Date: Thursday, 22 July 2021

WEEKLY ACCOMPLISHMENT REPORT Project:


Particulars:
CHS - SA 10 Units Work Package
Work Package 2 - CW + ST Works
Period: 2021.07.12 - 2021.07.17

BLOCK 7 LOT 23
Monday Tuesday Wednesday FAIR
Manpower Report RAINY BUT WORKABLE
RAINY AND UNWORKABLE
5
4
3
2
A.M
1 Thursday Friday Saturday
0 PM

Foreman Skilled Workers Helper


48.00 Total Workable Hours
- Total Unworkable Hours
Date: Thursday, 22 July 2021

WEEKLY ACCOMPLISHMENT REPORT Project:


Particulars:
CHS - SA 10 Units Work Package
Work Package 2 - CW + ST Works
Period: 2021.07.12 - 2021.07.17
Details of Work Accomplishment
ITEM DESCRIPTION QTY UNIT Previous This Date To Date Target REMARKS
A1000 Formworks Fabrication 83.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1030 Footing - Rebar Works Assembly 25.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1070 Installation of Electrical Rough-ins on Slab 2F 20.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1120 Installation of Sewerline Rough-ins on Slabs GF 5.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1430 Column GF - Rebar Works Assembly 77.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1460 Slab GF - Rebar Works Assembly 13.00 Man-Hours - - 0.00% 100.00% -
A1470 Beam 2F - Rebar Works Assembly 95.00 Man-Hours 50.00% 50.00% 100.00% 100.00% - substantially completed
A1480 Slab 2F - Rebar Works Assembly 16.00 Man-Hours - 100% 100.00% 100.00% - substantially completed
A1490 Wall Footing - Rebar Works Assembly 22.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1500 Column 2F - Rebar Works Assembly 45.00 Man-Hours - - 0.00% 100.00% -
A1510 Beam Roof - Rebar Works Assembly 47.00 Man-Hours - - 0.00% 100.00% - substantially completed
A1520 Footing - Rebar Works Fixing & Installation 18.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1530 Column GF - Rebar Works Fixing & Installation 53.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1540 Slab GF - Rebar Works Fixing & Installation 10.00 Man-Hours 0.00% 100.00% 100.00% 100.00% - substantially completed
A1550 Beam 2F - Rebar Works Fixing & Installation 80.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1560 Slab 2F - Rebar Works Fixing & Installation 12.00 Man-Hours - 100.00% 100.00% 100.00% - substantially completed
A1570 Wall Footing - Rebar Works Fixing & Installation 96.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1580 Column 2F - Rebar Works Fixing & Installation 32.00 Man-Hours - - 0.00% 100.00% -
A1590 Beam Roof - Rebar Works Fixing & Installation 40.00 Man-Hours - - 0.00% 100.00% -
A1600 Column GF - Formworks Installation 75.00 Man-Hours 100.00% 100.00% 100.00% - substantially completed
A1610 Slab GF - Formworks Installation - Man-Hours - - 0.00% 100.00% -
A1620 Beam 2F - Formworks Installation 92.00 Man-Hours - 100.00% 100.00% 100.00% - substantially completed
A1630 Slab 2F - Formworks Installation 138.00 Man-Hours - 100.00% 100.00% 100.00% - substantially completed
A1650 Column 2F - Formworks Installation 51.00 Man-Hours - - 0.00% 100.00% -
A1660 Beam Roof - Formworks Installation - Man-Hours - - 0.00% 100.00% -
A1670 Footing - Mixing, Pouring & Curing of Concrete 25.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1680 Column GF - Mixing, Pouring & Curing of Concre 34.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1690 Slab GF - Mixing, Pouring & Curing of Concrete 73.00 Man-Hours - - 0.00% 100.00% -
A1700 Beam 2F - Mixing & Pouring of Concrete 38.00 Man-Hours - 100.00% 100.00% 100.00% - substantially completed
A1710 Slab 2F - Mixing & Pouring of Concrete 104.00 Man-Hours - 100.00% 100.00% 100.00% - substantially completed
A1720 Wall Footing - Mixing & Pouring of Concrete 20.00 Man-Hours 100.00% - 100.00% 100.00% - substantially completed
A1730 Column 2F - Mixing & Pouring of Concrete 21.00 Man-Hours 0.00% - 0.00% 100.00% -
A1740 Beam Roof - Mixing & Pouring of Concrete 19.00 Man-Hours - - 0.00% 100.00% -
A1750 Column GF - Stripping of Forms 30.00 Man-Hours 50.00% - 50.00% 100.00% - on going with production
A1760 Slab GF - Stripping of Forms - Man-Hours - - 0.00% 100.00% -
A1770 Beam 2F - Stripping of Forms 29.20 Man-Hours - - 0.00% 100.00% -
A1780 Slab 2F - Stripping of Forms 43.80 Man-Hours - - 0.00% 100.00% -
A1800 Column 2F - Stripping of Forms 21.00 Man-Hours - - 0.00% 100.00% -
A1810 Beam Roof - Stripping of Forms - Man-Hours - - 0.00% 100.00% -
A1820 Installation of Sewerline Rough-ins on Slabs 2F 5.00 Man-Hours - - 0.00% 100.00% -
KEYPLAN Saturday, 10 July 2021 Saturday, 17 July 2021
WF
WF

WF

WF WF
WF
WF

WF
WF

WF
WF
WF
Date: Thursday, 22 July 2021

WEEKLY ACCOMPLISHMENT REPORT Project: CHS - SA 10 Units Work Package


Particulars: Work Package 2 - CW + ST Works
Period: 2021.07.12 - 2021.07.17
KEYPLAN Saturday, 10 July 2021 Saturday, 17 July 2021

F1 F1

F1 F1 F1

F1 F2

F1 F2

F3

KEYPLAN Saturday, 10 July 2021 Saturday, 17 July 2021


SC
C1 SC

SC

C1 C1
C1

C1 C1
SC

C2

KEYPLAN Saturday, 10 July 2021 Saturday, 17 July 2021

SC

Prepared By: Reviewed & Noted By:

Ericson G. Laab Engr. Jay Angelo B. Mallillin, MsCE, PMP


Project Control Assistant Head, Planning & Design

Assisted & Verified by: Received By:

Engr. Emerson P. Mendoza


Project Engineer