable is added.
z05 (2009-12-10)
This is the fifth commercial release
release.
Compared with issue 04 (2009-09-25) of V200, the installation scenarios of APM30H(Ver.B),
APM30H(Ver.B, +24V), TMC11H(Ver.B) are ad dded.
z04 (2009-09-25)
This is the fourth commercial release.
Compared with issue 03 (2009-06-30) of V200, the requirements for installation support
str ct re are modified
structure modified.
36
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Industrial Base Bantian Longgang
Sh
Shenzhen
h 518129
People’s Republic of China
www.huawei.com