Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

TOTAL JAMAICA LTD

TAIR RETROFIT 2021 - LEVEL R3


BILL NO. 4- HWT CLOCK TOWER
Item Description
THIS IS A FIXED PRICE CONTRACT.
Any quantity included is approximate and is inserted to establish rate
for the described item.
The contractor or his representative is invited to visit the site to
ascertain the prevailing conditions and establish quantities.

All items necessary to complete the works must be included in the


rate as no adjustments will be made to the final submitted figure.

All installations must be in compliance with the manufacturer's


specifications and must not void manufacturer's warranties.

All items supplied by Total have to be collected/loaded from Total's


Warehouse by the Contractor or his Representative and transported
to the site at his own expense, without any damage.

All paint colours/finishes must meet Total's standard. To ensure this


all colours/finishes must be approved by the Engineer prior to
purchase.
ALL DEBRIS must be removed from site at end of works.

Item Description N/A Qty. Unit Rate Amount J$

A TOTEM
1 Disconnect electricals; examine integrity of sign structure safely; item
Take down existing totem using appropriate equipment/craneage
and transport to Total Storage Facility at Brighton Beach. Each
vertical column should be removed independently to avoid
damage to person or property.
2 Supply and install totem base adapter as directed by Engineer. item
Include provision for modification to existing concrete base if X
necessary.
3 Assemble, erect using appropriate craneage, and install new 6.5m item
T-Air Monopod with LED Price Display including all necessary
electrical installation and surge protection/voltage regulator. Test
and commission totem and price sign
4 Assemble, erect using appropriate craneage, and install new 9m T-
Air Monopod with LED Price Display including all necessary
X
electrical installation and surge protection/voltage regulator.. Test
and commission totem and price sign
5 Provisional sum for the construction of new totem base item

Totem Sub-total carried to Summary -

B CANOPY / CANOPY FASCIA


1 Electrical installation to include all material and equipment required
to provide 110V/220V supply to canopy fascia. Circuit to be taken
from existing canopy light
2 Carefully remove existing canopy fascia panels and/or "EPPING" item
lightboxes as required and dispose
3 Install T-Air Teak (RAL7006) Canopy Fascia Panels as per drawing 65.20 m
TOTAL JAMAICA LTD
TAIR RETROFIT 2021 - LEVEL R3
BILL NO. 4- HWT CLOCK TOWER
4 Install illuminated "TotalEnergies" panels on T-Air Fascia as 2.00 ea.
directed by Engineer including all necessary electrical installation

5 Install illuminated red bar on canopy fascia as directed by Engineer 27.20 m


including all necessary electrical installation
6 Install illuminated address wording on canopy fascia as directed by 13.00 no.
Engineer including all necessary electrical installation
7 Clean and prepare canopy ceiling for receiving paint. All loose paint, 228.00 m2
dirt and any other foreign matter must be removed prior to paint
application. Oil and grease shall be removed with approved
solvents. Apply (minimum) two coats Sherwin Williams White
Enamel paint or approved equivalent.

8 Clean all associated guttering on canopy repair or replace defective item


sections
9 Remove all old stickers (incl. warning decals and product decals) item
and paint canopy columns with Sherwin Williams White Enamel
Paint or approved equivalent
10 Provisional Sum for replacement/repair of defective canopy item
roof/ceiling

Canopy Fascia Sub-total carried to Summary -

C SIGNAGE
1 Remove old directional signs and transport to warehouse. Replace no.
with T-Air directional signs X
2 Install new T-Air directional signs 1.00 no.
3 Install Signage on Canopy Columns - No Smoking / No Open 40.00 no.
Flame / Shut Off Your Engine / No Cell Phone
4 Install Filling Position Number panels on canopy columns 10.00 no.

Signage Sub-total carried to Summary -

D SHOP FASCIA
1 Carefully remove shop fascia panels and related signage and
transport to Total Warehouse NPW X
2 Install White RAL9010 Shop Fascia Panels incl. all necessary m
supporting equipment X
3 Install Shop Entrance Totem 1.00 ea.
4 ea.
Install "bonjour" signage above shop main entrance including circuit
X
to sub-panel box as required and all necessary electrical installation

5 Install "café bonjour" signage including new circuit and all necessary
X
electrical installation
6 Install square dustbins 1.00 no.
7 Install address wording on building X
8 To replace existing awning with teak grey awning X item
9 Install poster boards X item
Shop Fascia Sub-total carried to Summary -

E FORECOURT EQUIPMENT
1 Remove garbage bins on pump island and in front of shop and item
dispose
2 Install T-Air standard low service units 3.00 no.
3 Install non-illuminated fuel arch / simplified fuel arch 3.00 no.
TOTAL JAMAICA LTD
TAIR RETROFIT 2021 - LEVEL R3
BILL NO. 4- HWT CLOCK TOWER
4 Install Pierhead Protection with red banner and fill with clean
washed sand X
5 Remove and dispose of existing sandbox 1.00 no.
6 Install TOTAL T-Air Sandbox 2.00 no.
7 Construct plinth and install 'Air' Pump Station Arch 1.00 item
8 Install illuminated Diesel Spreader Box including all necessary item
electrical installation X

Forecourt Equipment Sub-total carried to Summary -

F PAINTING & FINISHES


1 To prepare surfaces for painting and supply and apply minimum two
coats paint as detailed below:
2 Building Exterior: Teak Grey (RAL 7006) Satin Finish with m2
white (RAL 9010) band above 5/6 of building height
3 Lube/Service Bays: Teak Grey (RAL 7006) Satin Finish X
4 Boundary Walls: Teak Grey (RAL 7006) Satin Finish up to 1m m2
height; White Low Sheen Emulsion above 1m
5 Curb Walls: Sherwin Williams White Oil Paint m
6 External Doors: Slate RAL7021 Satin Finish no.
7 Pump Island Surface: Light Grey RAL7001 Glossy Finish item
8 Pump Islands Curbs/Trim: Slate RAL7021 Satin Finish item
9 Bollards: Teak Grey (RAL 7006) Glossy Finish with red no.
reflective band
10 Yard Light Poles & Concrete bases: Sherwin Williams White item
Oil Paint
11 Vent Pipes: Sherwin Williams White Oil Paint with 6" band item
according to product (87 - Red / 90 - Green / Diesel - Black /
ULSD - Yellow)
12 Tank Covers: 87 - Red / 90 - Green / Diesel - Black / ULSD - item
Yellow

Painting & Finishes Sub-total carried to Summary -

G MISCELLANEOUS
1 Include sum for handling (stripping and unloading of 40' container) sum
and storage of equipment at secure location

Miscellaneous Sub-total carried to Summary -

H OTHER CIVIL WORKS (ALL SUMS PROVISIONAL)


1 Excavate soft spots to repair potholes, remove all loose material, fill sum
all potholes with marl and roll to compaction. Apply asphaltic
concrete overlay and roll to compaction (38mm thick).
2 Construct plinth/extension on remote pump island to accommodate
spreader box X
3 Replace/ Repair/ Straighten Pump Bollards item
4 Prepare curb walls; patch all cracks, openings and holes and finish item
flush with adjacent surface
5 Supply and install LED overhead yard lights as replacement for
existing Metal Halide yard lights including provision for excavating,
concreting for base, erecting lightpoles, re-connecting and making
good excavated areas
6 Repair/seal all leaks in canopy roof item
TOTAL JAMAICA LTD
TAIR RETROFIT 2021 - LEVEL R3
BILL NO. 4- HWT CLOCK TOWER
7 Other External Building Repair item
8 Provision for removal of "TOTAL" Logo on new equipment and item
installation of "TotalEnergies" logo and adhesives
This may be required for the following equipment
- Totem Brand Block & some panels
- Pumps
- Shop Totem
- Directional Signs

Miscellaneous Sub-total carried to Summary -


TOTAL JAMAICA LTD
TAIR RETROFIT 2021 - LEVEL R3
BILL NO. 4- HWT CLOCK TOWER

MEASURED WORKS
Item Description Amount

A Totem

B Canopy

C Signage

D Shop Fascia

E Forecourt Equipment

F Painting & Finishes -

G Miscellaneous -

H Other Civil Works

Measured Works carried to General Summary -

You might also like