PRE-COMMISSIONING CHECK SHEET E-238B

ELECTRICAL Sheet 1 of 2
CURRENT TRANSFORMER REV 5
PROJECT PROJECT WBS
DESCRIPTION No.

SUB-SYSTEM
SUB-SYSTEM No.
DESCRIPTION

TAG
TAG No.
DESCRIPTION

A. INDENT/CONTRACT No:
LOCATION: SYSTEM/PURPOSE:
SWITCHBOARD/EQUIPMENT NO: FEEDER/CIRCUIT:
MANUFACTURER:
CT SERIAL NO: TYPE: DRAWING NO:
CT RATIO: VA: CLASS:
TAG NO:
Initialed by
B. INSPECTION/TEST Contractor and Date
PDO

1. Inspect the current transformer for mechanical damage.

2. Check and ensure that connections are clean and tight.

3. Check and ensure that the wiring is cleated and core marking is correct.

4. Test and record the insulation resistance between phases (M).

5. Test and record the insulation resistance between phase and earth (M).

6. Polarity Check (flick check):

Winding R-phase Y-phase B-phase

7. Ratio Check:

Secondary Current Secondary Current (Amps)


CT Ratio Primary Current (Amps) measured between
winding points R-phase Y-phase B-phase
PRE-COMMISSIONING CHECK SHEET E-238B
ELECTRICAL Sheet 2 of 2
CURRENT TRANSFORMER REV 5
PROJECT PROJECT WBS
DESCRIPTION No.

SUB-SYSTEM
SUB-SYSTEM No.
DESCRIPTION

TAG
TAG No.
DESCRIPTION

8. CT Magnetisation and Winding Resistance Test:

Measured magnetising current in mA with following applied


Measured Winding voltages (V)
Core No CT Ratio between Phase Resistance
terminals () at ___C V at 1 A

R-ph

Y-ph

B-ph

R-ph

Y-ph

B-ph

R-ph

Y-ph

B-ph

Note:
1. Earth connections must be removed before test.
C. REMARKS / OBSERVATIONS:

COMPLETED BY CONTRACTOR APPROVED BY CONTRACTOR ACCEPTED BY PDO

NAME NAME NAME

COMPANY COMPANY REF. IND.

SIGN & DATE SIGN & DATE SIGN & DATE