Bored Piles - Design & Testing

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

BORED PILES

DESIGN &.. TESTING

S BUTTLING- SENIOR GEOTECHNICAL ENGINEER, MRTC


SA ROBINSON- SENIOR STRUCTURAL DESIGN ENGINEER, MRTC

SUMMARY two neighbours could be 50mm without significantly


Bored piles have been used extensively on the MRT, affecting the track which, being laid on ballast, can
primarily for the elevated structures. Generally, total be readily adjusted.
settlements of up to approximately 50mm can be b) The track could accommodate a differential lateral
accommodated, but pile settlements were originally movement of up to 30mm. Such a lateral movement
restricted to values much less than this, typically 10mm. of the track could be caused by differential
The variable soil conditions and different contractual settlement of the piles across the width of the cap,
arrangements led to several different pile design causing rotation of the cap and column, or by
methods being used. Extensive pile testing showed that translation of the cap.
pile designs were generally conservative, and allowed
piles to be shortened. A computer model. has be~n
2. For the multi-span continuous structures (used in
prepared which gives a better understanding of pile
special locations, e.g. to cross rivers, railways or major
behaviour.
roads), differential vertical movements of the
substructure of, say 50mm, would significantly affect the
INTRODUCTION stresses within the deck. Although it depends on the
particular span configuration and the reserve of strength
An examination of the SMRT route in relation to the
in each of these continuous bridges, it is generally
geology of Singapore shows that much of the alignment necessary to restrict the differential settlement between
is underlain by recent deposits of the Kallang formation. adjacent columns to approximately 10mm.
Elsewhere the weak rocks of the Jurong formation, and 3. However, for a typical span, i.e. a 20 or 25m long
the harder Bukit Timah granite, have been subjected to
pre-cast beam simply supported at each end, differential
tropical weathering, producing profiles of decomposition vertical movements can be readily accommodated. The
reaching to 30m below the surface in places. Since the
limit will be the rotational capacity of the bearings. For
loads to be carried by the columns of the v1aducts are the bearings used on the MAT (elastomeric bearings on
substantial, typically 13000 kN, piled foundations have
C102 and "pot" bearings elsewhere), the rotational
been necessary in order to avoid major settlement, capacity is normally O.D1 radians; allowing for dead and
except for those few areas where stiff strata were
live load rotations, this would permit differential
encountered close to ground level. Although driven piles
settlements well in excess of 50mm.
have been occasionally used, most notably at Bishan
4. The viaduct pre-cast beams have very high torsional
Depot and on some parts of Phase 2B, bored piles
rigidity. Because of this, if a beam is supported on four
have been installed for viaduct support on part of Phase
bearings (two on each crosshead), transverse rotat1on of
1, all of Phase 1A, all of Phase 2A and the balance of
one of the crossheads relative to the other can lead to
Phase 2B. This paper is concerned only with bored very significant changes in the bearing loads. In an
piles, for which the two main design criteria are:-
extreme case, all the reaction at one end of the beam
i) settlement and may be carried by one of the bearings, with the other .
ii) bearing capacity. taking no load. This would lead to overstress both w1th1n
In addition lateral stiffness may need to be the bearing and in the crosshead half-joint which
considered. supports it. ·
Some transverse rotation of the crosshead will occur
Settlement Criteria due to flexing of the columns caused by the normal live
From the point of view of the viaduct structures, the loads, but this may not become significant unless it is
magnitude of the total settlement would be of little additional to a transverse rotation of the pile cap,
consequence provided it was uniform. However, caused by differential settlement of the piles across the
differential settlement obviously needs to be limited. The width of the cap. A differential settlement of 5mm .
following factors are relevant:- between piles 5m apart (i.e. a rotation of 1 in 1000) 1s
sufficient to have a significant effect on the bearing
1. Track alignment: for a typical span where the loads.
columns are 20 to 30m apart:- If the four bearing arrangement is changed to three
a) Differential settlement of one column relative to its bearings (as was done for Phase 2B and subsequently
155
for Phase 2A) this problem disappears. highly to moderately weathered sedimentary rock of
5. The top surface of the viaduct has a drainage grades IV and Ill, or S2.
screed which is laid to falls. In order for this to function,
it is necessary to limit the differential settlement between Phase 2A
adjacent columns to approximately 25mm. In addition, For the piles on phase 2A the problems were totally
this amount of differential settlement is unlikely to be different again. Here the founding stratum was the much
noticeable. younger Pleistocene deposit called Old Alluvium. This
6. For the stations on Phase 2A, the design of the roof comprised sandy clays, clayey sands and weakly
structure is such that is cannot tolerate differential cemented sands, displaying some over-consolidation. It
settlements in excess of 10mm. was overlain by varying thicknesses of Kallang Deposits,
To summarise the above, the limits on differential comprising Marine Clays, Estuarine Clays and Fluvial
settlements are as follows:- Sands & Clays, much of which were covered by fill. The
a) Mutti-span continuous structures: risk of negative skin friction imposingsignificant loads
10 to 15mm between adjacent columns. on these piled foundations was therefore great. This was
b) Typical pre-cast beam span: particularly so in the Marina Bay extension, which is
25mm between adjacent columns. sited beneath recent reclamation of hydraulic fill over
c) Supports for stations in Phase 2A: 10-20m of Marine Clay. Latest survey figures showed
10mm between adjacent columns. that surface settlements had been at 40mm/year for the
d) Supports for beams with 4 bearing arrangement: last 3 years. It was therefore necessary to consider
1 in 1000 maximum transverse rotation of pile cap, carefully the likely magnitude of negative skin friction on
i.e. maximum differential settlement between piles, the box structures and on the piles themselves, and on
say 5m apart, to be 5mm. the consequent settlements. Since pile settlements will,
(No such restriction for beams supported by 3 in themselves, reduce negative skin friction this
bearings. becomes a complex analytical problem.
Using the rule-of-thumb that differential settlements The Old Alluvium was known to have variable
are unlikely to be more than half the total settlement, properties, particularly with regard to proportions of clay
the limits on total settlements are twice those given and sand. For this reason, alternative design methods
above. were used as follows:-
In order to ensure that the structural settlement Cohesionless soils:
criteria were met, the following limits for movement of
piles under maintained load tests were set:-

Working Load 150% of Working Load

Phase 1 & 1A 6mm 9mm where D = pile diameter


L __ pile length in Old Alluvium
Phase 28 9mm 20mm
-y', = effective unit weight of Kallan~rmation
-y', = effective unit weight of Old Alluvium
Pill DESIGN N,, N.-y = bearing capacity factors

Phase 1 0, = a.1r.D.L(p1, + -y'o.L) K,.tan ¢ 1


The only above ground contract on Phase 1 was 3
C102 and this had viaducts supported on piers on pile
caps over. groups of bored piles. The pile sizes, lengths where a = adhesion reduction factor
and reinforcement were all designed by the consultants, p', = vertical effective stress at bottom of Kallang
and the piles were generally of 1m diameter obtaining Formation
their bearing in the Bukit Timah Granite. Designs were K, = coefficient of. earth pressure for Old
based on conventional analyses of cohesion and Alluvium
concrete/soil adhesion, conservatively assessed, together ¢ 1 = eftective angle of internal friction for Old
with an allowance for end-bearing. Alluvium

Phase 1A Cohesive soils:


In Phase 1A of the SMRT the geology was quite
different. The whole of the alignment was underlain by
the Jurassic rocks of the Jurong Formation, in their
varied facies and in very different states of weathering.
Again the size and length was provided by the where N, = bearing capacity factor
consultant and was based on adhesion and end bearing C,, = undrained cohesion at base
using undrained strength parameters. It had been
assessed that various shear strengths were available
within the founding strata and, for the material of
weathering grade V, undrained shear strengths ranging where C, = average undrained cohesion in Old
from 45 to 150 kPa were used with an adhesion factor ' Alluvium
of 0.45. In material of grades IV & Ill, the shear strength
was taken as 200 kPa with an adhesion factor of unity. Working pile capacities were determined from
These weathering grades were then correlated ultimate capacities using a factor of safety of 3. Due
approximately with SPT 'N' values as measured in-situ, allowance was made for negative skin friction, but NSF
concluding with a general recommendation that piles and live load were not considered to be additive
should have 3 - 5m of socket into material with an N because of the transient nature of the live loads which
value of 200, which would generally correspond to would tend to reverse any NSF. Global design

156
parameters with regard to skin friction, end bearing, effects, so it will be necessary to restrict adjacent
elastic modulus and consolidation settlement were works of this nature, as part of the route protection.
assumed. C, values, shown on figure 1, were used with It is considered most unlikely that deep excavations
a derived from the Australian Piling Code (AS or tall embankments will be allowed near enough to
2159:1978). ¢ 1 was taken as 22° and used with a = 0.6. the MRT viaducts to have any significant effect.
Designs were then produced for various locations However, it does remain a remote possibility.
dependent on loads and depths of Kallang Formation, iii) Bending of the piles due to horizontal live loads
but it was not practicable to take account of all the such as traction, braking and centrifugal forces. The
variations in the properties of the founding material. bending moment is a maximum at the underside of
the pile cap, reverses to a peak of lower magnitude
Phase 28 at some distance down the pile, then gradually
In Phase 28 of the SMRT, the west line was again diminishes to zero. The extent of the bending effects
founded on weathered siltstones and mudstones of the depends on the stiffness of the surrounding ground,
Jurong formation, while the northern branch to Bukit but significant bending moments will rarely extend
Panjang crossed a zone of Gombak Norite in varying beyond 10m below the pile cap. Nominal
degrees of weathering. These piles were subject to reinforcement, of 1% of pile cross section, is
different contractual arrangements, in which the length normally sufficient for the maximum bending
was designed by the contractor. Several preliminary load moment in the piles.
tests were carried out, of which seven were In the event, reinforcement was typically provided in
instrumented, and these allowed the contractor's design the bored piles as follows:-
methods to be checked. The first method proposed was
the use of a formula from Smith & Pole (1980), which Table 1
was derived for granular soils:-
Reinforcement (as % of pile cross section)
·Q, -- 0.67.N.As
~
+ 14.N. de
_ .Ab (1) C102 1% for full pile length .
D Phase 1A 1% for full pile length
Phase 2A 1% for top 1f2 (10m minimum), 0.5% for
where As = Area of shaft remainder
Ab = Area of base Phase 28 1% for top 16m, 0 for remainder
D = diameter of pile
de = depth of socket
iii = average 'N' value over socket length LATERAL STIFFNESS
N = 'N' value at base
The permissible differential lateral movement of
Another contractor used the relationship 30mm, quoted in the settlement criteria, refers to a
movement occurring over a relatively long period. The
0, = 2.N.As + 130.N.Ab (2) maximum permissible lateral movement due to live
loads is smaller, approximately 10mm under the action
which was shown to give acceptable answers in terms of the maximum transverse loading (approximately 75t).
of field performance. In both cases factors of safety Calculations have been carried out to predict the lateral
were conventionally used, with 2.5 on Qu, or 2 on Qs movement of single piles, in fixed and free head
and 3 on Qb. conditions, using the methods of, for example, Poulos &
A third contractor has used the relationships between Davis (1980). Assumptions have to be made about soil
cohesion, adhesion and 'N' value shown in figure 2. For stiffness, and these are checked by carrying out lateral
N greater than 100 an adhesion of 200 kPa was used. load tests, usually by jacking apart adjacent piles.
The relationship between cohesion and N is derived
from Terzaghi & Peck (1967), and also shown in figure 2
are the adhesions derived by equations (1) & (2).
PRINaPLES OF PILE TESTING
DESIGN OF REINFORCEMENT FOR PILES Axial loads
In general the load reaction for maintained load tests
Vertical loads in the piles were calculated from the in Singapore is by kentledge blocks. This is certainly
vertical load and the moments acting at the underside true up to the 1450 tonnes used on SMRT, and is in
of the pile cap, assuming that the pile cap is rigid. contrast to UK practice where bored tension piles would
Horizontal loads were assumed to be resisted by the be used for such high loads. For the lower loads on
piles in bending, together with resistance from the soil working piles, up to about 500 tonnes, and where space·
in front of the pile cap and around the piles. was restricted such as in the median strips, prestressed
Since the maximum pile loads are low in terms of ground anchors were also used. Some general
concrete stresses, reinforcement is only required in information on pile testing is given in Buttling (1986).
areas where tension is expected. Possible causes of The two places where most attention is needed are
tension are:- in the measurement of load and of displacement. The
i) Axial tension in the piles due to particular loading use of pressure gauges in the hydraulic line as the only
combinations - there are very few cases where this means of determining load is not satisfactory. They are
arises. frequently too small to be read precisely, and are
ii) Lateral movement of the soil surrounding the piles, subject to friction and wear in the ram, amongst other
due to subsequent works nearby, such as things. Even up-to-date calibrations are no guarantee of
construction of an embankment or a deep precision in load measurement. This should be done• by
excavation. It would obviously be uneconomic or an independent load cell (hydraulic, electrical or
impossible to design the piles to resist all such mechanical), also recently calibrated, used in
157
conjunction with a spherical seating device to ensure borehole was put down at the exact location of each
axiality of load. test pile. The depths of the various N values were then
Settlement measurements by surveyors level are very noted and these were related visually to the arisings as
useful as a back-up, and to check on movements of each pile was bored. In practice the test piles generally
kentledge and reference beams. However, even with showed that the revised criteria were still conservative
parallel plate micrometers, they are not really accurate enough to allow for some error of judgement in
enough for a pile test. Dial gauges reading to 0.01mm assessing soil strength.
and with at least 50mm of travel and a large dial are The details of some of the test piles are shown in
readily available and should be used. They should be Figures 3 to 5, including the soil profile, instrumentation
mounted on a reference frame which is very stiff in the positions and the measured strain distributions. The
vertical plane, though not necessarily heavy, and more steeply sloping strain distributions indicate higher
protected from sun, and from engineers sitting on them! rates of load transfer, and therefore shear strength, while
Where thermal movements are likely to be a problem, the proportion of end bearing load is seen to be very
and readings will be taken throughout a 24· hour cycle, small except in TP6 which had a short socket into hard
at least one cycle should be recorded prior to load rock beneath 18m of soft to very soft overburden. The
application to detect any relationship between dial gauge contribution of the overburden is also seen to be small,
reading and temperature. and in TP5 where S4 was found right up to the surface
the skin friction is seen to be significant, though less
Lateral loads than in the S2.
Lateral load tests were carried out in order to verify Some load settlement curves are shown in figures 6
that lateral displacements were within the allowable to 9, and are seen to compare well with the allowable
limits. Generally pairs of adjacent piles were jacked limits of 6mm at working load {300 tonnes), and 9mm at
apart, as this is the most convenient method, and 150% WL. A total of thirty six tests were subsequently
deflections were measured with dial gauges. In some undertaken to 150% WL on working piles. Of these,
cases inclinometers were also used within the pile to thirty four were within the design criteria and only two
check on the deflected shape and the distance below exceeded them. These were within one pile cap and it
ground level that deformations reached. In all cases the is believed that this happened as a result of mis-
measured deflections over-estimated those in service interpretation of the ground conditions causing the piles
because the tests were carried out in a "free head" to be finished short of their required length. Two
condition compared to the "fixed head" condition of the additional piles were installed at similar length in order
piles embedded in a pile cap. to achieve compatibility of settlement with downrated
pile loads.

CONSTRUCTION &.. TEST RESULTS Phase 2A


Although the ground conditions posed no real
Phase 1 problems foe boring, concern over long term settlement
In practice the allowable settlements were sufficiently meant that some very deep piles were called ~or in the
small that very little end bearing load could be expected Old Alluvium. Along the east line, depths of Kallang
to be mobilised, yet piles were generally bored to virtual Formation of over 30m are quite common; hence some
refusal of the auger equipment in moderately weathered piles over 60m long were shown on the drawings.
granite of grade Ill, known here as G2. The These, together with the handling of temporary and,
performance under load test was excellent, well within sometimes, permanent casings, created construction
allowable limits, and no major problems were difficulties and it was not uncommon to find the
experienced. Permanent casings were provided for, permanent casing lifted in whole or in part as the
where there were likely to be significant thicknesses of temporary casing was removed.
overlying soft soils of the Kallang Formation. In the Thirty seven preliminary test piles were carried out
event they were not required as much as had been east of Kallang River, of which two were instrumented.
anticipated, yet they sometimes proved difficult to install. Later, six more were carried out on the Marina Bay
This may have been partly due to inexperience of the extension of which two were instrumented. Typical
procedure in Singapore, since it has been common to results are shown in figures 10 to 12. The results of
use driven piles in conditions where soft soils overlie the these were considered, along with results of pile tests
founding stratum. published by the PWD (Chin et al 1985, Yong et al
In some locations there were sewers or other deep 1982), and a picture of ultimate skin friction for the
pipelines adjacent to pile caps. In anticipation of a future various soil layers was developed. The methods of
requirement to excavate alongside these, and bearing in calculating ultimate capacity of piles proposed by Chin
mind the problems of temporary support and its (1970) were used, and from simple calculations it was
possible interaction with the foundation, contiguous deduced that the skin friction mobilised in the tests was
bored piles were provided in these areas. Inclinometer up to 300kPa. This allowed some reductions to be made
ducts have also been installed in order that the effects in the design pile lengths at several locations, most
of the opening up of any future trenches on the viaduct notably at Bedok Station where a construction problem
supports can be monitored. arose with a layer of unstable sand, and at Marina Bay,
where 3m was saved on the depth of each of about
Phase 1A 1500 piles.
At the start of construction it was decided to include
strain gauge instrumentation within the preliminary test Phase 28
piles, of which there were two on each of contracts 202, On the basis of the instrumented test piles the
203 and 204. At the same time it was decided to relax contractor derived alternative values for the ultimate skin
the design criteria to a 5m socket into material of N friction as shown in table 2, which show that the
value 100 or more. In order to achieve this on site a coefficients in equation (1) were too conservative.

158
TABLE 2 - ULTIMATE SKIN FRICTION VAWES closer to the ultimate shear resistance. This is a natural
DERIVED FOR JURONG FORMATION consequence of a design in which small settlements are
specified. In order to achieve this with any sense of
Soil Type N Average (ultimate) economy it is good practice to reduce the factor of
(blows/300mm) skin friction safety on calculated ultimate skin friction to about 1.2, in
qs (kPa) order to maximise on the capacity which can be
mobilised at small strain. A factor of safety on end-
bearing of about 10 is probably compatible with this,
Medium dense 5-20 35 and will ensure that. no embarrassing failure occurs
clayey silt should the skin friction have been marginally over-
'
Medium dense 20-50 50 estimated.
decomposed shale
Dense clayey 50-100 100
silt
DISCUSSION
Very dense 100-250 160 It is clear from the foregoing that, despite some quite
clayey silt tight settlement criteria, there has been very little
problem in the performance of the bored piles
Cemented siltstone/ 150-300+ 300 compared to their design. Generally the available factors
sandstone of safety against ultimate failure are very high, because
little of the base resistance can be mobilised at the
small working settlements. Economic design therefore
Only a few piles showed any settlement problem, and dictates that most of the skin friction should be
this was noted in one load test and in low pile head mobilised, reducing the factor of safety to about 1.2 on
stiffnesses measured in non-destructive testing. Two of ultimate, with a large margin on the end-bearing
the latter piles were cored, and revealed evidence of a capacity.
poor concrete/rock interface at the toe. This was then Back analysis of vertical load tests, both with and
held to be the cause of the poor static and dynamic without instrumentation, and use of the computer model
load responses. have shown that skin friction values of 300kPa have
Many of the piles on Phase 2B were driven, but been mobilised on many occasions; these are much
some were designed as bored piles and others were higher than the design values, even without the
changed to bored piles when hard ground was adhesion reduction factors. The Smith & Pole
encountered. The results of tests generally showed good relationship is clearly too conservative for Singapore
agreement with data obtained from the Phase 1A pile soils, while curves (2) and (3) in Figure 2 would each
tests. appear to indicate about half of the available ultimate
adhesion.
COMPUTf.R MODEL Lateral loads are generally of the order of 100kN per
pile, and can readily be accommodated. Tests on single
By careful analysis of the strain gauge results, piles showed small and acceptable lateral movements,
together with the information on gross pile movement bearing in mihd that fixed head conditions and passive
from extensometers, a picture of load transfer/ resistance of the pile cap would each help to reduce
displacement can be built-up, and this can be deflections and bending moments. Although there is not
related to soil strength, eg. SPT 'N' value. One way of enough data to be conclusive, it is likely that the lengths
using this information is within a mathematical model of of reinforcement used are excessive in relation to the
pile/soil interaction. One such simple model has been bending moments in the piles.
prepared (Buttling & Tam 1987), considering each pile as The computer model has been successfully used to
a series of cylindrical elements, the length of which back analyse instrumented test pile results, and hence
corresponds to a zone of soil which can be represented the load transfer/displacement relationships have been
by a single load transfer/displacement relationship or calibrated. Its use can then be extended into
'soil' type. Assuming an end bearing/displacement investigating the ultimate capacity of piles not tested to
relationship and postulating a pile tip settlement, the pile failure, the effects of reducing the length of a pile or the
behaviour can be modelled incrementally from bottom to effects of reducing friction in the upper part due to (i) a
top. The end results are a load distribution with depth deep pile cap or (ii) an adjacent excavation such as for
together with a pile top load and settlement. The a subway.
method has been programmed, and a series of runs It is hoped that further analysis will lead to a better
provides a load settlement curve. The model can then correlation between the 'soil' types and some
be used to back analyse instrumented test pile results, measurable property such as horizontal effective stress
adjusting the load transfers until a good fit is obtained or SPT 'N' value.
with the measured strains. It can similarly be used,
though with less precision, to back analyse load
settlement curves of non-instrumented pile load tests. CONCWSIONS
This model has been used to examine the data from 1. The design criteria, in terms of allowable deflection,
the Phase 1A, 2A & 2B pile tests, and a family of have been met without undue difficulty.
suitable load transfer/displacement curves has been 2. Bearing capacity has very rarely been a problem.
produced. Figures 13 to 20 show typical examples of 3. The design methods used have been refined during
comparisons between measured and computed load the course of the project but, on the basis of the
distribution, and load/settlement curves. From the load load test results, are still considered to be
transfer/displacement relationships in Figure 21, used to conservative.
produce the measured distributions, a reliable picture of 4. The computer model is a very useful aid to
the shear stresses mobilised at various levels can be understanding of test pile behaviour and the
produced. Generally these show that the shear stresses investigation of the effect of small changes on pile
are much higher than those used in the design, and are performance.
159
REFERENCES Poulos HG & Davis Pile foundation analysis and
EH (1980) design. John Wiley & Sons, New
Buttling S (1986) Testing and instrumentation of
York.
bored piles, 4th Int. Geotechnical
Smith & Pole (1980) Elements of foundation design.
Seminar, NTI, Singapore, 211-218.
Granada, London, 72-73.
Buttling S & Tam A simple model for pile
Terzaghi K & Peck Soil mechanics in engineering
RCK (1987) performance - its calibration and
RB (1987) practice. John Wiley & Sons, New
use (to be published).
Ct)in FK (1970) Estimation of the ultimate load of York, 2nd Ed., 347.
Yong KY, Cheah Ultimate load test of an
piles from tests not carried to
WB & Yap NC instrumented cast-in-situ bored pile
failure. 2nd SEACSE (SEAGC),
(1982) installed in stiff clay. 7th SEAGC,
Singapore, 81-90.
Hong Kong, 1, 453-463.
Chin YK, Tan SL Ultimate load tests on instrumented
& Tan SB (1985) bored piles in Singapore Old
Alluvium, Proc. 8th SEAGC, Kuala
Lumpur, 2, 54-64.

Undrained Shear Strength , Cu ( kN I m 2 )


0 100 200 300 L,OO 500 600 700
0 Cl
0
(!)
0

5 Ill

le -
..... 10
(!)
E
'

(!)

25
, -~ommended desigo
relationship
30
Figure 1 UNDRAINED SHEAR SlRENGTH FROM
UU TESTS - SOIL TYPE 0

160
180
Cu ( Terzaghi & Peck )

...... 160
"e
-
z-"' 140
~

-...
.£:
g' 120
Ql
( 3)
/
Vi
~ 100
.£:
/
-"-' lf)

-o
Ql
c
80 /
·a...
-o
c 60 /
----
::::>
c(l

/
c
0
'iii

]/ / ----- ----
-----
Ql
.£:
-o

-----
~

V/_____.
0
0 8 16 24 32 40 48 56 64 72 80 88 96 104
SPT ' N ' Value
Figure 2 Relationship between adhesion , undrained shear strength & SPT ' N ' value
12 MICROSTRAIN
50 lOO 150 200 250 n;r Description
reddish brown
SPT
blows/mm

3 clayey silt 1/300


reddish brown 12/300
6 silt 25/300
dark reddish
c\1 brown clayey
27/300
~

10 silt 52/300
~ 48J brown clayey
J'\E 300 silt (weathered 122/300
lll~ siltstone)
176})00
f::: 191/190
36/300
121/130
'
22.2 100/80
reddish brown 100/70
~· 25 TP4 26.0
SW siltstone
100/50
1, 2 ~ ~X tensclmtt~
Cmm::mw<alth
x or~ strain ~

( Q ) (b) (c )
t~ 3 I lnfornation for the Test pile at Carrronwealth (TP 4)
a. Position of extensometers and strain gauges in the pile.
b. Vertical strain distribution.
c. Borelog taken at the centre of pile location.

123 MICROSTRAIN
~
E
0
0 50 100 1'50 200 250 uc:' Description SPT
blows/mm
_j_
SOt l)>ard reddish
[b~own ligl:t greh 37/300
!'=layey s1lt wit
5 san.• sand and 46/300
5 r- fragments of roc
131;L230
~~d dark red
8.4' [rott led light
101/215
l"l~
fbsown clayey sil
~th coarse sand
i.dJ I~ 10 dark red light
100/260
Ji ~~~~ E 2.3 brownish grey
coarse grained
100/160
~ I'"' ~
~ ~siltstone
100/110
jE 15
a. hard brownish
6.5 yellow grey 100/130
~ r--, clayey silt with
100/130
rL ~iltstone
fragments of
100/150
Notes: v dense dark red
silty fine to 100/180
1,2,3 ~ex~ coarse sand
x ~ strain ga 19!'5 v dense dark red 100/210
25 TP' brownish yellow
Clerrenti clayey silt fine 100/50
(a) r12-- to rred sand 100/50
30 .___,____L._,_ _.___ _.__----J v dense dark red 101/100
grey· silty fine
to coarse sand 100/95
(b )
with fine gravel
F.gu.-. 4 I lnfornation for the Test pile at Clerrenti (TP 5) 100/200
a. Position of extensometers and strain gauges in the pile 36
b. Vertical strain distribution.
(c )
c. Eorelog taken at the centre of pile location.
162
12 MICROSTRAIN
~
E SPT
~ 50 XX) 150 Description blowslmm
.L stiff yellowish 11/300
red reddish
orange clayey
silt with fine 13/300
5 to rred sand 12/300
14/300
~ ~10
rirrn black peaty 8/300
lay
~ E tiff dark grey 13/300
~ l.:.Kk ~caty clay
J'l ~ I P-..5- nd si tv clay 8/300
~15
N
N irrn light brown-
w ~ clav ish grey silty 12/300
0 8/300
c1§..._ rv hard yellowish
red clayey silt
20 )100/150
20 ,~rd dark red SW
22 siltstone
dark red rned
grain SW silt-
Notes' 25
~6.5 i~o~~' with ioints
1 s aced close
1,2 are ext~ TP6
x are strain gauges Ulu Pmdan

30 ~---J'-----J'----'---'--___J
(a ) (b ) (c )

Figure 5 1 Information for the Test pile at Ulu Pandan (TP 6)


a. Position of extensometers and strain gauges in the pile.
b. Vertical strain distribution
c. Borelog taken at the centre of pile location.

LOAD ( tonnes )
200 400 500 800 1000

......
E 20
E
.......
1-
z
w 40
~
w
....J
I=
w
til
50
w
....J
a.
80 Pile No: TP 2
Location :Queenstown

100~----~----~------'--------~-------'

Figure 6 LOAD SETILEMENT CURVE OF THE


TEST PILE AT QUEENSTOWN ( T P 2 )
163
LOAD ( tonnes )
0 200 400 600 800 1000
0 I I

......
E 20
E
- -
......
1-
zw
~
40 - -
w
...J

~
1./l
w
60 - -
...J
0:::

80 - Pile No: TP 4 -
Location :Commonwealth

I I I I
100

Figur• 7 LOAD SETILEMENT CURVE OF THE


TEST PILE AT COMMONWEALTH ( TP 4 )

LOAD ( tonnes ) '


!:>

0 200 400 600 800 1000
0 I I

.....
E 20 - -
E
......
1-
z
w 40
~
- -
w
...J

~
1./l
w
60 - -
...J
a.
80 - Pile No: TP 5 -
Location :Clementi

I I I I
100

Figure 8 LOAD SETILEMENT CURVE OF THE


TEST PILE AT CLEMENTI( TP 5 )
164
LOAD ( tonnes )
0 200 400 600 800 1000
0~~~~~~~=-r-1~

......
E 20
E
.......
- -
1-
zw
~
ItO ~ -
w
...J

s
<f)
60 r- -
w
...J
a:
80 r- Pile No: TP 6 -
Location : Ulu Pondon

I I I J
100

Figure 9 LOAD SETILEMENT CURVE OF THE


TEST PILE AT ULU PANDAN ( TP 6 )

Load ( tonnes )

10

Figure 10 PILE LOAD TEST FOR PP 2 ( C 305 )

165
Load ( tonnes )

00 100 200 300 400 500 600 700 800 900


1st cycle
~
l-
E I 2nd cycle·
~10
.....
c
CIJ
E
CIJ
.....
.....
~ 20
I
------- 3rd cycle

Figure 12 PRELIMINARY TEST PILE TP 4 (a), MARINA BAY { C 310 )


30
-"'"' Load ( tonnes )

00 200 400 600 800 1000 1200 1400 1600

1st cycle
~
2nd cycle
E
E
~

3rd cycle
~ 20
E
JY
.....
_.
~

•"V:~
40

Figure 11 PILE LOAD TEST FOR P612, PASIR RIS STATION ( C 306 )
!:i
!:i ::::>
::::> C/l
8co C/l LIJ
a:
~
0
ln
LIJ
LIJ
~
1- ....1
::::>
~ 0
<( ~
<(
9 u

!
§ tI
r
~

N
0
C"'l

IJ
u
......
~
I.Cl
C"'l
~ Cl.
Cl.
Ill
<I>
c: LIJ
....1
c:
.9 a:
......
0
0
~ I ~
f
<(
0
....1 LIJ
5:
0
0
I ::::>
u
C"'l

t 1-
z
LIJ
~
I ~
1-

~
0
0 l:i:i
N
-
C/l

0
I 9
0
0
~

-I!!
C")

:::1
01
0 i.i:
0 0
0 2 N C"'l

( ww) 1N3W311l.35

167
LOAD ( tonnes )
100 200 300 400 ·<>¥ 500 600 700 800

10

,.....
E 15
~

~
~ 20~ co

25
I
1//
Ill/ ./
"'
~

STRAIN GAUGE RESULT


30~/Y;'f X CALCULATED RESULT

35

40

45
Figure 14 LOAD TRANSFER CURVE FOR PP 35 ( C 302 )

.<11
~
m~
wm
o:w
0:
0
w 0w
~ 0:

I~
_j :::J
:::J Vl
~ <l
~~

~
l
"
~

Ir
I<
)(
"' C"')
u
'-'

6
§ ~
I
fl
I(
1 In
Vl
0:

I
~
0:
~
clC
~
-
c
0
"
i
'-' 0
~

0 <D
<l a.
9§ M 0:
f2
I w
5:
~ a

~
I ~
w
~
w
_j
1-
1-
~
-
0
<l
g
~" 1.0
~

~
::J
til
0 u:
0 S2 ~ 0
C"')
0
~

( ww) lN3~3ll13S

169
~
!:J
::J !J
l{l ::J
t.n
a: IJJ
a:
§ c
~
IJJ c
t:( ~
....1 ::J
::J t.n

~ r 5L5 ::E

I I
v I
8 <I
N
~
I
I .......
0
....... ~

M
:c
c § u
~

c M
....0 a.
~ 1-
c
~
<(
g @ .
u.
IJJ
6:
::J
u
~
IJJ
::E
IJJ
....1
I=
IJJ

-
t.n
c
<5
;;:)

-
<D

~
::J
01
iJ:

( ww ) 1N3~311!3S

170
LOAD ( tonnes )
00 200 400 600 800 1000 1200
- 1400 1600

10
~

E
E
~

1- 20
z
w
:::E
-
::l
~
I=
w
(/) 30

40
MEASURED RESULT
- - x - - CALCULATED RESULT

50

Figure 17 LOAD TRANSFER CURVE FOR TP 3 ( C 310 )


LOAD ( tonnes )

010 I A
100
"'
200
1
I
~-:x-32- A
300
I I
X
400
I I
500
I I
600
I I
700
I I
800
I I
900
I I
-x-~-x-x-x-x-x
- x - x - x -...,.._)(_

E 10
E
~

1-
zw

:::l
"' .=~
1-
20
w
lf)

30 - - - - L O A D TEST RESULT

- • - - CALCULATED RESULT

Figure 18 LOAD I SETTlEMENT CURVE FOR P 3111 ( C403 )


·~-
0
8 (T)
0
~
:::::::-_X--~ u
0
g ~~~-·~------~--~:~'--- -
;;:;
a.

~
ea:
Ill
0
Cll
0
U)
c
c
.9
~

Cl
<(
g §

-
m

173
LOAD ( tonnes )

o
0

~-~-~~
100 200


300 400

r r
500

r r
600

E
E 10
- 1- MEASURED RESULT
~

1-
z
w
:::E Y'..: CALCULATED RESULT
~ w
..J
1-
~ 20
1/)

30

Figure 20 LOAD I SETTLEMENT CURVES FOR PILE S314, BUKIT BATOK ( C 405 )
•'<'·
80
'SOIL' TYPE 7

70

60

~
' SOIL ' TYPE 6
50

-
"E
.....
~

a:
w
lJ..
40

<(
a:
1-
0
<( 'SOIL' TYPE 5
0 30
...J

'SOIL' TYPE 4
20

' SOIL' TYPE 3


'SOIL' TYPE 2
10

' SOIL' TYPE I

0
0 2 4 6 8 10 12 14 16 18
DISPLACEMENT ( mm )

Figure 21 LOAD TRANSFER VS DISPLACEMENT

175

You might also like