DAILY WELL SERVICE OPERATION REPORT

DATE : 31 December 2020 RIG : IDB-ADI# 03 RT : CSG SIZE : 10-3/4", 40.5 ppf TD : 600 ft
FIELD AND WELL NO : BTG # 43 GL : TBG SIZE : 3-1/2" PBTD : 447 ft
PROGRAM NUMBER : BC043PHES2020-113 WELL HEAD TYPE : GREY (11" 2K BTTM FLG X 7-1/16" 2K TOP FLG) FLANGE SIZE : 7-1/16" X 2K
CHARGE TO : EOS-1300 DOWNHOLE EQP : PCP ASSY 39 - 750 ( SN OH - OH 43930704 ) TBG : 12 jts
PRIMARY JOB : PUMP RECONDITION - BAIL OUT SAND
RIG DAYS CODE MOVE OPRT SWOWS NPT UNPAID TIME DESCRIPTION OF OPERATIONS
EST 3,4 DAYS 4,0 00:00-04:00 * CONTINUE MOVE OUT RIG AND EQUIPMENT FROM BTG # 02 TO BTG # 43 USED BY 1 TANDEM AND 1 LOWBOY
ACT 1,08 DAYS 1,0 04:00-05:00 * SET LOADING RAM TO SPOTTED RIG CARRIER & R/U RIG COMPLETED @ BTG#43
RIG COST 0,5 05:00-05:30 * DISCONNECTED ELECTRIC SYSTEM DRIVE HEAD TO SWITCH BOARD AND N/D DRIVE HEAD
EST Rp286.652.800,00 1,0 05:30-06:30 * RECIPROCATTED ROTOR STUCK -OK, L/D 1-1/4" POLISHED ROD + 2 PCS PONY ROD ( 2 ft + 4 ft ) AND POOH W/ 1 PC ROTOR 23-750 DK
ACT Rp81.738.475,00 ON 14 JTS 7/8" X 25' S.ROD GOT OVERPULL 14 KLBS
DRAWING 0,5 06:30-07:00 * N/D ITBOP PCP AND PRODUCTION LINE
0,5 07:00-07:30 * HANDOVER JOB AND TGSM
2,0 07:30-09:30 * N/U 11" ANNULAR BOPE AND FUNCTION TEST - OK + DRIPPAN + WPF + TBG TOOLS
0,5 09:30-10:00 * L/D 7" TBG HANGGER + 1 JT 3-1/2" EUE TBG AND POOH W/ 7" TORQ ANCHOR + TAG BAR + PCP STATOR 39-750 ON 11 JTS 3-1/2" EUE TBG +
158'
o
160' 1 PC PUP JOINT ( 4 ft )
0,5 10:00-10:30 * RIH W/ 7" CSG SCRAPPER ON 13 JTS 3-1/2" EUE TBG TAG @ 402 ft ( SAND FILL 44 FT )
174' 0,5 10:30-11:00 * FILL UP AND PRESSURE TEST ALL JOINT TBG W/ RIG PUMP 300 PSI HOLD 10 MNT-OK
190' 1,0 11:00-12:00 * POOH W/ 7" CSG SCRAPPER ON STRING TO SURFACE
200' 0,5 12:00-12:30 * RIH W/ 3-1/2" MOLE SHOE ON 12 JTS 3-1/2" EUE TBG, SET @ 389 FT
202'
1,0 12:30-13:30 * N/U TRIPPING HEAD + KING SWIVEL
209'
1,0 13:30-14:30 * SET AND RIG UP FOAMING UNIT PT.UMB CREW
222'
2,0 14:30-16:30 * CONDUCTED INJECTION FOAMING F/ 402 FT - 423 FT
289'
305' 0,5 16:30-17:00 * N/D TRIPPING HEAD + KING SWIVEL
1,0 17:00-18:00 * ADD 1 JTS 3-1/2" EUE TBG, SET @ 420 FT AND N/U TRIPPING HEAD + KING SWIVEL
316'
318' 1,0 18:00-19:00 * RE-INJECTION FOAMING FROM 423 FT - 447 FT
322' 0,5 19:00-19:30 * HANDOVER JOB AND TGSM
336'
1,0 19:30-20:30 * CONTINUE RE-INJECTION FOAMING FROM 423 FT - 447 FT
0,5 20:30-21:00 * SAND SATTLE AND CHECK TOS, TAG @ 447 FT (NO SANDFILL)
346'
384' 1,0 21:00-22:00 * RIG DOWN FOAMING UNIT BY PT.UMB CREW
1,0 22:00-23:00 * N/D KING SWIVEL + TRIPPING HEAD
394'
402' 0,5 23:00-23:30 * POOH W/ 3-1/2" MOLE SHOE TO SURFACE
0,5 23:30-24:00 * PJSM GTE - NOV , RE-RIH W/ 1 PC PCP STATOR 39 - 750 ( SN OH - OH 43930704 ) + 7" X 3-1/2" TORQ ANCHOR + 1 PC TAG BAR ON
436'
442'
1 PC PUP JOINT ( 4 ft ) + 11 JTS 3-1/2" EUE TBG AND INSTALLED 7" TBG HANGER, STATOR SET @ 377,95 ft , BTTM TORQ ANCHOR @ 379,95 ft
TOC
447'
450'
495'

511'
NEXT STEP : N/D TBG TOOLS + WPF + DRIPPAN + 7-1/16" X 3K BOPE
518'

524'
548'