Professional Documents
Culture Documents
Technical Proposal - Downtown Views II R.3 - SECURED
Technical Proposal - Downtown Views II R.3 - SECURED
TABLE OF CONTENTS
SCHEDULE A1: Preliminary Programme
1. Programme of Works……………………………………………………………………..….006
2. Manpower Histogram……………………………………………………………………..….088
3. Cash Flow…………………………………………………………………………………......090
Page 2 of 736
Section 4 – Detailed Method Statement
3.1 Survey Works……………………………………………………………….………..….317
3.2 Earth Works…………………………………………………………………….…..…...322
3.3 RC Works……………………………………………………………………….…...…..325
3.4 Post Tensioning Works………………………………………………………….…...…335
3.5 Fit Out & Finishes…………………………………………………………………........342
3.6 Façade Works…………………………………………………………………….….....350
3.7 MEP……………………………………………………………………………….….….369
3.8 External Works………………………………………………………………….……....403
Page 3 of 736
SCHEDULE A16: Contractor’s Company Particulars
1. Sponsor, Registration & Licensing…………………………………………………..….…551
2. Company Information………………………………………………………………............576
3. Company Size & Structure…………………………………………………………..……..580
4. Financial Bank Details…………………………………………………………………..…..590
5. Client References…………………………………………………………………….....…..695
6. Computer & Office Equipment……………………………………………………........….699
Page 4 of 736
SCHEDULE A1
Preliminary Programme
Page 5 of 736
DOWNTOWN VIEWS II
Plot 3370587 Zabeel 2nd Dubai, UAE
1. PROGRAMME
This section will give an overview of the proposed construction programme for the main
works of “Downtown Views II” project.
We are pleased to submit our Outline Programme for your consideration. We have
developed this Programme having reviewed all the project information received to date, site
visit(s) and discussions with trade sub‐contractors.
We would like the opportunity to present and discuss our proposals with the Client and
his Representative and agree on a mutually acceptable programme for all parties during the
Adjudication Stage.
Page 6 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Site Facilities & Preliminary Works 44 14-May-18 05-Jul-18 05-Jul-18, Site Facilities & Preliminary Works
Initial Deliverables
Deliver 48 15-May-18 11-Jul-18 11-Jul-18, Initial Deliverables
Structural W
Works 519 20-Jun-18 05-Mar-20 05-Mar-20, Structural Works
Page 7 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Mock Up Ap
Apartment 60 05-Dec-18 02-Feb-19 02-Feb-19, Mock Up Apartment
Page 8 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Facade/Envelope/Roof Works
Facade/Enve 502 20-Feb-19 18-Oct-20 18-Oct-20, Facad
Authority Approval
Appr s 472 08-Sep-19 23-Dec-20 2
Testing & Commissioning
Com 217 05-Apr-20 23-Dec-20 2
Snagging & De-Snagging
De 60 13-Oct-20 23-Dec-20 2
Structural W
Works 494 20-Jun-18 05-Feb-20 05-Feb-20, Structural Works
Page 9 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Page 10 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Facade/Envelope/Roof Works
Facade/Enve 468 03-Mar-19 19-Sep-20 19-Sep-20, Facade/Envel
Page 11 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Authority Approval
Appr s 448 08-Sep-19 29-Nov-20 29-Nov
Testing & Commissioning
Com 221 05-Mar-20 28-Nov-20 28-Nov
Snagging & De-Snagging
De 60 23-Sep-20 03-Dec-20 03-De
Structural W
Works 444 20-Jun-18 08-Dec-19 08-Dec-19, Structural Works
Page 12 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Finishing & MEP Installations 510 24-Nov-18 01-Aug-20 01-Aug-20, Finishing & MEP Installati
Facade/Envelope/Roof Works
Facade/Enve 414 07-Mar-19 18-Jul-20 18-Jul-20, Facade/Envelope/Roof Works
Authority Approval
Appr s 382 08-Sep-19 24-Sep-20 24-Sep-20, Authority Ap
Testing & Commissioning
Com 211 07-Jan-20 17-Sep-20 17-Sep-20, Testing & Com
Snagging & De-Snagging
De 60 14-Jul-20 26-Sep-20 26-Sep-20, Snagging &
Structural W
Works 294 15-Aug-18 05-Aug-19 05-Aug-19, Structural Works
Page 13 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Summary
Tender Programme 07-Mar-18
Finishing & MEP Installations 441 13-Apr-19 27-Sep-20 27-Sep-20, Finishing &
Facade/Envelope/Roof Works
Facade/Enve 108 17-May-20 27-Sep-20 27-Sep-20, Facade/Env
Authority Approval
Appr s 366 22-Dec-19 22-Dec-20 2
Testing & Commissioning
Com 153 15-Jun-20 16-Dec-20 16
Snagging & De-Snagging
De 60 08-Oct-20 19-Dec-20 19
Page 14 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Critical Path
Tender Programme 07-Mar-18
DVMESP0010 Site Survey & Report, Setting Out 6 14-May-18 20-May-18 Site Survey & Report, Setting Out
DVMESP0020 Site Clearance 12 21-May-18 03-Jun-18 Site Clearance
DVMESP0030 Set up Temporary Site Utilities 32 28-May-18 05-Jul-18 Set up Temporary Site Utilities
918 20-Jun-18 23-Dec-20 2
Construction
Constructio
Tower 1 918 20-Jun-18 23-Dec-20 2
Structural W
Works 504 20-Jun-18 17-Feb-20 17-Feb-20, Structural Works
Page 15 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Critical Path
Tender Programme 07-Mar-18
Page 16 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Critical Path
Tender Programme 07-Mar-18
Page 17 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Critical Path
Tender Programme 07-Mar-18
Authority Approval
Appr s 113 01-Sep-20 23-Dec-20 2
DEWA Electrical
Electric 28 01-Sep-20 29-Sep-20 29-Sep-20, DEWA Ele
LV Side 28 01-Sep-20 29-Sep-20 29-Sep-20, LV Side
DVT1AA0260 Substantial LV installations as per DEWA Approved Drawings 0 01-Sep-20 Substantial LV installations as
Page 18 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Critical Path
Tender Programme 07-Mar-18
Page 19 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
DVAA000130 Construction NOC for Plumbing System 48 19-Aug-18 29-Oct-18 Construction NOC for Plumbing System
DVAA000140 Construction NOC for Drainage Systems 48 19-Aug-18 29-Oct-18 Construction NOC for Drainage Systems
DVAA000150 Construction NOC for LV Shop Drawings 48 30-Aug-18 06-Nov-18 Construction NOC for LV Shop Drawings
DVAA000160 Construction NOC for LDN 48 20-Sep-18 27-Nov-18 Construction NOC for LDN
DVAA000170 Construction NOC for Central Battery 48 20-Sep-18 27-Nov-18 Construction NOC for Central Battery
DVAA000180 Construction NOC for Structured Cabling 48 24-Oct-18 02-Jan-19 Construction NOC for Structured Cabling
DVAA000190 Material NOC for Structured Cabling 48 24-Oct-18 02-Jan-19 Material NOC for Structured Cabling
DVAA000200 Transf ormer Material Approval 48 24-Oct-18 02-Jan-19 Transf ormer Material Approval
DVAA000210 MV/HV Switchgear Material Approval 48 24-Oct-18 02-Jan-19 MV/HV Switchgear Material Approval
DVAA000220 Construction NOC for Fire Protection 48 14-Nov-18 23-Jan-19 Construction NOC for Fire Protection
DVAA000230 Construction NOC for Fire Alarm 48 09-Dec-18 13-Feb-19 Construction NOC for Fire Alarm
DVAA000240 Construction NOC for Smoke Management 48 09-Dec-18 13-Feb-19 Construction NOC for Smoke Management
DVAA000250 Construction NOC for GSM 48 09-Dec-18 13-Feb-19 Construction NOC for GSM
DVAA000260 Construction NOC for Natural Gas 48 27-Jan-19 03-Apr-19 Construction NOC for Natural Gas
353 13-May-18 30-Apr-19 30-Apr-19, Engineering / Design
Engineering / Design
Engineerin
Engineering & Shop Drawings Phase 353 13-May-18 30-Apr-19 30-Apr-19, Engineering & Shop Drawings Phase
Civils Drawings
Drawin 75 13-May-18 26-Jul-18 26-Jul-18, Civils Drawings
DVEDSCIF10 Issue of IFC Drawings (by Consultant) 0 13-May-18 Issue of IFC Drawings (by Consultant)
Submittals 48 16-May-18 12-Jul-18 12-Jul-18, Submittals
DVEDSCS010 Prep, Submit, Review & Re-submit of Shop D., Materials, Met 24 16-May-18 12-Jun-18 Prep, Submit, Review & Re-submit of Shop D., Materials, Method S. for Rafts, Foundations
DVEDSCS060 Prep, Submit, Review & Re-submit of Shop D., Materials, Met 24 30-May-18 28-Jun-18 Prep, Submit, Review & Re-submit of Shop D., Materials, Method S. for RC Super St. Walls & Columns
DVEDSCS050 Prep, Submit, Review & Re-submit of Shop D., Materials, Met 30 06-Jun-18 12-Jul-18 Prep, Submit, Review & Re-submit of Shop D., Materials, Method S. for PT Beams & Slabs
DVEDSCS070 Prep, Submit, Review & Re-submit of Shop D., Materials, Met 24 13-Jun-18 12-Jul-18 Prep, Submit, Review & Re-submit of Shop D., Materials, Method S. for RC Super St. Beams & Slabs
Approvals 40 31-May-18 26-Jul-18 26-Jul-18, Approvals
DVEDSCA010 Approvals of Shop Dwgs., Materials, Method Sts. for Rafts, Fo 20 31-May-18 28-Jun-18 Approvals of Shop Dwgs., Materials, Method Sts. for Rafts, Foundations
DVEDSCA060 Approvals of Shop Dwgs., Materials, Method Sts. for RC Supe 20 14-Jun-18 12-Jul-18 Approvals of Shop Dwgs., Materials, Method Sts. for RC Super St. Walls & Columns
DVEDSCA050 Approvals of Shop Dwgs., Materials, Method Sts. for PT Beam 25 14-Jun-18 19-Jul-18 Approvals of Shop Dwgs., Materials, Method Sts. for PT Beams & Slabs
DVEDSCA070 Approvals of Shop Dwgs., Materials, Method Sts. for RC Supe 20 01-Jul-18 26-Jul-18 Approvals of Shop Dwgs., Materials, Method Sts. for RC Super St. Beams & Slabs
MEP Drawings
Drawin 257 14-May-18 27-Jan-19 27-Jan-19, MEP Drawings
DVEDSMIF10 Issue of IFC Drawings (by Consultant) 0 14-May-18 Issue of IFC Drawings (by Consultant)
Submittals 180 06-Jun-18 12-Jan-19 12-Jan-19, Submittals
DVEDSMS020 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 60 06-Jun-18 16-Aug-18 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Drainage System
Page 20 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
DVEDSAIF10 Issue of IFC Drawings (by Consultant) 0 14-May-18 Issue of IFC Drawings (by Consultant)
Submittals 135 06-Sep-18 14-Feb-19 14-Feb-19, Submittals
DVEDSAS010 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 60 06-Sep-18 15-Nov-18 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Gen. Arrangement Plans
DVEDSAS070 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 60 13-Oct-18 23-Dec-18 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Wat erproof ing
DVEDSAS030 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 60 13-Oct-18 23-Dec-18 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Tiling Layouts
DVEDSAS040 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 60 30-Oct-18 10-Jan-19 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Reflected Ceiling Plans
DVEDSAS080 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 60 17-Nov-18 28-Jan-19 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Internal Doors
DVEDSAS060 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 60 06-Dec-18 14-Feb-19 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Staircases
Approvals 103 04-Oct-18 28-Feb-19 28-Feb-19, Approvals
DVEDSAA010 Approvals of Shop Dwgs., Materials, Method Sts. for General A 40 04-Oct-18 03-Dec-18 Approvals of Shop Dwgs., Materials, Method Sts. for General Arrangement Plans
DVEDSAA030 Approvals of Shop Dwgs., Materials, Method Sts. for Tiling La 40 08-Nov-18 07-Jan-19 Approvals of Shop Dwgs., Materials, Method Sts. for Tiling Layouts
DVEDSAA070 Approvals of Shop Dwgs., Materials, Method Sts. for Waterpro 40 08-Nov-18 07-Jan-19 Approvals of Shop Dwgs., Materials, Method Sts. for Waterproofing
DVEDSAA050 Approvals of Shop Dwgs., Materials, Method Sts. for Reflecte 40 28-Nov-18 24-Jan-19 Approvals of Shop Dwgs., Materials, Method Sts. for Reflected Ceiling Plans
DVEDSAA080 Approvals of Shop Dwgs., Materials, Method Sts. for Internal 40 17-Dec-18 11-Feb-19 Approvals of Shop Dwgs., Materials, Method Sts. for Internal Doors
DVEDSAA060 Approvals of Shop Dwgs., Materials, Method Sts. for Staircases 40 06-Jan-19 28-Feb-19 Approvals of Shop Dwgs., Materials, Method Sts. for Staircases
Architectural Final Finishing Works & Sp. Systems
Architectura 351 14-May-18 30-Apr-19 30-Apr-19, Architectural Final Finishing Works & Sp. Systems
DVEDSFIF10 Issue of IFC Drawings (by Consultant) 0 14-May-18 Issue of IFC Drawings (by Consultant)
Submittals 221 24-Jul-18 16-Apr-19 16-Apr-19, Submittals
DVEDSFS020 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 90 24-Jul-18 10-Nov-18 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Curtain Wall/Glaz ing
DVEDSFS010 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 90 18-Aug-18 06-Dec-18 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Lifts
DVEDSFS130 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 90 07-Oct-18 22-Jan-19 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Garbage Chutes
DVEDSFS140 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 90 19-Dec-18 04-Apr-19 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Internal Signage
DVEDSFS150 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 90 19-Dec-18 04-Apr-19 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Parking Management
DVEDSFS170 Prep., Submit., Review & Re-submittals of S.D., Materials, Me 90 31-Dec-18 16-Apr-19 Prep., Submit., Review & Re-submittals of S.D., Materials, Method S. for Building Cleaning System
Approvals 170 29-Aug-18 30-Apr-19 30-Apr-19, Approvals
DVEDSFA020 Approvals of Shop Dwgs., Materials, Method Sts. for Curtain W 60 29-Aug-18 25-Nov-18 Approvals of Shop Dwgs., Materials, Method Sts. for Curtain Wall/ Glazing
DVEDSFA010 Approvals of Shop Dwgs., Materials, Method Sts. for Lifts & E 60 26-Sep-18 20-Dec-18 Approvals of Shop Dwgs., Materials, Method Sts. for Lifts & Escalators
DVEDSFA130 Approvals of Shop Dwgs., Materials, Method Sts. for Garbage 60 11-Nov-18 05-Feb-19 Approvals of Shop Dwgs., Materials, Method Sts. for Garbage Chutes
DVEDSFA150 Approvals of Shop Dwgs., Materials, Method Sts. for Parking 60 24-Jan-19 18-Apr-19 Approvals of Shop Dwgs., Materials, Method Sts. for Parking Management
DVEDSFA140 Approvals of Shop Dwgs., Materials, Method Sts. for Internal S 60 24-Jan-19 18-Apr-19 Approvals of Shop Dwgs., Materials, Method Sts. for Internal Signage
DVEDSFA170 Approvals of Shop Dwgs., Materials, Method Sts. for Building 60 05-Feb-19 30-Apr-19 Approvals of Shop Dwgs., Materials, Method Sts. for Building Cleaning System
536 06-Jun-18 14-Mar-20 14-Mar-20, Procurement
Procurement
Procureme
Main Subcontractors
Subcon 74 06-Jun-18 06-Sep-18 06-Sep-18, Main Subcontractors
MEP Consumables
Consu 48 07-Jun-18 05-Aug-18 05-Aug-18, MEP Consumables
DVPMEPI010 Procurement Delivery of MEP Basic Materials / Consumables 48 07-Jun-18 05-Aug-18 Procurement Delivery of MEP Basic Materials / Consumables (Initial)
Electrical 202 07-Nov-18 08-Jul-19 08-Jul-19, Electrical
DVPMEPE040 Procurement, Mfg & Delivery of Bus Bars 120 07-Nov-18 30-Mar-19 Procurement, Mfg & Delivery of Bus Bars
DVPMEPE050 Procurement, Mfg & Delivery of LV Switch Gear/MDB's/SMDB 120 07-Nov-18 30-Mar-19 Procurement, Mfg & Delivery of LV Switch Gear/MDB's/SMDB's/MCC's/DB's
DVPMEPE020 Procurement, Mfg & Delivery of Central Battery system 120 28-Nov-18 20-Apr-19 Procurement, Mfg & Delivery of Central Battery system
DVPMEPE010 Procurement, Mfg & Delivery of Generators 120 28-Nov-18 20-Apr-19 Procurement, Mfg & Delivery of Generators
DVPMEPE030 Procurement, Mfg & Delivery of Power Cables 60 13-Dec-18 21-Feb-19 Procurement, Mfg & Delivery of Power Cables
DVPMEPE160 Procurement, Mfg & Delivery of Structured Cabling 120 03-Jan-19 23-May-19 Procurement, Mfg & Delivery of Structured Cabling
DVPMEPE070 Procurement, Mfg & Delivery of MV Switchgear 120 03-Jan-19 23-May-19 Procurement, Mfg & Delivery of MV Switchgear
DVPMEPE080 Procurement, Mfg & Delivery of Transformers 120 03-Jan-19 23-May-19 Procurement, Mfg & Delivery of Transformers
DVPMEPE060 Procurement, Mfg & Delivery of Wiring Accessories 120 20-Jan-19 12-Jun-19 Procurement, Mfg & Delivery of Wiring Accessories
DVPMEPE120 Procurement, Mfg & Delivery of Central Emergency Lighting E 120 20-Jan-19 12-Jun-19 Procurement, Mfg & Delivery of Central Emergency Lighting Equipment
DVPMEPE150 Procurement, Mfg & Delivery of Lighting Control System 120 21-Jan-19 13-Jun-19 Procurement, Mfg & Delivery of Lighting Control System
DVPMEPE090 Procurement, Mfg & Delivery of Light Fittings 120 21-Jan-19 13-Jun-19 Procurement, Mfg & Delivery of Light Fittings
Page 21 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
DVPMEPA020 Procurement, Mfg & Delivery of FCUs 90 17-Oct-18 02-Feb-19 Procurement, Mfg & Delivery of FCUs
DVPMEPA010 Procurement, Mfg & Delivery of AHU & FAHUs 120 22-Dec-18 12-May-19 Procurement, Mfg & Delivery of AHU & FAHUs
DVPMEPA070 Procurement, Mfg & Delivery of Valves & Accessories 90 22-Dec-18 07-Apr-19 Procurement, Mfg & Delivery of Valves & Accessories
DVPMEPA100 Procurement, Mfg & Delivery of Heat Exchangers 120 04-Feb-19 27-Jun-19 Procurement, Mfg & Delivery of Heat Exchangers
DVPMEPA040 Procurement, Mfg & Delivery of Chillers 120 04-Feb-19 27-Jun-19 Procurement, Mfg & Delivery of Chillers
DVPMEPA060 Procurement, Mfg & Delivery of VAV's 120 04-Feb-19 27-Jun-19 Procurement, Mfg & Delivery of VAV's
DVPMEPA030 Procurement, Mfg & Delivery of Smoke Management System 120 14-Feb-19 08-Jul-19 Procurement, Mfg & Delivery of Smoke Management System
Plumbing 147 26-Jan-19 20-Jul-19 20-Jul-19, Plumbing
DVPMEPP010 Procurement, Mfg & Delivery of Sewage & Submersible Pumps 90 26-Jan-19 11-May-19 Procurement, Mfg & Delivery of Sewage & Submersible Pumps
DVPMEPP020 Procurement, Mfg & Delivery of Transfer & Booster Pumps 90 26-Jan-19 11-May-19 Procurement, Mfg & Delivery of Transfer & Booster Pumps
DVPMEPP030 Procurement, Mfg & Delivery of Heat Pumps 90 04-Feb-19 20-May-19 Procurement, Mfg & Delivery of Heat Pumps
DVPMEPP050 Procurement, Mfg & Delivery of Sanitaryware & Sanitary Fitting 90 03-Apr-19 20-Jul-19 Procurement, Mfg & Delivery of Sanitaryware & Sanitary Fittings
Fire Fighting 120 24-Jan-19 17-Jun-19 17-Jun-19, Fire Fighting
DVPMEPF020 Procurement, Mfg & Delivery of Fire Hose Reel Cabinets 120 24-Jan-19 17-Jun-19 Procurement, Mfg & Delivery of Fire Hose Reel Cabinets
DVPMEPF030 Procurement, Mfg & Delivery of Fire Fighting Equipment 120 24-Jan-19 17-Jun-19 Procurement, Mfg & Delivery of Fire Fighting Equipment
DVPMEPF010 Procurement, Mfg & Delivery of Fire Fighting Pumps 120 24-Jan-19 17-Jun-19 Procurement, Mfg & Delivery of Fire Fighting Pumps
Natural Gas (SNG) 90 04-Apr-19 21-Jul-19 21-Jul-19, Natural Gas (SNG)
DVPMEPG010 Procurement, Mfg & Delivery of SNG Material (Tanks, pipes et 90 04-Apr-19 21-Jul-19 Procurement, Mfg & Delivery of SNG Material (Tanks, pipes etc.)
Architectural & Finishing Works Materials 390 03-Dec-18 14-Mar-20 14-Mar-20, Architectural & Finishing Works Materials
DVPABW0040 Procurement, Mfg & Delivery of Wet Area Waterproofing 45 03-Dec-18 24-Jan-19 Procurement, Mfg & Delivery of Wet Area Waterproofing
DVPABW0050 Procurement, Mfg & Delivery of Painting 45 03-Dec-18 24-Jan-19 Procurement, Mfg & Delivery of Painting
DVPABW0080 Procurement, Mfg & Delivery of False Ceiling Materials 120 03-Jan-19 23-May-19 Procurement, Mfg & Delivery of False Ceiling Materials
DVPABW0030 Procurement, Mfg & Delivery of Ceramic, Porcelain, Marble Til 78 19-Jan-19 20-Apr-19 Procurement, Mfg & Delivery of Ceramic, Porcelain, Marble Tiles
DVPABW0100 Procurement, Mfg & Delivery of Internal Doors, Joinery, Ironmo 120 12-Feb-19 06-Jul-19 Procurement, Mfg & Delivery of Internal Doors, Joinery, Ironmongery
DVPABW0110 Procurement, Mfg & Delivery of Steel Doors 120 12-Feb-19 06-Jul-19 Procurement, Mfg & Delivery of Steel Doors
DVPABW0120 Procurement, Mfg & Delivery of Metal Works & Joinery 120 02-Mar-19 23-Jul-19 Procurement, Mfg & Delivery of Metal Works & Joinery
Architectural Final Finishing Work & Building Systems
Architectura 360 08-Jan-19 14-Mar-20 14-Mar-20, Architectural Final Finishing Work & Building Systems
DVPAPS0030 Procurement, Mfg & Delivery of Curtain Wall/Glaz ing 120 08-Jan-19 29-May-19 Procurement, Mfg & Delivery of Curtain Wall/Glaz ing
DVPAPS0010 Procurement, Mfg & Delivery of Lifts 120 04-Feb-19 27-Jun-19 Procurement, Mfg & Delivery of Lifts
DVPAPS0130 Procurement, Mfg & Delivery of Disposal Systems 120 30-Jul-19 22-Dec-19 Procurement, Mfg & Delivery of Disposal Systems
DVPAPS0140 Procurement, Mfg & Delivery of Internal Signage 90 12-Oct-19 27-Jan-20 Procurement, Mfg & Delivery of Internal Signage
DVPAPS0170 Procurement, Mfg & Delivery of Building Cleaning System 120 23-Oct-19 14-Mar-20 Procurement, Mfg & Delivery of Building Cleaning System
DVPAPS0150 Procurement, Mfg & Delivery of Parking Management 90 25-Nov-19 10-Mar-20 Procurement, Mfg & Delivery of Parking Management
49 14-May-18 11-Jul-18 11-Jul-18, Mobilization
Mobilization
Staff & Labour
Labou 45 15-May-18 08-Jul-18 08-Jul-18, Staff & Labour
DVMESP0010 Site Survey & Report, Setting Out 6 14-May-18 20-May-18 Site Survey & Report, Setting Out
DVMESP0020 Site Clearance 12 21-May-18 03-Jun-18 Site Clearance
DVMESP0040 Set up Temporary Site Offices 32 26-May-18 03-Jul-18 Set up Temporary Site Offices
DVMESP0030 Set up Temporary Site Utilities 32 28-May-18 05-Jul-18 Set up Temporary Site Utilities
Initial Deliverables
Deliver 48 15-May-18 11-Jul-18 11-Jul-18, Initial Deliverables
DVMEID0010 Prepare & Submit Health & Safety Plan 18 15-May-18 04-Jun-18 Prepare & Submit Health & Safety Plan
DVMEID0020 Prepare & Submit Quality Assurance Plan & Procedures 18 15-May-18 04-Jun-18 Prepare & Submit Quality Assurance Plan & Procedures
DVMEID0030 Prepare & Submit Environmental Management Plan 18 15-May-18 04-Jun-18 Prepare & Submit Environmental Management Plan
DVMEID0070 Prepare & Submit Baseline Programme 24 15-May-18 11-Jun-18 Prepare & Submit Baseline Programme
DVMEID0080 Prepare & Submit Detailed Method Statement for the Carrying 24 15-May-18 11-Jun-18 Prepare & Submit Detailed Method Statement for the Carrying out and Completion of the Works
DVMEID0090 Prepare & Submit Detailed Schedule of Material Submittals 24 15-May-18 11-Jun-18 Prepare & Submit Detailed Schedule of Material Submittals
DVMEID0100 Prepare & Submit Detailed Schedule of the Drawings 24 15-May-18 11-Jun-18 Prepare & Submit Detailed Schedule of the Drawings
DVMEID0040 Approval of Health & Saftey Plan (by Consultant) 18 22-May-18 11-Jun-18 Approval of Health & Saftey Plan (by Consultant)
DVMEID0050 Approval - Quality Assurance Plan (by Consultant) 18 22-May-18 11-Jun-18 Approval - Quality Assurance Plan (by Consultant)
DVMEID0060 Approval- Environmental Management Plan (by Consultant) 18 22-May-18 11-Jun-18 Approval- Environmental Management Plan (by Consultant)
DVMEID0110 Approval- Baseline Programme (by Consultant) 18 29-May-18 20-Jun-18 Approval- Baseline Programme (by Consultant)
DVMEID0120 Prepare & Submit Resource & Cashflow Projections 18 21-Jun-18 11-Jul-18 Prepare & Submit Resource & Cashflow Projections
918 20-Jun-18 23-Dec-20 2
Construction
Constructio
Tower 1 918 20-Jun-18 23-Dec-20 2
Structural W
Works 519 20-Jun-18 05-Mar-20 05-Mar-20, Structural Works
Page 22 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 23 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 24 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 25 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 26 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 27 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 28 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 29 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 30 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 31 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 32 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 33 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 34 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 35 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 36 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 37 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 38 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 39 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 40 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Authority Approval
Appr s 472 08-Sep-19 23-Dec-20 2
DEWA Electrical
Electric 387 08-Sep-19 29-Sep-20 29-Sep-20, DEWA Ele
HV Side 122 08-Sep-19 01-Mar-20 01-Mar-20, HV Side
DVT1AA0100 Completion of Civil/MEP Works for HV S /St n. as per DEWA a 0 08-Sep-19 Completion of Civil/MEP Works for HV S /St n. as per DEWA approved drawings
DVT1AA0110 Invite DEWA for HV inspection 5 10-Sep-19 16-Sep-19 Invite DEWA for HV inspection
DVT1AA0120 HV Inspection Approval 10 17-Sep-19 30-Sep-19 HV Inspection Approval
DVT1AA0130 Receiving DEWA Estimation 1 01-Oct-19 01-Oct-19 Receiving DEWA Estimation
DVT1AA0140 Payment Against DEWA Estimation by Client 5 02-Oct-19 08-Oct-19 Payment Against DEWA Estimation by Client
DVT1AA0250 Delivery and Installation of DEWA Transformer & RMU Unit 0 09-Feb-20 Delivery and Installation of DEWA Transformer & RMU Unit
DVT1AA0310 Complete Laying HV Cables by DEWA 0 01-Mar-20 Complete Laying HV Cables by DEWA
DVT1AA0320 Complete Laying LV Cables from Transformer to ACB panel by 0 01-Mar-20 Complete Laying LV Cables from Transformer to ACB panel by DEWA
DVT1AA0330 S/Stn. Commissioning & RMU units energization by DEWA 0 01-Mar-20 S/Stn. Commissioning & RMU units energization by DEWA
LV Side 28 01-Sep-20 29-Sep-20 29-Sep-20, LV Side
DVT1AA0260 Substantial LV installations as per DEWA Approved Drawings 0 01-Sep-20 Substantial LV installations as
DVT1AA0270 Invite DEWA for LV Inspection 3 02-Sep-20 06-Sep-20 Invite DEWA for LV Inspectio
DVT1AA0280 First Inspection by DEWA 3 07-Sep-20 09-Sep-20 First Inspection by DEWA
DVT1AA0300 Rectification of DEWA comments 12 10-Sep-20 23-Sep-20 Rectification of DEWA c
DVT1AA0400 Re-inspection / LV Approval by DEWA 3 24-Sep-20 28-Sep-20 Re-inspection / LV App
Page 41 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 42 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Structural W
Works 494 20-Jun-18 05-Feb-20 05-Feb-20, Structural Works
Page 43 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 44 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 45 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 46 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 47 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 48 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 49 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 50 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 51 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 52 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 53 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 54 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 55 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 56 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 57 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 58 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 59 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 60 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Authority Approval
Appr s 448 08-Sep-19 29-Nov-20 29-Nov
DEWA Electrical
Electric 358 08-Sep-19 31-Aug-20 31-Aug-20, DEWA Electrical
HV Side 122 08-Sep-19 01-Mar-20 01-Mar-20, HV Side
DVT2AA0100 Completion of Civil/MEP Works for HV S /St n. as per DEWA a 0 08-Sep-19 Completion of Civil/MEP Works for HV S /St n. as per DEWA approved drawings
DVT2AA0110 Invite DEWA for HV inspection 5 10-Sep-19 16-Sep-19 Invite DEWA for HV inspection
DVT2AA0120 HV Inspection Approval 10 17-Sep-19 30-Sep-19 HV Inspection Approval
DVT2AA0130 Receiving DEWA Estimation 1 01-Oct-19 01-Oct-19 Receiving DEWA Estimation
DVT2AA0140 Payment Against DEWA Estimation by Client 5 02-Oct-19 08-Oct-19 Payment Against DEWA Estimation by Client
DVT2AA0250 Delivery and Installation of DEWA Transformer & RMU Unit 0 09-Feb-20 Delivery and Installation of DEWA Transformer & RMU Unit
DVT2AA0310 Complete Laying HV Cables by DEWA 0 01-Mar-20 Complete Laying HV Cables by DEWA
DVT2AA0320 Complete Laying LV Cables from Transformer to ACB panel by 0 01-Mar-20 Complete Laying LV Cables from Transformer to ACB panel by DEWA
DVT2AA0330 S/Stn. Commissioning & RMU units energization by DEWA 0 01-Mar-20 S/Stn. Commissioning & RMU units energization by DEWA
LV Side 29 02-Aug-20 31-Aug-20 31-Aug-20, LV Side
DVT2AA0260 Substantial LV installations as per DEWA Approved Drawings 0 02-Aug-20 Substantial LV installations as per DE
DVT2AA0270 Invite DEWA for LV Inspection 3 03-Aug-20 05-Aug-20 Invite DEWA for LV Inspection
DVT2AA0280 First Inspection by DEWA 3 06-Aug-20 10-Aug-20 First Inspection by DEWA
DVT2AA0300 Rectification of DEWA comments 12 11-Aug-20 25-Aug-20 Rectification of DEWA commen
DVT2AA0400 Re-inspection / LV Approval by DEWA 3 26-Aug-20 30-Aug-20 Re-inspection / LV Approval by
DVT2AA0430 Energized DEWA Transformer & Release of Temporary Power 1 31-Aug-20 31-Aug-20 Energized DEWA Transformer
DEWA Water 16 24-Aug-20 15-Sep-20 15-Sep-20, DEWA Water
DVT2AA0160 Completion of Building Water S upply Installat ions 0 24-Aug-20 Completion of Building Water S u
DVT2AA0180 DEWA Estimation 5 25-Aug-20 31-Aug-20 DEWA Estimation
DVT2AA0200 Payment to DEWA Estimate for Water Connection Fees 5 01-Sep-20 07-Sep-20 Payment to DEWA Estimate
DVT2AA0210 Inspection of the Building Water Sys tem by DEWA 5 08-Sep-20 14-Sep-20 Inspection of the Building
DVT2AA0230 Receipt and Installation of Main Meter 1 15-Sep-20 15-Sep-20 Receipt and Installation of
DVT2AA0240 Water Supply Available 0 15-Sep-20 Water Supply Available
Telecom System
Syst 23 31-Aug-20 01-Oct-20 01-Oct-20, Telecom S
DVT2AA0340 Completion of GSM Rooms & Containment Ready for DU Insp 0 31-Aug-20 Completion of GSM Rooms &
DVT2AA0350 Apply for DU Inspection 1 01-Sep-20 01-Sep-20 Apply for DU Inspection
DVT2AA0360 DU Inspection & Approval 5 02-Sep-20 08-Sep-20 DU Inspection & Approval
DVT2AA0380 TELECOM Rooms Handover to DU 0 08-Sep-20 TELECOM Rooms Handove
DVT2AA0410 TELECOM Cabling & Termination by DU 15 13-Sep-20 01-Oct-20 TELECOM Cabling &
DVT2AA0450 Telecom Connection up to Plot Limit Complete 0 01-Oct-20 Telecom Connection u
Sewerage System
Sys 15 24-Aug-20 14-Sep-20 14-Sep-20, Sewerage Syst
DVT2AA0150 Completion of Building Drainage Installation 0 24-Aug-20 Completion of Building Drainage
DVT2AA0170 Apply for Sewerage Inspection 5 25-Aug-20 31-Aug-20 Apply for Sewerage Inspection
DVT2AA0190 Sewerage Inspection and Approval 10 01-Sep-20 14-Sep-20 Sewerage Inspection and A
DVT2AA0220 Sewerage Hook up Complete 0 14-Sep-20 Sewerage Hook up Comple
Life Safety Sy
Systems ( Civil Defense ) 46 30-Aug-20 02-Nov-20 02-Nov-20, Lif
DVT2AA0290 Third Party Inspection 5 30-Aug-20 03-Sep-20 Third Party Inspection
DVT2AA0370 Incorporate / Rectify Third Party Comments 15 06-Sep-20 24-Sep-20 Incorporate / Rectify Thi
DVT2AA0390 Application for Initial Inspection by DCD 5 20-Sep-20 24-Sep-20 Application for Initial Ins
DVT2AA0420 Initial Inspection by DCD 2 27-Sep-20 28-Sep-20 Initial Inspection by DC
DVT2AA0440 Incorporate / Rectify DCD Comments 15 06-Oct-20 26-Oct-20 Incorporate / Re
DVT2AA0460 Final Inspection by DCD 2 27-Oct-20 28-Oct-20 Final Inspection
DVT2AA0470 DCD Clerance Certificate Obtained 0 02-Nov-20 DCD Clerance
DM Approval 27 03-Nov-20 29-Nov-20 29-Nov
DVT2AA0480 Application for DM Inspection 3 03-Nov-20 05-Nov-20 Application fo
DVT2AA0490 Initial Inspection for BCC by DM 3 08-Nov-20 10-Nov-20 Initial Inspe
DVT2AA0500 Incorporate / Rectify DM Comments 10 11-Nov-20 22-Nov-20 Incorpora
Page 61 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 62 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Structural W
Works 444 20-Jun-18 08-Dec-19 08-Dec-19, Structural Works
Page 63 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 64 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 65 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 66 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 67 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 68 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 69 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 70 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 71 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 72 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 73 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 74 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 75 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 76 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 77 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Authority Approval
Appr s 382 08-Sep-19 24-Sep-20 24-Sep-20, Authority Ap
DEWA Electrical
Electric 295 08-Sep-19 29-Jun-20 29-Jun-20, DEWA Electrical
HV Side 122 08-Sep-19 01-Mar-20 01-Mar-20, HV Side
DVT3AA0100 Completion of Civil/MEP Works for HV S /St n. as per DEWA a 0 08-Sep-19 Completion of Civil/MEP Works for HV S /St n. as per DEWA approved drawings
DVT3AA0110 Invite DEWA for HV inspection 5 10-Sep-19 16-Sep-19 Invite DEWA for HV inspection
DVT3AA0120 HV Inspection Approval 10 17-Sep-19 30-Sep-19 HV Inspection Approval
DVT3AA0130 Receiving DEWA Estimation 1 01-Oct-19 01-Oct-19 Receiving DEWA Estimation
DVT3AA0140 Payment Against DEWA Estimation by Client 5 02-Oct-19 08-Oct-19 Payment Against DEWA Estimation by Client
DVT3AA0250 Delivery and Installation of DEWA Transformer & RMU Unit 0 09-Feb-20 Delivery and Installation of DEWA Transformer & RMU Unit
DVT3AA0310 Complete Laying HV Cables by DEWA 0 01-Mar-20 Complete Laying HV Cables by DEWA
DVT3AA0320 Complete Laying LV Cables from Transformer to ACB panel by 0 01-Mar-20 Complete Laying LV Cables from Transformer to ACB panel by DEWA
DVT3AA0330 S/Stn. Commissioning & RMU units energization by DEWA 0 01-Mar-20 S/Stn. Commissioning & RMU units energization by DEWA
LV Side 28 01-Jun-20 29-Jun-20 29-Jun-20, LV Side
DVT3AA0260 Substantial LV installations as per DEWA Approved Drawings 0 01-Jun-20 Substantial LV installations as per DEWA Approved D
DVT3AA0270 Invite DEWA for LV Inspection 3 02-Jun-20 04-Jun-20 Invite DEWA for LV Inspection
DVT3AA0280 First Inspection by DEWA 3 07-Jun-20 09-Jun-20 First Inspection by DEWA
DVT3AA0300 Rectification of DEWA comments 12 10-Jun-20 23-Jun-20 Rectification of DEWA comments
DVT3AA0400 Re-inspection / LV Approval by DEWA 3 24-Jun-20 28-Jun-20 Re-inspection / LV Approval by DEWA
DVT3AA0430 Energized DEWA Transformer & Release of Temporary Power 1 29-Jun-20 29-Jun-20 Energized DEWA Transformer & Release of Te
DEWA Water 16 22-Jun-20 14-Jul-20 14-Jul-20, DEWA Water
DVT3AA0160 Completion of Building Water S upply Installat ions 0 22-Jun-20 Completion of Building Water S upply Installat ion
DVT3AA0180 DEWA Estimation 5 23-Jun-20 29-Jun-20 DEWA Estimation
DVT3AA0200 Payment to DEWA Estimate for Water Connection Fees 5 30-Jun-20 06-Jul-20 Payment to DEWA Estimate for Water Conn
DVT3AA0210 Inspection of the Building Water Sys tem by DEWA 5 07-Jul-20 13-Jul-20 Inspection of the Building Water Sys tem by
DVT3AA0230 Receipt and Installation of Main Meter 1 14-Jul-20 14-Jul-20 Receipt and Installation of Main Meter
DVT3AA0240 Water Supply Available 0 14-Jul-20 Water Supply Available
Telecom System
Syst 23 29-Jun-20 04-Aug-20 04-Aug-20, Telecom System
DVT3AA0340 Completion of GSM Rooms & Containment Ready for DU Insp 0 29-Jun-20 Completion of GSM Rooms & Containment Re
DVT3AA0350 Apply for DU Inspection 1 30-Jun-20 30-Jun-20 Apply for DU Inspection
DVT3AA0360 DU Inspection & Approval 5 01-Jul-20 07-Jul-20 DU Inspection & Approval
DVT3AA0380 TELECOM Rooms Handover to DU 0 07-Jul-20 TELECOM Rooms Handover to DU
DVT3AA0410 TELECOM Cabling & Termination by DU 15 12-Jul-20 04-Aug-20 TELECOM Cabling & Termination by
DVT3AA0450 Telecom Connection up to Plot Limit Complete 0 04-Aug-20 Telecom Connection up to Plot Limit
Sewerage System
Sys 15 22-Jun-20 13-Jul-20 13-Jul-20, Sewerage System
DVT3AA0150 Completion of Building Drainage Installation 0 22-Jun-20 Completion of Building Drainage Installation
Page 78 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 79 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Structural W
Works 294 15-Aug-18 05-Aug-19 05-Aug-19, Structural Works
Page 80 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 81 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 82 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 83 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 84 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Authority Approval
Appr s 366 22-Dec-19 22-Dec-20 2
DEWA Electrical
Electric 255 22-Dec-19 02-Sep-20 02-Sep-20, DEWA Electrical
HV Side 137 22-Dec-19 05-Jul-20 05-Jul-20, HV Side
DVP0AA0100 Completion of Civil/MEP Works for HV S /St n. as per DEWA a 0 22-Dec-19 Completion of Civil/MEP Works for HV S /St n. as per DEWA approved drawings
DVP0AA0110 Invite DEWA for HV inspection 5 24-Dec-19 30-Dec-19 Invite DEWA for HV inspection
DVP0AA0120 HV Inspection Approval 10 31-Dec-19 14-Jan-20 HV Inspection Approval
DVP0AA0130 Receiving DEWA Estimation 1 15-Jan-20 15-Jan-20 Receiving DEWA Estimation
DVP0AA0140 Payment Against DEWA Estimation by Client 5 16-Jan-20 22-Jan-20 Payment Against DEWA Estimation by Client
DVP0AA0250 Delivery and Installation of DEWA Transformer & RMU Unit 0 14-Jun-20 Delivery and Installation of DEWA Transformer & R
DVP0AA0310 Complete Laying HV Cables by DEWA 0 05-Jul-20 Complete Laying HV Cables by DEWA
DVP0AA0320 Complete Laying LV Cables from Transformer to ACB panel by 0 05-Jul-20 Complete Laying LV Cables from Transforme
DVP0AA0330 S/Stn. Commissioning & RMU units energization by DEWA 0 05-Jul-20 S/Stn. Commissioning & RMU units energiza
LV Side 28 05-Aug-20 02-Sep-20 02-Sep-20, LV Side
DVP0AA0260 Substantial LV installations as per DEWA Approved Drawings 0 05-Aug-20 Substantial LV installations as per D
DVP0AA0270 Invite DEWA for LV Inspection 3 06-Aug-20 10-Aug-20 Invite DEWA for LV Inspection
DVP0AA0280 First Inspection by DEWA 3 11-Aug-20 13-Aug-20 First Inspection by DEWA
DVP0AA0300 Rectification of DEWA comments 12 15-Aug-20 29-Aug-20 Rectification of DEWA comme
DVP0AA0400 Re-inspection / LV Approval by DEWA 3 30-Aug-20 01-Sep-20 Re-inspection / LV Approval by
DVP0AA0430 Energized DEWA Transformer & Release of Temporary Power 1 02-Sep-20 02-Sep-20 Energized DEWA Transforme
DEWA Water 16 22-Sep-20 14-Oct-20 14-Oct-20, DEWA
DVP0AA0160 Completion of Building Water S upply Installat ions 0 22-Sep-20 Completion of Building W
DVP0AA0180 DEWA Estimation 5 23-Sep-20 29-Sep-20 DEWA Estimation
DVP0AA0200 Payment to DEWA Estimate for Water Connection Fees 5 30-Sep-20 06-Oct-20 Payment to DEWA E
DVP0AA0210 Inspection of the Building Water Sys tem by DEWA 5 07-Oct-20 13-Oct-20 Inspection of the B
Page 85 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 86 of 736
DOWNTOWN VIEWS II Layout: Downtown Views II Tender Detail
Tender Programme 07-Mar-18
Page 87 of 736
DOWNTOWN VIEWS II
Plot 3370587 Zabeel 2nd Dubai, UAE
2. SCHEDULE OF MANPOWER
Man X hours for each trade have been estimated and loaded into the Tender
Programme. The Manpower histogram has been included as an attachment as “Manpower
Histogram” to the Tender Programme. Refinement of final resources will be calculated during
detailed planning at Contract Stage in conjunction with the selected subcontractor.
Page 88 of 736
DOWNTOWN VIEWS II
PROPOSED TENDER PROGRAMME MANPOWER HISTOGRAM
4500
4000
3500
3000
No. of Labour
2500
2000
1500
1000
500
MONTHS
0
M.1 M.2 M.3 M.4 M.5 M.6 M.7 M.8 M.9 M.10 M.11 M.12 M.13 M.14 M.15 M.16 M.17 M.18 M.19 M.20 M.21 M.22 M.23 M.24 M.25 M.26 M.27 M.28 M.29 M.30 M.31 M.32
T&C & HO 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 6 8 32 61 59 77 102 101 63 73 52 15
Mobilisation, Prelims & Enabling 166 216 224 224 216 224 216 224 224 202 224 216 224 216 224 224 216 224 216 224 224 209 224 216 224 216 224 224 216 224 216 166
Envelope/External Works 0 0 0 0 0 0 0 0 0 24 243 255 265 235 276 245 255 288 260 294 306 314 340 302 339 382 305 289 117 0 0 0
Specialist Finishes & Fit‐outs 0 0 0 0 0 0 0 0 0 0 0 0 144 278 374 454 444 488 469 518 489 552 812 789 879 912 793 625 427 258 52 0
Basic Finishes 0 0 0 0 0 0 13 140 294 412 407 488 822 838 882 789 863 973 843 845 704 710 579 438 243 158 53 8 0 0 0 0
MEP Works 0 0 0 8 16 15 18 81 197 304 507 602 834 846 891 988 993 1035 1102 1100 1084 1072 995 871 729 721 462 373 341 271 129 50
RC Structural works 0 52 256 469 469 753 874 1496 1644 1437 1365 1375 1372 1294 1122 1020 1038 1022 1005 829 696 373 46 0 0 0 0 0 0 0 0 0
#REF! 1
Total 166 268 480 701 701 992 1121 1941 2359 2379 2746 2936 3661 3707 3769 3720 3810 4031 3895 3810 3509 3238 3028 2677 2473 2466 1939 1620 1164 826 449 231
Page 89 of 736
DOWNTOWN VIEWS II
Plot 3370587 Zabeel 2nd Dubai, UAE
3. CASH FLOW
This section will give an initial overall overview of cash flow throughout the
construction duration for “Downtown Views II” project. Refinement of final cash flow
projection in compliance and in schedule as stipulated in contract conditions.
Page 90 of 736
DOWNTOWN VIEWS II
PROPOSED TENDER PROGRAMME OVERALL CASH FLOW
12% 120%
10% 100%
8% 80%
Monthly % Value
6% 60%
4% 40%
2% 20%
0% Adv.Pa
0%
M.1 M.2 M.3 M.4 M.5 M.6 M.7 M.8 M.9 M.10 M.11 M.12 M.13 M.14 M.15 M.16 M.17 M.18 M.19 M.20 M.21 M.22 M.23 M.24 M.25 M.26 M.27 M.28 M.29 M.30 M.31 M.32 M.32+
yment
Advance Payment 10%
Monthly 0% 0% 1% 1% 1% 1% 1% 2% 3% 3% 3% 3% 4% 4% 4% 4% 4% 5% 4% 4% 4% 4% 3% 3% 3% 3% 2% 2% 1% 1% 1% 0% 0%
Retention 10%
Cumulative 10% 10% 10% 11% 12% 13% 14% 15% 17% 20% 23% 26% 29% 33% 37% 42% 46% 50% 55% 59% 63% 67% 71% 74% 77% 80% 83% 85% 87% 88% 89% 90% 90% 100%
Page 91 of 736
SCHEDULE A2
Organization Chart
Page 92 of 736
DOWNTOWN VIEWS II
Plot 3370587 Zabeel 2nd Dubai, UAE
1. ORGANIZATION CHART
We include herewith our proposed “Project Organization Chart” for the project team
that will be in-charge of the execution of “Downtown Views II”.
Page 93 of 736
DOWNTOWN VIEWS II
............................................................ (TBA)
2
Senior Project Manager or
Project Manager
(TBA)
Name TBA
Scheduler (1) Document
Controller (1) Store Keeper (1)
10 25 Document
Controller (1)
BIM
Coordinator (1) Draftsman (6) 15 10
TBA TBA TBA
Project BUA: 295,988 m²
Page 94 of 736
SCHEDULE A3
Key Personnel
Page 95 of 736
DOWNTOWN VIEWS II
Plot 3370587 Zabeel 2nd Dubai, UAE
The CV’s of the proposed key personnel of the project team that will be assigned for this
project can be referred to the appendix following this section.
Page 96 of 736
NAME OF CANDIDATE: FENG RUI
JOB TITLE: PROJECT DIRECTOR
PROPOSED POSITION IN THE PROJECT: PROJECT DIRECTOR
BASIC INFORMATION
Date of Birth: 13th March 1979
Nationality: Chinese
Civil Status: Married
Years of Professional Experience: 14 years
Professional Qualifications: Master degree in Project Management
Member of Professional Bodies: -
Other Skills: (e.g. Computer Literacy, etc.) Microsoft Office Applications, AutoCAD
EDUCATION
From To Institution Location Major Degree
Candidate of
National University of MBA
2011 Present Singapore, NUS Business Singapore specialized Master
School in Real Estate
(MBA-RE)
University of Manchester,
MSC.in
Institute of Science and
2002 2003 United Kingdom Project Bachelor
Technology (UMI ST),
Management
Manchester, UK
BEng. in Civil
1997 2001 Tian Jin University, China Engineering Bachelor
WORKING EXPERIENCE
From To Company / Organization Location Position Job Description
Leader of the project team
comprising of 80-100 staffs,
responsible for cost control,
budget, QA/QC, project
China State Construction progress, contract, and related
Project
2015 Present Engineering Corporation Dubai, UAE matters. Report to headquarter
Director
Middle East LLC. management. Ensure the
project activities are complying
with respective regulations.
Coordinate with client and
consultant for project works.
China Construction
Chief Chief Representative of the
2009 Present (S.P) Development Co. Singapore project for the main
Representative
Ltd contractor.
1/5
Page 97 of 736
WORKING EXPERIENCE
Answerable to Project
Director and Corporate
Management.
Responsible for the project
progress, site safety and
budget control, etc.
Leading & managing the
project team, including
technical, site & financial
staff.
Key personnel to
coordinate between HQ
functional departments
(including tender,
procurement, adm in and
technical departments,
etc).
To be answerable to
respective authorities and
ensure the project activities
are complying with
respective regulations.
Answerable to Site
Manager.
Project In charge of project
China State Construction Planner/Struct master planning
2003 2004 Beijing
Engineering Co. (CSCEC) ural Responsible for site
Engineer progress of structural
works
2/5
Page 98 of 736
MAJOR PROJECT EXPERIENCE
sustainability.
Dubai Silicon Park will also feature intelligent
solutions from charging-docks for smart devices
on the street to smart pop-up furniture and
digital play tables, as well as optimally designed
bus shelters, piazzas shading, and other public
amenities. Visitors to the site will be directed to
the most advanced technology - Augmented
Reality - that converts real spaces to virtually
generated maps. All these facilities aim to
provide convenience and enjoyment to the
community. The total project value is USD 327
Million.
Viceroy Dubai is the ultimate destination for an
urban resort. This is located at the main
entrance of the Palm Jumeirah trunk. Enjoy the
beach, the exciting landscaping and yet, within
10 minutes, you can have a meeting at the world
famous Burj Khalifa. The location enjoys
Viceroy Hotel Project convenient and fast connections to the major
2015 2016 Dubai, UAE
Palm Jumeirah Director highways, providing great access to the whole of
Dubai. The site enjoys spectacular views not
only of the sea but also Dubai’s dynamic skyline.
A luxury hotel, serviced apartment and
residential apartment development on a prime
beach location. The total BUA is 170,000 m2 and
the total project value is USD 239 Million.
Chief Representative of the project for the
main contractor.
Answerable to Project Director and
Corporate Management.
Responsible for the project progress, site
safety and budget control, etc.
Leading & managing the project team,
Cabana Project including technical, site & financial staff.
Terrace House Manager Key personnel to coordinate between HQ
2009 Present @ Yio Chu Singapore / Chief functional departments (including tender,
Kang Road Representat procurement, adm in and technical
ive departments, etc).
To be answerable to respective authorities
and ensure the project activities are
complying with respective regulations.
Project value 38 Million Dollar, BUA
22,000m2,116 villas, one basement, 3
levels
3/5
Page 99 of 736
MAJOR PROJECT EXPERIENCE
ensure that the technical information
is conveyed to site team correctly.
Solely in charge of the work of two
blocks, including technical, site and
contractual issues.
As one of the key representatives of
project team, liaising with the client
and consultant.
Project value 1.1 Billion Dollar, BUA
58,000m2,5 buildings and sports yard
and swimming pool, (awarded 2013
Singapore excellent building quality –
school category)
4/5
5/5
BASIC INFORMATION
Date of Birth: 15 September, 1979
Nationality: Egyptian
Civil Status: Married
Years of Professional Experience: 14
Bachelor of Engineering, Civil Department
Professional Qualifications:
Member of Professional Bodies:
Windows Operating Systems: | Expert |Over 16 years’
experience
Microsoft Office Suite XP: | Expert |Over 16 years’
Other Skills: (e.g. Computer Literacy, etc.)
experience
AutoCAD: | Expert |Over 18 years’ experience
EDUCATION
From To Institution Location Major Degree
Civil
1998 May 2003 South Valley University Egypt Bachelor
Engineering
WORKING EXPERIENCE
From To Company / Organization Location Position Job Description
Support the project team to
ensure execution of the
project
Determine labor
requirements and dispatch
workers to construction sites
Plan, organize, supervise and
implement all construction
China State Construction Project
2016 Present Silicon Park activities to be carried out on
Engineering Middle East Manager
the project in compliance
with the specification
Monitor site QA/QC
Ensure safety and
environmental procedures are
followed
Provide full updates to all
stakeholders of the project
1/7
2/7
3/7
4/7
5/7
6/7
7/7
BASIC INFORMATION
Date of Birth: 14/02/1977
Nationality: Syrian
Civil Status: Married
Years of Professional Experience: 16 Years
Professional Qualifications: B.Sc. in Civil Engineering
Member of Professional Bodies:
Other Skills: (e.g. Computer Literacy, etc.) Auto CAD 2000& 2006 SAP2000
EDUCATION
From To Institution Location Major Degree
Damascus University Civil
1996 2001 Damascus Engineering Bachelors
WORKING EXPERIENCE
From To Company / Organization Location Position Job Description
Planning, organizing,
supervision, and
implementing all
construction activities to be
carried out on project in
Silicon Park Construction compliance with
Oct / 2016 Present CSCECME Manager specifications, method
statement, drawings,
schedules, site QA/QC,
safety and environmental
procedures, and
programmed requirements
(Project Management
Plane) within the approved
budget.
Planning, organizing,
supervision, and
implementing all
construction activities to be
carried out on project in
compliance with
Construction specifications, method
Bay Views Hotel
April/ 2016 Sep/ 2016 HLG Manager statement, drawings,
schedules, site QA/QC,
1/3
2/3
3/3
BASIC INFORMATION
Date of Birth: 1988 / 02 /14
Nationality: China
Civil Status: Married
Years of Professional Experience: 6 years
Professional Qualifications: College
Member of Professional Bodies: None
Other Skills: (e.g. Computer Literacy, etc.) Microsoft Word, Microsoft Excel, Microsoft Office Power Point
EDUCATION
From To Institution Location Major Degree
Shenyang Jianzhu Civil
2008-7 2012-7 China Bachelor
University Engineering
WORKING EXPERIENCE
From To Company / Organization Location Position Job Description
China State Construction
Construction Silicon park DSOA
2016-12 Now Engineering Corporation Dubai
Manager .Dubai U.A.E
(Middle East) L.L.C.
China State Construction
Viceroy hotel
2014-1 2016-12 Engineering Corporation Dubai Site Engineer
Dubai U.A.E
(Middle East) L.L.C.
China State Construction
2013-6 2014-1 Engineering Corporation Abu Dhabi Site Engineer SSH, Abu Dhabi, U.A.E.
(Middle East) L.L.C.
China State Construction
2012-8 2013-6 Engineering Corporation Abu Dhabi Site Engineer City of Lights , Abu Dhabi, U.A.E.
(Middle East) L.L.C.
1/2
2/2
BASIC INFORMATION
Date of Birth: 18th September 1981
Nationality: Singapore
Civil Status: Married
Years of Professional Experience: 13 years
Professional Qualifications: Bachelor’s degree
Member of Professional Bodies: Recognized by BCA and PE Board
Other Skills: (e.g. Computer Literacy, etc.) Proficient in MS Project, AUTOCAD, Adobe Photoshop
EDUCATION
From To Institution Location Major Degree
Chongqing
09.2000 07.2004 China Civil Engineering Bachelor
University
WORKING EXPERIENCE
From To Company Location Position Job Description
Project
06.2015 12.2015 Singtel Data Center West Singapore Contract Value: USD 187 Million
Manager
Project
09.2013 03.2015 28 Imperial Residences Singapore Contract Value: USD 7.80 Million
Manager
Senior
Architectural
05.2012 08.2013 Halmark Residences Singapore Contract Value: USD 44 Million
Design
Coordinator
Main
07.2011 04.2012 The Shore Residences Singapore Technical Contract Value: USD 110 Million
Coordinator
Main
United World College
09.2009 06.2011 Singapore Technical Contract Value: USD 151 Million
Southeast Asia Campus
Coordinator
Chemistry College
Project
10.2006 08.2007 Building Of Peking China -
Engineer
University
Project
09.2005 09.2006 China Telcom Building China Luban Award winner of the year 2007
Engineer
BASIC INFORMATION
Date of Birth: 17 October 1985
Nationality: Chinese
Civil Status: Married
Years of Professional Experience: 9+ years
Professional Qualifications:
Member of Professional Bodies: Candidate Member of RICS
Other Skills: (e.g. Computer Literacy, etc.) Microsoft Office, AutoCAD,
EDUCATION
From To Institution Location Major Degree
Construction
2004 2008 Tianjin University China Bachelor
Management
WORKING EXPERIENCE
From To Company / Organization Location Position Job Description
Valuation of variation,
Deputy submission of claim, Post-
2016.11 2017.09 CSCEC Middle East Silicon Park Contracts
Contracts Management, Pre-
Manager
Contract Procurement
In charge of lawsuits in
Project TGR & SAMA Tower
CSHK Dubai Contracting Commercial Contract
2014.12 2016.10 including preparation of
LLC Dept. Manager
statement of claim and
routine follow up.
1.Final account, Cost Analysis
& Lawsuits for Project XL &
TGR
Deputy
CSHK Dubai Contracting Commercial 2. Final account and
2013.06 2014.11 Contract
LLC Dept. Maintenance works for our
Manager
curtain wall division in Project
Burj Dubai, SAMA Tower,
Darwish Tower.
1/2
2/2
BASIC INFORMATION
Date of Birth: 04-06-1982
Nationality: Indian
Civil Status: Married
Years of Professional Experience: 11 years
Professional Qualifications: Bachelor Degree In Civil Engineering
Member of Professional Bodies: None
Other Skills: (e.g. Computer Literacy, etc.) Knowledge Auto Cad, Knowledge In Oil and Gas
EDUCATION
From To Institution Location Major Degree
Civil Bachelor Degree In Civil
2002 2004 Anna University Tamil Nadu
Engineering Engineering
WORKING EXPERIENCE
From To Company / Organization Location Position Job Description
Creating and implement Project
Quality Plan as per Corporate
guide, Project specification and
Client code of guidance.
Follow up day by day works with
China State Construction Logistic QC engineers.
QA/QC
2013.07 Present Engineering Corporation Complex – Arrange kick of Meeting and
Manager
ME LLC Jebelali -Dubai coordinate with all other trades
and subcontractors. Prepare
weekly monthly reports.
Monitor, respond Quality issues.
Other works assign by Project
Director.
Follow the day by day with site
Engineer and check as per the
quality standards, arrange and
follow up testing’s. Coordinate
Habbsan to
China State Construction Site Manager / with pipe line authorities, patrol
Fujairah crude
2012.10 2013.07 Engineering Corporation QA/QC line military authorities.
Oil pipe line
ME LLC Engineer Coordinate for Permit to work
project
system
Approved Job performing
authority in the ADCO , Dolphin
Oil lines
1/2
2/2
BASIC INFORMATION
Date of Birth: 20th March 1968
Nationality: Indian
Civil Status: Married
Years of Professional Experience: 30 years
Professional Qualifications: Bachelor of Science in Mechanical & Marine Engineering
NEBOSH -International Diploma
NEBOSH -International General Certificate
Abu Dhabi EHSMS Registration- “QUDORAT”
Member of Professional Bodies: Safety advisor – SARS holder
Safety Officer Diploma
OSHAS 18001 - 2007 – Internal Auditor
GRADE IOSH
Other Skills: (e.g. Computer Literacy, etc.) MS word, Excel, PowerPoint presentation
EDUCATION
From To Institution Location Major Degree
National Examination NEBOSH
2012 2013 Board of Occupational United Kingdom International Diploma
Safety & Health Diploma
National Examination NEBOSH
2007 2008 Board of Occupational United Kingdom International Professional Course
Safety & Health IGC
1987 2002 Indian Navy Lonavala, Pune, Mechanical
India and Marine
Specialized.
Bachelor
Civil
Engineering(p
erusing)
1983 1986 Board of Technical Kanhangad, Engineering
Diploma
Education, Kerala Kasaragod Automobile
2005 2005 National Institute of Bangalore, Safety Officer
Diploma
Security Management, India. Diploma
2002 2002 L.B.S. College of Mumbai, India Marine
Advanced Maritime engineer
Research
studies & Research Officer, Class
IV.
WORKING EXPERIENCE
From To Company Location Position Job Description
1/4
2/4
3/4
Relevant Experience
BUA 166,890 m2
Value -
Award Date 2018
Duration 38 months
2 Mirkaaz Mall
Client Ajman Holding LLC
BUA 55,509 m2
Duration 22 months
Construction of the new Mirkaaz Mall (G+1+R) commercial center which
composed of:
Retail
Entertainment Facilities
Project
Hypermarket
Details
Food Court
General Retail
Recreational Space along with External Parking area and Landscaping.
3 PN1502 Expo Village Development (CP06: Main Works for Parcels 10 & 11)
Dubai World Trade Centre
Client
LLC
BUA 168,746 m²
Value AED 618M
Award Date 12th October 2017
PARCEL 11
PARCEL 10
Towers: 2-Type A & 1-Type C
2 Towers: 1-Type A & 1-Type C
(starting from Level 2)
Starting from Level 2
Shared GF, 2 Podium including
Shared GF, 2 Podium including foundation, services
Project
foundation, services
Tower A3: (G+2P+14)
Details Tower A5: (G+2P+16)
Tower A4: (G+2P+14)
Tower C4: (G+2P+16)
Tower C4: (G+2P+16)
363 nos. apartment units
532 nos. apartment units
BUA 106,657.61 m2
Duration 24 months
Project
Details
Duration 24 months
BUA 33,435 m2
Duration 18 months
BUA 135,404 m2
Value US 150 million
Award Date 27th October 2016
Duration 38 months
BUA 136,306 m²
Value USD 130.55 Mil.
Duration 27 months
Akoya Artesia Towers is a 4 star hotel and serviced apartments that comprise
of 4 towers connected together with common Podium.
Tower (A) : G+3P+24 (Height: 110.18m) -- 4 Star Hotel
Tower (B) : G+3P+20 (Height: 89.68m) -- Serviced Apartment
Tower (C) : G+3P+19 (Height: 89.68m) -- Serviced Apartment
Project Tower (D) : G+3P+14 (Height: 73.50m) -- Serviced Apartment
Details The structural system is composed RC concrete structure with aluminum
and
Glazing curtain walls with Special Roofing Design at a high elevation.
BUA 48,000 m²
Project
USD 59.9455 Mil.
Value
Awarded
2010-08-24
Date
Construction
27 months
Period
Southern Sun Hotel is a four-star Hotel (4B+G+4P+MEP+18+R), which
constructed by CSCEC. A total of 353 en-suite rooms and suites comprise
Project the luxurious accommodation, which is a four-star hotel nearing completion in
Details the Tourist Club area of Abu Dhabi, close to the city’s corniche.
BUA 89,500 m²
Project
USD 238.2898 Mil.
Value
Awarded
2013-09-30 (on going)
Date
Viceroy Dubai is the ultimate destination for an urban resort. This is located at
the main entrance of the Palm Jumeirah’s trunk. Enjoy the beach, the exciting
landscaping and yet, within 10 minutes, you can have a meeting at the world
Project famous Burj Khalifa. The location enjoys convenient and fast connections to the
Details major highways, providing great access to the whole of Dubai. The site enjoys
spectacular views not only of the sea but also Dubai’s dynamic skyline. A luxury
hotel, serviced apartment and residential apartment development on a prime
beach location.
BUA 302,171m2
Project
USD 351.75 Mil.
Value
Awarded
2014-6-24 (on going)
Date
The (B+G+13) Resort Hotel will be constructed 5 stars hotel, which located on
Plot No. PJTRH02, at the Palm Jumeirah, Dubai, UAE, involves the
Project
construction of (B+G+13) Resort Hotel Building.
Details
The structural system of this project is composed of RC works. This will be
located just adjacent to the Viceroy Hotel project in Palm Jumeirah island.
BUA 75,646.9 m²
Project
USD 16.900 Mil.
Value
Awarded
2014-12
Date
The ARENCO CRESENT RESORT HOTEL project is a five star hotel and
located on Plot No.PJCRC39, at Palm Jumeirah, Dubai, U. A. E. The site
has a total plot area of 47,364 square meters, and total construction area is
Project
75,646.9 square meters.
Details
BUA 139,832 m²
Project
USD 54.500 Mil.
Value
Awarded
2014-7
Date
The Project locates at the heart of Jumeirah Village Circle. The proposed 59-
Project storey high-rise tower is comprised of a 4-star hotel with 234 hotel rooms,
234 hotel apartments and 30 penthouses, retail, specialty restaurant, and
Details
relevant hotel amenities, facilities and support areas.
BUA 54,000 m2
Project
USD 44.6501 Mil.
Value
Contract
2005-06-01
Period
Period
26 months
Project
Residential Tower (5B+G+34+Mech+R)
Details
BUA 125,470m2
Project
USD 42.465 Mil.
Value
Contract
2006-05-01
Period
Construction
19 months
Period
Project
3B+G+35+2 Mech, Residential / Commercial Tower
Details
BUA 65,879 m²
Project
USD 46.2837 Mil.
Value
Contract
2007-02-01
Period
Project
Office Tower (2B+G+4P+24+Roof)
Details
BUA 436,841 ㎡
Project
USD 363.4631 Mil
Value
Contract
2007-01-01
Period
Construction
25 months
Period
Skycourts is located within the Dubailand Residence Complex. Designed in
BUA 57,600 m²
Project
USD 102.6738 Mil.
Value
Contract
28 months
Period
Al Hikma Tower is office building (2B+G+61) with height is 282.36m. Structure
system is Steel frame +core wall system with malposition column + beam slab.
Mega steel truss to be located on transfer floor to connect the core wall with
outer tube. There are 32 Fins to be installed in the four corners of the tower, and
two big size of LED photos will be built on roof floor of building as the Roof
Project
Feature.
Details
First Prize of Scientific and Technological Achievements
(Provincial)(China State Construction)
BUA 389,735 m²
Project
USD 411.3803 M
Value
Contract
32 months
Period
City of Lights project is composed of 5 towers and 2 podiums. The 5 towers
divided into two parts. One part is luxury residence composed of C2 Tower
(35F) and C3 Tower (31F) with adjacent podium. The highest tower is 146m.
Project The other part is the residence and office composed of C10 (36F), C10A
Details (44F), and C11 (36F), the highest is 203.35m. The structure system of the
tower is frame-core wall structure. The facade is glass curtain wall, which can
make full use of local sunshine resources and increase the outdoor landscape
of better effect. There are swimming pools o the roof of the podium.
BUA 160,000m²
Project
USD 405.674 M
Value
Contract
36 months
Period
Project
3B+G+5P+34; 240m high
Details
BUA 132,000 ㎡
Project
USD 117 Mil
Value
Contract
60 months
Period
Doha Tower comprise of 4B+G+2P+44; 230m high. This project won the
following award and prize:
Project National Winner in Qatar for the MEED Quality Awards
Details ‘Best Tall Building Worldwide" and "Best Tall Building Middle East &
Africa" in the 2012 CTBUH Awards
BUA 300,000m²
Project
USD 72 Mil.
Value
Contract
24 months
Period
Project
Under ground is 4storeys; depth of the foundation is 17.8m.
Details
QA/QC Manuals
1.0 QA / QC Management
This section will give a brief overview of the QA/QC procedures of CSCEC ME that will be
implemented for this “Downtown Views II” project.
CSCEC ME is committed to meeting the highest levels of quality in all its business activities.
The organization aims to practice and promote the highest quality standards within all projects.
CSCEC ME will not compromise on our commitment to meet client requirements, deliver
exceptional service, identify, and eliminate all unnecessary quality-related costs. CSCEC ME aim
to meet the following goals:
Meet or exceed the expectation of our customers;
Systematically eliminate abortive work in all workplaces; and
Continually improve our performance through regular reviews.
It is a requirement that good quality management is a primary consideration for all CSCEC
ME projects and that all operations are carried out to the highest standards. Within the CSCEC
ME framework for quality management, each project of CSCEC M is required to:
Maintain quality management systems meeting the requirements of ISO 9001 and
continually improve our performance.
Ensure that resources and infrastructure necessary to ensure improvement is
provided.
Adhere to requirements set by applicable authorities, international codes and
standards.
Ensure the integrity and appropriateness of quality inspection, auditing and testing
activities to ensure free and honest reporting;
Set and achieve clearly defined quality objectives;
Provide all necessary information, training and supervision to all its personnel and
subcontractors.
Ensure all employees are made aware of their individual responsibilities in relation
to quality;
Promote our quality management system to sub-contractors, suppliers, customers
and the communities associated with our business.
Other relevant documents related to QA/QC procedures are enclosed such as Corporate
QHSE Manual, QA/QC Policy, QA/QC Plan and ISO certificates.
COPYRIGHT ©
No part of this manual may be reproduced in any form by print, photocopy, microfilm or any other means
wholly or in part or disclosed to any person outside CSCEC without the written permission of the
Management. This document is intended for use by the staff or the interested parties who enter into an
agreement with CSCEC.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
TABLE OF CONTENTS
Table of Contents
6 Management Responsibility
7 Resource Management
9.1 General
9.2 Monitoring & Measurement
9.3 Control of Non Conformance
9.4 Analysis of Data
9.5 Improvement
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
SECTION 1 - ISO 9001 : 2008, ISO 14001 : 2004 & OHSAS 18001:2007
REQUIREMENTS & DOCUMENT MATRIX
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
4.4.1 Resources, Roles, Responsibility and Authority 5.1, 5.2, 6.5.1, 6.5.2 &
7.1
4.4.2 Competence, Training and Awareness 7.1 & 7.2 HR-P-02
4.4.3 Communication 6.5.3 & 8.6 I-P-02
4.4.4 Documentation 5.3, 10 QHSE M
4.4.5 Control of Documents 5.4 I-P-01
4.4.6 Operational Control 8.9.1
4.4.7 Emergency Preparedness and Response 8.11 HSE-P-04
4.5 Checking
4.5.1 Monitoring and Measurement 8.10, 9.2.4
4.5.2 Evaluation of Compliance 9.2.4
4.5.3 Nonconformity, Corrective and Preventive
9.3, 9.5.1, 9.5.2 & 9.5.3
Action
4.5.4 Control of Records 5.5 I-P-03
4.5.5 Internal Audit 9.2.5 I-P-04
4.6 Management Review 6.5.4 I-P-05
QHSE MANUAL REFERENCE
OHSAS 18001:2007 REQUIREMENTS
SECTIONS PROCEDURES
1 Scope 2, 2.1
2 Reference Publications 2, 2.3 (but not related)
3 Terms & Definitions 3
4 OH&S Management System Elements 6, 8 & 9
4.1 General Requirements 6,8 & 9
4.2 OH&S Policy 6.3 QHSEM
4.3 Planning
4.3.1 Hazard Identification, Risk 8.2 HSE-P-01
Assessment and determining controls
4.3.2 Legal and Other Requirements 8.3 HSE-P-02
4.3.3 Objectives & Programme(s) 6.4.1& 8.4
4.4 Implementation and Operation
4.4.1 Resources, roles, responsibility, accountability
5.1, 5.2, 6.5.1 & 6.5.2
and authority
4.4.2 Competence, training and awareness 7.1 & 7.2
4.4.3 Communication, participation and Consultation 6.5.3 & 8.6
4.4.4 Documentation 5.3, 10 QSHEM
4.4.5 Control of documents 5.4 I-P01
4.4.6 Operational Control 8.9.1
4.4.7 Emergency Preparedness and Response 8.11 HSE-P-04
4.5 Checking
4.5.1 Performance Measurement & Monitoring 8.10, 9.2 & 9.4
4.5.2 Evaluation of compliance
4.5.3 Incident investigation, non-conformity, corrective
and preventive Action
9.3, 9.5.1, 9.5.2 & 9.5.3 HSE-P-03
4.5.4 Control of records 5.5 I-P-03
4.5.5 Internal audit 9.2.5 I-P-04
4.6 Management Review 6.5.4 I-P-05
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
The QHSE Manual and its supporting procedures integrate the Quality, Health, Safety
and Environmental requirements of China State Construction Engineering Corporation
and is based on the management system standards of ISO 9001 : 2008, ISO 14001 :
2004 and OHSAS 18001:2007 for Quality, Environment and Occupational Safety &
Health respectively.
This QHSE manual and its supporting procedures are intended to:
Operate company’s business in line with company’s policy, customer needs and
statutory requirements.
Demonstrate the ability to consistently provide a product that meets customer and
applicable regulatory requirements.
Enhance customer satisfaction through effective application of the QHSE
Management System, provision of continual improvement in the QHSE processes
which minimize / prevent defects and assurance of conformity to customer and
applicable regulatory requirements
Assure conformance with the company’s QHSE Policy, and likewise demonstrate
such conformance to customers and all other interested parties.
Achieve elimination, or minimisation, of occupational health and safety (O H & S)
hazards to employees and other interested parties who may be exposed to O H& S
hazards associated with our activities and to create safe working environment.
Achieve avoidance, reduction and control of environmental pollution from activities
being carried out or operated.
Prevent, minimize and control wastages thus achieving conservation of natural
resources.
The scope of this integrated management system of the company shall be based on:
‘Design, Construction and Completion of Construction Projects & Design Installation and
commissioning of Mechanical Electrical and Plumbing Works; in Middle East Countries”.
2.2 Application
All requirements of ISO 9001: 2008 shall be applicable to the nature and scope of the
company’s business processes.
However, the ISO 9001: 2008 clause, “7.3 Design and Development”, shall be treated as
inapplicable if and only if the particular building construction project completely adopts
the building design of the customer or his representative and bears no responsibility over
the design and development process.
“Design & Build” projects, if undertaken by the company, shall be controlled through
consultants engaged and managed by the company.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
All requirements of ISO 14001: 2004 and OHSAS 18001:2007 shall be applicable to the
nature and scope of activities the company is engaged in.
For the purpose of system alignment and in-house standardisation, the most stringent
clause(s) / sub-clause(s) of any one management standard compared with its
corresponding clause(s) / sub-clause(s) of the other management standard(s) shall be
considered for application in the integrated management system of the company.
For example, clause 4.2.3 Control of Documents in ISO 9001 : 2008 and ISO 14001 :
2004 has more stringent requirements as compared with clause 4.4.5 Document and
Data Control in OHSAS 18001:2007 . Therefore, the requirements called in 4.2.3
Control of Documents of ISO 9001: 2008 and ISO 14001 : 2004 shall be adopted for
application in the company’s integrated management system.
On the whole, the HSE portion of this integrated management system has been primarily
developed from the ISO 9001 Quality Management System model. But where there are
unique requirements specific to ISO 14001: 2004 and OHSAS 18001:2007 standards,
for example, 4.4.7 Emergency Preparedness & Response, this QHSE Manual shall bear
additional section / sub-section to address 4.4.7 Emergency Preparedness & Response,
and specific QHSE procedure shall also be documented.
1.3.1 ISO 9000 : 2005, Quality Management Systems - Fundamentals & Vocabulary
1.3.2 ISO 9001 : 2008, Quality Management System - Requirements
1.3.3 ISO 14001 : 2004, Environmental Management Systems - Requirements with
guidance for use
1.3.4 OHSAS 18001:2007 , Occupational, Health & Safety Management Systems -
Specification
1.3.5 Customer Specifications (Developers / Consultants)
1.3.6 Specified British Standards
1.3.7 Specified Codes of Practices
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
d) Statutory Requirements
Auditor - The individual who carries out the QHSE audit. Appointed by the
auditing organisation or team to perform part or all of an audit.
Lead Auditor - The team leader who supervises an audit team before and during
an audit, and for reports and corrective actions after the audit.
A person who is qualified and authorised to manage and direct an
audit.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Non-conformance / - Material and product, or work / process that does not meet the
Nonconformity requirements of the relevant specifications, contract or regulation.
- Any deviation from work standards, practices, procedures,
legislation & regulations, management system performance etc. that
could either directly or indirectly lead to product defects, injury or
Illness, property damage, damage to workplace environment, and
environmental pollution or a combination of these.
Interested Parties - Person or group having an interest in the QHSE performance and
success of our business processes.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Incident - Event that gave rise to an accident or had the potential to lead to
an accident.
(“Near-miss”, where no ill health, injury, damage, or other loss
occurs, is also called an incident)
Accident - Undesired event giving rise to death, ill health, injury, damage or
other loss.
Hazard - Source or situation with a potential for harm in terms of injury or ill
health, damage to property, damage to workplace environment,
or a combination of these.
The above-stated definitions shall often be used in our integrated management system of
quality, health, safety and environment and thus envisaged as essential for the
interpretation and common understanding of CSCEC management and staff.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
P.O.Box: 63932,
Dubai,
United Arab Emirates
Tel: +971 – 4 - 4537268
Fax: +971 – 4 - 4537368
Email:
The main office can be contacted for details of its worksite offices located at the
respective sites of building construction works.
VISION:
Ensure we create safe and hygienic working environments for workmen involved in the
project.
Achieve client satisfaction fully for delivering the product qualitatively in time.
We treat employees as the most valued asset of the company and recognise that the
quality, motivation and performance of our employees are the key factors in achieving our
success.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
CSCEC shall
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Budget
Preventive Actions, Continual Review and Tender
improvement and Customer
Projects Submissions Project
Control
Communication Project Reporting &
Procurement Budget &
Control & Materials , Works & Services (worksites Requests Costing
Supplier /
)
Sub- Design & Development Control of
Quality
Contractor
Design Design Control Documents &
& Safety
Assessment
& Coordination Data Analysis
Control of outsourced design
Procurement Control
& Supplier / Sub-Con
Suppliers / Sub- Assessment
Procurement ASL Insurance,
Finance
Contractors Quotations
Bonds & Funds
IT Admin
Computers, Facilities &
Deputy General
Managers
Management
Representative
Senior Project Accountants Procurement Quantity Manpower Clerical Deputy Tender and
Note : The Project Surveyors & Officers Cost Control
Managers Assistants
QHSE Team will be (stationed at respective Manager
reporting to the Chief site offices)
Representatives and
Project Managers
Project Managers Accounts Senior Quantity
(stationed at respective Assistants Surveyors &
site offices) Quantity Surveyors
Project Teams
(stationed at respective
site offices)
Note : Refer to the site-specific Project Quality Plan and Project Health & Safety Plan and Environment Management Plan for details of individual
Project / Site Organisation Chart and HSE Organisation Chart.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If any document is printed it becomes uncontrolled and for reference
only.
1. Existing and potential developers (or appointed consultants) call for pre-qualification
and / or tender participation for new projects.
2. Awards contracts, and provides acceptance, approvals, inputs and feedback to
submissions, proposals and queries from CSCEC.
3. Developers and their representatives monitor the works progress and QHSE
operational requirements in the awarded projects, and issue reminders & raise
complaints, as appropriate.
4. Buyers and end users provide request for defects-servicing and ease-of-use
requirements.
5. Authorities monitor the projects on compliance with legislation and other requirements
(eg. DM/TECOM/JAFZA/RTA etc) and issue notices/ orders, and imposes fines /
summons / court orders, as appropriate.
6. Public demands safe, secured, pollution-free and disruption-free neighbourhood.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
11. The General Manager and his management team shall review the organization’s
QHSEMS, at planned intervals, to ensure its continuing suitability, adequacy and
effectiveness. This review shall include assessing opportunities for improvement
and the need for changes to the QHSEMS, including the policy and objectives by
audit of the implemented QHSEMS.
QHSE Department
1. The Quality & Safety Department, headed by the Management Representative, shall
mainly function in a supporting role to the implementation, maintenance and
improvement of the QHSEM management system (QHSEMS) pertaining to ISO
9001: 2008, ISO 14001:2004 and OHSAS 18001:2007.
2. The Quality and Safety Department shall provide the overall coordination and
supervision of the implemented QHSEMS.
3. The Quality and Safety Department shall be responsible for the development and
control of both the initial and revised issues of the QHSE Manual and QHSE
Procedures.
4. The Quality and Safety Department shall generate the initial Project Quality Plan
(PQP) and the Project HSE Management System for mobilizing projects for their
review & customization and revision to suit specific needs, if any.
5. The Quality & Safety Department shall collect statistical data on compiled customer
complaints / feedback, nonconforming materials / works, internal audit results, HSE
non conformance (of inspection failures, authority summons and accident rate), etc
from the projects and / or internal auditors for the overall analysis by the
Management Representative and top management in Operations and / or
Management Review Meetings.
6. The Quality and Safety Department shall also be responsible for periodic inspection
of worksites and coordinating company-wide improvement programs, if any.
7. The Quality and Safety Department advises the top management on emerging
QHSE issues, regulations and specifications. The department takes charge of
disseminating information to projects on HSE legislation updates.
8. The Quality and Safety Department shall be responsible for conduction of in-house
QHSE awareness programs, HSE Aspects/ Hazards Identification and Impacts /
Risks Evaluation Training and QHSE Site Implementation Training.
9. The Quality and Safety department shall be responsible for planning and conducting
Internal Audits, assuring the adherence of the IMS through the company’s’ different
level.
10. The Quality and Safety Department shall particularly monitor performance indicators
of projects in the form of Internal Audit Results, Accident Frequency Rates (AFRs),
related authorities, Demerit Points and Corporate HSE Inspection / Audit Results,
etc, and propose to top management to accord incentives or disincentives to these
projects, as appropriate.
11 The Quality and Safety Department shall ensure QHSE records of the completed
projects in a suitable storage place till the expiry period of those records.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Administration Department
1. The Admin Department shall be responsible for preparing the company level
documents inclusive of annual report, and the like.
2. The Admin Department shall be responsible for contacting government, applying for
approval and authorisation, etc.
3. The Admin Department shall be responsible for public relations, especially contacting
the Embassy and the Consulate.
4. The Admin Department shall be responsible for contacting the Head Office.
5. The Admin Department shall be responsible for reception affairs inclusive of
transportation, hotel and dinner.
6. The Admin Department shall set up office system and keep office in order.
7. The Admin Department shall be responsible for managing of reception desk.
8. The Admin Department shall be responsible for procuring office building, security and
maintenance of office premises and facilities at the Head Office.
9. The Admin Department shall be responsible for controlling and managing company’s
vehicles inclusive of procurement, repairs, maintenance, license renewals, insurance,
top up of cash cards, etc.
10. The Admin Department shall provide transport service for eligible staff through
the use of company vehicles and drivers.
11. The Admin Department shall be responsible for identifying & directing the staff on
conservation of resources.
12. The Admin Department shall be responsible for managing of head office meeting
inclusive of arranging place, suggesting agenda, drafting minutes and supervising the
implement of meeting resolution.
13. The Admin Department shall also be responsible for provision of site office furniture
and equipment (except for computers & accessories which are taken charge by the IT
Department) for mobilising projects.
14. The Admin Department shall approve request forms for purchase of office stationery
and equipment.
15. The Admin Department shall be responsible for general insurance matters inclusive
of claims.
16. The Admin Department shall be responsible for other mission and tasks assigned by
the Top Management.
HR Department
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Procurement Department
IT Department
1. The IT Department, headed by the IT manager, shall be responsible for daily network
administration and system management in the Head Office.
2. The IT Department shall provide technical support for all end users in operating
systems, hardware, communication devices and other peripherals.
3. The IT Department provides end-user training as appropriate.
4. The IT Department establishes policies, rules and regulations, as appropriate,
pertaining to computer and network usage.
5. The IT Department shall be responsible for overall control on use of photocopy
machines, facsimiles, and telephone and internet facilities.
6. The IT Department ensures security of intranet through backup of system in the main
frame, and restriction of access to controlled network files through passwords.
7. The IT Department processes all approved requests for computer, computer
peripherals and software, and provides the necessary supplies to the site offices
through new purchases or site-to-site transfers.
8. The IT Department is responsible for the application of telephone lines as per project
requirements at the worksites.
Finance Department
1. The Finance Department, headed by the Financial Manager, shall be responsible for
cash flow planning and monthly preparation of cash flow position.
2. The Finance Department shall ensure prompt receipt of payment from clients /
debtors.
3. The Finance Department shall control and ensure proper payments to sub-
contractors / suppliers / creditors and payroll.
4. The Finance Department monitors project costs and financial performance through
monthly job costing reports to the General Manager and Deputy General Managers.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
5. The Finance Department shall compile annual statutory accounts and liaise with
auditors on finalisation of audited accounts.
6. The Finance Department shall also be responsible for insurance procurement
pertaining to Contractor’s All Risks, Workmen’s Compensation and Performance Bonds.
Projects / Worksites : Project Team (inclusive of the Project Quality Plan Team
and Project HSE Committee)
1. The project team at the respective worksite, headed by the Chief Project
Representative / Project Manager, works together with the client, client
representatives (Consultants, Resident Engineers / Architects, Clerks-of Works, etc),
sub-contractors, staff & workers and neighbours to achieve the common goals of
meeting the project specifications in terms of on-time handover and QHSE
requirements.
2. The project team develops and accordingly updates / revises specific Project QHSE
Objectives (inclusive of HSE Management Programmes), Project Quality Plan,
Project HSE Management System, in-house Works Instructions & Method
Statements, Work Programmes, Inspection & Test Plans, Shop Drawings and
Checklists / Forms to coordinate and control the execution of works in the project.
3. The project shall control its suppliers and sub-contractors, and gear them towards
the Project QHSE Objectives.
4. The project shall focus on customer requirements inclusive of statutory and
regulatory requirements, and respond to customer calls on time.
5. The project shall perform supplier and sub-contractor assessment as required by the
Procurement Department.
6. The project shall measure and monitor data on client complaints / feedback, non-
conforming materials / works, QHSE inspection & test failures, etc, and submit
compiled and analyzed data to the Corporate Quality & Safety Department.
7. The project team shall undertake effective corrective actions for QHSE non-
conformities and effective preventive actions for potential QHSE non-conformities
thus contributing to continual improvement.
8. The HSE Committee of the project that includes the Project Manager and HSE
Manager shall be responsible for identification and evaluation of HSE Aspects /
Hazards and Impacts / Risks from the provided corporate register.
9. This identification and evaluation of HSE Aspects / Hazards and Impacts / Risks
shall be an ongoing process by the Project HSE Committee.
10. The Project Manager / HSE Manager of the project shall maintain an approved and
updated Register of HSE Aspects / Hazards and Impacts / Risks
11. The Project Manager and team shall be responsible for customising and finalising
the HSE Objectives for those aspects and hazards respectively associated with
significant impacts and risks.
NOTE : The detailed responsibility & authority of each site office staff (inclusive of
the Project Manager) shall be made available in the site-specific Project Quality
Plan and HSE Management System of the individual project
Maintenance Department
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
1. After receiving the Initial Completion Certificate of the project, a Maintenance team to
cover the Defects Liability Period will be formed and will be managed by the Project
Team Manager or another manager will be appointed. The Project Team will be hand
over all the documents required to the Maintenance Team.
2. The Maintenance team shall carry out defects servicing during the maintenance /
defects liability period of the handed-over project.
3. The Maintenance Team shall promptly respond to customer and end user calls, and
carry out the defects rectification in the soonest possible time.
4. The Maintenance Team shall take data on common defects for analysis by top
management to initiate improvement activities.
5. The Maintenance Team Shall maintain the completed project records in a suitable
place till the expiry period of those records.
All suppliers and sub-contractors engaged in the projects shall deliver timely supplies
and sub-contract works for project execution as per the developer / consultant
specifications, contractual requirements, statutory and regulatory requirements and in-
house QHSE requirements.
The above stated documentation is hierarchical, i.e., from QHSE Policy down to QHSE
Records
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Top management of CSCEC shall ensure that customer requirements are determined
and fulfilled in order to achieve customer satisfaction.
Refer to the following page for the documented Quality, HSE and Environmental Policy
of CSCEC.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Quality Policy
Our Policy is to build a first grade construction process product by assigning the utmost
importance to Quality in order to achieve high levels of Client satisfaction. The policy
further stipulates that no task or service is so urgent that Quality requirements should be
compromised.
We shall ensure that the Quality Policy is communicated and understood within the
organization, and made available to all interested parties.
The Quality Policy and respective Key Performance Indicators (KPI) for each functional
department shall be annually reviewed for its continuing suitability and appropriateness,
and accordingly revised if required.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Managerial and supervisory staffs have individual responsibilities for the implementation of
this policy and must ensure that environmental issues are given adequate consideration in
the planning and day-to-day supervision of all work.
CSCEC will fully comply with the duties placed upon it within the requirements of all
applicable UAE legislation whilst at all times complying with, as a matter of best practice, the
requirements and duties set out within Approved Guidance as issued by regulatory
authorities and other organisations. As part of the company’s commitment to maintaining the
highest levels of environmental management, it is the intention that the company will operate
systems and procedures in line with the requirements of ISO 14001:2004.
All employees, sub-contractors and suppliers are expected to co-operate and assist in the
implementation of this policy, whilst ensuring that their own works, so far as is reasonably
practicable, are carried out without risk to themselves, others or the environment. This
includes co-operating with management on any environment related matter.
CSCEC will take all practical steps to ensure that potential hazards and risks to the
environment are identified and that suitable and effective preventive control measures are
implemented. All employees will be provided with the necessary resources, equipment,
information, instruction and training to fulfil the requirements of this policy.
The directors have overall responsibility for all environmental matters. The operation of this
policy and the associated procedures will be monitored and reviewed on a regular basis to
ensure that they remain current and applicable to the company’s activities.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
To this end the Company has a continuing programme for the systematic development of
standards and procedures to satisfy the legislative, and moral, requirements of Health and
Safety Management.
Provide a safe working environment that is without risk to health and welfare of
employees, subcontractors and the general public.
Monitor or Audit the performance of all activities against this Safety Policy.
Continually strive to improve the overall safety, health and performance of the Company.
Ensure that safety is an integral part of the management of the Company, and
All employees, sub-contractors and subcontractors are expected to co-operate and assist in
the implementation of this policy, whilst ensuring that their own works, so far as is reasonably
practicable, are carried out without risk to themselves or others. This includes co-operating
with management on any health and safety related matter.
CSCEC will take all practical steps to ensure that potential hazards and risks to the safety
and wellbeing of all persons involved in their operations are identified and that suitable and
effective preventive control measures are implemented. All employees will be provided with
the necessary resources, equipment, information, instruction and training to fulfil the
requirements of this policy.
The directors have overall responsibility for all health and safety matters. The operation of
this policy and the associated procedures will be monitored and reviewed on a regular basis
to ensure that they remain current and applicable to the company’s activities.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Objectives and targets shall be specific to relevant department and worksites. They shall
be developed through legal and other requirements to which CSCEC subscribes, and
information about significant HSE aspects / hazards.
NOTE: The Process Matrix Form (Performance Indicators) Form No. PM-F-05
indicates the main Performance Indicators and measures for each
department/process from the Corporate and Project Levels. However the
objectives shall be measured as applicable based on the project circumstances
and additional measure can be added as per the project requirement.
6.4.2 QHSEMS
Accountability for the Health Safety and Environmental Legal compliance and
performance rests ultimately with the Managing Director. The management of this is
subsequently delegated to Mr Zhu Jianchao, Deputy General Manager as part of the role
as Management Representative for the Company.
the planning of the QHSE is carried out in order to meet the requirements of the
organisation’s business process model (see Figure 1), as well as the QHSE
Objectives, and
the integrity of the QHSEMS is maintained when changes to the QHSEMS are
planned and implemented.
Site-specific Project Quality Plans and HSE Plan / HSE Management Programme shall
cover the detailed responsibility and authority of each worksite management and staff.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Refer to Section 5 QHSE Management System of this manual for the responsibility and
authority of the Management Representative.
I-P-14 Training
PD-P-01 Procurement Planning
PD-P-02 Procurement
PD-P-03 Vendor Evaluation
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Personnel (including sub-contractors’ personnel) performing work that can affect product
quality and that can cause significant environmental impacts and / or occupational health
& safety risks shall be competent on the basis of appropriate education, training, skills
and experience. CSCEC shall retain associated records.
CSCEC shall define, document and communicate roles, responsibilities and authority to
facilitate effective QHSE management and ensure that its personnel (including sub-
contractors’ personnel) are aware of :
(i) the relevance and importance of their activities and how they contribute to the
achievement of the QHSE policy, QHSE objectives and QHSE management system
requirements,
(ii) the HSE impacts and risks, actual or potential, of their work activities and the HSE
benefits of improved personal performance,
(iii) their roles and responsibilities in achieving conformity with the requirements of the
HSE management system, and
CSCEC shall identify training needs as required pertaining to HSE hazards / risks and
QHSE management system, determine the competence level for personnel performing
work and provide training or take other actions to meet these needs. CSCEC shall also
evaluate the effectiveness of the actions taken. Appropriate records of education,
training, skills and experience shall be maintained.
I-P-14 Training
I-P-02 Internal Communication
HSE-P-01 HSE Risk Assessment and HSE Plan / Management Programme
HR-P-01 Staff Recruitment
HR-P-03 Staff Payroll
7.3 Infrastructure
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
CSCEC shall determine and manage the work environment needed to achieve
conformity to product and other QHSE requirements.
CSCEC shall plan and develop the processes needed for product realisation that shall
be consistent with sub-sections 5.1 - 5.3 and 6.3 - 6.4 of this manual.
The respective Project Manager shall formulate Project Quality Objectives (incorporated
in the Project Quality Plan) prior to the start of the project. Though these Project Quality
Objectives shall be built on the basis of common project goals like on-time completion,
control the non-conformities, client satisfaction etc, they shall be regularly reviewed and
updated to drive the project through continual improvement and overcome significant
weaknesses, if any.
The respective Project Manager and team shall also develop the project-specific Project
Quality Plan prior to the start of the project. This quality plan shall take into account of
the following:
The Project Quality Plan shall also be regularly reviewed and updated as per the
requirements of the construction progress by the Project Manager.
CSCEC shall identify the HSE aspects and hazards of its activities, products and
services within the scope of this QHSE management system that can control, and those
that it can influence taking into account planned and new developments, or new or
modified activities, products and services.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
CSCEC shall evaluate the significance of these HSE impacts and risks that require
control measures.
CSCEC shall document information pertaining to HSE aspects / hazards and impacts /
risks, and maintain such information up-to-date.
CSCEC shall ensure that significant HSE impacts and risks and the corresponding
effectiveness of the control measures are taken into account in establishing,
implementing and maintaining its environmental management system.
CSCEC shall identify and have access to relevant legal and other HSE requirements to
which it subscribes related to its HSE aspects. CSCEC shall determine how these
requirements apply to its HSE aspects and hazards.
CSCEC shall keep this information up-to-date, and shall communicate legal and other
HSE requirements to its employees, suppliers / sub-contractors and other relevant
interested parties.
CSCEC shall ensure that these applicable legal and other requirements to which it
subscribes are taken into account in establishing, implementing and maintaining its
environmental management system.
CSCEC shall establish HSE objectives and targets at each relevant function and level.
The HSE Manager of each project shall determine the project-specific HSE objectives
based on identification of (i) HSE aspects / hazards and evaluation of HSE impacts /
risks, (ii) compliance with applicable legal and other requirements, and (iii) continual
improvement. He shall then formulate and maintain comprehensive HSE Plan /
Management Programme incorporated with measurable HSE objectives and targets,
where practicable.
The HSE-related objectives for the functional departments of the Head Office are stated
this manual.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
The site-specific HSE objectives are documented in the HSE Plans / Management
Programmes of the projects. Each HSE objective shall be traceable to action plans /
measures with corresponding targets, responsibilities and required resources
The HSE Plan / Management Programme shall be reviewed on a biannual basis for any
amendment and updated if required.
CSCEC shall determine the requirements related to the product that includes:
CSCEC shall review the requirements related to the product prior to its commitment to :
submit tenders
accept contracts
accept changes to contracts
Records of the review and actions arising from the review shall be maintained.
Where product requirements are changed, CSCEC shall ensure that relevant documents
are amended and that relevant personnel are made aware of the changed requirements.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
CSCEC shall generally not communicate on significant HSE aspects common to the
construction industry and its customers (stakeholders). However, this external
communication on significant HSE aspects, if necessary, shall be effected as per site-
specific documented procedure or flow chart.
Design & Development shall only be applicable to CSCEC for any undertaken project
that is of the category, “Design & Build”.
CSCEC shall outsource the scope of design and development in any awarded design &
build projects. In other words, it shall control the design and development function
through a Design Department that manages the external design consultants responsible
for the design of the building.
CSCEC shall ensure the responsibility of the design professionals (i.e. the consultants)
in addressing the following essential requirements:
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
CSCEC shall evaluate and select suppliers based on their ability to supply product in
accordance with the stipulated requirements.
CSCEC shall establish and implement inspection or other activities necessary for
ensuring that the purchased product meets the specified requirements. The purchasing
information of CSCEC shall include the intended verification arrangements and method
of product release if CSCEC or its customers intends to perform verification at the
supplier’s premises.
CSCEC shall plan and carry out production and service provision under controlled
conditions. CSCEC shall also identify, plan and carry out those processes (including
maintenance activities) that are associated with the identified significant HSE impacts
and risks requiring control measures. These controlled conditions include the following:
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
The operational control shall also include the identification, traceability and preservation
of the product, wherever applicable, as outlined below:
Where appropriate, CSCEC shall identify the product by suitable means throughout
product realization. CSCEC shall identify the product status with respect to monitoring
and measurement requirements.
Where traceability is a requirement, CSCEC shall control and record the unique
identification of the product.
CSCEC shall bear responsibility, and provide the necessary care for any customer
property under its control or being used by CSCEC in production and service provision.
CSCEC shall identify, verify, protect and safeguard any such customer property in its
care, and ensure prompt reporting and maintenance of records for lost, damaged and
unfit-for-use customer property to the customer.
CSCEC shall identify, handle, package, store and protect the product and its
constituents throughout the phase of product realization. CSCEC shall, in this way,
preserve the conformity of product during internal processing and delivery to the
intended destination.
CSCEC shall determine the monitoring and measurement to be undertaken and the
monitoring and measuring devices needed:
CSCEC shall establish, implement and maintain plans and procedures to identify the
potential for, and responses to, incidents, accidents and emergency situations, and for
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
preventing and mitigating the environmental impacts, occupational illness and injury that
may be associated with them.
CSCEC shall periodically respond to actual emergency situations and accidents, and
prevent or mitigate associated adverse HSE impacts / hazards.
CSCEC shall review and revise, where necessary, its emergency preparedness and
response procedures, in particular, after the occurrence of incidents, accidents and
emergency situations.
9.1 General
CSCEC shall plan and implement the monitoring, measurement, analysis and
improvement processes needed:
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
CSCEC shall apply suitable methods for monitoring, and where applicable,
measurement of its processes and activities. These methods shall demonstrate the
ability of the processes / activities to achieve planned results in the form of specific and
measurable quality objectives in the QHSE Manual & site-specific Project Quality Plan,
and HSE objectives and targets in the site-specific Environmental Management Plan(s) /
Programme(s).
CSCEC shall monitor and measure the characteristics of the product to verify that
product requirements have been met. This shall be carried out at appropriate stages of
the product realization process in accordance with the planned arrangements (refer to
8.1 and site-specific Project Quality Plan).
CSCEC shall maintain records as evidence of conformity with the acceptance criteria.
Such records shall indicate the person(s) authorizing the release of the product.
CSCEC shall not proceed with the product release and service delivery until the planned
arrangements (refer to 8.1 and the site-specific Project Quality Plan) have been
satisfactorily completed, unless otherwise approved by a relevant authority, and where
applicable, by the customer.
CSCEC shall establish, implement and maintain documented procedures, to monitor and
measure, on a regular basis, the key characteristics of its operations and activities that
can have significant environmental impact(s) / occupational health and safety risk(s).
The HSE monitoring and measurement activities shall be proactive based on compliance
checks with HSE management programme, (refer to site specific HSE management plan
/ programme with HSE objectives and targets), operational criteria (refer to HSE
Operational Control Procedures and applicable legislation and regulatory requirements.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
The HSE monitoring and measurement activities shall be reactive for HSE accidents, ill
health, incidents and other historical evidence of deficient HSE performance.
Relevant records of monitoring and measurement data and results shall be maintained
to facilitate subsequent corrective and preventive actions.
CSCEC shall also establish, implement and maintain a procedure for periodically
evaluating compliance with applicable legal requirements, and other requirements, if
any, to which it subscribes. Records of the results of the periodic evaluations shall be
maintained.
CSCEC shall conduct internal audits of its processes / activities and functions at planned
intervals to determine whether the QHSEMS
conforms to planned arrangements (refer to 8.1, 8.2, 8.3 & 8.4), to the requirements
of ISO 9001 : 2008, ISO 14001 : 2004 and OHSAS 18001:2007 standards and to in-
house QHSEMS requirements, and
is effectively implemented and maintained.
The management responsible for the area being audited shall ensure that actions are
taken without undue delay to eliminate detected nonconformities and their causes.
Follow-up activities shall include the verification of the actions taken and the reporting of
verification results.
Selection of auditors and conduct of audits shall ensure objectivity and impartiality of the
audit process
CSCEC shall identify and control QHSE non conformance to prevent its unintended
occupancy, use or delivery, as appropriate (e.g. material / works not meeting quality
criteria OR ineffective / absence of HSE measures in work area as required by HSE in-
house operational criteria).
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
The control shall include taking of action to eliminate the detected nonconformity.
CSCEC shall maintain records of the nature of nonconformities and any subsequent
actions taken.
CSCEC shall define the controls and related responsibilities and authorities for dealing
with QHSE non conformance (inclusive of accidents and incidents) in a documented
procedure.
CSCEC shall determine, collect and analyze appropriate data to demonstrate the
suitability and effectiveness of the QHSEMS and to evaluate where continual
improvement of the effectiveness of the QHSEMS can be made. This shall include data
generated as a result of monitoring and measurement and from other relevant sources.
customer satisfaction
supplier / subcontractor performance
conformity to product requirements
characteristics & trends of processes and products including opportunities for
preventive action (including internal audit results)
HSE performance (inspection results by authorities / agencies, accident frequency &
severity rates, internal audit results, etc)
Projects shall perform a periodic analysis of the above-mentioned data (at intervals of
every 6 months) for self-regulated review and improvement (by means of corrective and
preventive actions) in areas of weaknesses, as applicable.
Each project shall submit an overall yearly analysis report to the Management
Representative two weeks prior to the Management Review Meeting for the top
management’s review and follow up action at the company level.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
CSCEC shall continually improve the effectiveness of the QHSEMS through the use of
QHSE policy, QHSE objectives and targets, audit results, analysis of data, corrective
and preventive actions, and management review.
CSCEC shall take action to eliminate the cause of nonconformities in order to prevent
recurrence. Corrective actions shall be appropriate to the effects of the nonconformities
encountered.
CSCEC shall establish a documented procedure to define the detailed steps for the
corrective action.
CSCEC shall establish a documented procedure to define the detailed steps for the
preventive action.
Refer to form no. I-F-02 Master List of Procedures on the electronic CD.
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
QA/QC / QA/QC / MR
A 13/07/08 Original Copy HSE HSE
Manager Manager
Rev. Date of Prepared Reviewed
Nature of Revision Approved By
No Revision By By
The only official, current & controlled version of any documented procedure and its related record(s) is the one available on the network. If
any document is printed it becomes uncontrolled and for reference only.
Our Policy is to build a first grade construction process product by assigning the utmost importance to Quality
in order to achieve high levels of Client satisfaction.
The policy further stipulates that no task or service is so urgent that Quality requirements should be
compromised.
CSCEC is committed to comply with our customers’ quality requirements inclusive of applicable legislation
and regulations.
We are committed to provide continuous efforts to identify and eliminate or manage defects associated with
its construction activities through continual improvement of Integrated Management System.
We shall ensure that the Quality Policy is communicated and understood within the organization, and made
available to all interested parties.
The Quality Policy and respective Key Performance Indicators (KPI) for each functional department shall be
annually reviewed for its continuing suitability and appropriateness, and accordingly revised if required.
TEMPLATE ONLY
CLIENT:
CONSULTANT:
PROJECT NAME
PROJECT ID
ISSUE RECORD
Document Ref: Date Signature
Created By Insert Project Quality Insert Date
Manager Name
REVISION RECORD
Revision No & Date Page No’s Revised Remarks
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 4
9. APPENDICES ............................................................................................................ 35
1. INTRODUCTION
1.1. PURPOSE
The purpose of this Project Quality Plan (PQP) is to describe the overall strategy for delivering
the Client’s Requirement at the Project Level.
The PQP shall be demonstrating the integration functional deliveries between various
departments at the project level for delivering the output of the Client.
1.2. SCOPE
The scope of this document is to cover the remaining phase of the Insert Project Name. in
defining the controls to be implemented by the various departments at the project level.
1.3. SCOPE OF WORK
Insert the Project Scope of Work as per mentioned in the Contract or the letter of Intent.
1.4. PROJECT MANAGEMENT SYSTEM
The Project Management System is the continuity of the Corporate Integrated Management
System.
It is the system developed for defining and identifying the project policies, objectives and
procedures necessary to control quality, health, safety and environment on the Insert Project
Name.
1.5. CUSTOMER SATISFACTION
Customer Satisfaction sits on top of the main aspects of our Top Management deliverables. They
shall endorse all the resources and facilities for achieving it. The Project Director/Project
Manager (Titles might change as per the Project Organization Chart) will be leading the project
team to guarantee the success of this major objective.
Customer satisfaction survey shall be done once a year or as required to record and improve any
areas of concern raised by the client. This enhances the continual improvement process to
achieve positive progress for the Company’s performance.
Please refer to the following documented procedure:
I-P-09 Customer Satisfaction.
1.6. CONTROL OF THE PROJECT QUALITY PLAN (PQP).
The PQP is a controlled document and shall not be altered or changed except by the authorized
personnel who will be either the Senior Quality Personnel at the Project Level or at the
Corporate Level.
The PQP shall be subject to review and change in case there is any change to the Scope of Work
or the Corporate Policies or Objectives from the Corporate or Project level
The latest revision of the PQP shall be maintained on the main server and the IP address shall be
addressed through an Internal Memo.
Any updates or review shall be communicated through an Internal Memo.
1.7. DEFINITIONS AND ABBREVIATIONS
1.7.1.Definitions
Client
Insert Client Name
1.7.2.Abbreviations
Note: The below abbreviations can be reviewed based on the content of the document.
CSCEC - China State Construction Engineering Corporation
PQP – Project Quality Plan.
PMT – CSCEC’s Top Management Team
PMS – Project Management System.
IMS – Integrated Management System
SSH – Southern Sun Hotel
SUPPLIER - supplier is a person from whom procurement activity is carried out by
Issue of a purchase order
QA - QUALITY ASSURANCE is the planning and organizing of a system or program to
maintain a required level of quality or reliability. This includes auditing the
system’s operation and related controls to assure that they are being executed
properly and functioning as expected. Quality shall be assured by Contractor/Client.
QC – QUALITY CONTROL is a part of Quality Assurance, implements the latter
by examining physical characteristics and comparing them to established and acceptable
Quality Documents as stated in the quality assurance program or plan
Quality shall be controlled by Sub-Contractor in accordance with the Quality
Documents.
ITP - INSPECTION & TEST PLAN means the document which contains sequence of
activities in a process, highlights the applicable Quality Documents, and inspection
criticalities.
PAR - PREVENTIVE ACTION REQUEST means to eliminate the causes of a
potential nonconformity or other potentially undesirable situation
CAR - CORRECTIVE ACTION means to eliminate the causes of a detected non-
conformity or other undesirable situation.
QUALITY DOCUMENTS - means drawings specification, procedure, record
formats, codes and standards specified in the documents issued by the
Contractor/Company to the Subcontractor.
SITE - means the place, designated by Client for further development, where the
construction activities shall be carried out by Sub-contractor.
PROCEDURE - describes how a process is performed.
TPI - Third Party Inspection
Doc. – Document.
No. – Number
DOCUMENT TITLE Site Project Quality Plan Page 6 of 35
Rev. – Revision.
Ref. – Reference.
Eot – Extension of Time
Note: For other General Abbreviations, please refer to the IMS Control CD –
Corporate QHSE Manual Doc. No. QHSEM Rev C.
1.8. REFERENCES.
2.1. LEADERSHIP
Leadership is one of the main skills that the Company’s Top Management ensures that it exists by
the Project Management Team (PMT). They will be the Key players in assuring, monitoring and
controlling the success of the Project Management System.
The PMT are the group of personnel assigned by the Managing Director to overview monitor and
control the performance and deliverables of the project.
The PMT for Insert Project Name are the following personnel:
Project director.
Chief representative.
Senior project manager.
Project manager.
Deputy chief representative.
Note: The above positions might change based on the project Organizations
The project policy is the guidelines on which its basis this document have been developed and the
project objectives are being set to achieve the Client’s requirement. In other terms it will be the
guide for delivering the project requirement as per the project specification and local authorities.
In order to satisfy the Project Quality Objectives, the Project Management Team committed to
implementing a fully functional Project Management System (PMS) that:
DOCUMENT TITLE Site Project Quality Plan Page 7 of 35
Ensures that the activities are undertaken through continual improvement process.
The Project Director will work through the period of the project to sustain and review the polices for
achieving the set objectives of the Project.
Submit payment Certificates in the agreed time frame.
Managing the Initial and the Final Handing over in a satisfactory manner.
Note: The above quality objectives shall be cascaded with the Scope of work.
Delivering the project as per the Client’s Requirement, QA/QC policy and Project
Programme.
Leading the Projects’ Department output.
Reviewing all the submittals for issuance to the Client.
Interfacing with the client & Consultant for resolving any concerns.
Responsible to deliver the project as per the programme and protect the company
interests concerning any EoT might be raised during the construction period.
Responsible to deliver the Project within the Estimated Budget.
The Project Manager is the main point of contact representing the Project Management Team
for the Southern Sun Hotel Project.
3.2. TECHNICAL MANAGER:
Ensure that all the work shall be executed as per the method statement and ITP.
Manage and guide the Site Engineer.
Review the daily reports before submission to the consultant.
Review the shop drawing, method statement and ITP prior to start any activity.
Ensure that the site team understands their role and outputs.
Ensure that all the resources and tools are available and in a good condition.
Ensure that all the safety requirements are being taken prior to start any activity.
Check the work at site and ensure that there no any non-conformances.
Ensure that all the materials being used are from the approved supplier and being inspected.
Liaise closely with Technical and QA/QC department
SITE ENGINEER:
QA/QC MANAGER:
Ensure that the documents retained are a true and accurate record.
Ensure that all the technical submittals are developed within the agreed submission
plan.
Ensure that all the construction at site as per the agreed method statement and
Inspection and Test Plans.
Assure that all the activities are being executed at site in a safe manner.
Manage the MEP construction team and ensure that there is a proper coordination
between different disciplines.
Manage the MEP subcontractors and ensure that they are briefed with all the
requirement of the project.
Ensure that the procurement process is ongoing based on the agreed schedule.
Responsible for the development of Status Reports as required demonstrating the
project status with respect to progress, submittals, Safety and Quality issues.
Ensure that the availability of adequate resources are present for each task.
Development and Submission of Monthly Reports.
Responsible to ensure that all the outgoing documents have the proper reference
numbers as per the control sheets.
Assisting the PMT in any administrative work.
4. PROJECT PLANNING
4.1. PLANNING
Plans will be developed as required throughout the Project. The Plans which will be developed are
the Project Quality Plan and Health Safety & Environmental Plan.
This Project Quality Plan (PQP) describes the arrangements for quality to be adopted and
implemented by the Project Team. It also describes the interface and controls to be undertaken by
the Insert Project name team members and identifies those common procedures to be implemented
for managing the project.
The HSE Plan describes general project arrangements for HSE and the activities that will deliver the
strategy, execution philosophy and performance expectations The plan also identifies those people
with specific responsibilities and accountability for HSE activities. It is to be used in conjunction with
the developed policy and procedures issued by CSCEC to give instruction on what measures need to
be taken to ensure that HSE risks are reduced to a level As Low As Reasonably Practicable It is
designed to be continually reviewed and updated.
5. PROCESS MANAGEMENT
All the project deliverables shall be monitored and controlled through identified processes
The following section “6” identifies the key processes required for managing the project and how
they will addressed and controlled.
The Following Documents Hierarchy Are The Documents Used For Identifying Various Processes As
Applicable To The Project Deliverables:
CORPORATE DOCUMENTS
QHSE POLICY
QHSE MANUAL
QHSE PROCEDURES
6. KEY PROCESSES
Note: The below Key Processes and its contents can be changed based on the Project Scope of Work.
It is the first process being taken by the Project Team. During this process all the deliverables shall be
identified by the project team based on the project scope. The output from this process shall identify
the other process required for delivering the project.
The main owner of the process shall be the Project Management Team.
Please refer to the following documented procedure:
PM-P-02 Data Mobilization.
PM-P-06 Project Execution.
Based On The Project Documentation (I.E. Drawings And Specifications), All The Required Shop
Drawings Shall Be Identified And A Submission Plan Shall Be Developed.
The Technical Engineers In Respect To Their Disciplines Shall Be Responsible For The Development Of
Any Shop Drawings Required For This Project. Development Of Shop Drawing Shall Be Adhering To
The Following Sections Of The Project Specifications Insert The Project Specifications Clause If
Applicable Or Otherwise Modify The Statement.
All The Drawings Shall Have A Proper Referencing Number Facilitating Its Control And Traceability.
The Reference Number Shall Indicate The following:
Relative Discipline.
Running Number.
Revision.
All The Shop Drawings Shall Be Submitted Under A Transmittal Cover Sheet (Refer To Appendix B –
“Insert The Name Of The Cover Sheet As Agreed With The Consultant”). All the Submitted
Transmittal Shall Have A Proper Reference Number And Registered For Easy Reference.
The Process Owner Shall Be The Technical Manager.
Please refer to the following documented procedures:
TD-P-01 Planning Drawing Submission.
TD-P-03 Development of Drawing..
I-P-11 Correspondence and Technical Submission.
The Technical Engineers During Their Review Process For The Design Drawings Shall Identify Any
Issues Requires Clarifications Or Which Might Have Potential Conflicts At The Construction Stage.
This Shall Be Done Through Sending Request For Information To The Consultant.
Please Refer To Appendix B, Indicates The “Insert The Name Of The Cover Sheet As Agreed With The
Consultant” Form That Shall Be Used During The Project Period.
The Technical Engineers shall be held responsible for this process.
Please refer to the following documented procedure:
TD-P-04 Preparing and Monitoring Request For Information.
In Order To Control The Drawing Version, All The Drawing Shall Have A Proper Sequential Numbers
And A Revision Number. In Case The Submitted Drawing To The Engineer, Need To Be Distributed To
The Project Team. The Technical Department Shall Stamp The Drawing “For Information” And
Distribute It Through Technical Explanation.
After The Approval Is Being Granted From The Engineer, The Drawings Shall Be Distributed Through
Another Technical Explanation And Stamped “For Construction”.
A Drawing Register Shall Be Always Updated Indicating The Developed Drawing Status And Shall Be
Distributed On Agreed Time Frame For The Reference Of Other Departments.
When A New Drawing Revision Is Being Issued The Old Revision Shall Be Stamped “Superseded”
The Contract Drawings Shall Be Stamped “Contract Drawings” As It Is Very Important To Identify
Them As They Shall Be The Basis For Future Comparison Or Reference.
The Original Version Of Drawings Shall Be Kept By The Contract Or Technical Department.
The Process Owner Shall Be The Technical Manager.
Please refer to the following documented procedure:
TD-P-02 Incoming Drawing Control.
After The Contract Is Reviewed The Project Planner Will Develop The Overall Baseline Programme
(I.E. Construction Schedule) Thus Identifying All The Tasks To Be Executed Based On The Scope Of
Work, The Following Steps To Be Followed:
General meeting(S) with construction team, procurement and technical will be held in order to
finalise the “Project execution plans” including the logistics of the site, the coordination between the
site the site offices and the overall main milestones of the project.
.As result of these meeting the planner will develop a level 01 & 02 detailed programme, to be
presented to the project teams for their approvals/comments.
Advance copy of the level 03-04 programme will be sent to the consultants / project manager for
informal review and comment (should take a week time)
DOCUMENT TITLE Site Project Quality Plan Page 21 of 35
By incorporating all above comments the programme will ready to be submitted as a construction
Programme to the Consultants for approvals.
The Project Progress Shall Be Monitored Based On The Baseline Programme And The Project
Progress Report Shall Be Developed.
The Progress Reports Will Consists Of 3 General Major Parts:
A Progress Update Demonstrating The Project Status As To Compare With The Base
Line Programme As Regards To The Timing And The Quantities Of Works Achieved
Report Of Delays Generated Due To The Contractor Lack Of Performance Together
With A Proposed Recovery Plans To Overcome Such Delays Especially When It Is In
The Critical Path.
Report Of Delays Generated Due To The Client / Consultants Lack Of Performance,
Highlighting If These Delays Would Generate Any Eots To The Project.
The developed schedule or programme of work and progress reporting shall be adhering to the
following sections of the project specifications Insert the Project Specifications Clause if
applicable or otherwise modify the statement.
The construction schedule shall be sent via a letter to the consultant.
The process owner for submitting the construction schedule shall be the Senior Planner.
Please refer to the following documented procedure:
PM-P-04 Project Planning.
6.6. PREPARATION OF METHOD STATEMENT AND INSPECTION AND TEST PLANS (ITPS)
The QA/QC department shall be responsible for identifying the main Method Statement and ITPs
required for the execution of the work.
This shall be done after the contract review process and through the Interfacing with different
department such as the Technical and Construction departments.
A Submission Plan Shall Be Developed For Monitoring The Preparation And Submission Dates. The
Submission Dates Shall Be Anticipated Based On The Approved Construction Schedule Considering
Enough Time For The Review Process To Take Place Prior To Start Any Activity At Site. The Review
Duration Shall Be Within Insert Agreed Durations Days As Per The Project Specs Insert The Project
Specifications Clause If Applicable Or Otherwise Modify The Statement.
Please refer to Appendix C indicates the following:
A Method Statement Template.
An Inspection and Test Plan Template.
Check List Template.
All The Produced Method Statement Shall Be Adhering To Insert The Project Specifications Clause If
Applicable Or Otherwise Modify The Statement And Shall Be Submitted Through Insert The Name Of
The Cover Sheet As Agreed With The Consultant (Refer To Appendix B)
The process owner for the development of the Method Statement and ITPs shall be the Project
Quality Manager
Please refer to the following documented procedure:
PM-P-05 Method Statement.
For controlling the quality of the work all the executed permanent activities shall be subject for
Inspection as per the approved Drawings, Method Statements and ITPs.
The Inspections can be divided into two stages:
6.7.1.Initial/Preparatory Inspections
These shall take place during the starting of any new activity at site. This shall be carried out by
Construction Manager, Site Manager, Site Engineers, Sr. QA/QC Engineers and QA/QC Engineers.
This is essential to ensure that the work will be carried out as per the approved Drawings, Method
Statement and ITPs. Also they shall ensure that the Inspections shall be submitted as per the ITP’s
hold points.
6.7.2.Ongoing Inspections
All the completed work at site shall be subject to Inspections on a regular basis by the Supervision
Consultant.
The Site Engineers shall be held responsible for checking the completed work at site prior to request
for Inspections. After conforming the work is being completed as per the Drawings, Method
Statement and ITPs, a “Request for Inspection” shall be raised attaching all the supporting
documents such as the approved drawings and checklist as applicable.
All the Inspection Request shall have a controlled reference number which shall indicates:
Disciplines (i.e. STR, ARC, ELEC, MECH, e.t.c).
Running Number.
Revision.
The QA/QC department shall advise the Construction department regarding the proper
reference numbers that shall be used through an Internal Memo.
An Inspection Request Summary shall be maintained and controlled by the Document Controller
registering all the Incoming and Outgoing Inspection.
The Inspection Process shall be adhering to Insert the Project Specifications Clause if applicable or
otherwise modify the statement of the project specifications
Please Refer To Appendix B, Indicates The “Insert The Name Of The Inspection Sheet As Agreed With
The Consultant” Form That Shall Be Used During The Project Period.
The process owner for the preparation and submission of the Site Inspections shall be the
Construction Manager.
Please refer to the following documented procedure:
PM-P-08 Project Inspection.
The testing shall be carried by third party who shall be approved by the Consultant. The QA/QC
Engineer shall be responsible to follow up the entire test that required to be conducted at site. They
shall be coordinating with the Laboratory for collecting the results and clarifying any requirement by
the Consultant.
All the testing requirements shall be followed as per the approved ITPs
All the tests request shall be prepared by the QA/QC Engineer and a reference number (Ref. No.)
shall be maintained in a proper sequence. The Ref. No. shall include:
Test Category.
Running No.
The categories of the planned test to be carried as follow:
Compaction Test.
Rebar Test.
Concrete Test (Compressive and Durability).
General Structural Test.
General Architectural Test.
Test Required for Facde.
General MEP Test.
All the equipments used for testing shall be calibrated and verified by the QA/QC
Engineers.
The testing Process shall be adhering to Insert the Project Specifications Clause if applicable or
otherwise modify the statement of the project specifications
The process owner for the Site Testing shall be the QA/QC Engineers.
All the material required to be procured for the project execution shall be identified and a
procurement plan shall be developed based on the approved construction schedule.
The developed plan shall be monitored and controlled to ensure that the sourcing of suppliers is
being done on the agreed schedule and the plan shall be updated as required in case there are any
changes in the construction schedule.
The Procurement Plan shall be submitted to the consultant for approval.
The Procurement Plan submission shall be adhering to Insert the Project Specifications Clause if
applicable or otherwise modify the statement of the project specifications.
After the suppliers are being selected, the follow documents shall be sending for approval:
A Supplier prequalification shall be sent to the consultant for approval through a Technical
Submittal.
A Material Submittal Shall Be Submitted For The Consultant Approval. Please Refer To Appendix C,
Indicates The Material Submittal Form That Shall Be Used During The Project Period.
The process owner for the Material Procurement shall be the Corporate Procurement Department.
Please refer to the following documented procedure:
PD-P-01 Project Procurement Plan.
PD-P-02 Procurement Procedures.
6.12. COMMUNICATIONS.
This Process Is Essential To Ensure The Flow Of Information And Coordination Either Internally Or
Externally
The Followings Table Shows The Meetings That Shall Be Held To Ensure The Proper Communication
Process Between The Different Parties Of The Project (I,E Client Representative, Engineer
Representative, Main Contractor And Sub Contractors)
Note: The below meeting shall be as mentioned in the project specifications.
Coordination
As Required Mc Mc,Sc
Meetings
As Requested By The
Extra Meetings Cr Cr,Er,Mc
Client
The Process Owner Shall Be Each Responsible Party For Holding The Meeting As Per The Above
Table.
Please refer to the following documented procedure:
I-P-02 QHSE Communication
6.13. REPORTING
During The Project Period The Following Reports Shall Be Prepared And Submitted To The Engineer
As Per The Agreed Time Frame:
6.13.1.Daily Site Reports
They shall be prepared by the planning department and submitted on a daily basis. The content of
the daily site reports shall be adhering to the project specifications Insert the project specifications
clause If applicable or otherwise modify the statement. The reporting format shall be agreed by the
engineer’s representative. mention how the daily site reports will be send to the Consultant.
6.13.2.Progress Reports
They Shall Be Prepared By The Planning Department Collecting All The Required Information From
The Other Departments. The Progress Report Shall Be Submitted On A Monthly Basis. The Content
Of The Report Shall Be Adhering To The Project Specifications Insert The Project Specifications
Clause If Applicable Or Otherwise Modify The Statement Mention How The Progress Reports Will Be
Send To The Consultant.
The Process Owner Shall Be Sr. Planning Engineer.
6.14. SUBCONTRACTORS
After the contract is being awarded to any subcontractor, the Project Manager shall lead the kick off
meeting with subcontractor please refer to appendix D indicating the Minutes of Meeting Template
for the Sub Contractors Kick of Meetings.
A regular coordination meeting shall be held at regular basis with all subcontractors for discussing
the progress, submittals, quality and safety issues related to their deliverables. The interval of these
meetings shall be decided based on its requirement and the project basis. Please refer to appendix D
indicates the Minutes of Meeting templates for Sub-Contractor Coordination Meeting.
The Process Owner Of This Process Shall Be The Construction Manager.
Please refer to the following documented procedure:
PM-P-07 Controlling Subcontractors
6.15. CONSTRUCTION.
The Construction department shall be monitoring the work at site and ensure that all the tasks are
being delivered in a safe manner and as per the approved construction schedule.
On agreed basis there shall be an internal construction meeting held for discussing the Progress,
Resources, Safety, Quality, Team Performance, Logistics/Materials, Subcontractors and any other
issues that might cause delays to the project.
The construction department shall ensure that they are using the latest drawings and other technical
submittals by referring to the latest register controlled by Technical, QA/QC department and
Document Controller.
The site team shall issue on an agreed basis an internal report recording the progress at site and any
areas of concerns.
The construction team shall be monitoring and controlling all the sequential reference number of
the requested inspection by deploying a proper sequential reference number as mentioned in
sec.5.7. through the control sheets.
The Process Owner Of This Process Shall Be The Construction Manager.
Please refer to the following documented procedure:
PM-P-07 Controlling Subcontractors
6.16. TRAINING
A training programme shall be planned to cover various aspects of the project activities. The training
programme shall be covered both under the Corporate Level and the project level.
This document focuses more on the training which shall be held at the project level. Mainly this will
be covering the Trades Training which shall be held prior to start any activity at site.
The Training programme shall be covering different disciplines as per the scope of work and the
training subjects can be identified from the approved construction schedule and the procurement
log.
The training duration shall be planned based on the scope of work and the construction schedule.
The planned training can be in any of the following forms:
Presentations.
Site Training.
Inductions.
All the training attendees shall be registering their attendance and the attendance records shall be
maintained.
The Process Owner Of This Process Shall Be The Sr. Qa/Qc Engineer.
All The Ingoing And Outgoing Submittals Shall Be Send, Receive, Monitor And Control By The
Document Controller.
All The Submitted Documents Shall Be Adhering To The Project Specification Insert The Project
Specifications Clause If Applicable Or Otherwise Modify The Statement
The Process Owner Of This Process Shall Be The Document Controller.
Please refer to the following documented procedure:
I-P-11 Correspondence and Technical Submission.
6.18. NON-CONFORMANCE
6.18.1.Internal Control:
In Order To Control And Administer The Quality At Site All The Activities Shall Be Monitored By The
Qa/Qc Department. This Shall Be Through Random Inspections, Site Walk, Internal Surveillance And
Material Inspections.
At The Project Level Two Documents Shall Be Used For Identifying And Notifying The Non-
Conformed Party. This Either By Issuing Quality Violation Or Internal Non-Conformance Report.
The Quality Violation Report Shall Be Used In Case There Is Any Non-Conformance Occurred At The
Site Due To Trades’ Workmanship Or Any Activity Being Executed Deviating From The Project
Specifications, Drawing, Method Statement And Itps.
The Non-Conformance Report Shall Be Used In Case There Is Any Deviation With Regard To The
Implementation Of Company’s Integrated Management System Procedures.
Also It Shall Be Used As An Official Report For Issuing External Non-Conformance To The
Subcontractor Whom Failed To Deliver Their Work As Per Agreed Contract, Thus Failure In Adhering
To The Drawing, Method Statement, Project Specifications And Drawings.
All Violations Shall Be Analysed And A Root Cause Shall Be Identified In Order To Agree And
Implement The Most Appropriate Remedial And Preventive Action.
Before Issuance Any Of The Above Documents The Sr. Qa/Qc Engineer Or The Qa/Qc Engineer Shall
Assign A Reference Number To Each Document For Traceability Purpose.
All The Issued Reports Shall Be Logged And Its Status Updated Accordingly.
Please refer to the following documented procedure:
I-P-06 Control of Non-Conforming Products.
6.18.2.External Control:
During The Project Period The Engineer’s Representative May Issue A Non-Conformance Report Due
To Any Violation At Site. As Per This Contract The Non-Conformance Report Will Come In The Form
Of “Non-Compliance Notification”. The Reference Number For Each Notification Shall Be Controlled
By The Engineer On The Basis Of Their Internal System
The Qa/Qc Engineer Shall Be Receiving These Notifications, Log It And Start Analyzing Its Root Cause,
Remedial Action And What Is The Preventive Action. After Deciding What The Appropriate Action
That Shall Be Taken Is, A Reply Shall Be Send Through A “Closing Non- Notification Report”. Each
Closing Report Shall Have A Reference Number Which Is Being Assigned By The Qa/Qc Engineer Prior
Sending It To The Consultant.
The Internal, External NCRs And Quality Violations Shall Be Logged And Its Status Updated.
The Process Owner Of This Process Shall Be The Sr. QA/QC Engineer.
6.23. SAFETY
The Safety Requirements and procedures Shall Be Managed By The Senior Safety Personnel At
Site. Please Refer To The Project Safety Plan.
Project Manager along with other Head of department shall agree the resources required for the
Handing over and finalizing the snagging list.
During the snagging period a programme shall be developed and monitored to ensure a closure of all
pending items
The project closure and handing over shall be adhering to project specification requirement Insert
the Project Specifications Clause if applicable or otherwise modify the statement
7. PERFORMANCE MEASUREMENT
The PMT shall set certain objectives for measuring the performance of the project team during the
execution period of the project.
The planned objectives shall be monitored through agreed interval meetings based on the planned
project duration and the risk associated in failure of delivery for any of the planned items.
Please refer to the following documented procedure:
I-P-10 Monitoring KPIs
7.2. AUDITS
The implementation of the Project Management System (PMS) shall be verified by performing audits
on agreed duration.
The Audits shall be carried by the Corporate QA Team, they are responsible for establishing,
maintain and implementing an Audit Schedule for all the company’s project and Southern Sun Hotel
Project shall be within their Audit Schedule
Audit Findings shall be recorded and followed up by the use of action plans where corrective actions
or improvements with a close out timescale are agreed (i.e. preventive actions).
Audits shall:
Verify compliance to procedures
Identify areas of non conformity – corrective actions
Identify potential problems – observations
Identify potential improvements – improvements
Confirm the effectiveness of procedures.
Please refer to the following documented procedure:
I-P-04 Internal Audit.
8. CONTINUAL IMPROVEMENT
At Agreed Interval A Project Review Meetings Shall Be Conducted Chaired By The Pmt To Discuss The
Overall Strategy Of The Project Management System And If There Any Areas Need To Be Change Or
Improved.
The Procedure At The Ims Is Being Addressed For The Corporate Management Review Meetings But
It Shall Be Employed At The Project Level As Applicable.
Please refer to the following documented procedure:
I-P-05 Management Review Meeting.
I-P-08 Continual Improvement.
The Pmt Shall Prepare A Close Out Report Demonstrating The Various Aspects Of The Project And
Expressing The Problems Experienced During The Project And How It Was Dealt With.
Please refer to the following documented procedure:
PM-P-10 Project Completion Analysis.
9. APPENDICES
Insurance
We confirm that M/s. China State Construction Engineering Corporation (Middle East) (L.L.C),
is insured with us under Workmen’s Compensation Insurance per following details:
Territorial Limits : United Arab Emirates and elsewhere in the world in respect of
non-manual business trips
AUTHORIZED SIGNATORY
Method Statement
Project Information
Item Description
Project Location Plot 3370587 Zabeel Second Dubai, United Arab Emirates
Client EMAAR
Structural
WME consultants
Consultant
Landscape
NLME
Consultant
The complete details will be as per the following tabulation including the summary of Built-
Up areas (BUA).
Existing dewatering
7 connection outside plot limit
This section will give a brief overview of the major quantities of the project as a preliminary
understanding of the overall major quantities relate to “Downtown Views II” project. This given
major quantities is indicative only as per rough estimation.
Description Quantity
Concrete 178,583 m³
Reinforcement 36,445,370 kg
Formwork 753,156 m²
The general scope of works includes but is not limited to design, construction, completion,
obtaining authority approvals, one year maintenance and remedying of defects during Defects
Liability Period for the proposed residential/ commercial building “Downtown Views II” 3 towers
project.
ITEM DESCRIPTION
4 Dewatering
9 Waterproofing
10 Facade
11 ID Works
S/N DESCRIPTION
3 Lighting & Power to Transformer, Substation and RMU Room at Ground Floor
12 Miscellaneous metalwork
14 Bath Screens
Provisional Sum
2. PROJECT UNDERSTANDING
This section will address the brief description of the project challenges and solutions that
will be implemented for successful completion of “Downtown Views II” project.
C. Proposed Solution:
In-depth analysis of plant and equipment.
Study and plan for reasonable sequence of works to allow for unhindered mobility
of construction equipment at site.
Make use of available space within the site for temporary road access, workshop
areas, lay down areas, temporary offices and ancillary facilities. This is to
minimize necessity of labour and material transfer.
Allow temporary road to be located on the intended development permanent road
plot. This is to minimize additional soil compaction requirement for temporary
works.
Allow for adequate plant & equipment to facilitate construction activities in normal
working hours.
Allow for safeguards and budgetary provisions to ensure compliance with
authorities regulation concerning construction noise.
B. Proposed Solution:
Reasonable sequence of concrete pouring works to allow the use of available site
access.
Consider partial delay of zones to allow closer access for concreting machineries.
Use of mobile concrete pump with higher reach capacity.
Use of high capacity stationary pumps and concrete placing boom for towers.
B. Proposed Solutions:
Consideration for reasonable zoning plan and construction sequence
arrangement.
Convenience / time schedule and price factor of formwork system will be
compared.
Cycle analysis of formwork and back propping simulation was undertaken for the
proper study of the form work requirement.
The equipment which can meet construction requirement with high productivity
will be selected.
CSCEC ME will early involve in the project during the development of design in relation
to constructability, quality, best value, efficient construction methodology, material
availability, supply chain and procurement strategies.
CSCEC ME has vast and broad experience in coordination and cooperation with
various subcontractors and construction activities in relatively congested lay down areas
and imposed pressure on site logistics and operation of construction plant and
equipment.
CSCEC ME has rich experience in RC Work & Formwork. Large scale form work,
custom-tailored curved formwork from factory and solid formwork support system will
provide a good casting condition for concrete, which will result a fair face finish with
face care on time.
CSCEC ME has completed many projects successfully in GCC area with our internal
construction team and strong local formwork specialist partner.
CSCEC ME has done various projects in GCC market and has set up long- term
cooperation with many local suppliers and subcontractors.
CSCEC ME has set up its own manufacture factory in Dubai, such as MEP ventilation
duct factory in Jebel Ali and Timber factory in Sharjah. In China, there are many huge
material factory, with good cooperation with CSCEC ME which can support any
infrequent material in local market.
Method of Construction
Foundation
Concept Description:
The project foundation, divided into 7 major Zones. Zones 1, 2&3 for towers and zones 4, 5,
6&7 for podium. Delay zone 4-1 & 6-1 to facilitate access to mid-section of podium.
Concrete Pouring Sequence:
Ground Floor
Concept Description:
The project ground floor, divided into 7 major Zones. Zones 1, 2&3 for towers and zones 4, 5,
6&7 for podium. Delay zone 4-3 & 6-3 to facilitate access to mid-section of podium.
Concrete Pouring Sequence:
Concept Description:
The project podium level 1, divided into 7 major Zones. Zones 1, 2&3 for towers and zones 4,
5, 6&7 for podium. Delay zone 4 & 6 to facilitate access to mid-section of podium.
Concrete Pouring Sequence:
Zone 1-1: 963m²; 1-2: 845m² Zone 1-1: 361m³; 1-2: 317m³
Zone 2-1: 660m²; 2-2: 788m² Zone 2-1: 248m³; 2-2: 296m³
Zone 3-1: 972m²; 3-2: 765m² Zone 3-1: 365m³; 3-2: 287m³
Zone 4-1: 1072m²; 4-2: 1446m² Zone 4-1: 322m³; 4-2: 434m³
Zone 5-1: 1377m²; 5-2:1251m²; 5-3: 1183m²; Zone 5-1: 413m³; 5-2: 375m³; 5-3: 355m³
5-4:1082m² 5-4: 325m³
Zone 6-1: 1378m²; 6-2: 1058m²; Zone 6-1: 413m³; 6-2: 317m³
Zone 7-1: 851m²; 7-2: 1216m²; 7-3: 1171m² Zone 7-1: 255m³; 7-2: 365m³; 7-3: 351m³
Concept Description:
The project podium level 2, divided into 7 major Zones. Zones 1, 2&3 for towers and zones 4,
5, 6&7 for podium. Delay zone 4 & 6 to facilitate access to mid-section of podium.
Concrete Pouring Sequence:
Zone 1-1: 963m²; 1-2: 845m² Zone 1-1: 361m³; 1-2: 317m³
Zone 2-1: 721m²; 2-2: 787m² Zone 2-1: 270m³; 2-2: 295m³
Zone 3-1: 972m²; 3-2: 795m² Zone 3-1: 365m³; 3-2: 298m³
Zone 4-1: 1309m²; 4-2: 1446m² Zone 4-1: 393m³; 4-2: 434m³
Zone 5-1: 1377m²; 5-2:1251m²; 5-3: 1183m²; Zone 5-1: 413m³; 5-2: 375m³; 5-3: 355m³
5-4: 1082m² 5-4: 325m³
Zone 6-1: 1379m²; 6-2: 1057m²; Zone 6-1: 414m³; 6-2: 317m³
Zone 7-1: 861m²; 7-2: 1216m²; 7-3: 1171m² Zone 7-1: 258m³; 7-2: 365m³; 7-3: 351m³
Concept Description:
The project podium level 3, divided into 7 major Zones. Zones 1, 2&3 for towers and zones 4,
5, 6&7 for podium. Delay zone 4 & 6 to facilitate access to mid-section of podium.
Concrete Pouring Sequence:
Zone 1-1: 953m²; 1-2: 998m² Zone 1-1: 357m³; 1-2: 374m³
Zone 2-1: 721m²; 2-2: 869m² Zone 2-1: 270m³; 2-2: 326m³
Zone 3-1: 972m²; 3-2: 765m² Zone 3-1: 365m³; 3-2: 287m³
Zone 4-1: 1309m²; 4-2: 1446m² Zone 4-1: 393m³; 4-2: 434m³
Zone 5-1: 1377m²; 5-2:1251m²; 5-3: 1183m²; Zone 5-1: 413m³; 5-2: 375m³; 5-3: 355m³
5-4: 1082m² 5-4: 325m³
Zone 6-1: 1370m²; 6-2: 1160m²; Zone 6-1: 411m³; 6-2: 348m³
Zone 7-1: 847m²; 7-2: 1216m²; 7-3: 1159m² Zone 7-1: 254m³; 7-2: 365m³; 7-3: 348m³
Concept Description:
The project podium level 4, divided into 7 major Zones. Zones 1, 2&3 for towers and zones 4,
5, 6&7 for podium. Delay zone 4 & 6 to facilitate access to mid-section of podium.
Concrete Pouring Sequence:
Zone 1-1: 958m²; 1-2: 979m² Zone 1-1: 359m³; 1-2: 367m³
Zone 2-1: 722m²; 2-2: 868m² Zone 2-1: 271m³; 2-2: 326m³
Zone 3-1: 980m²; 3-2: 822m² Zone 3-1: 368m³; 3-2: 308m³
Zone 4-1: 1406m²; 4-2: 1446m² Zone 4-1: 492m³; 4-2: 506m³
Zone 5-1: 1377m²; 5-2:1251m²; 5-3: 1183m²; Zone 5-1: 482m³; 5-2: 438m³; 5-3: 414m³
5-4: 1082m² 5-4: 379m³
Zone 6-1: 1378m²; 6-2: 1194m²; Zone 6-1: 482m³; 6-2: 418m³
Zone 7-1: 876m²; 7-2: 1216m²; 7-3: 1185m² Zone 7-1: 262m³; 7-2: 365m³; 7-3: 356m³
Typical Floor
Concept Description:
The superstructure, divided into 3 major Zones or one zone per tower.
AREA VOLUME
Zone 1-1: 1344m²
Zone 2-1: 1183m² Zone 1-1: 321m³
Zone 3-1: 1189m² Zone 2-1: 292m³
Zone 3-1: 299m³
Concept Description:
The superstructure, divided into 3 major Zones or one zone per tower.
AREA VOLUME
Roof Floor
Concept Description:
The superstructure, divided into 3 major Zones or one zone per tower.
AREA VOLUME
Concept Description:
The superstructure, divided into 3 major Zones or one zone per tower.
AREA VOLUME
Foundation
1. Tower footprint, Zones 1-3 to be prioritized.
2. Two numbers of 48m radius Mobile Concrete Pump shall be employed at suggested
locations in casting the towers foundation.
3. Zones 5 & 7 to be casted by two numbers of 54m radius Mobile Concrete Pump at
suggested locations.
4. Zones 4 & 6 to be partially delayed until level 4 completion of Zones 5 & 7.
Superstructure Level
Superstructure Level
3.3.1 Introduction
To successfully execute all the concrete works for this project, CSCEC ME’s technical
team had a thorough and in-depth study and analysis to come up with the most effective and cost
efficient formwork system that will be considered as the most feasible formwork and supporting
structure. Several criteria were taken into consideration while selecting the system that would
ensure the accuracy of the shapes, dimensions and positions of concrete structures and members.
Furthermore, the system must have sufficient rigidity and stability and must be capable of
withstanding the weight and lateral pressure of concrete placement and construction load.
General characteristics of the formwork system should be simple structure along with its
components, easy to install and remove, and to ease and facilitate rebar placement, concrete
placement and curing.
The other factor that helps us finalize the most feasible formwork system is the
construction cycle analysis which is another criterion and part of the study proposal of an effective
formwork system.
Formwork System
Monolithic pouring of all concrete members such as slabs, walls, columns, beams,
central core and staircase.
Speed up construction thus it will shorten the overall duration of the project.
Shorter slab cycle for typical floors
For the back propping system of slab, usually we will require 3 sets of back propping
system and 2 sets of aluminum slab formwork system for typical floors.
A. Preparation
In order to facilitate the installation, all the formwork elements need to be numbered and
labeled before arriving at the site.
Before installation of the formwork, ensure that all the formwork surface has been cleaned
and brushed with release agent.
Propping System
Formwork will be removed in a manner not to damage the concrete, and at times to suit
the requirements for its curing and to prevent restraint that may arise from elastic shortening or
shrinkage. Forms, shores and bracing will not be removed until the concrete has gained sufficient
strength to carry its own weight and construction and design loads, which are liable to be imposed
on it.
This section will give the general details of the proposed site logistics plan for the
“Downtown Views II” project.
The general concept of this site logistics is to provide a dynamic logistics that would
allow different stages and adjustments as the project work progresses from commencement up
to completion of the project.
CSCEC ME will utilize the remaining area from within the plot limit excluding the area
occupied by the building footprint. Approximately the remaining area that can be utilize for
logistical requirements is around 15,000 m². Allocation for temporary offices are as follows: for
client and consultant use is at 600 m², for CSCEC ME offices at 1,200 m² and for subcontractor
offices at 600 m². The structure for these offices shall be two storeys cabin. For labor welfare
facilities provision of 1200 m² total floor area with mess halls, rest area and sanitary facilities,
housed in two numbers of single storey cabin, 100m² for clinic. For storage facilities an
allocation of 850 m². Remaining areas will include temporary road access, lay down and
workshop areas.
The complete details of the site logistics can be referred to the attached Site Logistic Plan
following this section.
7.5
MAIN STORAGE
14.99
T3
T1
FUTURE UTILITIES CORRIDOR 7.5 (400 m²) 7.5
22.13
N 2788328.181
E 494779.381 PLOT
LIMIT
LABORATORY
WATER TANK
T2
GENERATOR
178.47
(50 m²)
(50 m²)
(70 m²)
PLOT PLOT
LIMIT LIMIT
6.1
PLOT LIMIT
TEMPORARY ROAD
TEMPORARY FENCE
5-1 ADJACENT ROVE HOTEL
3029 m² TEMPORARY OFFICES
BUILDING
7.0
56.2
3283 m³
0M
8
WID
ED
RIV
TB1
TB1
MAIN STORAGE
E
TB1
TB1
WA
PC1
7.0
430
Y
TB1
1
C3
P-
0M
7
C8
PC1
P-
TB1
2
1070 THK RAFT TB1
C3
P-
SSL -0.080
WORKSHOP AREAS
WID
430
PC1
PC22
TB1
ED
4
C3
2170 THK RAFT
P-
TB1
TB1
SSL -0.080
1250 THK RAFT 1500 THK RAFT
PC1
430
SSL +0.100 SSL +0.350
RIV
1
C3
TB1
P-
250 PC1
4-2 6-2
1
1
2
1
2
145
C3
C8
C8
C3
1
1
C8
9A C3
C3
C3
C3
PC1 PC1 PC1 PC1 PC1 PC1C PC1C PC1 TB1
4A
P-
P-
P-
P-
LAY DOWN AREAS &
P-
P-
C1 TB1 TB1
P-
P-
P-
TB1
C1
TB1 PC1 TB1 TB1 TB1 P- TB1 TB1 TB1
EW
P-
35
WM-ST-204
TB1
.19
TB1
OTHER TEMPORARY
TB1
TB1
AY
TB1
TB1
TB1
RW01
2170 THK RAFT
FACILITIES
TB1
TB1
RW01
TB1
250
703 m²
2600 THK RAFT
1145 m²
TB1
TB1
TB1
SSL +0.350
430
SSL -0.550 SSL +0.100 25
250
3250 THK RAFT 1250 THK RAFT
900
TB1 1
2
C8
1A C3
5
PC1C
P-
PC1 P-
-C
A
TB1 C1
C5
T3
P- TB1
P-
69 m³ 136 m³
0
565
TB
1
3-1
900
NOTE:
565
SSL +0.100 0 PC17
565
3
0
-C
TB1
T1
PC16
900
2600 THK RAFT
SSL -5.300 T3-PA PC14
430 3250 THK RAFT
1
-C
565
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
0 SSL +0.350
T3
PC12 PC11
1-1
565
1643 m²
5650
PC21 TB1 PC11 1500 THK RAFT
1500 THK RAFT
C1
C2
PC2
C2
PC1 PC1 PC1 P-
C1
C1
PC1 PC1
C1
PC1 PC18
P-
900
470
P-
P-
P-
P-
P-
2
C1
TB1 TB1 TB1 TB1 TB1 TB1
P-
5-2
TB1
PC15 5650
9
4523 m³
2
565
-C
0 WM-ST-201
250
T1
2600 THK RAFT 5650
2600 THK RAFT SSL -0.550 430
1679 m²
SSL +0.100 SSL -0.080 2
SSL +0.350 5650
2350 THK RAFT
2
-C
2820 THK RAFT
T3
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
5650
5650
1999 m²
3
6146 m³
3 1
-C
T3
C1
C2
PC2
2
P-
C1
1
C1
C1
C2
C2
PC2 PC1 PC1 ZWME-S-003
WM-ST-205
C8
C2
PC1
P-
PC1 PC1 PC1 PC1
P-
P-
P-
P-
P-
7.0
P-
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
250
900
518 m³
TB1
0M
200
TB1
THK
250
UPS
TAN
TB1
TB1
TB1
TB1
TB1
TB1
D
SSL +0.100 1500 THK RAFT
3250 THK RAFT
SSL -0.550
5
2350 THK RAFT
-C
C7
C7
C7
C7
C7
PC1B PC1B PC1B PC1B PC1B PC1B
T1
SSL +0.350
P-
P-
P-
P-
C7
WID
P-
P-
TB1 TB1 TB1 TB1 TB1
TB1
TB1
650
PC21
1
TB3
TB3
TB3
TB3
61.2
-C
ED
T1 SSL +0.100
TB1
TB1
PC9
4
1 SSL -0.080
250
C6
C8
C9
C2 PC1B
C4
PC1 PC2A P- PC1B 3000 THK RAFT
P-
P-
P-
TB1
4
P-
2820 THK RAFT
C8
RIV
2
P-SW8 PC2A
P-
C4
430 3000 THK RAFT
9
P-
SSL +0.100
PC1
1
EW
C3
P-
TB1
TB1
TB3
TB3
TB3
TB3
C7
C7
C7
C7
C7
C7
P-
P-
PC1B PC1B PC1B PC1B PC1B PC1
P-
P-
P-
TB1
P-
AY
TB1 TB1 TB1 TB1 TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
1
C1
PC3
P-
5
C1
1
3
1
3
3
PC2 PC4
1
C2
C8
C2
C2
C2
C2
C8
C8
PC2 PC2 P-
C2
PC2 PC2 PC2 PC2 PC2
P-
P-
P-
P-
P-
P-
P-
P-
P-
TB1
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
6 TB1
C3
P-
ADJACENT PLOTS
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
REBAR
1
1
C6
C6
P-
1
3
2
C5
C5
C5
C5
C5
C5
C5
4
C5
C5
P-
P-
C5
C5
PC1 PC1 PC1
P-
P-
P-
P-
P-
P-
P-
PC1
P-
6
P-
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 PC1
7-1
PC1 PC1
MA REA (5
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
AG
WA EMEN
A
NA
3657 m² R
TO
1
1
C6
C6
PC1
P-
P-
(800 m²)
TB1
G 0 m²)
1
STE
1
P-
TB1
R S ²)
C5
C5
C5
C5
1
1
2
PC1 PC1 PC1 PC1 PC1 PC1
C5
C5
C5
C5
C5
C5
C5
P- PC1 PC1 PC1
P-
P-
P-
6
P-
P-
P-
P-
P-
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
PC1
BA (450 m
PC1 PC1
566 m³ R E
T
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
IN
AB ²)
5 1 1 1 1 1 1
PLOT
1
1
C6
PC1 PC1
C5
C5
C5
C5 C5 C5 C5 C5 C5 C5
1
PC1 PC1 PC1 PC1 PC1 PC1
C5
P- PC1 P- P- P- P- P- PC1 P-
P-
PC1
P-
P-
P- PC1
YC
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
TB1 TB1
RE 600 m LIMIT
TO =
1-S X25m
A
TB1
TB1
RE
m
(12
TB1
TB1
TB1
TB1
TB1
A GH EXIT
TB1
TB1
TB1
TB1
RE
TB1
TB1
A
ELF
PC1 1 PC1
430
C6
P- TB1
2
C6
1
1
C5
5
1
TB1
C5
PC1 PC1
C5
P-
C5
PC1
P-
P-
P-
P-
TB1 TB1 TB1
RW
K
AN
2900 THK RAFT
T2
-C
T
1
430
TER ²)
BO
2470 THK RAFT
WA 0 m
SSL -0.080
430
LA
SSL +0.350
(5 IN
AB ²)
TB1
R YC
TB1
TO
TB1
TB1
TB1
RE 600 m
430
RA
1500 THK RAFT
K
7.0
NE ²) TO
SSL +0.350
SSL +0.350
N =
1500 THK RAFT
GE (40 m TA 1-S X25m
SSL +0.350
ER
AT m²)
0M
m
(12
5
1
1
1
W
C5
C5
C5
C5
C5
(50
PC1 PC1 PC1 PC1 PC1
P-
P-
P-
P-
P-
TB1 TB1 TB1 TB1 TB1 TB1
R
5650
TO
2
C6
RA
P-
WID
NE 0 m²)
T2
GE
-C
2-1
TB1
5650
C5
C5
P-
SSL -5.300
TB1
TB1
TB1
TB1
TB1
TB1 3
-C
T2
2900 THK RAFT
15
RIV
WM-ST-202
5650
2
250 5650
5650
EW
6
C5
C5
C5
PC1 PC1 PC1 PC1
P-
P-
P-
1643 m²
TB1 TB1 TB1 TB1
INIC
AY
CL m²)
5
SSL +0.350
5325 m³
2900 THK RAFT
SSL +0.350
2900 THK RAFT
0
(13
SSL +0.350
R
TO PURPOSE OF ISSUE
4
250
-C
T2
AC
TR
250
250
SSL +0.100
91.4
O E
BC FFIC BIN
4
SU O EY CA 00 m² PROJECT
R =6 DOWNTOWN VIEWS II
TO
2-S 25m)2
mX PROPOSED RESIDENTIAL & COMMERCIAL
(12
E BUILDING (3 TOWERS) ON PLOT NO. 3370587,
FIC ZABEEL SECOND, DUBAI.
ADJACENT PLOTS R OF CLIENT
TO AD EMAAR PROPERTIES
AC BIN ² RO
NTR EY CA 200 m
1 DE
CO.P.J.S.C
LAY DOWN AREA O R )2= I
IN C
TO
2-S X50m
M .W
(800 m²) MA (12
m
00
39.
LEAD CONSULTANT
T/ T ARCHGROUP
IEN
ARCHITECTS.PLANNERS.ENGINEERS.PROJECT MANAGERS
CO FFIECY CAB0INm²
OTOR 2=60
2-S X25 m)
GH m
(12 DRAWING
001 R0
7
This section will address the general methodology for surveying work and its related
activities and concerns for the construction of “Downtown Views II” project.
A. INTRODUCTION
The general methodology for survey work will be presented as per the below items. All
surveying work will be carried out by a qualified and highly experienced surveyor along with its
subordinates.
Summary
Survey Preparation
Foundation Construction
GPS Observation
Quality Control
B. SUMMARY
Considering the design character and structure type, many methods will be adopted to
assure survey requirement of accuracy, such as scientific surveying technique, advanced survey
equipment and strict verifying and rectifying method. Plan control grid will be set by two levels,
first level is site horizontal control network, and second level is building gridline control network.
The site horizontal control network is based on control points provided by the clients, using
total station to set general plan control network. The building gridline control network is
based on the coordinate data of general plan control network, using method of polar coordinates
to set the control points of building gridline.
Altitude control network is based on altitude points provided by the client, using high
C. SURVEY PREPARATION
The survey preparation work for this project will be presented as per the
below given details.
It includes reviewing and verifying of construction drawing, handover and repletion of
survey reference point, identification and adjustment of survey equipment, method
statement and data preparation, surveying of construction site.
Organization of personnel. The complete details of the survey as per the table:
Major survey equipment and accuracy as per the below table:
Quantity of
Position Responsibilities Competency
Workers
±(1mm+2ppm.D) Angle
Total GTS- Plan control network surveying accuracy
3
station 601AF and building floor ±1''; distance surveying
surveying accuracy (1mm+2ppm.D)
Automatic
NA2 5 Leveling ±0.7 mm
level
The major surveying equipment will be presented as per the below photos.
GTS-601AF
Total Station NA2
Automatic Level
F. FOUNDATION CONSTRUCTION
F.1 Transfer of Foundation Partial Gridline
Before foundation was located, gridline control peg shall be verified. Then major control
gridlines shall be transferred by total station. Mark the gridline with black ink line, mark the
column, beam, and opening with red triangle mark. Please find the detailed information from
following chart as example.
Detailed Chart
H. QUALITY CONTROL
Survey in charge shall comply with the requirement of construction progress and
surveying method statement to arrange surveying work.
Survey equipment shall be maintained on time and keep recorded.
The operation of survey equipment shall strictly comply with relative regulations.
Survey work has to comply with safety regulations.
4.2 EARTHWORK
This section will address the general construction methodology of Backfilling works and its
related activities and concerns “Downtown Views II” project.
A. Work Process
Place the backfill materials in layers and compact by vibratory rammer machine: Bottom
cleaning → backfill materials inspection → backfilling by layer → compacting each layer →
maximum dry density test → surface trimming and inspection
B. Materials
Make sure backfill material meet the requirement of BS 1377. And get approval from
Engineer and control the size distribution of backfill soils in accordance with BS 1377-2.
Make sure the structural filling has a maximum plasticity index of 6% for Type 2 granular
material and non-plastic for Type 1 granular material. Carry out optimum moisture-maximum
density test in accordance with BS 1377 method 3.5 to determine the optimum amount of
water for each fill materials to obtain maximum dry density. Sub grade will be placed with the
water content between, optimum moisture content -2% and optimum moisture content +1%.
Capping will be placed with the water content between, optimum moisture content -2% and
optimum moisture content.
The foundation will be cleaned before backfilling and level up the material in layer. The
moisture content will be inspected before compacting and will be vibrated each layer completely
in a certain sequence. Loose and air-dry it or add dry material when moisture is high to avoid
"rubber-soil". Potable water will be applied or increase the compacting times when filling is dry.
D. Placement
Backfill and fill materials will be placed in layers. Before compaction, each layer will be
moistened and aerated as necessary to provide the optimum moisture content of the soil
material. Each layer will then be compacted to the required percentage of maximum density.
Around structures: Backfill and fill materials will be placed evenly adjacent to structure
up to the required elevations. Extra care will be taken to prevent wedging action of the
Back fill against structure by placing the material uniformly around the structure up to
approximately the same elevation in each lift.
Trenches: Satisfactory soil will be provided containing no rocks or stone greater than
50mm in size and free of other deleterious material.
E. Compaction
Percentage of density requirement and area classification:
Compaction requirement
Cohesionless soil Cohesive soil BS 1377
Area classification BS 1377 relative density degree of compaction
Under foundations and slabs on
grade of buildings 77% 95%
F. Moisture control
Soil material that has been removed because it is too wet to permit compaction may be
stockpiled or spread in approved locations and permitted to dry. Drying can be assisted by
harrowing or pulverizing, until the moisture content is reduced to a satisfactory value as
determined by moisture-density relation tests.
The moisture in compacted fill or backfill material will be maintained within 2% above or
below the optimum moisture content as determined by BS1377.
G. Anti-termite treatment
A toxic barrier will be created within soil beneath and around the buildings, through which
termites cannot pass. All internal and external backfill will be treated prior to casting ground slabs.
Particular emphasis will be given to site cleanliness during the works and make sure that no
timber cardboard or other cellulose containing materials discharged during the work are left in or
on the ground on completion of the project.
A. Reinforcement works
All of the reinforcement bars that will be used for the structure will be a Type 2 High Yield
Deformed Steel bar that complies with ASTM A615 Grade 60 with a characteristic strength of
not less than 460 N/mm2.
o Reinforcement Connection
All reinforcements will adopt straight thread connection or lapping connection according
to the size of reinforcement's diameter.
The space between two connecting points and the lapping length of tensile and
compression reinforcement will meet the standard and requirement of the drawings.
Reinforcement Straight Thread Connection: Before connecting reinforcement, screw off
the plastic protecting cap on the reinforcement, with screw thread exposed, and clean up the filth
on the thread. When connecting reinforcement, screw the reinforcement that has already got rid
of sleeve barrel to the reinforcement connected and screw the reinforcement joint tight with
torque wrench until the wrench makes a sound at the adjusted moment value, painting a mark to
prevent from missing screwing. Layout of straight thread connecting is as follows:
Reinforcement will be fixed together by ample use of tying wire. Tying wire will not be
allowed to intrude into the concrete cover.
Reinforcement will be kept secured in the correct positions using approved temporary or
permanent chairs, spacers, etc., maintaining specified cover by means of cover spacers
secured to prevent displacement. Reinforcement will not be placed directly on formwork and
raise it into its correct position as the concrete is being placed. Reinforcement will not be
inserted into concrete already placed in position.
Unless otherwise permitted, top steel reinforcement will be supported firmly in the
position specified before concrete is placed, either by links or steel chairs.
B. Concrete works
The majority of the structural elements are composed of reinforcing steel bars with
concrete frame. The structural element of the main building concrete structure mainly includes
column, beam and slab. All of the concrete work will confirm to American Standard ACI 318 as
per project specifications.
o Concrete Sequence
The general construction sequence for concrete works will be presented as per the
followings table. Adjustment is anticipated dependent on the project general requirements and
specifications.
D. Stair Formwork
The general methodology for the staircase work, described as follows:
F. Scaffolding System
This section will address the general method for scaffold work and its related activities
and concerns for this project.
Based on the characteristics of this project and the time overlapping of structure,
decoration and MEP works, the external walls of some sub-projects use the double pole bowel-
coupler scaffold, which is laid out along all the external walls.
The longitudinal spacing of the vertical bar is 1.5m and its transverse spacing is 1.2m.
The distances between the internal vertical bar and the surface of wall are 300mm. The distance
between the bottom bar and the ground surface is 300mm, three handrails are required for the
working storey and its interval is 500mm.
o Interval of the Points Connecting to the Wall
The vertical and longitudinal spacing and the free height of the upper section of the
scaffold are all no more than 6m.
o Diagonal Bridging
The diagonal bridging will be erected at the same time with scaffolding and its diagonal
bar, which is 6m wide on the horizontal plane of projection, has a 45-degree angle with the
surface level. The diagonal bar must have a joint to the whole scaffold.
o Safety Netting
At the outside of the scaffold, the safety netting will be required. For the entrance of
corridor, the level safety netting is also required.
procedure.
b) The point connecting to the wall could be removed only after all the top
component parts have been removed thoroughly
c) During the removal works, all the loosen bars will be moved immediately in
case of supporting and depending by mistake
d) For the scaffold used for the old building, it will be removed firstly after
finishing the removal of roof structure and exterior-protected structure. Then
the steel structure will be removed as a whole.
A. INTRODUCTION
This project has post tensioned slabs for the superstructure on most of the floors
except mechanical floors. The scope of work for Post tensioning is design and build of all PT
members.
This general method statement provides the control sequence in construction and
methodology procedure which details the activities of the post-tensioned slab as per approved
shop drawings. The following activities are covered in this general method statement:
Delivery of materials and mobilization
Dead End fabrication
Supply and installation of anchorages
Supply and installation of ducts
Cutting and installation of strand
Stressing tendons, following concreting works
Cutting of tendons after stressing approval
Grouting of Tendons and Patching of tendons
C. MAJOR EQUIPMENT
The main equipment for the post tensioning process is the hydraulic jack. Jack will be
fixed on the tool at the end of the anchor.
Hydraulic Jack
Electric Pump
High-pressure electric pump is used to provide hydraulic jack push and pull direction for
the pre stressing procedure. It is with pressure gauge used to measure the amount of pressure
in the subsurface during the process.
D. GENERAL METHODOLOGY
d.1 PT Slab System Installation
The anchor locations will be marked out on edge boards showing heights of slot and bolt
hole required to be cut and drilled. Discrepancies will be recorded between the shop drawing
and actual deck dimensions, and report to the Project Engineer. Main construction key points
will be given as per below items.
It will be positioned and tied at correct height, where top stressing pockets are
required.
Anchors will be bolted and recess forgers to edge board/pans.
Ducting from anchor will be laid out and joints will be taped firmly.
The strand will be set up in a bripac and coil identification number will be recorded.
Length of tendon will be measured, pull out strand and cut to length. (Enough
length for stressing will be allowed.)
Strands will be pushed into duct, checking shop drawing for number in each
tendon.
Stressing of Strands
Shop drawing will be checked for any specified stressing sequence to followed and
jacking force to be used.
Every strand in each tendon will be stressed to full design load.
The wedges will be “Knocked-off” before releasing jack pressure (or use automatic
“knock-off” nose with jack).
When all strands are stressed, the distance will be measured between wedges and
paint will be marked and value will be recorded on record sheet, within an accuracy of
1mm.
All actual elongations/extensions will be (+) 10 % of the theoretical
elongations/extensions.
Stressing Reports will be submitted to the Project Engineer as soon as possible for
checking and formal submission for approval.
Final Stressing
That all strands have been stressed to required load, and the extension records
have been submitted to the Project Engineer.
That approval to cut all strands has been received in writing. Grinder will be used to
cut back the exposed strands so as to give minimum of 25mm cover to the external
concrete face.
A dry pack mixture will be made in the proportions of; 3 parts sand, 1-part cement
and 1-part liquid.
The amount of water that will be added may vary depending on the condition of the
sand to be mixed, (it may be very dry or wet).
As a general rule: Very dry sand - mix to proportions above
Very wet sand - add only re patch (ie.no water)
Texture of dry mix must be mould able in the hand.
Once the dry pack has been thoroughly mixed, filling the pocket will be started by tightly
packing the mix around the exposed anchor and strand. Packing of dry pack is initially with the
hand around block and wedges and then by using timber to pound the pack tight.
All excess dry pack and strand off-cuts will be cleaned up and deposited at rubbish removal
location. Once all cables have been cut and sealed and the dry pack has cured the slab is ready
to be grouted.
All anchors will be checked, cut and sealed. Using air, all grout tubes and ducts will
be checked for blockages, and clear blockages.
Pump/mixer will be checked if it is in working order and that all hoses are clear.
Freshness of cement will be checked.
Water will be recycled in the pump/mixer.
Additive will be added, mixed and recycled for 2 minutes.
Cement will be added slowly, 1 bag at a time, until consistent mix is obtained.
Cement will be added up to and until 200kg has been mixed, (recycling mix at all
times). ok
All cement bags will be disposed off correctly.
Bucket will be positioned at far end bleed tube. (To catch excess grout).
Grout hose will be connected to near tube and start pumping.
‘1 No. can’ will be allowed good quality grout to come from end tube before bending
tube over and closing off using tie wire.
PUMPING will be stopped and closed off near tube.
All previous Steps will be repeated for all tendons until deck/pour complete will be
repeated.
When completed, excess grout will be pumped to waste area agreed with builder.
Down mixer will be washed and cleaned and hoses will be flushed until clean.
Equipment will be stored in secure, safe location.
On the day following completion of grouting, all tubes to be cut off flush with
concrete, and deposited in rubbish area.
The same order of works will be applicable from the substructure up to the superstructure
of this project. The below discussion of the detailed method statement will indicate the
comprehensive procedures on how each scope of finishing works will be done for this
project.
The detailed construction methodology for finishing works will be presented as per below,
however the other scope of finishing work will be done in general.
Plastering Works
Once the block work has been completed and first fix carried out, one wall will be used as
a mockup for plastering which will be incorporated into the finished works. Plastering will then
be carried out to walls as design requires. Please note that at these stage plaster board ceilings
/ bulkheads have not been fitted. Carrying out plastering at this stage will allow the bulk of the
plaster to be machine applied.
Plastering work will start from the preparation of surfaces to receive any plaster. The
adjacent work will be protected from soiling, spattering, moisture deterioration, and other harmful
effects caused by plastering.
The solid substrates will be prepared for plaster that are smooth or that do not have the
suction capability to bond with plaster according to the specified specifications.
The plaster mixes will be prepared with respect to the different indicated mixes as per
specifications.
Screed Works
The screeding works will be carried out after the removal of forms. Once the forms have
been removed, all surfaces will be carefully examined and any irregularities found in the concrete
surface will be immediately rubbed down in a manner which is satisfactory to the Engineer to
produce a smooth, uniform and continuous surface. Blow holes will be filled with a cementitious
mortar. Concrete containing voids, holes, honeycombing or similar depression defects will be
completely removed and replaced to the satisfaction of the Engineer.
Cement mortar for filling holes left by the formwork ties and components will consist of
cement, fine aggregates and water suitable ratio which is as per specifications. Consistency must
be achieved which is suitable for compacting the mortar into the holes; the mix will be adequately
compensated against shrinkage by use of a suitable admixture.
By considering the severe drying conditions, additional applications (if required) may de
done following the completion of the finishing works. For all the concrete sections and surfaces,
CSCEC ME will take precautions to limit the effects of hydration.
Screed must be protected to avoid premature drying and excessive hot and cold
The following important construction key points will be applicable for the execution of the
floor finishes of this project which comprise of the following:
o Before leveling the base course, all the rubbish such as concrete debris
will be cleaned away. Waterproofing layer will be protected during base course
preparation.
o The tiles used in this project will be carefully selected and well matched so that
it has the same color and texture and the size and the thickness will be the
same.
o Selected tiles are immersed in water before using.
o Base course leveling: According to the design standard of floor and wall, the
leveling coat will be 1:4 dry cement mortars.
o The drainage slope is set up in the room with floor drains.
o Make level before leveling. The leveling is placed in accordance with the level.
o Snap the control lines before setting out.
o Tiling will be made according to the design. If there is no design requirement
for such works, the tiling work will start from the door to wall side, and the
fragment will be in the place not remarkable.
Painting Work
Prior to any start of any painting work, surface examination will be done as per the
substrates conditions and status. The maximum moisture content must be evaluated and will be
approved for compliance.
After examination, then preparation will be carried out by cleaning the substrates of
substances that could impair bond of paints, including dust, dirt, oil, grease and incompatible
paints and encapsulants. For any presence of any primers, this will be removed and will be re
primed substrate with compatible primers or apply tie coat (if required) to produce and achieve
the specified paint system.
Application stage will commence accordingly after completing the above mentioned
procedures. Apply paints according to the manufacturer’s written instructions and
recommendations. Paints will be applied to produce films without cloudiness, spotting, holidays,
laps, brush mark, roller tracking, runs, snags, or other surface imperfections. Cut in sharp lines
while painting and color the breaks.
Cleaning and protection must be done after the paint application. CSCEC ME will ensure
to protect work of other trades against damage from paint application. Any damage will be
rectified of other trades by cleaning, repairing, replacing and refinishing. Any damage will not be
left unrepaired or not rectified.
All of the painting works for this project will be executed as per the finishing and painting
o Any metal fixing used for the primary or secondary supports of the windows
and doors, will be in accordance with all specifications.
o The installation will be strong and reliable. The number of anchoring /anchoring
position and the fixing method will strictly comply with the design requirement
and the relevant specifications.
o The wind tight standard will be ensured and even outlook connection will also
be obtained.
o A low-tack tape prior to dispatch from the factory will protect the significant
surface of all window and door components. If during fixing or glazing any
such protection is moved, it must be refitted or replaced immediately.
o All glass will be fixed in accordance with the glass manufacturer’s instructions,
all glass panels will have rounded edges to prevent any damage to the gaskets,
and all glass will be cleaned by the Contractor before the completion of the
works.
o Complete ironmongery, right positioning and perfect overall functioning are
essential.
The setting out process will start up to the required levels, with member’s plumb, true to
line, cut and fitted. Then the joinery will be fitted to other construction; scribe and cope as required
for the complete accuracy of the fitting. The location of the furring will be correlated as well as
blocking, grounds and similar supports to allow attachment of other construction. The application
of any field treatment will be done to cit surfaces of preservative-treated lumber and plywood.
Making sure that the joinery work will be securely attached to substrate by anchoring and
fastening as indicated from the drawings. Common wire nails will be used for fastening unless
otherwise indicated from the specifications. The fasteners will be selected that will not fully
penetrate members where opposite side will be exposed to view or will receive finish materials.
The above mentioned general installation procedure and key points will be done as per
drawings and project specifications.
Downtown Views II
A. INTRODUCTION
CSCEC ME will provide the construction methodology for the unitized curtain wall
system as the majority and general elements of the facade system.
B. SCOPE OF WORK
The tower façade can be described as having the following types:
FT01 = structurally glazed curtain wall unitized system with metal panels at floor
transitions. Insulated glazing unit, aluminum mullions and transoms, top hung out
swinging operable unit. Finish coating according to architects.
FT01.1 = Curtain wall stick system at conditions where the tower interfaces with the
podium and doors are provided. Insulated glazing unit, aluminum mullions and transoms.
Finish coating according to architects.
FT02 = rear ventilated metal façade, formed aluminum sheet with T min = 3mm with
hidden fixing. Finish coating according to architects.
FT03 = Curtain wall stick system. Insulated glazing units, with aluminum mullions and
transoms, with integrated single leaf doors. Refer to architects door schedule and
drawings for all locations.
FT03.1 = Curtain wall stick system at larger balconies. Insulated glazing units, with
aluminum mullions and transoms, with integrated single leaf doors. Refer to architects
door schedule and drawings for all locations.
FT04 = Mechanical louvers, integrated into curtain wall unitized system.
FT04.1 = Glass Fins System, integrated into curtain wall unitized system.
FT05 = Curtain wall stick system. Insulated glazing units, with aluminum mullions and
transoms, with integrated double leaf doors. Refer to architects door schedule and
drawings for all locations
FT07 = Folding door system at amenities, insulated glazing units, aluminum door frame
assembly. Finish coating according to architects.
FT08 = Custom metal panel screen at podium.
FT08.1 = Integrated louver system at podium.
C. DESIGN
The façade design for all three towers are the same. This is mainly due to the towers footprint
similarity in shape and size. The levels and numbers of mechanical floors with different façade
treatment are the noticeable differences mainly due to towers height.
D. DELIVERY TO SITE
After the products / materials had arrived at the designated port, the container trailer will
deliver them to the construction site or assembly factory after clearing customs. It will take several
hours from port / assembly factory to site. The qualified supplier or sub-contractor will comply with
the local regulations of UAE with respect to the allowed weight or load and will have a proper
planning and timing of delivery to avoid the traffic congestion during peak hours. The container
trailers will arrive on site according to the planned route. The material deliveries to site will be
scheduled in advance and booked to arrive at a predetermined times. The below figure will
indicate the flow of delivery routes from port to specific area.
At Port location
At Project Site
At Working Area
The following table will give the general delivery procedures that will be carried out at the
site with the proper allocation of manpower and supervision.
E. ASSEMBLY PROCEDURES
The assembly of panels and other facade elements will be done by allocating an
assembly workshop which is to be agreed by the relevant parties. Suitable assembly equipment
will be used along with the proper assembly staff delegated for the project such as assembler,
package and delivery workers, QA/QC, administrator and forklift driver.
The designed facade materials will be strictly tested in its quality after assembly. Then
transport the qualified ones to construction site for erection.
Other relevant information for the assembly process of the facade material will be
presented as per below details.
Injecting sealant
E.9
F. PRE-INSTALLATION ACTIVITY
The pre-installation check and site survey are the main activities that will be involved in the
pre-installation activity.
As soon as CSCEC is satisfied that the required façade installation area on the
building is sufficiently advance, clear, clean and safe for the subcontractor
installation works to commence, CSCEC will “release” the area in writing. Included
with this “release” will be the co- ordinates and values for the setting out control
points and levels (bench marks) provided on the building in each of the areas
included within the released area.
Subcontractor will then carry out a dimensional survey check of certain elements of
the structure interfacing with our works.
Following subcontractor survey checks, CSCEC will rectify any discrepancies that
have been noted. Following completion of the CSCEC’s remedial works, the area
will be handed over accordingly in writing. Please note that the sequence and
timing of the “release” and “handover” of the works areas to Subcontractor is critical
to the timely completion of the works within the specified programme constraints.
Prepare and deliver to site, access and installation equipment required for the start
of subcontractor’s installation activities.
Distribution of panels to
F.11 respective installation area.
G. INSTALLATION METHODOLOGY
The critical factor to achieving a successful high-rise tower project is planning and
executing the installation works with the correct level of expertise and proficiency.
The works are substantially repetitive and therefore dedicated teams must be
allocated to each specific task, where upon these teams can proceed up to the higher and
succeeding floors with ease and skill, at the required pace.
This installation methodology sets out a concept of how the works will be executed in
general for each of the primary facade types.
Detailed work method statements, along with the necessary safety considerations
and risk assessments will be developed and agreed for the specific tasks prior to installation
of each commencing on site.
The other main considerations for the planning of facade work are the site logistics
and the required equipment for the successful completion of the scope of work. Adequate
material lay down area shall be allocated prior to the delivery of all related materials at the
site. The suitable hoisting and installation equipment will also be considered to achieve the
target completion of work. Electric operated floor crane is commonly used and it will be
located on several floors above the floor on which the panels are to be installed. In the use
of floor crane a steel counter weight will be utilized. The counterweight of floor crane shall
be minimized and use of jacks to meet the uniform distribution load of floor slab.
Floor Crane
Distribution of materials at
G.1 the designated areas
A. SCOPE OF WORK
The MEP scope of works of this project includes all items required for a full functioning
of the Building’s part that includes the following:
B. WORK PROGRAMME
B.1 General
Work programme will define the baseline plan and updated plans for completing the works
and will identify all intermediate milestones that represent major deliverables. It will allow for
progress reporting and support earned value management to evaluate progress payments. All
interfaces with other disciplines will be clearly identified on work programme.
weekly progress meetings. In addition, a 90-day rolling window programme will be updated and
presented weekly to highlight milestones, submittals and critical path activities.
In case certain activities shown on the progress programme fail behind schedule to
the extent that any of the mandatory critical dates or milestone completion dates are at risk of
being delayed, a supplementary recovery programme will be prepared to regain compliance with
the last previously approved progress programme.
All programmes will be reviewed and approved by the Engineer. The Engineer is allowed
14 days for initial submission review and 7 days for re-submittal reviews of the preliminary
programme and progress programmes, and 21 days for initial submission review and 14 days for
re-submittal reviews of the baseline programme.
B.5 Narratives
The narratives provided with programmes will include planned and actual progress,
critical path progress and concerns, potential delays, submittal status, earned value and variances.
These will be stand-alone documents and will not require their corresponding programmes to be
attached in order to understand the narrative.
C.1 Mobilization
Mobilization activities should be initiated following the execution of sub-contract
agreement with the Contractor and should be performed according to the instructions and Site
Logistics Plan of the Contractor. A mobilization plan should be prepared and mobilization
activities should be executed accordingly.
C.5 Organization
Project management team will be composed of members with the necessary skills and
will be in sufficient number to carry out the works as defined in the tender scope of works
documents. Special attention will be given to the responsibility for coordination, scheduling,
engineering, design review & shop drawing production, timely preparation of submittals, method
statements and other technical work, inspection & testing, health safety and environmental
performance, procurement, commissioning, take-over and closeout. The management team
will have the full authority necessary to execute the works to a satisfactory completion.
The management team will have sufficient experience in the satisfactory completion of
similar works of similar magnitude. The ratio of general labor to skilled labor, of skilled labor to
supervisors, and of supervisors to management will be such that the pass down effect of
knowledge, experience, policies and procedures would result in an effective work force that can
perform the work on time with a level of required quality.
Following the execution of sub-contract agreement with the Contractor, an initial
organization chart will be submitted to the Contractor. This chart will be updated as the project
progresses.
The project management team will have the following capabilities:
Prepare and maintain a work programme and resolve project related issues
Establish HSE policies, procedures and activities and provide a safe and healthy
project working environment
Prepare and provide samples, presentations and mock-ups for review and approval
in a satisfactory, professional and timely manner according to the programme
Prepare and submit all submittals in a timely manner according to the programme to
ensure timely completion of project
Prepare and perform procurement in a satisfactory, professional and timely manner
according to the programme
Coordinate activities of suppliers to ensure timely deliveries for installation
Coordinate MEP construction activities to ensure the availability of required
supervisory, skilled manpower and adequate construction labor to maintain the project
programme
Coordinate necessary inspections with relevant parties as required for the progress of
works
Participate in project meetings to review the progress of construction, and identify and
resolve outstanding construction related issues
Prepare and submit weekly, monthly progress reports and other progress, status and
technical reports and submit these to the Contractor, as required
Coordinate and/or perform all required inspection and testing for quality control,
pre-commissioning and other performance of work, and maintain a record of tests
and inspections
Maintain an accurate and up-to-date record of as-built documentation
Observe the work for compliance with technical specifications, maintain a list of
observed deficiencies and report corrective measures to the Contractor
Assemble as-built and record documents and submit these to the Contractor
Prepare a written report upon systems and sub-systems and submit to the Contractor
Participate in system inspections, testing, pre-functional preparation and start-up
sessions and make corrections listed in the punch list prepared by the Contractor
Cooperate with the commissioning team and provide all labor, materials, equipment
and personnel expertise in compliance with specifications
D. SUBMITTALS
D.1 Submittal Register
Subsequent to the execution of sub-contract agreement with the Contractor, a submittal
register identifying submittal number and description of each submittal required for the project
will be prepared and submitted to the Contractor. This register will support the necessary
dates of work programme and will indicate date of submission, review time, approximate date of
return and type of submission.
The following main submittal groups will comprise the submittal register:
In case of revise and re-submit, all revised content will be clearly marked and identified
in re-submittals. The review time will be 14 days first re-submittals and 7 days for second re-
submittals.
A safety manager, whose full-time duty will be connected with health and safety aspects
of the project, will be appointed. Safety manager and supervisory safety staff will be authorized
to take urgent appropriate action to make the site safe and to prevent unsafe working practices.
Arrangements for training of site staff to enable them to undertake properly their
health and safety responsibilities.
Arrangements for job specific health and safety training of all workers.
Arrangement to ensure that, at least once a week, all workers will receive a toolbox
talk with their supervisor.
Details of quantity and specification of all necessary safe condition monitoring
equipment.
The means and frequency by which safety facilities shall be inspected tested and
maintained.
Details of the proposed first aid provisions.
Details of how, where and by whom the auditable health and safety records will be
kept and maintained.
Details of the arrangements and frequency of site safety inspections.
A comprehensive health and safety inspection checklist to be used during site
safety inspections.
Details of int er n a l safety audit schem e to b e i m p l e m e n t e d regarding
safety management system and the physical site conditions.
The safety plan and procedures will be internally reviewed on a continuous basis, will be
revised if activities and experiences on site necessitate. Procedures will be revised and/or
new procedures will be issued whenever the character or extent of an activity is changed or
a new activity of different nature is introduced. Such procedure revisions will be aimed at
enhancing the standards of safety being implemented on site.
F. QUALITY ASSURANCE
Quality assurance plan and quality procedures will be issued to the Contractor
for review and approval before the relevant works will start.
F.3 Audits
A schedule of internal and external audits to be conducted will be submitted with quality
assurance plan. The scope and the method of the audits will allow verifying that all aspects of
the work are conducted according to the project specifications. The Contractor will have the right
to conduct audits and inspections of all works that are being executed.
All internal audits will be communicated to the Contractor after the completion of the audit.
Non compliances found during the audits will be recorded as non-conformance records.
Regular and appropriate training will be given to all personnel involved in the operation
of quality management system to ensure their competence to do their work. The records of
these training will be maintained for audit purposes.
G. DESIGN WORKS
G.1 Design Review
The first phase of design works will be review of tender calculations and drawings. During
this phase, tender design documents will be examined thoroughly. After review is completed, the
issues of concern regarding design, if any, will be communicated to Contractor for information.
Queries will also be communicated to Contractor via RFI (request for information) before
proceeding with shop drawing production.
a. Electrical Systems
Schematic Diagrams
Equipment Schedules
Single Line Diagrams
b. Plumbing Systems
Schematic Diagrams
Equipment Schedules
Waste Water Plans
Sewage Water Plans
Rain Water Plans
Hot/Cold Water Plans
Plumbing Technical Room Layouts
Plumbing Detail Drawings
c. HVAC Systems
Schematic Diagrams
Equipment Schedules
Heating and Cooling Plans
Ventilation and Air Conditioning Plans
Exhaust Air Network Plans
HVAC Technical Room Layouts
HVAC Detail Drawings
matrix table will provide a paragraph by paragraph comparison between the specification and
the proposed equipment. The Compliance matrix will state the compliance conditions as “Noted
(N)”, “Full Compliance (C)”, “Partial Compliance with Remarks (PC)” and “Non-Compliance (NC)”.
Substantiating documentation will be referenced in the compliance matrix table.
Material submittal will be re-submitted to the contractor within the specified period of revision.
and communicated to head office management for approval. After review of the alternatives,
management will decide on the supplier/manufacturer to proceed with.
Following the approval, procurement staff will make final negotiations with the
supplier/manufacturer and a purchase agreement will be made. This agreement will
ensure that:
The production will meet the project specifications
The materials will be produced in accordance with the work programme
The necessary technical documents of the final product will be prepared
The packing of the product will conform to the project specifications
I.6 Delivery
The following issues will be taken into account in delivery arrangements:
Minimizing long-term storage and preventing over-crowding of construction spaces
Coordinating delivery with the installation time to ensure minimum
holding time for sensitive items
The Contractor will be notified of the arranged delivery in advance. The estimated time of
delivery, quantity and volume of delivery, packing conditions and other specific details of the
materials will be communicated to the Contractor to allow for making necessary arrangements
according to the site logistics plan before materials are delivered.
As the materials are delivered on-site, a request for inspection will be submitted to
the Contractor for inspection of the delivered materials. The Contractor’s representatives will
check the material and the compliance of the delivered materials with project specifications will
be verified. Any damages on materials will be inspected. An inspection & test record will be
prepared for the delivered materials.
I.7 Storage
Following the acceptance of materials by the Contractor, the materials will be unloaded,
handled and stored at locations specified in site logistics plan. The storage locations will be of
two types: enclosed warehouses and exterior storage areas.
Warehouses will be utilized to store sensitive equipment and materials. The temperature
and humidity conditions within the stated range in the manufacturer’s instructions will be
maintained in warehouses.
Materials subject to damage will be stored in their original enclosures, loose products
will be stored on shelves or in bins or in neat groups of similar items.
Exterior storage areas will be assigned to store materials & equipment which are robust
or difficult to handle. Substantial platforms will be provided to support materials above ground
to avoid possible damages on exterior storages. Surface drainage will be adequate to prevent
flooding of water along equipment bases. Loose materials will be stored on clean solid surface.
The storage locations will be arranged and maintained in such a way that the:
Complete computer software package and equipment of the system will be tested and
performance of the system will be verified. The performance criteria will be functionality, system
capacity, hardware interaction, hardware and software interaction and report generation.
Systems will be accepted by testing parties if the performance of the system equals
or exceeds the criteria stated in specifications. After completion of the test, all equipment will be
re- packed to be delivered to site for installation.
K. MOCKUP WORKS
Mockup areas will be designed, constructed and populated with mockups to demonstrate:
Mockups will be of three types: Prototype mockups, visual mockups and in-place
(technical) mockups. Prototype mockups will be located in manufacturer’s production facilities
and will be used for testing purposes. Visual mockups will allow for verifying material, color
and interface details between elements. These mockups will be located within specified mockup
facility or within a staging area on building site. In place mockups will be used for verification of
workmanship of installation. Approved in-place mockups will be part of the permanent works.
The execution and workmanship of the following points will be checked during mockup
inspection:
The performance of MEP mockups in the mockup facility will be checked by Interior fire
suppression system, fire extinguishers and cabinets for fire protection system; waste water piping,
water distribution piping and sanitary fixtures for plumbing systems; cooling units, exhaust fans
for HVAC system; electrical outlets, lighting fixtures, power supply to equipment for electrical
systems.
The below listed method statements will be prepared to define the method of installation
As the case for design documents and materials, method statements will be
subject to submittal procedure as explained in Section under Submittals.
M. CONSTRUCTION WORKS
M.1 General
MEP construction works will cover the mechanical, electrical, plumbing, fire protection and
ELV system works stated in the Tender and Scope of Works Documents.
Prior to the start of construction works, approval of relevant method statements and
inspection & test plans will be ensured.
All safety measures will be taken to allow for safe working conditions on site. Periodic
toolbox meetings will be held at site to inform the workers on safety issues. HSE manuals will be
available to all workers. Safety conditions will be monitored on-site daily. Any adverse condition
that may involve risk to workers will be communicated to the Contractor, and necessary actions
will be taken according to the Contractor’s instructions.
Fan Coil Unit /Blower units, electric water heaters installation, Piping and ducting ancillary
installation such as valves, dampers, etc. and fan installation works will also be executed during
the first fix MEP installation phase.
works. Fire protection rooms will be fitted with fire pumps, and gaseous fire suppression system
equipment.
progress meetings, HSE meeting and special meetings together with the Contractor staff. The
documentation required for the meetings will be prepared and submitted to the Contractor prior
to the meeting.
within the scope of inspection and test plan will not begin until the plan is approved.
The following will be clearly identified in the ITP:
All required inspections and tests required by project specifications
Required testing frequency
The accept and reject criteria
Records required for compliance
Procedures and instructions to be used for control of each activity
Inspection, witness, hold and test points
Inspection and test plans will be submitted and approved as described in Section.4
Submittals.
Prior to inspection and testing, project specifications and approved shop drawings will be
reviewed, availability and condition of
Testing equipment will be checked. All inspections and tests will be conducted in
accordance with specified standards. The quality of workmanship will also be checked.
After completion of inspections and tests, results will be reported to the Contractor.
Inspection and test records will identify the following:
Name and quantity of items inspected/tested
Inspection/test procedure reference
Observations
Specified requirements
Acceptability
Deviations and non-conformances
Corrective action
Evaluation of results
O.5 Non-Conformances
The quality control plan will establish a system to identify, document, control and process
of nonconformance. When material, equipment, documentation or performed work does not
comply with the requirements of project specifications, a non-conformance report will be
prepared and submitted to the contractor and non-conformance procedures will be executed.
Prompt action will be taken to identify the causes of each non-conformance and corrective
action necessary to prevent recurrence.
The following information will be provided to the Contractor for non-conformances:
Identification of non-conformance
Description of non-conformance
Evaluation of non-conformance to establish the cause
Recommended corrective action
Date non-conformance is identified
Date corrective action is completed
Each non-conforming item will be clearly identified with a distinguishing status tag. Tagged
items will not be covered until the Contractor’s approval of non-conformance and corrective action.
A non-conformance log will be developed and maintained to track all non-conformances.
Statistical techniques will be employed to identify non-conformance trends. Preventive measures
will be proposed, and their effectiveness will be closely monitored.
P. COMMISSIONING
As the construction works are completed, commissioning works will be performed to
ensure that all equipment and systems perform as individual systems and function interactively
with other systems according to the project specifications.
approved by the Engineer. The test data will be recorded at each step of testing and test results
will be reported to the Engineer. A punch list for pre-functional testing will be prepared according
to the test results. The deficiencies listed in the punch list will be corrected before the start of
functional performance testing.
After successful completion of pre-functional tests and start-up, functional performance
testing will be executed. The proper and integrated operation of systems according to project
specifications will be demonstrated and verified during functional testing. Functional performance
tests will be carried out according to the procedures developed and approved by the Engineer.
Systems will be tested under various modes such as during low cooling loads, high loads,
pressure loads, component failures, unoccupied, varying air temperatures, fire alarm, power
failure, etc. During the testing process, areas of deficient performance will be identified and
recorded in the punch list. Items of non-compliance in material, installation and setup will be
corrected and re-tested.
The commissioning team will provide the Engineer with monthly commissioning reports.
The progress report will contain an update of commissioning schedule, progress of
commissioning activities and the new/outstanding deficiencies to be corrected.
After successful completion of commissioning works, final commissioning report will be
prepared and submitted to the Engineer for approval.
The instruction programme will include training on each system, sub-system and
equipment. The training modules will mainly cover the following:
Fire Protection Systems
Fire Alarm Systems
Refrigeration Systems
HVAC Systems
HVAC Control Systems
Electrical Service and Distribution
S. PROJECT CLOSE-OUT
S.1 Substantial Completion
The following works will be completed prior to substantial completion:
a. Inspection and Declaration: The completed works will be inspected with the Contractor
and the Engineer, deficiencies and defects will be identified. The deficiencies will be
repaired as required to conform to the project specifications. Then, a written certificate
will be submitted to the Engineer to state that the works are complete and ready for
final inspection.
T. OPERATIONAL READINESS
Following substantial completion and issue of Taking over Certificate, operational
readiness validation phase will commence to ensure that the Central Utility Buildings will be fully
operational for the planned opening.
A. SCOPE OF WORK
The landscaping works is under Provisional Sum however; CSCEC ME will provide the
construction methodology as part of this submission. This project has external areas that have
been designed to receive Hard and Soft Landscaping elements. The external works will include
the following scope of works:
Exterior Civil and Structural Works
Exterior Hard Landscaping
Exterior Soft Landscaping
Roads and Parking Areas
All excavated materials will be removed from site as per the requirements of the employer
and will be disposed of in pre-arranged and approved locations.
Structural works will be required to form planter areas and sub bases for the roads and
paved areas. These works will be undertaken from approved shop drawings and method
statements during contract execution.
Specified waterproofing works will be undertaken and will be installed with an approved
waterproofing material to protect the structures from water ingress and any application thereof
will be based on specifications and areas will be offered for inspection before the application of
final finishes to these structures elements – 50mm minimum water depth will be achieved for 48
hours.
All detailed Method Statements and materials will be submitted for approval, prior to works
execution on site.
Exterior Render
The render for use externally will be composed of one-part cement and four parts of sand,
and will be applied to the finished indicated thickness externally. Plaster or render will be mixed
in clean buckets and gauge boxes. All tools will be kept clean and fresh plaster or render will
be contaminated with set plaster or render. The ingredients for the plaster or render will be
mixed three times dry and three times while water is added.
The working time permissible after the addition of water to the plaster or render mix will
be thirty minutes. Mixed plaster or render that has exceeded this limit will be removed from the
site and not re-tempered and used in the Works.
All surfaces to be rendered will be sprayed with water, which to be allowed to dry
out before a key coat of cement slurry is applied. All undercoats are to be scratched to form a key
and have been left in a moist condition for at least three days. All plastering will be executed in a
good quality of workmanship and made good to wood frames, skirting, pipes, fittings and the like.
Plaster work is to be finished with a smooth, trowel face, MRB will make full use of grounds, rules
and angle trowels to ensure that all wall faces finish plane and true to line in all directions and
that all angles are straight, true and plumb. Any tile trim and accessories will be installed during
the installation phase and kept clean and stain free at all times.
Plaster will be cured at least for 3 days after the plaster has developed enough strength,
not to be damaged by water.
Setting out of paving shall be as per design and approved Shop drawings
Proper Leveling of Substrate below will be with level edge / straight edge
Paving will be laid over the bedding substrate as per the approved
pattern/design
Pavers will be leveled with rubber mallet / hammer to attain required leveling
and bonding
Uniform joints on all sides will be maintained between the pavers using required
spacers
Joints will be grouted with approved dune sand materials
As final leveling, plate compactor will be driven over the pavers
Stone Works
Stone finishes will be set in place by providing the relevant build-up underneath as
reflected in design drawings and specifications. Mix design for bedding / adhesive shall be
submitted for consultant’s approval.
Setting out of Stone flooring shall be as per design and approved Shop drawings
Proper Leveling of Substrate below will be with level edge / straight edge
Stone will be laid over the bedding substrate as per the approved pattern/design
Stone will be leveled with rubber mallet to attain required leveling and bonding
Uniform joints on all sides will be maintained between the stone using required
spacers
Joints will be grouted with approved grouting material, color to be approved by
the consultant
As final finishing if not provided during the manufacturing process, where required
flooring will be polished or honed for perfect leveling.
Road works will only proceed if all relevant approvals of Shop Drawings, materials
and inspections. All works will proceed as per the approved shop drawings. The shop
drawings will include any movement and/or construction joints required in the base and
corresponding finishes.
This section will give a brief overview on how the project teams can manage the
implementation of the “Downtown Views II”.
5.1.1 Introduction
CSCEC ME LLC has highly qualified staff with extensive knowledge and experience on
residential “Downtown Views II”.
While creating the suitable organization chart to the project, our main aim is to achieve a
successful construction process and completion in line with the Project and Employer’s
requirements.
The nominated staffs at the time of tender are the staff members with high-end capabilities,
skills and expertise who are highly qualified to render a quality and professional services.
A. Policies
The respective CSCEC ME LLC Company Policies provide the framework for the operations
and supporting functions in which The CSCEC ME LLC conduct their activities. The Directors
and employees of all companies have set for themselves standards of conduct in the
relationship with each other, Employers and with all those they deal with in their work as stated
in the Respective Codes of Business Conduct.
As part of the CSCEC ME LLC primary business activities, Design / Engineering,
The management plans are supported by project procedures, instructions, inspection and
test plans, checklists and work method statements.
The Project Management Plan will be the lead plan supported by the project-specific plans
for the key disciplines. For the purpose of this submission we have referenced the applicable
plans for the main sections of work and provided the commentary on the key controls applicable.
The Project Quality Plan also provides a system for managing, monitoring and recording the
performance of the quality system.
The Project Quality Manager is responsible to ensure all planned quality assurance and
control activities are implemented and completed by the relevant Project team members.
Our Quality planning will focus on:
Identified constraints and risks
Quality objectives and targets
Resources required
Competency and training needs
Material controls
Inspection and verification requirements
Performance assessment of the system
Continual improvement
Further to the continual improvement, we have successfully used the following evaluation
format at a Steering Group level to indentify underperforming areas of the Project to ensure
continuous improvement. Each Party completes the schedule and brings to the meeting their
respective ratings which are discussed and consensus reached on the rating for the month. For
underperformance, the projects leadership team, set objectives for improvement, which are then
evaluated at the next steering meeting.
covered in divisional procedures. The following deals with the matter of material quality:
H. Pre-Award Assessment
Prior to awarding of a supply agreement for high-volume material as per the Procurement
Plan, potential suppliers are short-listed. The Project Commercial Manager
(Subcontracts/Procurement) arranges with the Project Quality Manager to conduct visits to the
potential suppliers' production premises to assess their capability and resources to meet the
required standard of quality.
The Project Quality Manager assigns the appropriate person to conduct the assessment.
Where special technical skill is required, the Project Quality Manager coordinates with the
Project Manager to identify the person.
Reports are completed of the visits and forwarded to the Project Commercial Manager
(Subcontracts/Procurement) for evaluation.
I. Material Certification
For suppliers as required through specification are to provide conformance certificates or test
reports confirming compliance of the material traceable to the batches supplied. Proof of
calibration for equipment used in the certification testing is also to be included.
These certificates or/and test reports are forwarded to the Project Quality Manager for review.
Any corrective and preventive action arising from the review is handled according to approved
company procedure.
process certain inspection or/and tests would be required, the frequency and the person
responsible for the inspection and testing, acceptance criteria and type of records required.
All these planned inspection and testing are derived by correlating requirements from the
Construction Programme, Contract specifications, Work Method Statements, construction
drawings, shop drawings and industrial standards.
Inspection and Test Plans (ITP) are developed and controlled according to approved
Company procedure. It is required that all Supervisors responsible for the activities on the ITP to
sign on the ITP to indicate having read and understood the requirements.
Appointed subcontractors are requested to submit their own ITP or QA Plan for review by the
Project Manager, relevant Section Manager and the Project Quality Manager.
Where the subcontractor is unable to produce ITP or where submitted ITP does not meet the
requirements, the Project Quality Manager decides whether to assist the subcontractor in
amending the ITP or issue CSCEC ME LLC produced ITP for their use.
Any interfaces with the Employer or Employer's representatives with regard to joint
acceptance inspection must be included in the ITP to ensure these are carried out. HOLD points
are included into the ITP only when it is required contractually. Additional hold points requested
by Employer must be agreed with the Project Manager.
A briefing is held whenever an ITP is issued for all engineers, supervisors and
subcontractors involved to explain the usage of the ITP as well as to highlight any issues
identified. This briefing is called by the Project Quality Manager and conducted by the originator
of the ITP or other nominated person by the Project Quality Manager.
M. Verifications
To ensure a most robust inspection and testing regime, verification is carried out to ensure
the personnel responsible to carry out the planned inspection and testing have done so
effectively and in a timely manner.
The Project Quality Manager is responsible to identify the area and activity, plan, and assign
personnel to carry out the verification activity. The frequency depends on the criticality of the
activity, but generally, this is carried at least once a month for all critical Packages.
Personnel who are nominated to undertake the verification must be one removed from the
process activity or area. The verifying personnel are also rotated with regards to the assigned
activity or area.
Reports are completed and submitted to the Project Quality Manager for review and
coordinate any further action required.
5.2.1 Introduction
The planning management team for this project will comprise of Planning Manager and
Planning Engineers.
The nominated key personnel at the tender stage are highly qualified managers and
engineers with intensive planning management experience in the field of actual project
implementation.
A. Planning Manager
To provide up front planning, resource loading and leveling, progress reporting, updated
schedule and cost information and analysis of project trends in schedule and cost, thus enabling
management to make informed decisions. To provide Project Management with analysis and
subsequent recommendations as to potential problem areas, possible work-around, etc.
Support Proposal group with pre-contract proposal schedules (summary or detailed) as TTS
(Tendering Time Schedule). Set up project execution schedules, support site construction
activities with updated construction schedules and analysis, and interface with various project
subcontractors to coordinate schedule integration. Interface with clients to support their planning
and scheduling requirements. Dynamically and regularly, monitor and control project schedule
during tendering and execution stage.
The below given flowchart for planning management will indicate on how the planning team
will initiate the planning of the project up to the project close out stage in coordination with the
generated and derived programme of the project. This is one way of tracking on the relevant
milestones of the programme taking into consideration the critical path and activities related to
the project.
This section will give a brief overview on how the technical teams can manage the
implementation of the “Downtown Views II”.
5.3.1 Introduction
The technical team for this project will comprise of Technical Manager, Technical Engineers,
Structural Engineers, Architects, etc. The team will be holding the full responsibility of the
technical aspect of the project for structural and architectural concerns.
The nominated key personnel at the tender stage are highly qualified engineers and
managers with vast array of engineering, construction and architectural experiences that makes
them strong, confident and competent leaders for this project to successfully implement the
project with respect to integrity, safety, structural stability and quality of big scale and mega
project like this “Downtown Views II”.
Source Selection
In selecting sources of supply for any material or service we seek a competent, reliable
supplier with a good competitively priced product solution, who is interested in being a valued
member of the project team, and who shares our values. Usually this objective is best achieved
by comparative shopping in a way that allows CSCEC ME LLC Management to make an
accurate judgment based on these criteria. Sometimes, the choice is obvious, and should be
made outright using negotiations to assure an equitable fit. But usually, particularly in the case of
a new requirement, the most effective approach is to conduct a competition.
It should be assumed that regardless of the selection method used, someone will be
unhappy and will seek to protest. Therefore, unambiguous descriptions of the basis to be used
for selection, and rigorous evaluations with thorough documentation are a must, and will save
lots of grief later.
This procurement package must provide the Subcontract definition based on and
accurately reflecting all of the applicable prime contract requirements.
Key events pertaining to subcontractor efforts in support of the in-house project master
schedule. These milestones will start from the end-item delivery date that will support the overall
program, working backward using executable durations, based on experience, to the start of
subcontractor production. Compatible in-house milestones will also be established starting with
subcontract placement, working backward through negotiation and receipt of contractor
proposals to subcontractor task definition.
The method of selection and the criteria that will be the basis of selection of the
successful subcontractor, as well as the contract form anticipated.
The expertise to integrate and coordinate the functional inputs with the prime contract
requirements and goals and the program schedule, programmatic and budgetary constraints will
be in the Project Site Office. They will conduct meetings with various subcontractors and will
handle the communications prior and after award of subcontract. In addition, they will
administrate the sub contract up to clearing the final account and successfully close out the
project.
o Subcontractor Selection
The team conducts the source selection process following applicable policies and
procedures, and prepares the results for review and approval by CSCEC ME LLC project
management team, Engineer & Client representative.
The subcontractors’ management team will recall the subcontractors who had bid earlier
during the tender to re – quote for the project with a very well defined scope and schedule
requirement, and will ensure that that the submitted bids will be matching and in line with overall
project requirements
If the service / material is an off the shelf item requiring no development effort, this effort
is curtailed to monitoring delivery commitments to assure they will be met.
partner, each member is expected to provide the technical and management excellence of his
parent functional organization necessary to assure that the subcontract achieves the results
committed to by the functional organization. Each team member will also be responsible for
monitoring and controlling his scope with the budget allocated to his functional organization for
the subcontract, and will share with all of the team members the responsibility for adherence to
the overall subcontract cost and schedule constraints.
Each team member, along with his or her functional manager, is expected to assume this
"ownership" attitude toward the segment of the product that they have committed to provide.
They are also charged with accomplishing their organization's commitments for the subsystem
or equipment as a whole. This is at once an individual, an organizational, and an integrated
team attitude. These objectives require each team member to establish effective relationships
and work in concert with the other functional team members to assure that all interdependent
program tasks are completed successfully.
This section will give a brief overview on how the material management team can manage
the implementation of the “Downtown Views II”.
5.5.1 Introduction
The material management team for this project will comprise of Materials Manager, Material
Engineers, etc. The team will be holding the full responsibility of the material technical and
quality aspects of all the materials that will be used for this project. It will also include in how the
materials will be consumed, handled, delivered, loading and unloading procedures, lifting
requirements and storage of materials in coordination with the construction, plant and logistics
team including the testing of materials in compliance with all standard operating procedures of
CSCEC ME LLC and the project.
The nominated key personnel at the tender stage are highly qualified managers and
engineers with high end experience in the field of material engineering.
A. Materials Manager
The Material Engineer will be resident on site and will report directly to the Project Controls
Manager on all matters relating to materials. He will lead a team of engineers that will monitor
the condition of all materials that includes visual inspection and material testing at the site. He is
also responsible for the implementing of schedule of testing if materials with respect to the
frequency and type and properties that requires testing. The materials and Logistics manager
will plan prior to the commencement of the project to properly allocate material lay down areas,
material storage areas, lifting equipment, schedule of loading and unloading of materials in
compliance with the delivery schedules and procedures along with the reconciliation of the
procurement and construction activities of the project.
The material management strategy of CSCEC ME LLC will include the procedures on how
the materials will be delivered to the project site in coordination with the procurement team.
B. Delivering to Site
Deliveries to site will be controlled by implementing and managing a booking-in system. The
system is to be managed by the Logistics Team and coordinated with Construction Team and
site Security Team. All deliveries shall be notified to the Logistics Manager 48 hours in advance
using the Delivery Booking-in Request Form.
All deliveries will be approved by the relevant Project Construction Manager for the specific
area before being finally submitted to the Logistics Manager. Deliveries that arrive unscheduled
may be refused access or have to wait until access is clear.
Vehicles arriving in accordance with the planned schedule will be required to present
documented proof of delivery to the Site Security Team and will be issued a temporary vehicle
pass to allow access to the relevant delivery district. Delivery vehicle drivers will not exit their
vehicles if they do not have the appropriate PPE to wear when outside their vehicle. CSCEC ME
LLC will provide temporary staging areas to allow for material inspection and for temporary
storage. The staging areas will be coordinated with the relevant Construction Manager.
Contractor/Supplier requires
delivery to the Project
Contractor/Supplier completes
delivery request form and submits
to Project/Construction Manager
D. Unloading Areas
There will be areas allocated for materials handling and unloading located adjacent to the
respective works areas. These areas will be clearly identified in the Site Logistics Management
Plan.
Materials are not permitted to be left unattended within these areas and drivers must not
leave vehicles unattended whilst being unloaded. Materials Handling management personnel
and Tower Crane slinger signalers and / or Mobile Crane slinger signalers will control all delivery
vehicle movements and their instructions must be obeyed by all drivers. Delivery vehicle drivers
will not exit their vehicles if they do not have the appropriate PPE to wear when outside their
vehicle.
F. Storage on site
CSCEC ME LLC shall establish a lay down / storage yard for the main stores during
execution of the works. The location of the lay down storage are shall be agreed with the
Contractor on Project award. Other localized on-site storage areas are all subject to approval
from the Project Logistics Manager and the Project Construction Managers.
Materials are to be stored in onsite areas on a short term basis and are to be delivered to
site “just in time”. This area will be controlled by the storekeepers under the Project Logistics
Managers supervision.
Due to the phasing of the construction, areas will be available for temporary storage of
shuttering and formwork during the construction period, these areas will change as the project
progresses.
Areas allocated for storage will be available for short term storage only and subcontractors
will only be allowed to store materials for periods that ensure no damage is likely to occur from
the heat and humidity from the summer months and likewise for the winter months if materials
could be subject to damage from water. All materials stored will be palletized for ease of
relocation.
As the project develops, materials storage areas will be changed to suit the requirements of
specific materials being delivered as required, Storage plans will be distributed to all parties.
Subcontractors will need to control deliveries in such a manner that minimal stock would be
stored on site, and deliveries of as needed materials will have to be carefully scheduled.
5.6.1 Introduction
The labour management team for this project will comprise of Labour Manager and or the
Logistics Manager and its subordinates. The team will be holding the full responsibility of looking
into the labour welfare of all the site workers who will be engaged for this project. The labour
manager will work closely with the Logistics manager especially when working during the
construction duration of the project to monitor and identify the requirements of the project as the
project progresses up to completion. If the labour manager will not be available, then the
Logistics manager can take charge in lieu of the labour manager.
Part of the labour management strategy is the education on skills and regulations for all
construction staff will be given before mobilization into jobsite, to improve their working skills and
adjust mentality.
Education will be given to strengthen quality-consciousness, by organizing workers to study
local codes, standards and regulations, explaining detailed technical requirements of working
organization to construction staff so as to make them understand the characteristics of the works,
so that they can finish the rated tasks with skilled operations to achieve high quality, and the
5.7.1 Introduction
The approach and strategy for the development of a site logistic team is to provide a set of
leaders for the implementation of effective and efficient construction support facility for the
construction of the project by the CSCEC ME LLC’s Project Management Team, its
subcontractors and suppliers, this document has been produced at Tender stage and will be
further updated when the project progresses.
The CSCEC ME LLC’s Project Logistics Team will constantly look to update the site logistics
plan and will be supported by detailed drawings to include temporary facilities and services,
temporary use of the internal roads network, logistics management, lay down areas, allocated
storage and external access/egress locations. The document will be distributed to the Client,
Consultants, Project Director and Project Construction Managers and Sub contractors.
A. Logistics Manager
The Logistics manager will be based on site and will report directly to the Project Manager.
He has the responsibility of managing all project related logistics requirements during the
execution of the contract; this will also include the Plant department and general stores. The
logistics manager will be assisted by a team of suitably qualified superintendants and assistants.
The Logistics manager will prepare and implement the project logistics plan. The Logistics
manager will work closely with the project HSE team to ensure all logistics requirements are
implemented in line with the project HSE standards and requirements.
5.7.8 Security
Security Services will be provided for the project on a 24/7 basis and the security team will be
responsible for security, emergency response, traffic in and around the project. Their scope will
be increased or reduced as required to meet project needs.
5.7.10 Contractors
The logistics team will review and approve sub-contractor logistics plans, and coordinate with
adjacent developers to ensure that potential conflicts are avoided. The subject headings
denoted below (logistical Interfaces) should be addressed during the compilation of logistics
plans and may be used as guidance notes.
5.8.1 Introduction
This Risk Management Plan of CSCEC ME LLC will be the guideline for the project Risk
Management Procedures which will include a tentative risk registry and developed and
discussed with all relevant parties at the initial stage when project is awarded. The main
purposes of this procedure are to decrease the probability of negative impact of project
uncertainties basically. Furthermore, the CSCEC ME LLC will try to increase the probability of
positive effects of potential opportunities through this procedure implementation
For the better communication and consequence maximization, all relevant parties will be
invited and facilitated to develop and maintain these procedures during the whole construction
period.
H Rated as High
Seriousness
low E D C A
Likelihood
medium D C B A
high C B A A
Risk Table
5.8.7 Implementation
From this stage, individual execution of counter measures will be taken place by the risk
owners according to each Risk Management strategy developed up to the date. Each
implementation will be monitored by the Project Manager and fed back by the risk owner in a
proper manner.
CSCEC ME LLC will have in-house Risk Management Teams in HQ and the teams will
fully support the site Risk Management Organization and monitor the executions being
progressed in site in accordance with the internal Risk Management Procedures.
Risk Proforma
The Risk Identification Proforma is used to record all risks, their owners, risk assessment,
action required and timescales. Details are transferred on the Risk Register. Anyone can raise a
Risk Mitigation Proforma. The CSCEC ME LLC’s Risk Proforma is below:
Risk Proforma
Risk Registry
The Risk Register is opened during the planning process group. AII risks are recorded
and prioritized The Risk Register is a living document and is formally updated and re-issued at
the end of each phase.
Impact
Risk
Environment
schedule
Quality
Ref Risk Cause control Risk Grade
Safety
cost
measure
• The above given numbers in cell indicate the point of each position in Probability and impact
Grid chart.
- Red: serious, Higher than 15 points
- Yellow: Normal, Between 14 - 6 point
- Green: Ignorable, 5 points or lower
“'Rather than fighting with risks, we control them. Because we know what they are"
management plan & procedure will be developed and a complete risk rigster will be generated
with the project initial stage directly after award. The process of generating the risk registry will
involve all the stakeholderes in the project in several brain storming sessions to develop and
identify different threads & opportunities which the project might face and it will remain as a
guide line document which will require to be revised and updated on monthly and regular basis.
5.9.1 Program and Manage the Testing and Commissioning Process for Project
Close Out Procedures
A. General
CSCEC ME LLC will conduct T&C to check the suitability of the installation and
performance of the system. Partial Acceptance Test (PAT) and System Acceptance Plan (SAT)
will be prepared and submitted for approval from the Engineer, PAT will cover physical
inspection of material/equipment specification, model, etc. while the functional check of the
operation of the system will be covered through SAT. After this, internal T&C of own scope of
works shall follow and integrated testing and commissioning shall be carried out to verify the
functioning of the system with those of the other System-wide Contractors and Civil Contractors.
D. Test Running
On completion of ITC to the satisfaction of the Engineer, CSCEC ME LLC will confirm in
writing to the Engineer that the Works provided by CSCEC ME LLC under the Contract is
suitable and ready for the purpose of Trial Running.
The Engineer will take the lead in the production of the Test Running Program, which
shows all the tests to be performed within the time allocated.
Towards the end of Test Running, the Engineer shall conduct the System Performance
Test with the participation of the Contractor to demonstrate that the overall system is fully
operational ready for normal and degraded conditions.
Upon completion of the Test Running, the Contractor shall submit a statement confirming
that the system is safe and ready for commencement of Trial Running.
E. Commissioning Management
F. Overview
Abbreviations and Definitions
The following are common abbreviations used in this document.
CxA Commissioning Manager
CON Design Consultant
MC Main Contractor’s Commissioning Team
CO Change Order
EN Engineer/Project Manager
FT Functional Performance Test
CMP Commissioning Management Plan
Mfr Equipment Manufacturers
OP Operator: Client Asset Management
PC Pre-functional Checklist
Subs Subcontractors to MC
RFI Request For Information
Commissioning Scope
Commissioning is a systematic process of ensuring, through actual verification of
performance, that all building systems perform interactively according to the design intent and
the Employer’s operational needs.
The Commissioning process is intended to achieve the following specific objectives:
- Ensure that applicable equipment and systems are installed according to the
manufacturer’s recommendation and to industry-acceptable standards and that they
receive adequate operational check-out by the installing contractors.
- Verify and document proper performance of equipment and systems and the inter-
relationship between systems.
- Ensure that complete O&M documentation is delivered to the Employer.
- Ensure that the Employer’s operating personnel are adequately trained.
Commissioned Systems
The following systems shall be commissioned by MC in this project. All general references
to equipment in this document refer only to equipment, building components, and external
interface elements that are to be commissioned.
1) Building Services
o Security and Screening Systems
o Security and Screening System “Access Control System”
o CCTV System
o Addressable Fire Alarm System
o Water Fire Suppression Systems
o Personnel Security / Explosive Screening Equipment
o Conveying Systems
o Elevators Traction
o Elevators Hydraulic
o Escalators
o Moving Walks
o Chilled Water System
o Air Conditioning and Ventilation Systems
o Smoke Exhaust System
o HVAC Automatic Control System
o Computer Room Air Conditioning Units
o Potable Water Supply System
o Plumbing Fixtures
o Sanitary Sewerage System
o Storm Water System
o Water Feature
o Electrical Systems
o Static UPS System
o MV Power Supply Systems
o LV Power Supply Systems
o Lightning Protection System
o Lighting System
o Architectural Feature Lighting System
o Architectural Lighting Dimming Control System
o Addressable Fire Alarm System
o Public Address System
o Power Monitoring and Control System
o Stand-by Power Generation
o Telephone PABX System
o Wireless Distribution System
o Fiber Optic Network Distribution System
o Structured Cabling System
o Personnel Identification and Access Control System
2) Building Fabric / Architectural
o Curtain Wall
o Roof Waterproof Membranes
o Building Maintenance Units (BMU)
3) External Interfaces
o Canal
o Roads
o Landscaping
3)Subs:
Demonstrate proper system performance
4)Mfr.:
Equipment manufacturers and vendors provide documentation to facilitate the
factory acceptance test, commissioning work and perform contracted startup.
H.4 Scheduling
The MC Team shall liaise with the CxA to schedule the commissioning activities. The
format for scheduling commissioning activities, Detailed Commissioning Schedule, in Appendix I.
The MC shall integrate all commissioning activities within his project schedule. The CxA shall
provide the initial schedule of primary commissioning events with the estimated start and end
date for each event at the commissioning scope meeting, which shall be held at the start of the
work to coordinate the different commissioning activities.
12) The outcome of the Commissioning Scope meeting shall notify and increase the
understanding of all parties concerning commissioning management process and
their respective responsibilities. The meeting shall provide the CxA additional
information needed to finalize the Commissioning Plan, including the commissioning
schedule.
Prior to this meeting each CON shall be required to compile all drawings and specifications for
each respective discipline, and the construction schedule by trade for handover to the CxA. The
CxA shall keep minutes of the meeting and distribute them to each participant.
Issue Protocol
For requests for information The CxA shall approach the subcontractor directly. If the
(RFI) or formal documentation enquiry requires information from an external Contract
requests: Package the EN shall resolve
For minor or verbal information The CXA shall approach the informed party.
and clarifications:
For notifying sub contractors The CxA documents deficiencies through the MC to the
of deficiencies: Sub Contractor. Deficiencies shall be recorded / posted in
the Zutec Commissioning Issues Log and reported to the
EMPLOYER
For scheduling functional tests The CxA provides input to, and coordination of the testing,
or training: and the scheduling through the MC and the affected
subcontractors.
For scheduling commissioning The CxA selects the date and schedules through the MC
meetings: and the subcontractors.
For making small changes in The MC may make small changes in operations
specified sequences of sequences to improve efficiency or control or to correct
operations: deficiencies, through the responsible contractor, but shall
document the change and provide all changes of specified
sequences to the CxA, CO and affected Subcontractors.
Subcontractors disagreeing Try to reach a resolution with the CxA first. Then work
with requests or interpretations through MC who shall work with CxA directly or through
by the CxA shall: the EN to resolve the situation.
1) An update of the schedule with list of requested schedule changes and new items
added to the schedule.
2) A list of new and outstanding deficiencies.
3) A description of commissioning progress corresponding to the plan etc.
The MC keeps a log of all commissioning-related issues that require current or future
attention, Commissioning Issues Log.
The CxA regularly communicates with all members of the commissioning team, keeping
them informed and updated of commissioning progress and scheduling issues through memos,
progress reports, etc. Commissioning Memorandum is an example for the memos.
1) The general scope of work, including all resources needed to perform commissioning
tests, particularly for but not limited to operators, maintenance staff, test staff, testing
tools, measurement devices, simulation items.
2) The list and specifications of the tests to be done, including testing conditions,
sequence of testing for each system, subsystem and equipment, written work products,
and training.
3) These documents shall use the specifications, respectively
“General System Start up and Testing Procedures
“General Commissioning Requirements”
“General Submittal Requirements” and
“General Operation and Maintenance Data”
As a model format or template, to be developed and adapted for each system or sub-
system.
The CxA shall review and approve these submittals with respect to commissioning
issues expressed in the contract documents, primarily to aid in the development of
functional testing procedures and only secondarily to verify compliance with contract
specifications. The CxA shall notify the MC the items missing or areas that are not in
conformance with the Contract Documents and, which require correction and
resubmission.
Pre-functional checklists are primarily static inspections and procedures to prepare the
equipment or system for initial operation. However, some Pre-functional checklist items entail
simple testing of the function of a component, a piece of equipment or system.
detailed Start-up Plans for all equipment. The MC shall ensure that there is written
documentation that each of the manufacturer-recommended procedures has been
completed and that such documentation has been submitted and approved by the CxA
prior to being needed on site, and issue the necessary “Notice to Proceed”.
The CxA shall direct the preparation of the pre-functional checklists and procedures.
Those checklists indicate and define the required procedures to be executed as part of
startup and initial checkout of the systems.
The subcontractor responsible for the purchase and installation of the equipment
shall develop the full Start-up and Initial Checkout Plan by combining the pre-functional
checklists with the manufacturer’s detailed start-up and checkout procedures from the
O&M manual and the normally used field checkout sheets. (Plan and Documentation
Requirements for Start-up) Provides a transmittal document and template for the start-up
plan. The plan shall include checklists and procedures with specific boxes or lines for
recording and documenting the execution of checking and inspection and a summary
statement with a signature block at the end of the plan. The MC shall ensure that all such
checkout sheets are submitted for approval by the CxA in advance of the time that they
shall be needed on site, in order to obtain the CxA’s permit to proceed.
The full Start-up and Initial Checkout Plan shall mainly consist of:
- The pre-functional checklists.
- The manufacturers’ standard written start-up procedures exactly same with the
installation manuals with check boxes by each procedure and signature block
added by hand at the end.
- The manufacturers’ normally used field checkout sheets.
- The Subcontractor submits the full Start-up and Initial Checkout Plan to the CxA
for review and approval.
The MC reviews the plans and format for documenting them, noting any procedures
that need to be added and then submits the Start-up and Initial Checkout Plan to the CxA
for approval.
MC. The execution of the Start-up and Initial Checkout procedures shall be
directed and executed by the Subcontractor or Vendor. When checking off
pre-functional checklists, signatures may be required of other
Subcontractors for verification of completion of their work or interfaces. The
CxA shall observe the procedures for each piece of primary equipment,
unless there are multiple units, in which case a sampling strategy may be
used as approved by the CxA. In no case should the number of units
witnessed be less than four on any one system, nor less than 20% of the
total number of identical or very similar units. Subcontractors and vendors
shall perform Start-up and Initial Checkout and provide the CxA with a filled,
signed and dated copy of the completed Start-up and Initial Checkout
procedure forms. All original records produced by the said procedures shall
be organized and submitted to the CxA for the records of the project by the
MC. The MC shall, maintain full copies of all such documents as part of the
O&M Manual documentation.
The sampling strategy shall be submitted to the CxA’s approval, for each
system in the commissioning scope, together with the Start-up and Initial Checkout
Plan.
The Subcontractors shall clearly list any outstanding items of the Start-up and
Initial Checkout procedures that were not completed successfully, at the bottom of
the procedures form or on an attached sheet. The procedures form and any
outstanding deficiencies shall be provided to the CxA within one (1) working day of
test completion. The MC shall review and submit, with the procedures form and any
outstanding deficiencies to the CxA. The CxA shall issue a non-compliance report or
an approval form to the MC.
The MC shall work with the Subcontractors and vendors to correct and retest
deficiencies or uncompleted items. In this respect, the MC shall report to the CxA
and others as necessary. The installing Subcontractors or vendors shall correct all
areas that are deficient or incomplete according to the checklists and tests in a
timely manner, and shall notify the MC as soon as the outstanding items have been
corrected and resubmit an updated Start-up and Initial Checkout procedure form
M.1 Overview
The objective of functional performance testing is to demonstrate that each system
is operating according to the documented design intent and Contract Documents.
Functional testing facilitates bringing the systems from a state of substantial completion to
full dynamic operation. Additionally, during the testing process, areas of deficient
performance are identified and corrected, improving the operation and functioning of the
systems. In general, each system should be operated through all modes of operation.
Inter-system integration performance shall further be tested and checked. The CxA in
conjunction with the MC oversees and coordinates the development of the functional test
procedures in a sequential written form; and coordinates, oversees and documents the
actual testing, which shall be performed by the installing subcontractor or vendor.
Prior to execution, the Functional Test Procedures shall be reviewed by the MC and
Subcontractors for conformance with the Testing Requirements and with regard to
feasibility, safety, equipment and warranty protection. The MC shall then submit the
respective test forms to the CxA for review and approval. Functional testing and
verification may be achieved by manual testing (persons manipulate the equipment and
observe performance) or by monitoring the performance and analyzing the results using
the control system’s trend or activity log capabilities or by stand-alone data-loggers.
The purpose of any given specific test is to verify document compliance with the
stated criteria of acceptance given in the test form.
▪ Project name
▪ Name or Type of Test
▪ Unique test ID number, and reference to unique pre-functional checklist and
start-up documentation ID numbers for the piece of equipment
▪ Trade or Supplier Contractor
▪ System and Equipment or Component Name(s)
▪ Equipment Location and ID number
▪ Original Test or Re-test
▪ Test Date
▪ Participating Parties
▪ Weather Conditions (if applicable)
▪ Test Location
▪ Time of Test
▪ Expected Test Duration
▪ Witness and Sign-off Project name
For any given system, prior to performing functional testing, the MC waits until the
Start-up and Initial Checkout form has been submitted with the necessary signatures,
confirming that the system is ready for functional testing. The CxA shall, witness, and
document the functional testing of all equipment and systems according to the
Specifications and the Commissioning Management Plan. The subcontractors shall
execute the tests. The control system is tested before it is used to verify performance of
other components or systems.
▪ Non-Conformance:
- The MC shall record the results of the tests on the procedure or test form. All
deficiencies or non-conformance issues shall be noted and reported to the CxA
on Form–6 (Commissioning Non-Compliance / Corrective Action Report).
- Corrections of minor deficiencies identified, may be made during the tests at the
discretion of the Test Engineer. In such cases, the deficiency and the resolution
shall be documented on the Functional Test Procedure form.
- The MC records the results of the test on the Functional Test Procedure form.
Deficiencies or non-conformance issues are noted to the CxA on Form–6. The
MC discusses the issues with the executing subcontractor, and advises the CxA
of the conclusions reached. Subcontractors then correct the deficiencies, notify
the CxA and return Form–6 certifying the corrections. The MC shall schedule
retesting through the CxA
- When there are no disputes on the deficiencies and the subcontractor accepts
the responsibility to correct them:
Approval of Tests:
The MC shall note each satisfactorily function on the test form. Formal approval
of the test shall be made later after review by the CxA. The final decision as to
acceptance rests with the CxA. The CXA shall give final approval on each test using
the same form, providing a signed copy to the MC.
Each non-compliance issue shall be referenced to the specific functional test, inspection,
trend log, etc. where the deficiency is documented. The functional performance and efficiency
section for each piece of equipment shall include a brief description of the verification method
used and include observations and conclusions from the testing.
5.10.1 Introduction
The handover strategy of CSCEC ME LLC will include the following general procedures that
will be incorporated and integrated into the final operator sign off, FFE and OSE management
strategy.
After the completion of all the pre requisite activities of this project such as rectification of all
works indicated at the snagging list, an inspection of the concern and related parties will be
done and after all the scope of the inspection has been approved, then all of the area that will be
ready will be handed over to the client with corresponding completion of the below enumerated
procedures of the handing over strategy.
CSCEC ME LLC will arrange training sessions at dates to be notified by the Engineer before
the date of the issue of Taking-Over Certificate, attended by sub CSCEC ME LLCs, suppliers,
manufacturer's representatives, for induction and training of the Employer's long-term
maintenance personnel in the operation, cleaning and maintenance of various parts of the
Works.
agencies will be completed and on file with the Building Permits Directorate office; all deferred
submittal items must be completed and on file with the office, including manufactured roof/floor
trusses, stairs, elevators, etc. The Building Inspector will determine whether all phases of the
building systems are ready to be signed off.
Prior to applying for a Certificate of Occupancy, a final inspection on the Projects will be
passed. Upon successful completion of the final inspection, application for the Building Permits
Directorate for a Certificate of Occupancy is possible.
5.10.9 Warranties
The CSCEC ME LLC will provide a schedule of all the warranties to be provided under the
Contract to the Engineer for review 4 weeks prior to the completion date. Where required in the
Specifications, the CSCEC ME LLC will provide an approved warranty for the warranty period
indicated.
Proposed Subcontractors
1. HSE Management
This section will give a brief overview of the HSE procedures of CSCEC ME that will be
implemented for this “Downtown Views II” project.
CSCEC ME is a leading engineering and construction company and is committed to the
delivery of infrastructure to enable economic and social development in a sustainable way. We
commit to world class fulfillment in everything we do, through our core business of engineering
and construction and by delivering major projects.
The CSCEC ME values are Integrity, Care, Respect, Commitment and Accountability.
CSCEC ME will aim to achieve the following:
Strive to achieve Zero incidents in pursuit of our health, safety and environment
quality vision
Adopt the highest health, safety, and environment and quality standards.
Establish an effective Zero Harm culture through leadership accountability and
commitment. Training, education, systems and behavior modification.
Uphold the STOP.THINK Bill of rights
Enforce adherence to the STOP.THINK Rules
Comply with all applicable legislation and the health, safety, environment and
quality standards, policies and procedures set by CSCEC and our Clients
Maintain regular, transparent and effective communication with all employees.
other stakeholders and communities affected by our operations
Identify, assess and respond in an appropriate manner to all occupational health,
safety, environment and quality risks
Promote efficient use of resources and reduce or prevent pollution in support of the
global climate change agenda
Communicate the CSCEC HSE Policy to all employees, suppliers and
subcontractors and make all aware of their individual rights and obligations.
Continually improve our health, safety, environmental and quality management
performance through taking accountability and responsibility for targets as well as
objectives
Provide the necessary resources to enable implementation of the HSE policies
The CSCEC ME vision for Health, Safety, Environment and Quality is TOGETHER TO
ZERO HARM. All of the other relevant documents for the HSE procedures are enclosed in this
section such as the Corporate QHSE Manual, HSE Policy, HSE procedures and ISO certificates.
Preventing pollution, reducing waste and ensuring, wherever practicable, that measures are implemented
to protect and preserve the environment.
Considering the effects that our operations many have on the local community.
Taking action to eliminate or reduce, as far as practicable, any potentially adverse environmental impacts.
Promoting environmental awareness amongst our suppliers, contractors and partners by implementation
of operational procedures
Seeking to work in partnership with the community by behaving in a considerate and socially responsible
manner.
Ensuring effective and expedient incident control, investigation and reporting.
Publicising this environment policy and other relevant environmental information
Managerial and supervisory staffs have individual responsibilities for the implementation of this policy and
must ensure that environmental issues are given adequate consideration in the planning and day-to-day
supervision of all work.
CSCEC will fully comply with the duties placed upon it within the requirements of all applicable UAE legislation
whilst at all times complying with, as a matter of best practice, the requirements and duties set out within
Approved Guidance as issued by regulatory authorities and other organizations. As part of the company’s
commitment to maintaining the highest levels of environmental management, it is the intention that the
company will operate systems and procedures in line with the requirements of ISO 14001:2015.
All employees, sub-contractors and suppliers are expected to co-operate and assist in the implementation of
this policy, whilst ensuring that their own works, so far as is reasonably practicable, are carried out without risk
to themselves, others or the environment. This includes co-operating with management on any environment
related matter.
CSCEC will take all practical steps to ensure that potential hazards and risks to the environment are identified
and that suitable and effective preventive control measures are implemented. All employees will be provided
with the necessary resources, equipment, information, instruction and training to fulfill the requirements of
this policy.
The directors have overall responsibility for all environmental matters. The operation of this policy and the
associated procedures will be monitored and reviewed on a regular basis to ensure that they remain current
and applicable to the company’s activities
To this end the Company has a continuing programme for the systematic development of standards and
procedures to satisfy the legislative, and moral, requirements of Health and Safety Management.
Provide a safe working environment that is without risk to health and welfare of employees,
subcontractors and the general public.
Provide necessary training for all employees.
Provide each employee with a copy of the Company Safety Policy.
Publicise the Company Safety Policy.
Monitor or Audit the performance of all activities against this Safety Policy.
Regularly review the safety policy and institute appropriate improvements.
Continually strive to improve the overall safety, health and performance of the Company.
Ensure that safety is an integral part of the management of the Company, and
Comply in all respects with current legislation.
To a management system in line with the requirements of OHSAS 18001:2007
All employees, sub-contractors and subcontractors are expected to co-operate and assist in the
implementation of this policy, whilst ensuring that their own works, so far as is reasonably practicable, are
carried out without risk to themselves or others. This includes co-operating with management on any health
and safety related matter.
CSCEC will take all practical steps to ensure that potential hazards and risks to the safety and wellbeing of all
persons involved in their operations are identified and that suitable and effective preventive control measures
are implemented. All employees will be provided with the necessary resources, equipment, information,
instruction and training to fulfil the requirements of this policy.
The directors have overall responsibility for all health and safety matters. The operation of this policy and the
associated procedures will be monitored and reviewed on a regular basis to ensure that they remain current
and applicable to the company’s activities.
TEMPLATE ONLY
This template requires the items in red italics to be considered and replaced with
Project specific details in BLACK non italic text or deleted if not applicable.
On completion of the template there should be no red italic text remaining (including
these notes).
This Project Health, Safety & Environmental Plan is distributed to registered copy holders both within
and outside the Company. A list of registered holders is retained by the Project Director who will
ensure that revisions are issued to registered copy holders.
Where the need arises, unregistered copies of the Plan may be distributed, provided approval is
obtained from the Project Director.
This copy of the Project Health, Safety & Environmental Plan is issued to:
Mr/Miss/Ms/Mrs
Company
Date
REVISION HISTORY:
F Date
Approved by:
Date
Prepared by:
G
Date
Approved by:
INTRODUCTION
Health & Safety Principles and Objectives.
This H e a l t h S a f e t y a n d E n v i r o n m e n t ( H S E ) M a n a g e m e n t P l a n detail the
specific risk-based approaches that are aimed to control, eliminate the Health and Safety
hazards/ Environmental aspects or mitigate risks/ impacts associated with the execution of
the project works undertaken by China State Construction Engineering Corporation Ltd (CSCEC)
CSCEC having reviewed the hazard and risk studies conducted for the design of the Project
verified and implemented the output in the detailed engineering design. This HSE Plan is a
step forward, for physically implementing those already agreed management controls that
apply to this phase of the project, to eliminate or reduce to As Low As Reasonably
Practicable (ALARP), the HSE risks inherent with the activities that are carried out for the
construction project.
This HSE Plan is a structured guide for all workers, visitors and sub-contractors to help them
perform all assigned project tasks, without injuries to people, damage to asset or the
environment.
Reading, understanding, implementation and compliance to this plan are compulsory for all
workers and sub-contractors of CSCEC involved in the execution of the Project.
CSCEC shall STOP any task that cannot be carried out such that there are no injuries to
people, damage to asset and the environment.
Pre tender information has been taken into account in the developing this Construction Phase
Plan. It will be maintained and developed throughout the project to ensure it constantly reflects
the management of specific risks to health, safety & environment arising from the project.
This Plan describes how we manage Health, Safety and Environment on this Project. I
expect everyone working on the project to comply with its requirements and work to
maintain the standards it has set.
Signed:
Date:
1 DESCRIPTION OF PROJECT
Contents (Cont’d):
Document Title Project Health, Safety & Environmental Plan Page 8 of 67
Project:
Revision No B Date 10/04/2014
AG/2014
2.9.1 Excavation
APPENDICES:
2. RISK ASSESSMENTS
3. LIFTING PLAN
Time scales
Hold points
The proposed schedule of the Project and respective milestones shall be inserted
here.
(Only the major milestones may be required)
Contact address
Contact address
Contact address
Planning restrictions.
Parking restrictions.
Noise restrictions.
Vibration restrictions.
1.3.3 Security
Detail the site security arrangements derived from the Risk Assessment and consider:
Details to be included:
State what the initial set up is and what the subsequent set up will be
1.4.1 Policies:
The directors have overall responsibility for all health and safety matters. The operation
of this policy and the associated procedures shall be monitored and reviewed on a
regular basis to ensure that they remain current and applicable to the company’s
activities.
1.4.2 Dissemination
HSE policies shall be communicated to workforce in a way that they can relate the Policy
requirements to their work.
CSCEC shall obtain approval for this HSE Management Plan and issue a clear
directive on how the plan shall be maintained and implemented, and thereby agree
to provide sufficient resources to perform all HSE critical activities to the right quality
within the agreed schedule.
CSCEC Project Director shall attend and chair monthly meetings which include HSE
performance review, committee meetings, and shall act promptly on HSE reports and
issues.
1.4.3 Visibility
The Management of CSCEC at all levels will provide strong, visible leadership,
commitment and personal involvement in all aspect of HSE:
Prompt box:
HS&E Manager
Crane Supervisor
First Aiders
Emergency Co-ordinator
Logistics Co-ordinator
EXCAVATE/ DIG
ISOLATION OF SERVICES
HOTWORKS
Lunchtime briefing.
Monthly meeting.
Monthly report.
Weekly meetings.
Site manager
Minimum once prior to
Pre-start meetings Manager with direct
commencement
control
Project /Administration
Welfare Committee
At least monthly Manager and workforce
Meetings
representation
safety induction;
Police.
Emergency Services.
CSCEC Project Director in conjunction with the Corporate QHSE Manager will
Assign HSE tasks, set SMART (specific, measurable, achievable, realistic & timely),
proactive targets and ensure that all staff, Sub-contractors and workers know and
understand what is expected from them.
CSCEC Project Director will:
Define overall HSE tasks and targets for the entire workforce and Sub-
contractors.
Assist Regional Managers, Site Managers, Engineers, Crew leaders,
officers and task supervisors for the Project in developing their own tasks
and targets.
Monitor performance against tasks and targets
CSCEC Project Manager, Site Managers, Engineers, & Supervisors will:
Assist in defining HSE tasks and targets for workers, which they lead.
Monitor and report performance against targets.
Disseminate performance appraisal reports of workers, which they lead.
In carrying out the work for the Project, CSCEC shall refer to Company codes,
standards, procedures and guidelines applying which ever are more stringent.
CSCEC its employees and Subcontractor’s shall obey any reasonable written or verbal
instruction given by the Client in respect of health, safety and environmental controls.
Risk Assessment shall be carried out for the activities which are dangerous and non-
routine and shall be submitted with the Method statements for approval to Client /
Consultant.
The responsibility for conducting the risk assessment lies with the Construction
Manager and he will be assisted by Safety Department for preparing and reviewing the
same. Implementation of the Method Statement and Risk Assessment will be the
responsibility of the Section Engineer.
Prior to the commencement of any activity, the approved method statements and Risk
Assessments will be briefed to all operatives; staff involved in the task and a counter
signature will be taken as a mark for their approval.
All Risk Assessments generated during the project construction period shall be
recorded in the project risk register. The purpose of a risk register is to collate and
monitor risk within in the project, and also to priorities and target high-risk areas and
subsequent actions to be taken to reduce the risk in the workplace. The aim is to
decrease the incidence of lost time injuries and reduce associated costs to the project.
A risk register may also identify areas for additional staff training required within an
organization.
Formats of the Risk Assessments that shall be implemented in this Project is Placed at
Appendix –
The following techniques in this section will be used for monitoring compliance with:
requirements
A routine inspection of every workplace will be carried out at least once a week and
report will be generated in the below mentioned form ../../../Documents and
Settings/hmeakin/Local Settings/Temporary Internet Files/Content.Outlook/Local
Settings/11 Inspect audit/11 App/11_B Directors Tour Dec05.doc to record the
observations made and the remedial actions to be taken.
The following persons are responsible for carrying out routine inspections on a weekly
basis:
Construction Manager
3. Level Area Bi- monthly HSE-F- 09
(Name)
Daily/
5. All Area HSE Officer HSE- F-10
Weekly
Workplace inspections will be carried out by the person in control of the specific
workplace, whether CSCEC or sub-contractor. Where subcontractors are required to
carry out such inspections, the responsible CSCEC manager must have a system of
ensuring the adequacy of the inspection process. Inspections carried out by CSCEC
will be recorded on the Inspection Form HSE-F -35 .
Inspections on the below mentioned areas will be carried out and recorded as
described in the company procedure /salutatory inspection format. HSE F 37
Inspections of any Working platform (or part thereof) or Personal
Suspension Equipment
Excavations
Confined Space
Cofferdams and Caissons
HSE Compliance monthly monitoring will be carried out to verify that agreed
procedures and methods are being implemented and are producing the required
results.
Compliance monitoring will be carried out by:
a. The Project HSE manager/supervisor controlling the area in which work takes
place.
b. Visiting HSE Manager .
CSCEC projects will effectively use the monthly HSE Monthly monitoring Sheet HSE-
F- 13. Project Director/Manager, HSE Manager and Construction Management will
discuss the activities action dates, and it will be highlighted in the HSE Monitoring
Sheet for necessary compliance by the concern. The filled monitoring sheet will be
circulated to all concerns for necessary compliance, and a copy will be displayed at
Main Notice Boards.
2.3.4 HSE Performance Score.
Monthly HSE Compliance Monitoring sheet will be reviewed at the end of the month by
the Project HSE /Project Manager. HSE Monitoring compliance sheet and its
supportive documents will be verified and project HSE compliance performance score
shall be prepared by using the project HSE score evaluation sheet.HSE F-68/69
Project HSE performance score will be discussed in the project HSE meeting
and adequate attention shall be given to lacking areas and non compliances.
HSE Officers will conduct daily site walks, and site conditions will be assessed and
communicate with construction management/immediate supervisors for necessary
rectification works. Any significant issues, which need project management
attention and action may be recorded in the Daily workplace inspection report- HSE –
F 15 and circulated to concern for necessary action. All closed out action of the
reports to be maintained at the project safety file.
2.3.6.2 Weekly Site Walkabout.
This is a regular Site safety walkthrough that is arranged to spot any major deficiencies
management of HSE concerns on site. Any non-compliance shall be rectified
immediately or within the stipulated time given. All concerned site HSE representatives
and construction key personnel shall be presented in this weekly site walkabout. The
report of HSE walkabout shall be prepared in HSE Format F- 10 and circulated to all
concern for necessary closed out action.
The generated report shall be substantiated with all necessary documents and photos
and filed properly. The action in the closing report shall be verified by the Safety
Manager/Safety Supervisor on site.
The HSE Inspection Plan for the Project and the Forms and Checklists that will be
used for this Project is placed at Appendix
Service of the external agency may be benefited for carrying out special inspection
requirements as advised by client/local authority.
Quarterly
Plant & Equipments. 1. Plant Dept. Prior Mobilization, Record HSE F 38.8
2. Operator & Supervisor. monthly.
Checklist
3. Plant Engineer.
rd Daily.
4. 3 Party. Visual
Weekly.
Examination
Yearly.
Yearly.
HSE audits are conducted on the Project by the Corporate HSE Audits as per the
approved HSE Audit Plan of the Integrated Management System, Audit Procedure.
All audits will be carried out in compliant to CSCEC HSE-MS Procedure and evaluate
the compliance of this HSE Plan
These audits will determine the level of compliance with HSE goals and procedures
for the project and will note all non-conformances. Corrective actions for all non-
conformances will be given in the audit report. All audits will be recorded in a written
report, HSE –F-12, which shall be available for review.
The CSCEC HSE department shall record and report HSE non-compliances and
corrective actions, and shall order WORK STOPPAGE in non-compliant situations.
A register of non-conformances shall be established and maintained by the HSE
department and communicated.
CSCEC team shall reward HSE performance in accordance with CSCEC HSE
Incentive policy and program. The HSE incentive and disciplinary action policy
focused on individuals and group HSE rewards and also disciplinary action measures.
CSCEC Projects shall distribute monthly safety awards to workforce for their active
involvement in HSE progression and management at site and substantial involvement
in the Hazard reporting.
Note: CSCEC shall implement a warning system applicable for all contractor &
sub-contractors in accordance to ministerial order no (28/1) year 1981- Labor
Law
Safety Training will be provided to all employees through internal and external
sources. Information on Training Targets is available with project HSE. The Project
Training Matrix will be developed during the project phase.
MS/RA briefing and Tool Box Talks will be provided to all employees prior to the start
of any Activity. The HSE Officers will assist to provide Tool Box Talk information to
Supervisors.
Documents of all training, with the signatures and names of employees who
participated in the training along with evidence photos will be recorded.
2.4.1 Inductions
All personnel including visitors must attend a safety induction training course by the
HSE officer prior to the commencement of works at site.” Team Leaders, Site
Engineers and supervisors have responsibility to assemble their newly join workforce
to attend safety induction course conducting by site safety representative. Records of
the Safety Induction will be preserved in the HSE data base and a safety Induction
sticker will be issued to the attendees on completion for easy identification. Generally
the Safety induction will cover the following topics and other special instructions from
the client/local authorities:
1. CSCEC EHS policy.
Document Title Project Health, Safety & Environmental Plan Page 34 of 67
Project:
Revision No B Date 10/04/2014
AG/2014
Drug & Alcohol Testing may be carried out at any time; positive results for drugs or
excess alcohol, or refusal to take a test could result in termination of contract or refusal
of entry to site. If you use any medication that could affect your ability to work safely,
notify your direct supervisor.
Document Title Project Health, Safety & Environmental Plan Page 35 of 67
Project:
Revision No B Date 10/04/2014
AG/2014
Safety Helmets, High Visibility Vests & Safety Footwear are mandatory on
site.
You must wear additional Personal Protective Equipment where this has been
specified.
Make sure your Foreman/team leader has briefed you prior to starting work –
if not, stop and ask.
Strictly follow the details of the agreed method statements, task briefing or
daily activity briefing.
Racial or sexual harassment on site or directed at the public is il and will not be
tolerated.
Fully comply with all health and safety signs – do not cross barriers or enter
no-go areas.
Never pour oil or other pollutants down drains – know your hazardous
materials and use them safely.
4. Unplanned Events
Report all accidents and near misses to allow us all to learn by our mistakes.
Know the best means of escape from your wok area and your assembly point.
All drivers must wear safety helmets, hi-vis & safety footwear when not protected
by their cab.
Observe Speed limits as low as possible less than 40 km/hr while traveling through
the site.
You must remain seated, wear safety belt while driving the vehicle.
Gate pass is must for all vehicle, contact site HSE Manager for further
arrangement.
Don’t make any unauthorized modification on the vehicle body unless you are
permitted to do so.
Visitors to the site must be escorted at all times by a fully inducted person and obey
all instructions.
Note: CSCEC shall implement a warning system applicable for all contractor & sub-
contractors in accordance to ministerial order no (28/1) year 1981- Labor Law
3. Plant Operators (excavators, fork lift trucks & dumpers, Asphalt pavers, INFRA related equipments)
4. Hoist Operators
9. Core Drilling
14. Scaffolders
15. Carpenters
16. Masons
17. Plumbers
18. Electricians
21. Tillers
22. Cladders
The objective of the Scheme is to provide an opportunity to all staff to generate some
good suggestions in regard to the Corporate HSE Management, Risk control, Safe
working practices and Environment and so on. Suitable prizes shall be awarded to
those staff or a team for a suggestion that has merit or that shows special effort
adopted by the Company Management.
In order to communicate the current Health and Safety performance on the site and to
inform and instruct all concerned about future changes, a number of safety meetings shall
be conducted with all key personnel’s. Schedule of meetings is mentioned in HSE Plan
section.1.6.5
Minutes of the meetings shall detail the actions and responsible arising from the
meeting, be signed and copied to all attendees and are to be dismayed on notice
boards for the information of all the employees.
At any time it may be necessary for the safety of the personnel to evacuate the
construction site quickly. Preservation of life and property is only possible if the
evacuation procedure is effectively followed. The emergency exercise will be
conducted once in every 6 months time to educate employees of the procedures to be
followed.
In case of fire emergency the contact person and telephone Nos., actions to be taken
are exhibited in the Appendix Forms no: will be displayed through safety bulletin
boards.
Fire Marshal
Local Client/consultant
Fire
Ambulance
Police
Procedures for selection of contractors and suppliers who are competent and will
make adequate provision for health and safety are detailed in the CSCEC
Procurement department procedures.
All contractors and suppliers selected to work on this project will be subject to these
procedures, Contractors and suppliers will be made of any changes
Progress meetings
Formal correspondence
Verbal instructions
Workplace inspections
3. Construction experience.
Subcontractors will be required to follow the work practices and systems described
below while performing work at CSCEC worksite in order to continually improve safety
performance:
Attend safety orientation, pre-job meeting or kick-off meeting provided CSCEC prior
to any work beginning.
Monitor employees for substance abuse and report nonconformities to CSCEC.
Ensure personnel have the required training and competency for their work.
Participate in CSCEC safety meetings, regular periodic safety meetings, and job
safety analysis or hazard assessments and on the job safety inspections.
Perform a pre-job safety inspection that includes equipment.
Report all injuries, spills, property damage incidents and near misses
Comply with onsite and DoT safety rules and regulations.
Implement CSCEC safety practices and processes as applicable.
Clean up and restore the worksite after the job is over.
Ensure compliance with regulations at all times.
The Hazardous chemicals information will be collated by the store keeper where he
provide a copy of eth MSDS to the safety department and he will be making a
Hazardous chemicals assessments and the information will be passed to the operative
through the site store keepers. .
Managers must ensure that work equipment is suited to the task, properly
maintained and the users are competent to operate it.
Salutatory examinations, tests and routine inspections will be programmed and all
certification and records are kept available and retrievable.
Any devices preventing contact with moving parts (e.g. mechanical or electrical
interlocks, guards etc. ) must be in good order and fitted during operation.
The design of any supporting structure, including existing structures, loading bays,
hoist ties, grillages etc must be checked by a competent person.
Control devices such as start/stop switches shall satisfactorily perform their
intended function.
Alarm system shall be provided where appropriate. For instance, to warn people of
an imminent start-up where moving plant may endanger any person.
Noise and vibration levels shall not be a risk to hearing or health.
First aid provisions will meet the requirement of UAE Regulation/Local rules.
A fully equipped First aid centre / room and trained first aider are located along
side the project offices, these facilities will be available 24 hours per day.
As a minimum all subcontractors will be required to provide trained first aiders and
first aid equipment.
All injuries will be dealt by the CSCEC first aider. If required the first aider will refer
the patient to the nearest hospital or clinic.
The names of the first aid personal will be written and displayed in all site safety
notice boards and all the operatives and staff will be briefed on the site first aid
measures.
The location of the first aid room will be depicting in site layouts.
The accident book will be kept and maintained in the site first aid clinic.
b. An Ambulance.
All Lost Time Injuries where a person does not report for work the next day
All reportable serious injuries and dangerous occurrences
All accidents & incidents involving member of the public
All incidents which result in damages to plant and equipment
All near misses that could have had serious consequences
All environmental or pollution incidents in accordance with local environmental
guidelines.
CSCEC shall ensure that all incidents/accidents and/or dangerous occurrences that
took Place on site are reported and investigated in accordance with our Environmental
Health & Safety Management System procedures. The immediate Supervisor and/or
Manager shall report the accident/incident to the EHS manager and investigate it with
the worker or person who was involved in the accident/incident (where possible) and
render a report to HSE Manager for further advice and actions.
All accidents resulting in lost time shall be investigated by senior HSE personnel where
a thorough accident investigation report is generated highlighting the direct and root
causes, recommending proper corrective and preventive actions and then forwarded to
all concerned parties for their necessary actions.
All accidents and lessons learnt shall be addressed and published to all concerned by
Safety Manager via all available communication means such as meetings, toolbox
talks, memos, alerts, notice boards, etc.
Fatalities
Major Injuries/Reportable Serious Injuries
Accidents to member of the public
Lost Time Injuries
Dangerous Occurrences- usually failure of lifting machinery, electrical short
circuit, collapses of structures, false work or scaffolding.
High Potential Incidents.
Contractors are required to inform the CSCEC Project Director/HSE Manager of any
incidents on site by the quickest possible means. Formal notification will be made to
the CSCEC Project Director within 24 hrs using the Accident Incident Report sheet.
The employing contractor will be reported to the Health & Safety Manager and
Preliminary Incident Report form, ref. HSE- F-39 to be submitted within 48 hours.
The immediate supervisor / Construction Manager along with HSE manager will look
into the underlying reasons for the accident, and necessary corrective and preventive
action shall be initiated to avoid such recurrences. The controls shall be selected as
per the Hierarchy of Controls in accordance with Risk Management Procedure. The
findings shall demonstrate that any risks to health and safety are eliminated.
2.9.1 Excavations
Prior to commencing any excavation works a survey will be carried out to identify if
there are any buried services in the area, if services are identified the excavation will
be carried out with a banks-man digging trial holes or by conducting a hand dig.
Depending on the size and depth of the excavation will determine the method of
support i.e, shoring, stepping or sloping.
A physical barrier and warning signs will be placed around all excavation regardless of
depth. If spoil is to remain adjacent to the excavation then the 1m method will be used,
(4m depth spoil will be placed a minimum of 4m away from the excavation edge).
All excavations will be carried out under the control of a “Permit to Dig”
When any works are being carried out which involves personnel working at heights
above water the following precautions are to be taken. Any works over water are to be
subject to the company "Permit to Work" system.
A fence or barrier and warning signs must be provided to any structure or scaffold
where there is a risk of persons falling from such structures into water. Where possible
systems to prevent falls in to water will be adopted first, such as physical barriers or
restraint systems. A buoyancy aid of a tested and approved pattern are to be worn by
all personnel working over water
Adequate lighting for the whole of the period of work is to be provided. Lighting must
be adequate for night work and must illuminate the immediate surrounding water
surface.
All electrical equipment will be subject to third party testing and inspection, Temporary
Electrical supplies from generators will be positioned on suitable hard standing with a
bund or drip-tray; this will be located way from the water’s edge.
All generators will be fitted with earth rods. All distribution boards will be fitted with
automatic trip devices.
Where practicable all electrical tools will be 110v, where possible cables will be
arranged off ground to prevent damage and trip hazards. A Risk Assessment is to be
carried out and appropriate measures to be instituted to reduce the risks.
Where practicable all lifting will be carried out by mechanical means to reduce the risk
of manual handling injuries. Where manual handling of materials cannot be avoided
then task specific manual handling assessments will be carried out and the relevant
training will be given to those carrying out the tasks.
The Dredging contractor will carry out any diving related activities; the contractor will
provide safe diving procedures to include in this plan. All divers must hold a valid
medical certificate and be a registered industrial diver.
Due to the local climate and works been carried out under direct sunlight, it is
mandatory that operatives are covered at all times. The wearing of shorts and vest
without sleeves are not permitted on site. All operatives on site will wear full coveralls
Fall control shall be required for personnel exposed to heights greater than
The first step is to assess the workplace and the work itself. Fall hazard shall be
eliminated wherever possible by changing the sequence of the job, by working from
ground level or by the use of special tools, equipments.
The second step also requires assessing the workplace and work processes. If fall
hazard cannot be completely eliminated during the first step, project management
must take a proactive approach to the prevention of fall by improving the workplace
(collective protection). Early installation of stairs, guardrails, scaffolds, and travel
restriction systems can ensure a safe work environment.
The third step is to use fall arresting equipment. Use fall arresting equipment, however,
only after determining that potential fall cannot be eliminated by changing work
procedures or workplace or collective protection cannot be used. Equipment such
harnesses, lanyards, shock absorbers, fall arresters, lifelines, anchorages and safety
nets can reduce the risk of injury if a fall occurs.
Scaffolds
Personal working on tubular or other scaffolds shall use a fall arrest system unless the
scaffold complies with the fall prevention system requirements described in the
Local/CSCEC Scaffolding standard.
Scaffolds shall be erected and used in compliance with the local scaffolding standard
and under the supervision of a competent person in scaffold erection.
Before use the scaffold, the user must check the scafftag to verify that the scaffold was
inspected and the scafftag signed by a competent scaffold inspector within seven days
before the day of use.
A scaffold visual inspection shall be conducted by the user before each use. If for any
reason a user considers a scaffold to be unsafe he shall immediately contact his
supervisor. The supervisor shall immediately remove the Scafftag and place barrier
The full body harness will meet ANSI (American National Standards Institute) or
EN (European Norms) standards. Safety belts are prohibited.
A visual inspection shall be conducted by the user before each use of fall arrest
equipment.
Fall arrest equipment inspected and rejected for further use shall be destroyed to
prevent further use and inspection record shall be updated to include the method
of disposition.
is large enough and so configured that an employee can bodily enter and perform
assigned work; and
Has limited or restricted means for entry or exit (for example, tanks, vessels, silos,
storage bins, hoppers, vaults, and pits are spaces that may have limited means of
entry.); and
Is not designed for continuous employee occupancy.
Confined spaces shall be classified Class A or Class B confined spaces. All the
confined spaces entrances shall be identified with a sign reading DANGER- PERMIT
Document Title Project Health, Safety & Environmental Plan Page 52 of 67
Project:
Revision No B Date 10/04/2014
AG/2014
The confined space entry permit is described EHSMS. HSE –F-06 Confined space
entry permit) and shall include:
All personnel deployed for confined space works must be trained through an
approved trainer and must be competent enough to carry out the task.
All personnel in confined spaces and attendant will carry portable lighting.
at least one attendant outside the permit space into which entry is authorized for
the duration of entry operations
If hot works are done inside a confined space this one must be reclassified as
Class A confined Space. Hot work permit will also be necessary and CSCEC Hot
Work standard shall be followed.
Either double insulated or ground fault circuit interrupter protected electrical tools
and low current, low voltage (24 volt maximum) lighting systems shall be used in
damp or metallic hazardous confined spaces.
Electrical and pneumatic tools shall be selected to eliminate sparks and other
hazards as required by the conditions of the confined space.
Gas cylinders should not be used with in a confined space. Should there be
condition arises where gas cylinders have to be used inside the confined spaces,
special precautions are to be taken and it shall be approved by H & S Department.
At no circumstances, CO2 fire extinguisher shall be taken into the confined space.
CSCEC must agree the information required for inclusion in the HS file with the
planning engineer at the earliest opportunity.
The CSCEC team will collate information. This will normally include:
2. Any residual hazards which remain and how they have been dealt with (for
example, surveys, or other information on asbestos, contaminated land, water
bearing strata, buried services etc)
3. Key structural principles (e.g. bracing, post tensioned units), safe working loads for
floors and roofs etc.
8. Information and ‘As Built’ Drawings including safe access to and from service
voids, fire doors and compartmentalization, fire pumps, wet risers, hose reels etc.
Contractors will provide information for inclusion in the HSF to CSCEC. The CSCEC
Project Director will ensure that all the HSF information is provided to the planning.
The operating and maintenance manuals will be collected from the Sub Contractors/
Suppliers on completion of their work and handed over to the client by Project Director
at the time of phased handover/completion of contract.
Document Title Project Health, Safety & Environmental Plan Page 54 of 67
Project:
Revision No B Date 10/04/2014
AG/2014
Environmental policies.
Environmental Representative:
A suitable and competent project staff will be appointed by the Project Director to act as
Environmental Coordinator of the project. He will ensures that all necessary care must
be given to all project activities from preventing environmental impacts arising from
various project operations. If this role is not formally delegated, it remains with the
Project Director. More guidance on environmental issues is available in EHSMS
section 8. Protecting the Environment
For Environmental representatives, the memo or letter would normally be issued
by the Project Director.
Audits may include system audits or audits at project level. An example checklist is
included within the linked report/checklist standard form. EHSMS Environmental Audit
Check List – F-26
HSE –F- 36 HSE Non compliance Report .This report sheet is used to record non
conformances.
Trade License
SCHEDULE A12:
This section of the Technical Proposal document requirement shall be provided in the
commercial section of the tender submission.
Tenderer’s Exclusions,
Deviations & Qualifications
SCHEDULE A13:
This section of the Technical Proposal document requirement shall be provided in the
commercial section of the tender submission.
Contractor’s Company
Particulars
2. COMPANY INFORMATION
This section will address the Company Introduction of CSCEC as part of our technical submission
to provide a brief overview of our company profile, experience and capabilities for the construction
of the “Downtown Views II” project.
China State Construction Engineering Corporation Middle East L.L.C. (CSCEC ME LLC) is an
integrated part and one of the major overseas operational entities of China State Construction
Engineering Corporation Ltd. (CSCEC), whose shares are traded on the Shanghai Stock
Exchange. CSCEC as our parent company has more than 26 overseas registered offices
worldwide and with over 5000 projects completed in more than 100 countries. CSCEC is the
world’s largest transnational construction company in developing countries and the No. 1
homebuilder in the world.
China State Construction Engineering Corporation Middle East LLC (CSCEC ME LLC)
commenced operations in the UAE in 2003 and completed its formation on March 26, 2005 in
Dubai. In the Middle East Region, CSCEC ME is one of the region’s largest construction groups
with offices across the GCC. The company’s regional Headquarters are located in Dubai UAE.
Through the utmost support of our parent company (CSCEC) in mainland China and with
the fast growing expansion of CSCEC ME in the market, we have received numerous company
honors, merit and awards in different aspects of business segments with respect to our overall
active performance worldwide. CSCEC ME hereby present our latest ranking and awards with
high moral and pride as per the following:
In order to achieve our corporate goals, a strong team of dedicated and experienced staff
and skilled workforce who work from our regional and site offices already established in the region
supports CSCEC.
As we strive to face the future challenges, CSCEC is always in line with its corporate vision
and mission along with its core values and spirit. All of these serves as our driving force to meet
our aim to be one of the most competitive international contractors in the Middle East.
Growing to be
the most
internationally
Integrity
Expanding a competitive Quality
innovation
happy living Construction assurance and
transcendence
environment and real estate value creation
Win-Win
enterprise
integration
group
Since 2003 as the first operations of CSCEC ME, we have rapidly penetrated the UAE
market and became well known in completing landmark and mega projects in GCC including
Qatar and Kuwait.
During these years (2003 - present), CSCEC ME has become a prestigious and respected
Company across the GCC which is fully capable of bringing a wide range of projects into reality,
such as residential and industrial buildings, public works and various infrastructure developments.
We have successfully diversified ourselves from initially being a conventional building contractor
to a comprehensive total and innovative solution provider whose business has reached nearly all
the sectors of the construction industry in the Middle East region. We are now able to offer to our
clients a full range of options from Contracting, Design and Build to Project Financing, across a
range of disciplines. At the same time, we have created a Project Investment/Development
business.
The complete wide spectrum of our line of business will be presented as per the following:
We also Pioneering
The world’s We are one We are one and leading
enjoy the
largest of the largest of the largest international
fastest growth
homebuilder enterprises real estate contracting
of any
& China’s engaged in enterprises services in
infrastructure
largest integrated boasting of China as the
construction
building building the largest first & largest
and
Contractor design land reserves International
investment
Contractor
CSCEC has abundant human resources with respect to the professional management
team with labour / workforce from different intercontinental countries worldwide.
3,000,000+
Worldwide Employees
230,000+
Managers
48,387
CSCEC Staff
Ltd. 1,363
Engineers & CSCEC
Technician ME
106,349 LLC
Labor
Other 10,400
staff
75,387
In addition, the complete breakdown of CSCEC’s human resources are presented as per
the following:
Currently, CSCEC ME has more than 10,400 skilled workers (in-house under each
particular company of CSCEC ME visas, including structure, fit-out, MEP), and is able to provide
extra workers from our many long-term subcontractors if required.
CSCEC ME has always stand firm in building its company reputation in the market by
being a Comprehensive Contractor with Professional Resource Supports in various sources as
follows:
In House Special Division - Building, Infrastructure, MEP, Oil and Gas, Steel
Structure.
o 9 Management Staff
CSCEC always pay attention to promotion and exploration of the international leading
construction technology. We make sure to be always updated and aware on the latest innovation
in the market, which is subject for study and investigation, and be implemented in the actual site
construction. One clear evidence of using some of the latest technologies is through the
construction and completion of not only high-rise but also for super high-rise structures with
creative designs.
CSCEC ME has made the adjustment of the Company Organization Structure to achieve
the strategic objective that is to become the largest international contractor in the Middle East in
the future. According to the principles of department setting for CSCEC ME, all departments are
set up as follows thus to clarify their functions and responsibilities, promote the internal
cooperation of each other and improve the overall operational efficiency.
The main responsibilities are preparing corporate planning and strategy, office
management, Party masses work, IT management, etc. The detailed description are discussed
on the succeeding paragraphs.
Corporate planning and management mainly includes preparing the corporate planning
and strategic planning; setting up the corporate organization structure and business procedure;
setting up the operational system; authorization and internal control; important information
disclosure; writing and editing corporate letters, reports and other official documents; corporate
promotion and publication management, etc.
Office management mainly includes setting up the corporate office regulations; corporate-
level meeting management; official documents management; corporate stamps and licenses
management; public relationship management; secretarial work, etc.
General Management Department take its responsibilities for fix asset management;
housing management; vehicle management; headquarters working area management;
connecting work with superior departments; other works such as logistics management,
administrative work and liaison affairs, etc.
Human Resources Department is responsible for setting up the corporate HR rules and
regulations; recruitment, employment and personnel assignment; promotion and demotion;
training, education, career development and management; remuneration management; employee
performance appraisal, incentive system implementation; employee welfare and insurance;
employment contracts and personnel archive management; etc.
The responsibilities for Financial and Accounting Department consist of setting up the
corporate financial and accounting rules and regulations; accounting analysis, internal audit and
countercheck; fund management; budget control; etc.
Legal Affairs Department is responsible for setting up rules and regulations for the
corporate legal affairs; reviewing or drafting the legal contract documents; drafting the corporate
contract templates; authorization documents and notarization management; legal dispute case
management; daily operation's legal appraisal and consultancy; etc.
The responsibilities of Labor and PRO Department include setting up rules and regulations
for labor management; labor recruitment and training; labor archive management; labor
employment management; maintaining and coordinating the public relationship with local
authorities; etc.
Business Development Department is responsible for the market developing plan and
market entry plan in the Middle East region; client relationship and public resources maintenance;
market macro and micro environment analysis; market data collection and analysis; mega projects
tracking and developing; supporting divisions and regional operations in the market development;
providing support and supervising projects construction progress undertaken by all divisions; etc.
The responsibilities of the Mega Projects Tender Department consist of setting up the
corporate rules and regulations for tender; reviewing and appraising all tender proposals;
tendering for large- scale mega projects; tendering for new business projects; providing support
for divisions and regional operations in tender pricing; etc. Mega projects refer to the projects
valued at more than AED 500 Million.
Project Financing and Investment Department is responsible for setting up rules and
regulations on the project financing and investment matters; project tracking, project initiation;
feasibility analysis and project appraisal; organizing the making and implementation of financing
proposals; liaising with banks and other financial institution;coordinating with relevant
departments to negotiate with financial institutions; organizing the making and implementation of
financing project initiation proposal, feasibility study, implementation proposal and investment
contract, etc.
coordination management; project progress appraisal; signing the objective and responsibility
contracts and projects performance appraisal; project completion summary; etc.
Engineering Department
The main responsibilities for the Engineering Department are setting up corporate
technical management system and engineering database; technology import and training
organization; projects basic information collection; in charge of the internal and external technical
matters on the corporate level; providing technical support to divisions and regional operations;
offering technical support in mega size projects; technical awards application; technical journals
compilation; providing support to divisions and regional regarding design proposals for tenders;
Planning Department
QHSE Department
QHSE Department is responsible for the overall quality, health, safety and environment
management on the corporate level and project level; maintenance of QHSE management system;
QHSE training; internal and external management system audit; etc.
D. Divisions
Building Division
Building Division is fully responsible for the business development, project construction
and management, etc. in the building sector.
MEP Division
MEP Division takes full responsibility for business development, project construction and
management, etc. in the MEP sector.
Steel Structure Division takes charge of business development, project construction and
management, etc. in the steel structure sector.
E. Committees
In compliance with the adjustment of the organization structure, four relevant committees
are set up as follows:
Executive Committee
The Executive Committee is the corporate top decision making body, which consists of
President and CEO, (Executive) VPs, CFO and President Assistants. The Executive Committee
Meetings are held at regular or irregular intervals mainly focusing on the key and vital issues, such
as the corporate business planning, resources allocation, department management system, key
projects appraisal and investment, major activities in corporate management, etc. The Executive
Committee will supervise the execution of the departments, divisions and regional operations as
well.
Functional General
Management Management Regional
Business Development & Project Management Center Division Operation
Department Department
Labor &
PRO
Dept.
Building Projects Civil and Infrastructure Projects MEP Projects Steel Structure Projects Other Projects
President / CEO
Yu Tao
Vice
President Vice Vice Executive Vice Executive Vice President President
President &
Assistant CFO President President President President Chief Engineer Assistant Assistant
Ma Wenlong Li Ye Dong Wei Yang Chunsen Wu Ming Tian Sanchuan Zhu Jianchao Bao Jianguo Lee See Hee
Project Legal
Financing & Affairs Engineering
Investment Dept. Dept.
Labor and
PRO Planning
Dept. Dept.
CSCEC has a proven positive record of financial milestone and achievement as presented
as per the following charts.
As No.1 Construction Company globally, CSCEC has a solid foundation and wide range of project
experience in the field of building construction especially for high-rise structures by using
innovative solutions and methodology. The projects presented below are the completed super
high-rise buildings in China by CSCEC.
This section shall be provide an overview of CSCEC ME’s bank information and
relationship status in compliance to the project document requirements. Further documentations
and reference details apart from the provided list can be arranged and submitted during the tender
adjudication stage.
5. REFERENCES
Following this document are CSCEC ME’s client references to the company’s past
construction works projects.
Copier:
Kyocera TASKalfa 5002i Monochrome Digital Multifunction Copier (Scan, Copy & Print)
Specifications:up to 50 copies ppm
Kyocera TASKalfa 5052ci Color Digital Multifunction Copier (Scan, Copy & Print)
Specifications:up to 50 copies ppm
Printer:
HP Color LaserJet Enterprise M750dn
Plotter:
HP Design jet T2530 36-in Postscript eMFP (Scan, Copy & Print)
Server:
HP Proliant ML10 Gen9 E3-1225 v3 2x8GB(L) 4x4TB SATA LFF NHP DVD-RW
1x350W
Switches:
Cisco Catalyst 2960X-48TSL Switch hub
Backup System:
WD 16TB Mycloud EX4 Network Storage, EASEUS TODO Backup Advanced Server
LED Monitor:
HP Pro Display P240VA LED 24" Wide 1920 x 1080 Input Connectors VGA+1 HDMI, Tilt,
Laptop
Lenovo E570 i5-7th Gen, 8GB DDR3, 1TB HDD, DVDRW, 15.6W HD Antiglare
Display, DOS
Lenovo E570 i7-7th Gen, 16GB DDR3, 1TB HDD, DVDRW, 15.6W HD Antiglare
Display, Windows 10 Pro
Software
Windows 10 Pro
Office 365 Plan E3 (Annual Subscription)
Acrobat DC Professional
Primavera P6 8.4
Anti-virus
Autodesk Design Suite Standard (Annual Subscription)
Autodesk Building Design Suite Premium (Annual Subscription)
Autodesk Infrastructure Design Suite Premium (Annual Subscription)
Details &
TC#1 TC#2 TC#3 TC#4 TC#5 TC#6
Configuration
Hammer Hammer Hammer Luffing Luffing Luffing
Crane Type Head Crane Head Crane Head Crane Crane Crane Crane
Mast Climbing Climbing Climbing External External External
Support Bracket Bracket Bracket Bracket Bracket Bracket
As per layout As per layout As per layout As per layout As per layout As per layout
Location plan plan plan plan plan plan
Max. Hook
Height 275m 265m 225m 260m 250m 215m
Jib Length 60m 60m 60m 70m 70m 70m
Required
Capacity 8T@20m 8T@20m 8T@20m 2T@70m 2T@70m 2T@70m
*TC erection by mobile crane once raft completion
*TC-4/5/6 dismantling by adjacent TC-1/2/3
*Dismantling of TC-1/2/3 by Derrick & Roof Crane.
The proposed layout of the major equipment that will be allocated for this project will
include the following:
The complete details of the above-mentioned major plant and equipment can be referred
to the attached appendix of this section.
7.5
T3
MAIN STORAGE
14.99
T1
22.13
N 2788328.181
E 494779.381 PLOT
LIMIT T2
LABORATORY
WATER TANK
GENERATOR
178.47
(50 m²)
(50 m²)
(70 m²)
PLOT PLOT
LIMIT 6.1 LIMIT
8A
8A
3A
P-
P-
P-
P-
PC1 PC1 PC1 PC1
0B
C7 C2
C2
C2
C7
PC1 PC1 PC1 C4
C7
C7
C7
P- P-
C1
P-
P-
P-
8
C1
PC2A TB1 PC2A
8
TB1 TB1
8
TB1
8
TB1 TB1 TB1 TB1 TB1 TB1 TB1
P-
TB1
P-
PC1 PC1 TB1 PC1 TB1 TB1 PC1
MAX. HOOK HEIGHT: 275m
TB1
P-
PC1
C3
5
1
P-
C8
5A
C8
P-
P-
TB1
5
C8
WM-ST-201
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
1
JIB LENGTH: 60m
TB1
TB1
PC1
TB1
TB1
5 TB1
TB1
2A
2A
WM-ST-201
2A
P-
P-
2B
P-
P-
C8
C3
C3
PC1
C1
STR
PC1 PC1 PC1 PC2 PC2
C8
C8
P- PC1
C3
PC1
C8
5
C8
C1
PC1
P-
P-
P-
C8
P-
200 URAL
TB1
C8
0
0
P-
0
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
P-
UCT
5 PC1 TB1 TB1
PC1
THK WALL
REQUIRED CAPACITY: 8T @ 20m
TB1
TB1
NON
1
PC1
C8
P-
P-
C3
5A
1
TB
TB1
7 TB1
PC1 WM-ST-201
PC1
PC1
P-
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
C3
TB1
5A
PC1
P-
C8
TB1
TC-2
1
TB
1
TB1
C8
1
TB
P-
4
C8
P-
9A
P-
C2
C8
1A
1A
1A
TB1
P-
2
P-
P-
P-
P-
PC1
C3
2
C1
PC1 PC1 PC1 PC2 C3
C3
PC2
C8
PC1 PC1
C8
PC1
C8
C8
PC1
2B
P-
P-
P-
P-
PC1
0
2
PC1A
2
2
C8
C1
PC1A 1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
TB1 TB1 PC1 TB1 TB1
P-
P-
C8 RW01
P- 18
2
WM-ST-201
SSL -1.750
PC1 WM-ST-202
PC1
P-
C3
1A TYPE: HAMMER HEAD
400 THK RAFT
TB1
PC1
1
C3
P-
P-
C2
TB1
9
6
C8
P-
TB
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
PC1A
TB1
TB1
1
MAX. HOOK HEIGHT: 265m
TB1
P-
C2
4 9
C8
TB1
P-
TB1 PC1
PC1A
1 TB1
JIB LENGTH: 60m
2
C3
1
C8
0A
P-
2
P-
C8
C3
P-
1
PC1 PC1 PC1 PC1
1
C3
P-
C8
P- PC1 PC1
C3
C3
C3
C8
PC1
C8
PC1 PC1 PC1
C1
P-
C8
TB1
P-
P-
C8
P-
P-
P-
RW01 PC1
P-
P-
P-
2
2
P-
2
TB1 2 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
C8
TB1
2
TB1
7.0
56.2
4
C8
P-
TB1
TB1
0M
TB1
TB1
TB1
TB1
TB1
RW01
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
RW01
PC1
8
9
C2
WID
TB1
P-
TC-3
C8
P-
TB1
1
1
1
P-
C3
11
P-
P-
C3
P-
C3
1
1
C3
PC1 C3
C8
PC1 PC1 PC1 9A
4
C3
C3
P-
C8
C8
PC1 PC1 PC1
C8
P-
C8
2 P-
P-P-
2
PC1
P-
C1
P-
P-
2
PC1
2
2
C8
P-
PC1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
C8
P- P-
2
PC1
ED
TB1
2 TB1
4A
PC1 TB1 LL
C1
C8 WA
P-
AIN
RET
THK
RIV
300
TB1
TB1
TB1
4
RW01
C8
TB1
P-
EW
TB1
RW01
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
PC1
9
C2
MAX. HOOK HEIGHT: 225m
P-
4
AY
PC1
C8
7.0
P-
430
2 1 TB1
1
0A
1
TB1
C3
2
P-
P-
C3
1
C8 C3
1
C8
C3
PC1
C3
C2
C3
PC1
C8
C8
PC1
P-
P- PC1 P- PC1
0M
PC1
P-
3A
P-
P-
P-
P-
P-
2
2
C8
C1
TB1 PC1 TB1 PC1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 PC1
P-
P-
1070 THK RAFT TB1
2
TB1
C3
P-
SSL -0.080
TB1
REQUIRED CAPACITY: 8T @ 20m
TB1
WID
430
PC1
RW01
PC22
TB1
RW01
TB1
TB1
TB1
TB1
TB1
TB1
TB1
ED
4
2170 THK RAFT C3
P-
TC-4
TB1
TB1
SSL -0.080
1250 THK RAFT 1500 THK RAFT
PC1
430
SSL +0.100 SSL +0.350
RIV
1
C3
TB1
P-
TC-4
250 PC1
2
1
1
1
C8
C8
C3
C3
145
1
C3
TB1
C8 PC1 9A
C3
C3
PC1 4A PC1 PC1 PC1 PC1C C3 PC1C PC1 TB1
P-
P-
P-
P-
P-
P-
C1 TB1 P- TB1
P-
P-
TB1 PC1 TB1 TB1 TB1 C1 P- TB1 TB1 TB1 TB1
P-
EW
35
TC-3
WM-ST-204
TB1
TC-6
.19
TB1
TYPE: LUFFING CRANE
TB1
TB1
TB1
AY
TB1
TB1
RW01
2170 THK RAFT
TB1
LOCATION: EXTERNAL
TB1
RW01
TB1
250 2600 THK RAFT
TB1
TB1
SSL +0.350
TB1
430
SSL -0.550 SSL +0.100 250 3000 THK RAFT
250
TB1
3250 THK RAFT
900
1250 THK RAFT
1
C8
C3
1A
5
PC1C
P-
PC1
-C
P-
A
C1
TB1
C5
T3
TB1
P-
P-
0
565
TB
1
900
565
SSL +0.100 0 PC17
565
3
REQUIRED CAPACITY: 2T @ 70m
0
-C
TB1
T1
PC16
900
2350 THK RAFT
2600 THK RAFT
SSL -5.300 T3-PA PC14
430 3250 THK RAFT
1
565
-C
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
0 SSL +0.350
T3
PC12 PC11
TC-1
5650
PC21 TB1 PC11 1500 THK RAFT
1500 THK RAFT
TC-5
PC2
3
C1
SSL +0.350
C1
C2
PC2
C2
PC1 PC1 PC1
C1
C1
PC1
P-
PC1
C1
PC1 PC18
P-
900
470
P-
P-
P-
P-
P-
TB1 TB1 TB1 TB1 TB1 TB1 250 3000 THK RAFT
C1
P-
TB1
PC15 5650
9
2
565
-C
0 WM-ST-201
250
T1
2600 THK RAFT 5650
2600 THK RAFT SSL -0.550 430
SSL +0.100 SSL -0.080 250
SSL +0.350 5650
2350 THK RAFT
2
LOCATION: EXTERNAL
-C
2820 THK RAFT
T3
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
1250 THK RAFT
5650
5650
3
1
-C
3
C1
T3
C2
PC2
C1
C1
C1
P-
C2
C2
PC2 PC1 PC1 ZWME-S-003
WM-ST-205
C8
PC1
C2
PC1 PC1 PC1
P-
PC1
P-
P-
P-
P-
P-
7.0
P-
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
8 900
TB1
250
JIB LENGTH: 70m
0M
WM-ST-201 200
TB1
THK
250
UPS
TAN
TB1
TB1
TB1
TB1
TB1
TB1
D 3000 THK RAFT
SSL +0.100 1500 THK RAFT
3250 THK RAFT
5
2350 THK RAFT SSL -0.550
-C
C7
C7
C7
C7
C7
PC1B PC1B PC1B PC1B PC1B PC1B
T1
SSL +0.350
P-
P-
P-
P-
C7
WID
P-
P-
TB1 TB1 TB1 TB1 TB1
TB1
TB1
650
13
WM-ST-201
PC21
1
TB3
TB3
TB3
TB3
61.2
-C
ED
T1 SSL +0.100
TB1
TB1
PC9
4
250
C6
C9
C8
C2
PC1B
C4
PC1 PC2A PC1B 3000 THK RAFT
P-
P-
P-
P-
TB1
4
P-
2820 THK RAFT
C8
TC-6
TB1 TB1 TB1 TB1 TB1 TB1 250
RIV
2
PC2A
P-
P-SW8
C4
430 3000 THK RAFT
9
P-
SSL +0.100
PC1
EW
C3
P-
TB1
TB1
TB3
TB3
TB3
TB3
TYPE: LUFFING CRANE
C7
C7
C7
C7
C7
C7
P-
P-
P-
P-
PC1B PC1
P-
PC1B PC1B PC1B PC1B
TB1
P-
AY
TB1 TB1 TB1 TB1 TB1
TB1
TB1
TB1
TB1
TB1
TB1
10 LOCATION: EXTERNAL
TB1
TB1
TB1
TB1
TB1
TB1
WM-ST-201
1
C1
PC3
P-
5
3
C1
1
3
1
PC2
3
PC4
7
C8
C2
C2
C2
C2
C2
PC2
C8
C8
C3
PC2 PC2
P-
PC2 PC2 PC2 PC2 PC2 C2
P-
P-
P-
P-
P-
P-
P-
P-
P-
P-
TB1
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
6
C3
P-
ADJACENT PLOTS
TB1
REQUIRED CAPACITY: 2T @ 70m
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
REBAR
1
1
C6
C6
Note:
4
1
P-
2 3 4
C5
C5
C5
C5
C5
C5
C5
P-
P-
C5
C5
PC1 PC1 PC1 PC1 PC1 PC1 PC1 C5 PC1 C5 PC1
P-
P-
P-
P-
P-
P-
P-
PC1
P-
6
TB1 TB1 TB1 TB1 TB1 TB1 TB1 P- TB1 P- TB1 TB1 TB1 PC1
TB1
PC1 PC1
MA REA (5
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
A
WA EMEN
A
NA
OR
1
1
C6
C6
PC1
P-
P-
(800 m²) T
TB1 P-
G 0 m²)
STE
C5
1
3
1
1 1 1 1 2
C5
C5
C5
R S0 m²)
C5
TB1
1
C5 C5 C5 PC1 C5 PC1 C5
P-
P-
P-
P-
P- P- P- P- P-
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
PC1
2. Tower crane to be erected
BA
PC1 PC1
T
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
TB1
achieved adequate
TC-5 1 1
IN
AB ²) PLOT strength.
1
1
5
1
PC1 C6 PC1
C5
C5
C5
C6
C5
C5
C5
C5
C5
C5
C5
1
PC1 PC1 PC1 PC1 PC1 PC1
C5
PC1 PC1 P- P-
P-
P-
P-
P-
P-
P-
P-
P-
P-
P-
PC1 PC1 PC1
YC
P-
TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1 TB1
TB1 TB1
RE 600 m LIMIT
TO =
1-S X25m
EA
TB1
TB1
m
(12 3. TC-4/5/6 to be dismantled
TB1
R
TB1
TB1
TB1
TB1
EA GH EXIT
TB1
TB1
TB1
TB1
TB1
by adjacent TC.
AR
TB1
ELF
1
PC1 PC1
C6
C6
430
TB1
P-
P-
1 2
C6
1
C5
1
5
TB1
C5
P- PC1 PC1
C5
C5
PC1 PC1 P-
P-
P-
P-
TB1 TB1 TB1
RW
2900 THK RAFT
N K
TA
T2
4. TC-1/2/3 to be dismantled
-C
1
430
TER m²)
BO
2470 THK RAFT
WA
SSL -0.080
430
(50
LA
SSL +0.350
IN
AB ²) by Derrick Crane.
TB1
YC
TB1
R
TB1
TO
TB1
TB1
TB1
RE 600 m
430
RA
1500 THK RAFT
K
7.0
TO
SSL +0.350
SSL +0.350
NE ²) TA
N =
1500 THK RAFT
GE m 1-S X25m
(40
TER ²)
TC-2
SSL +0.350
0M
WA m
(12
5 1 1 1 5
m
1
C5 C5 C5 C5
C5
C5
(50
PC1 P- PC1 P- PC1 P- PC1 P- PC1 PC1 P-
P-
TB1 TB1 TB1 TB1 TB1 TB1
R
5650
TO
2
C6
RA
P-
WID
NE ²)
T2
GE (40 m
-C
TB1
TB1
5650
C5
C5
P-
SSL -5.300
TB1
TB1
TB1
TB1
TB1
TB1 3
-C
T2
2900 THK RAFT
15
RIV
WM-ST-202
300 THK RETAINING WALL 5650
2
250 5650
5650
EW
5 5 6
6
C5
PC1 C5 PC1 C5 PC1 C5 PC1
P-
P- P- P-
TB1 TB1 TB1 TB1
INIC
AY
CL m²)
5
0
(13
SSL +0.350
PURPOSE OF ISSUE
R
TO
4
250
-C
T2
250
SSL +0.100
91.4
ON ICE
SSL +0.100
14
WM-ST-202
C
4
B F
SU
PROJECT
R EMAAR PROPERTIES
TO OA
D
R AC ABIN
m ² R
CO.P.J.S.C
T YC 00
DE
LAY DOWN AREA ON RE )2=12
WI
IN C
TO
2-S X50m
MA m M. LEAD CONSULTANT
(800 m²) (12 00
39. ARCHGROUP
T/ T
ARCHITECTS.PLANNERS.ENGINEERS.PROJECT MANAGERS
EN
CLI LTAN
P.O.BOX: 38390, DUBAI, UNITED ARAB EMIRATES
TEL: +971 - 4 - 3341449, FAX: +971 - 4 - 3357449
U E MAIN CONTRACTOR
NS
CO FFIECY CAB0INm²
OTOR 2=60
)
2-S X25m
GH m DRAWING
(12 TOWER CRANE LAYOUT
ENTRY
PLOT
LIMIT
10.5
1 1 : 300
1:300 @A0
DRAWING NUMBER
AG-159
REV
2
R15 002 R0
7.5
MAIN STORAGE
14.99
FUTURE UTILITIES CORRIDOR 7.5 (400 m²) 7.5 T3
22.13
T1
N 2788328.181
E 494779.381 PLOT
LIMIT
LABORATORY
WATER TANK
GENERATOR
T2
178.47
(50 m²)
(50 m²)
(70 m²)
PLOT PLOT
LIMIT LIMIT
6.1
PLOT 6.1 7.00 M WIDE DRIVEWAY 7.00 M WIDE DRIVEWAY
LIMIT LEGEND:
PLOT LIMIT
TEMPORARY ROAD
BUILDING
7.0
TEMPORARY OFFICES
56.2
0M
8
WID
LABOR WELFARE
ED
RIV
EW
AY
7.0
MAIN STORAGE
0M
25
WID
300
WORKSHOP AREAS
ED
T3 G+54+R
THK
. PT.
SLA
B
T1 G+67+R
RIV
25
145
EW
.1
AY
9
25
T3- T3-
OTHER TEMPORARY
B4 B1
T3-
CB1
B8
T3-
25
200
THK
. RC 25
FACILITIES
25
.SL
AB
25
5 T3- T3-
B4 B5
T3-C 25
25
200 25
THK
25
25
. RC
SSL .SL
+21 AB
.000
25
B9
3
T3-
T3-
AB
-C
3-1
CB4
B3 T1-B13
T1
.SL
WM-ST-T1-201
T3-
T3-
. RC
CB1
25
SSL
CB5
+20
THK
200 .950
T3-
THK
200
. RC
.SL
T3- AB
T3- B6 1
CB2 T3-C
25
T3-
B2
25
300
THK
. PT.
CB4
AB
SLA
25
.SL
T1-CB2
T3-
B11
AB
T1-CB1
. RC
.SL
T3-
THK
. RC
1189 m²
1-1
200
THK
T1-CB9
T3-B13
200
200
THK T1-B3
. RC
T1-CB5
.SL T1-B3 T1-B4
AB
T1-CB6
T1-CB7
T3- T1-B7
2
T3-
-C
300 CB3 B7 T1-CB3
T1
T1-CB8
THK SSL +20.950
25
. PT.
B10
T1-CB7
SLA T3-
CB3
T1-CB6
B
T3-
T1-B2 10 T1-B6
299 m³
T1-CB4
200 T1-B1
T1-B8
THK