SERVICES TENDER BOARD APPROVAL

GENERAL LABOUR RATES FOR PROPOSED NEW COAT COMPLEX AT THELDENIYA

Site No. 2336 15 June 2021

Description Unit Rate


Considering the floor height and work interruptions due to the current pendamic situations, special
and reasonable rates are recommended for the following items. Rates effects from 1st January 2021.
Formwork to sides of column in all floors (Ground to 4th floor level) (floor-to-floor
m2 725.00
height 4.50m)

Ditto- to sides and soffit of beams in all floor levels (Ground to 4th floor level) (floor-
m2 725.00
to-floor height 4.30m)

Ditto- to soffit of slab in all floor levels (Ground to 4th floor level) (floor-to-floor
m2 725.00
height 4.50m)

Ditto- to sloping soffit of staircase/soffit of landing/sides of risers/edge of the


sloping slabs in all floor levels (Ground to 4th floor level) (floor-to-floor height m2 750.00
4.50m)

…………………… …………………… …........................


MANAGER (C) CEst SPM / RPM / RA

…........................
Cc: DATE
1. SPM/RPM/RA
2. Estimate Division
3. Contracts & Planning
4. Billing Section