TOTAL JAMAICA LTD

TAIR RETROFIT 2020 - LEVEL R4


BILL NO. 5 - TEMPLE HALL
Item Description
THIS IS A FIXED PRICE CONTRACT.
Any quantity included is approximate and is inserted to establish rate
for the described item.
The contractor or his representative is invited to visit the site to
ascertain the prevailing conditions and establish quantities.

All items necessary to complete the works must be included in the


rate as no adjustments will be made to the final submitted figure.

All installations must be in compliance with the manufacturer's


specifications and must not void manufacturer's warranties.

All items supplied by Total have to be collected/loaded from Total's


Warehouse by the Contractor or his Representative and transported
to the site at his own expense, without any damage.

All paint colours/finishes must meet Total's standard. To ensure this


all colours/finishes must be approved by the Engineer prior to
purchase.
ALL DEBRIS must be removed from site at end of works.

Item Description N/A Qty. Unit Rate Amount J$

A TOTEM / PRICE DISPLAY


1 Disconnect electricals; examine integrity of sign structure safely; 1.00 item
Take down existing totem using crane and transport to Total Storage
Facility at Brighton Beach. (Dispose all "Epping" signage) Each
vertical column should be removed independently to avoid
damage to person or property.
2 Supply and install totem base adapter as directed by Engineer. 1.00 item
Include provision for modification to existing concrete base if X
necessary.
3 Assemble, erect using appropriate craneage, and install new 6.5m 1.00 item
T-Air Monopod Flag totem including all necessary electrical
installation and voltage protection. Test and commission totem and
price sign
4 Install Freestanding double-sided price display as directed by 1.00 item
Engineer include provision for modification/construction of plinth for
price display

Totem Sub-total carried to Summary -

B CANOPY / CANOPY FASCIA


1 Electrical installation to include all material and equipment required
to provide 110V/220V supply to canopy fascia. Circuit to be taken
from existing canopy light
2 Clean and prepare existing canopy fascia panels for receiving paint. 63.51 m
All loose paint, dirt and any other foreign matter must be removed
prior to paint application. Oil and grease shall be removed with
approved solvents. Apply (minimum) two coats Sherwin Williams
Teak Grey (RAL 7006) paint Glossy Finish or approved equivalent.
TOTAL JAMAICA LTD
TAIR RETROFIT 2020 - LEVEL R4
BILL NO. 5 - TEMPLE HALL
3 Install T-Air Teak Canopy Fascia Panels as per drawing X m
4 Install illuminated "TotalEnergies" panel on T-Air Fascia as directed 2.00 ea.
by Engineer including all necessary electrical installation

5 Install illuminated red bar on canopy fascia as directed by Engineer X m


including all necessary electrical installation
6 Supply and install address wording adhesive on canopy fascia as 10.00 no.
directed by Engineer (TAIR FONT; 200mm height)
7 Clean and prepare canopy ceiling for receiving paint. All loose paint, 130.93 m2
dirt and any other foreign matter must be removed prior to paint
application. Oil and grease shall be removed with approved
solvents. Apply (minimum) two coats Sherwin Williams White
Enamel paint or approved equivalent.

8 Clean all associated guttering on canopy and repair or replace 1.00 sum
defective sections.
9 Remove all old stickers (incl. warning decals and product decals) item
and paint canopy columns with Sherwin Williams White Enamel
Paint or approved equivalent

Canopy Fascia Sub-total carried to Summary -

C SIGNAGE
1 Install new T-Air directional signs X no.
2 Install Signage on Canopy Columns - No Smoking / No Open 16.00 no.
Flame / Shut Off Your Engine / No Cell Phone
3 Install Filling Position Number stickers on canopy columns 4.00 no.

Signage Sub-total carried to Summary -

D SHOP FASCIA
1 Install Shop Entrance Totem 1.00 ea.
2 Install "bonjour" signage on sunscreen above shop main entrance ea.
including circuit to sub-panel box as required and all necessary X
electrical installation
3 Install square dustbins X - no.
4 Install address wording on building X item
5 Install poster boards X item
Shop Fascia Sub-total carried to Summary -
TOTAL JAMAICA LTD
TAIR RETROFIT 2020 - LEVEL R4
BILL NO. 5 - TEMPLE HALL
E FORECOURT EQUIPMENT
1 Remove garbage bins on pump island and in front of shop item
2 Install square dustbins on pump island 2.00 no.
3 Install product information panel 4.00 no.
4 Install Pierhead Protection with red banner and fill with clean X no.
washed sand
5 Remove existing sandbox 2.00 no.
6 Install TOTAL T-Air Sandbox 2.00 no.
7 Construct plinth and install 'Air' Pump Station Arch X item
8 Install illuminated Diesel Spreader Box including all necessary X item
electrical installation

Forecourt Equipment Sub-total carried to Summary -

F PAINTING & FINISHES


1 To prepare surfaces for painting and supply and apply minimum two
coats paint as detailed below:
2 Building Exterior: Teak Grey (RAL 7006) Satin Finish 29.70 m2
3 Lube/Service Bays: Teak Grey (RAL 7006) Satin Finish X m2
4 Boundary Walls: Teak Grey (RAL 7006) Satin Finish up to 1m X m2
height; White Low Sheen Emulsion above 1m
5 Curb Walls: Sherwin Williams White Oil Paint m
6 External Doors: Slate RAL7021 Satin Finish no.
7 Pump Island Surface: Light Grey RAL7001 Glossy Finish 6.40 m2
8 Pump Islands Curbs/Trim: Slate RAL7021 Satin Finish 1.02 m2
9 Bollards: Teak Grey (RAL 7006) Glossy Finish with red X no.
reflective band
10 Yard Light Poles & Concrete bases: Sherwin Williams White X item
Oil Paint
11 Vent Pipes: Sherwin Williams White Oil Paint with 6" band item
according to product (87 - Red / 90 - Green / Diesel - Black /
ULSD - Yellow)
12 Tank Covers: 87 - Red / 90 - Green / Diesel - Black / ULSD - item
Yellow

Painting & Finishes Sub-total carried to Summary -

G MISCELLANEOUS
1 Include sum for handling (stripping and unloading of 40' container) sum
and storage of equipment at secure location

Miscellaneous Sub-total carried to Summary -


TOTAL JAMAICA LTD
TAIR RETROFIT 2020 - LEVEL R4
BILL NO. 5 - TEMPLE HALL
H OTHER CIVIL WORKS (ALL SUMS PROVISIONAL)
1 Excavate soft spots to repair potholes, remove all loose material, fill item
all potholes with marl and roll to compaction. Apply asphaltic
concrete overlay and roll to compaction (38mm thick).
2 Construct plinth/extension on remote pump island to accommodate X item
spreader box
3 Replace/ Repair/ Straighten Pump Bollards item
4 Prepare curb walls; patch all cracks, openings and holes and finish item
flush with adjacent surface
5 Supply and install LED overhead yard lights as replacement for X item
existing Metal Halide yard lights including provision for excavating,
concreting for base, erecting lightpoles, re-connecting and making
good excavated areas
6 Repair/seal all leaks in canopy roof item
7 Other External Building Repair X item
8 Provision for removal of "TOTAL" Logo on new equipment and item
installation of "TotalEnergies" logo and adhesives
This may be required for the following equipment
- Totem Brand Block & some panels
- Pumps
- Shop Totem
- Directional Signs

Other Civil Works (Provisional) carried to Summary -


TOTAL JAMAICA LTD
TAIR RETROFIT 2020 - LEVEL R4
BILL NO. 5 - TEMPLE HALL

MEASURED WORKS
Item Description Amount

A Totem

B Canopy

C Signage

D Shop Fascia

E Forecourt Equipment

F Painting & Finishes -

G Miscellaneous -

H Other Civil Works (Provisional)

Measured Works carried to General Summary -