Professional Documents
Culture Documents
3 PMP Template
3 PMP Template
3 PMP Template
[Type text]
Document Control
Document Control
Document History and Version Control
Version Date issued Reason for issue / changes made Author
Reviewers
Name Position
Authorised by
Name Position Date Version
2
Table of Contents
Table of Contents
1 Introduction 5
2 Project Definition 6
2.1 Background 6
2.2 Objectives 6
2.3 Critical Success Factors 6
2.4 Scope 6
2.4.1 Scope Inclusions 6
2.4.2 Scope Exclusions 6
2.5 Assumptions 6
2.6 Constraints 6
2.7 Dependencies 6
2.7.1 Internal to Project 6
2.7.2 External to Project 6
3 Project Schedule 8
4 Project Organisation 9
5 Project Governance 10
3
Table of Contents
6 Procurement 15
7 COST MANAGEMENT 17
7.1 REVENUE 17
7.2 CASH-FLOW 18
7.3 BUDGET 18
7.4 COST MANAGEMENT PROCESS 19
4
1 Introduction
1.1 Document purpose
xxx
My feedback on the template is that we should ditch and start fresh, it’s a real dog to use. The
appendices will require reordering.
Sections 1 & 2 were to be cut and pasted from our charters and then reworked.
5
2 Project Definition
2.1 Background
Xxx
2.2 Objectives
Xxx
2.4 Scope
2.4.1 Scope Inclusions
Xxx
2.4.2 Scope Exclusions
Xxx
2.5 Assumptions
Xxx
2.6 Constraints
Xxx
2.7 Dependencies
2.7.1 Internal to Project
Xxx
6
2.8 Benefits & Measures
Xxx
2.9 Approach
Xxx
7
3 Project Schedule
3.1 High Level Project Schedule
Xxx
8
4 Project Organisation
4.1 Project Organisation Structure
Xxx
9
5 Project Governance
5.1 PROJECT ORGANISATION
AAA Events Management Pty Ltd (AAAEM) is proposing to be the nominated company appointed and
funded by the Sponsors to manage and implement the MyTown Show Society Night Events as
defined in section 2.
The nature of this project requires the need for an organisational structure that focuses on eight
distinct areas and the individual and interacting dependencies being addressed and fulfilled as a
precursor to the delivery of an event management plan. Refer Appendix J – Organisational Charts.
The AAAEM CCB will be the project bids ultimate governing body. It takes high level decisions and is
responsible for ensuring that AAAEM’s organisation, processes and resources are appropriate to
deliver the project. The board has its own guidelines which set out the arrangements for the conduct
of its business.
The AAAEM CCB sets out the delegated authority levels for the corporate governance structure for
the project committees and subcommittees. All committees have clear terms of reference to
establish their role, membership, frequency and administration.
10
In addition, job descriptions set out the roles and responsibilities including the delegated authority
the individual possesses for the discharge of the functions for which they have responsibility.
For those change requests not requiring AAAEM CCB approval, the timeframe for this process is a
five working day turnaround. Any request for change to this plan will need to be submitted to the
Project Manager via the Senior Team Manager, using a Formal Change Request Form.
The Project Manager will assess the request in regards to impact on time and/or cost and
communicate the decision back to the Project Team.
Coordinating communication across the AAAEM MyTown Show Society Night Event Bid
Project
Managing shared resources across the AAAEM MyTown Show Society Night Event Bid Project
Monitoring compliance with the Project Management standards, policies, procedures and
templates
Developing and managing sub-project policies, procedures, templates and other shared
documentation (organisational process assets)
Providing expertise in the areas of IT, Finance, Vendors and Micro layout.
11
5.3 GOVERNANCE MANAGEMENT PROCESS
The programme governance forums facilitate the delivery of AAAEM’s obligations. Delivery will
involve MyTown Show Society, their vendors, AAAEM’s contractors and AAAEM’s project teams, so
effective governance must address each interaction.
On approval of the initial project management plan a detailed plan will be created and become the
responsibility of the project manager to implement. This will include:
Decisions can only be made by individuals with the appropriate delegated authority
An escalation path for issues that are beyond the project manager’s authority will involve the
AAAEM CCB and will include exceptions or changes that have an impact on the project
success and exceed agreed upon thresholds.
The overarching financial management of the project will be the responsibility of the Finance
Manager who will be responsible for liaising between the MyTown Show Society and the
project team.
o Membership will be established against these – each individual should know why
they are there
12
Scheduling (time)
Budget (cost)
Scope
Changes that may be the result of unforeseen requirements that were not
initially planned and may impact the project scope
A committee structure will be used to facilitate oversight of the project activity across all levels.
A proposed committee structure is provided below:
xx
14
6 Procurement
6.1 PROCUREMENT MANAGEMENT
Procurement is the process encompassing the procurement of works, supplies and services from the
marketplace. The process will manage variations, settlements and remedy breaches. Procurement
activities will endeavour to adhere to the following protocols:
Best Affordable Value: acquiring product that are of value and standard at best value
approach for providing and delivering AAAEM’s project objectives. These opportunities need
to be sought regarding scalability and efficiency vs value as well.
Effective Supplier Relations: AAAEM has a large long standing network of supplier relations.
This needs to be taken into account when tendering and that this sometimes give
opportunity for better rates.
Standardised Approach: The systems needs to be consistence and fair to all suppliers
engaged in the tender and especially when procuring goods of a similar nature.
Governance and Control: The Commonwealth Procurement Rules is the Australian legislation
that gives legal requirements and needs to be adhered to.
Open Tender: An open-ended approach that utilises the larger market by advertising and
inviting submissions. This can encompass multi-stage procurements providing the initial
stage is of the same approach.
Limited Tender: Limited tender involves an entity approaching one or more supplies
directly to make submissions. This is used when the process does not meet the
requirements for open tender. When conducting a limited tender the relevant exemption or
limited tender condition must be reported to AusTender.
TENDER
Temporary upgrade of 250 seats Open
Add 550 seats (make 800) Open
Add 300 seats (make 1100) Open
Security Barriers Open
Stage Limited
15
Toilets Open
Light and sound Open
Fireworks display Open
Fireworks larger crowd Open
Present for band competition Limited
Internal ticketing system No Tender
Work force Open
A tender estimation will be already completed by this PMP being completed. Once approved the
tenders will go out immediately on the 4 th of September 2018 till the 25th of September 2018. There
will be a months period for negotiation where the 25 th of October letters of approval will be awarded.
Conditions of tender will be a 10% deposit is paid 30 days before the show scheduled for the 26 th and
27th of July 2019, and the terms of trade will be remaining arrears 45 days after the show.
16
7 COST MANAGEMENT
Cost management is the overall process of estimation, budgeting, planning, managing and controlling
the costs of the project to ensure the project exists within approved financing parameters.
7.1 REVENUE
AAAEM’s revenue is going to be generated by two means. The first is the cost of the show plus 10%
which represents a safe low-risk but low return revenue stream. The second one is through the sales
and marketing of event tickets. AAAEM receives 10% of each ticket sold. This income stream is high
risk but is mitigated by the first revenue stream. AAAEM has significant strength in marketing analysis
and forecasting. This will be monitored monthly and adjustments made to reach targets. The cost
duration will be 14months where the last two months have no cost to the client as they are internal
reporting, analysis and lessons learned. A schedule of the potential profit and loss for all parties has
been detailed below. This takes into account three levels of audience attendance levels and makes
the assumption that all aspects of AAAEM’s budget will be approved. Previous events have told us
that 3 weeks before the event is generally 60% of the total number to attend.
PROFIT OR LOSS
17
7.2 CASH-FLOW
The nature of the event means that the bulk of the money coming from ticket sales is going to
happen closer to the event and not before marketing has started. Previous experience tells us that 3
weeks before the event 60% of the attendees will have paid upfront at a reduced rate, the following
40% will be received up to when the event is over. The delay in receiving cash flow has prompted us
to use a lot contractors on 30 days terms of trade that will receive payment after the event and
tickets are finalised. The cash flow chart presented as Annexure ??, shows a maximum debt exposure
of $18,774.80 in February 2019. This risk needs to be mitigated and monitored to ensure the cash
position stays strong during the whole project.
7.3 BUDGET
The table below is a monthly schedule of the costs associated with the event. If this is approved it
will become the budget baseline in which cost management will be used against.
CASH FLOW
18
7.4 COST MANAGEMENT PROCESS
Once the baseline for the project has been approved it will be used as part of the three metrics we
will use to monitor budget:
Schedule Performance Index (SPI): Measured from values 0-1. Progress made against
planned rate eg. Value of 0.8 is 80 cents worth of work for every planned $1. (EV/PV)
Cost Performance Index (CPI): Measured from values 0-1. Worth of work from every $1
spent eg. Value of 0.8 is 80 cents worth of work for every planned $1. (EV/AC)
Schedule Variance (SV): Negative is behind schedule, positive mean ahead (EV-PV)
Cost Variance (CV): Negative means over budget, positive under budget (EV-AC)
All metrics will be calculated weekly by the finance SME but reported monthly to the PM unless a
variance of +/-20% is produced and will be reported immediately for corrective measures.
19
8 Stakeholder and Communication
Management
Stakeholder and Communications Management Sections of PMP
In order to create these plans, the following steps were undertaken and or proposed:
1) Identify Stakeholders: brainstorming sessions with key project staff (such as the Project
Manager and SMEs) were held prior to the commencement of the project. Stakeholders
were organised within typologies in the plan, including but not limited to those listed in
sections 8.1.1 and 8.1.2.
2) Plan Stakeholder Management: a key questionnaire was issued to stakeholders, or key
representatives of the stakeholder group, in order to initiate progressive dialogue in
regards to the impact, influence and expectations each have with the project. The
document was designed to obtain the current feelings, thoughts and concerns, and the
resulting data input into the plan.
3) Manage Stakeholder Engagement: Strategies chosen to ensure effective engagement
with stakeholders include: Stakeholder Questionnaire, Analysis of stakeholders via
Interest and Influence numbering systems (see Appendix _____), Communications
Schedule Plan (refer section 8.2 and Appendix _____), and the Stakeholder Management
Plan (refer section 8.2 and Appendix _____).
20
4) Control Stakeholder Engagement: Further to the engagement strategies, it is critical
that the progression and usefulness of these strategies is monitored and controlled.
Chosen methods to assist in this endeavour are a Feedback Review at each Phase Gate,
and regular stakeholder community meetings.
8.1.1. Internal 14
Internal stakeholder refers to the entities within this project. Key internal stakeholders
include:
- Client (MSS Board)
- Project Sponsor
- Project Manager
- SMEs
Further detail and analysis of internal stakeholders is located in Appendix ____ as part of the
Stakeholder Management Plan.
8.1.2. External 14
External stakeholder refers to the entities outside of the project, but still have an interest in or
influence on the project, such as:
- End Users (event and festival attendees)
- Entertainer and Band
- Local Councils
- Surrounding Neighbourhoods
- Key Suppliers
Further detail and analysis of external stakeholder is located in Appendix ____ as part of the
Stakeholder Management Plan.
Appendix _____ frames the processes and controls required for effective stakeholder
engagement throughout the life of this project by AAAEM. This plan shall; be continually
reviewed, be updated as changes dictate or at the start of each project phase, and become an
energetic plan that unites the stakeholders. Engagement will be facilitated predominately
through formal face-to-face meetings, with meeting minutes taken by the PM and circulated
as per the Communications Schedule Plan, framed in Appendix ____. Informal engagement
shall take place via email communications. Newspaper notifications, local government
website notifications and other forms of mass media will be utilised to provide information to
the larger stakeholder groups, such as surrounding neighbourhoods.
21
The purpose of the Communications Schedule Plan (Appendix _____) is to identify and set
out clear lines of communications between all facets of the project, ultimately to ensure the
success of the project and satisfaction of all stakeholders.
Changes to the baseline requirements and key criteria, other than regular informational
updates, of these plans can occur through review and upon the authority of the Project
Sponsor, as per the Change Management Process (DO WE HAVE THIS??). This can be
initiated either from within or external to the Project Team.
The Communications Schedule Plan will ensure stakeholders are provided the necessary
information at the appropriate times, in a manner that is able to be recorded; and will act as a
feedback mechanism from the stakeholders and client to the Project Team, with regular and
relevant information. The need for methods of communications that are regular, clear and
useful is particularly apparent when considering the context of the role of this new event
within the existing Mytown festival.
The nature of this project, being run as a separate entity within an existing festival, has
necessitated the use of a Communications Schedule Plan that is tailored to the unique
structure and environment within which it is to be delivered. Specifically, multiple, largely
existing teams are required to deliver multiple facets of the festival on the whole, and this new
project must integrate and communicate with them effectively. The integration of the new
event is likely to cause some disruption to the existing structure, although with the aim to
minimise this as much as possible (SEE RISK SECTION), and therefore change or update
existing methods of communications. Furthermore, the identification of large stakeholder
groupings (e.g. general public, thousands of festival attendees, surrounding neighbourhoods)
has illuminated the need for vast publications of progressive updates. As aforementioned,
face-to-face contact with stakeholders is preferred and will be used frequently, though
electronic forms of communications will be utilised as well as standard notices for these large
groups, Electronic record keeping, including meeting minutes and change control records, and
frequent Project Team checkpoints shall be enforced to decrease the likelihood of
miscommunication, whilst increase the streamlining, accessibility and clarity of information.
Appendix _____ contains the Communications Schedule Plan, identifying the method of
communication, the schedule or intervals at which communications will be performed,
method of delivery, owner and distribution, for both internal and external stakeholders. The
document will be reviewed regularly and updated accordingly, in response to the specific
needs and progression of the project
22
9 Risk Management
The Risk Management plan will outline all Project risks and map a clear pathway for controlling,
minimising or eliminating each risk. The Project Manager will be responsible for implementing and
updating the Risk Management Plan throughout the life of the Project.
9.1.3. OPAs
1. Processes, policies and procedures
a. AAAEM has a full set of documented Processes, policies and procedures
2. Organisational knowledge base
a. AAAEM maintains a lessons learnt register which contains site visit information
24
9.3. Risk Identification Methodology
A number of analytical tools and techniques are incorporated into AAAEM’s risk management
strategy. The outputs produced include:
Risk Management Plan
Risk Impact and Probability Assessment (see Appendix XXXXX)
Project Risk Register (see Appendix XXXXX)
The Risk Impact and Probability Assessment created a matrix which was incorporated into Risk
Management Plan, with residual risk and impact projected after agreed controls and contingency
actions were applied. The Project Risk Register will be the primary reporting too through which risks
will be tracked and audited.
Qualitative risk assessment is to be conducted through the Stakeholder and Communication Plan.
The Probability and Impact matrix is laid out in the following table. The Risk Impact and Probability
Assessment (see Appendix A) defines the level of each risk identified in the Risk Register (see
Appendix B).
25
The Risk Impact and Probability Assessment has identified no initial ‘Exposure – Very High’ risks and
only two ‘Exposure – High’ risks. Risk responses of Transfer, Tolerate, Treat and Terminate are laid
out in the Risk Register. Residual risks probability along with impact was assessed utilising the same
assessment tool. In a number of cases risks were reduced however many stayed at the same level,
this is laid out in the Risk Register.
AAAEM has a 10% tolerance to project cost and time. The threshold at which this risk becomes
unacceptable is 20% to project cost and time.
9.1
26
10 Project Controls
Xxx
27
11 Appendix
11.1\
28
29
Ref Type Description Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Total
PLANNING PHASE
Create marketing plan $650.00 $650.00
Monitor marketing performance and adjust $688.00 $688.00 $688.00 $688.00 $688.00 $688.00 $688.00 $688.00 $688.00 $688.00 $344.00 $7,224.00
Consult with B2B partners about packages $860.00 $860.00
Monitor B2B performance $688.00 $688.00 $688.00 $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $167.00 $4,639.00
Conduct ticket pricing audit $860.00 $860.00 $1,720.00
Monitor ticket sales $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $344.00 $3,784.00
Revise Risk Plan $860.00 $860.00
Project Management $1,300.00 $650.00 $650.00 $650.00 $650.00 $650.00 $650.00 $650.00 $650.00 $650.00 $650.00 $1,300.00 $9,100.00
TENDER
Temporary upgrade of 250 seats $300.00 $2,700.00 $3,000.00
Add 550 seats (make 800) $1,600.00 $14,400.00 $16,000.00
Add 300 seats (make 1100) $700.00 $6,300.00 $7,000.00
Security Barriers $400.00 $3,600.00 $4,000.00
Stage $75.00 $675.00 $750.00
Toilets $200.00 $1,800.00 $2,000.00
Light and sound $450.00 $4,050.00 $4,500.00
Fireworks display $1,800.00 $16,200.00 $18,000.00
Fireworks larger crowd $700.00 $6,300.00 $7,000.00
Present for band competition $1,500.00 $1,500.00
Internal ticketing system $250.00 $2,250.00 $2,500.00
SETUP SHOW
Project Manager $695.00 $695.00
Project Coordinators x 2 $688.00 $688.00
Supervisors x 2 $1,040.00 $1,040.00
Workers (Low skilled) x 5 $1,380.00 $1,380.00
Workers (Skilled) x 3 $1,041.00 $1,041.00
Professional Planners x 2 $1,042.00 $1,042.00
SHOW DAY OPERATIONS
Project Manager $1,390.00 $1,390.00
Workers (low skilled) x 15 $7,452.00 $7,452.00
Supervisors x 2 $1,040.00 $1,040.00
Project Coordinator x 4 $1,386.00 $1,386.00
Workers skilled x 4 $2,800.00 $2,800.00
SHOW REMOVAL
Project Manager $695.00 $695.00
Workers (Low skilled) x 5 $1,380.00 $1,380.00
Workers skilled x 3 $1,041.00 $1,041.00
Supervisors x 2 $1,040.00 $1,040.00
CLOSURE
Lessons Learned $0.00 $0.00
Update AAAEM $0.00 $0.00
Close accounts $0.00 $0.00
AAAEM final Report $0.00 $0.00
Close phase completion $0.00 $0.00
TOTALS $5,390.00 $3,230.00 $2,370.00 $2,026.00 $2,026.00 $2,026.00 $2,026.00 $2,026.00 $2,886.00 $10,001.00 $25,615.00 $59,575.00 $0.00 $0.00 $119,197.00
COST PLUS 10% $539.00 $323.00 $237.00 $202.60 $202.60 $202.60 $202.60 $202.60 $288.60 $1,000.10 $2,561.50 $5,957.50 $0.00 $0.00 $11,919.70
11.2 COSTS GRAND TOTAL $5,929.00 $3,553.00 $2,607.00 $2,228.60 $2,228.60 $2,228.60 $2,228.60 $2,228.60 $3,174.60 $11,001.10 $28,176.50 $65,532.50 $0.00 $0.00 $131,116.70
30
PROFIT OR LOSS
Estimated Case: Low Mid High
Total Attendence for 2 nights 1000 1600 2150
Maximum available seat per night 800 1100 1100
Revenue
Avg ticket price $125.00 $125.00 $125.00
Total revenue $125,000.00 $200,000.00 $268,750.00
Expenses
Total expenses $117,116.70 $124,116.70 $131,116.70
Profit / (Loss)
Operational profit $7,883.30 $75,883.30 $137,633.30
31
DRAW-DOWN SCHEDULE
DATE AMOUNT
Sep-18 $5,929.00
Oct-18 $3,553.00
Nov-18 $2,607.00
Dec-18 $2,228.60
Jan-19 $2,228.60
Feb-19 $2,228.60
Mar-19 $2,228.60
Apr-19 $2,228.60
May-19 $3,174.60
Jun-19 $11,001.10
Jul-19 $28,176.50
Aug-19 $65,532.50
Sep-19 $0.00
Oct-19 $0.00
TOTAL $131,116.70
32
CASH FLOW
33
MyTown Show Society Night Events Governance Chart
AAAEM
Project
Management
Office
HR – Staff Event
Marketing & Hotels, Crowd Control, Hospitality, Entertainment
recruitment & Logistics &
Promotion Accommodatation Handling & Catering & & Scheduling
Management Master Layout
SME & Transport SME Security SME Amenities SME SME SME SME
34
MyTown Show Society Event Organisation Chart
AAAEM MSS
Project
Office
35
GOVERNANCE EVENT SCHEDULE
Governance Schedule
Governance Event Action/Timeframe Method of Delivery Document Control/Distribution
Project Status Report Written reports by the PM are to be Email PM reports are for the information
provided fortnightly to the PMO of the PMO only, not to be
dispersed. The collated information
across all project areas may be
distributed to the Client as an
overall project update.
Project Meeting Status meetings are to be held once Face to face, members may join via Minutes taken, recorded and
a month, facilitated by the PMO and video link or teleconference. dispersed electronically to
attended by all Project Managers attendees. Key messages and
learnings are collated and dispersed
to the Project Team where it has
been deemed necessary by the PM.
Monthly CCB Meeting Decision making meeting, held once Face to face, members may join via Minutes taken, recorded and
a month to review change requests video link or teleconference. If a dispersed electronically to
which have been escalated to a CCB member is unable to attend, a proxy attendees and PMO. Decisions are
decision may be sent in lieu of CCB member. documented in the Decisions
register and the PMP is updated.
Project Team notified of decision.
Weekly Project Team Manager Team meeting, held weekly. All Face to face, members may join via Minutes taken, recorded and
Meeting (SME) Project Team Managers are invited, video link or teleconference. dispersed electronically to
facilitated by PM. attendees and the Project Team
where it is deemed necessary by the
Project Team Manager (SME).
Monthly Project Team Meeting Team meeting, held monthly. All Face to face, members may join via Minutes taken, recorded and
Project Team members are invited. video link or teleconference. dispersed electronically to
attendees. Key messages and
learnings are dispersed to the
36
Project Team.
Stakeholder Meeting Status update and information Face to face, members may join via Minutes taken, recorded and
sharing meeting, held bi-monthly video link or teleconference. dispersed electronically to all
between Stakeholder Advisory members of the Stakeholder
Group, PM and Communications Advisory Group, PM,
and Stakeholder Manager. Communication and Stakeholder
Manager.
Residual
Risk Residual Residual Risk
Impact Probability Exposure Impact Probability Exposure
37
Availability or cancelation of primary talent - Brief Urbane
is traveling from an international location and has
commitments outside of Australia which could impact on
1 his availability 1 0.1 0.55 1 0.1 0.55
The soundness of budget assumptions made by the
Project Sponsor – a number of options are to be
presented around ticket prices, expected attendance
2 numbers and expenses associated with the Event. 0.5 0.3 0.4 0.1 0.1 0.1
Impact on existing Mytown Rural Show including but not
limited to livestock, Equine Competitions, access to and
3 from the Show for daytime visitors and vendors. 0.1 0.1 0.1 0.1 0.1 0.1
Expertise gaps in the primary stakeholder in large event
4 management. 0.1 0.3 0.2 0.1 0.1 0.1
Volunteer Management for event control - to support
the Business Case proposal of utilising Mytown Rural
Show volunteers a dedicated AAAEM resource is
5 proposed. 0.1 0.1 0.1 0.1 0.1 0.1
Availability of accommodation for expected influx of
6 visitors above normal Mytown Rural Show numbers. 0.1 0.3 0.2 0.1 0.1 0.1
Weather – Even though June is known as a stable month
for weather in South East Queensland wet weather can
7 impact adversely on any outdoor event. 0.5 0.3 0.4 0.5 0.1 0.3
Weak ticket sales – an option is to be presented to the
Project Sponsor to reduce the Event to a single night if
ticket sales remain weak 60 days before the date of the
8 Event. 0.5 0.3 0.4 0.5 0.1 0.3
Local residents noise complaint – an option to provide
local residents discounted ticketing prices is to be
10 considered. 0.1 0.3 0.2 0.1 0.1 0.1
38
Contractual obligations of Primary Talent to deliver shows
on or around the dates of the Mytown Rural Show, along
with contractual obligations which relate to permissions
11 for side shows. 0.5 0.3 0.4 0.5 0.1 0.3
The friendship between the Mytown Rural Show Society
board member and the Primary Talent – The pressures of
managing an event can have an impact on a personal
relationship which is not based upon a business
12 relationship. 0.5 0.1 0.3 0.5 0.1 0.3
13 Injury/Illness
- Pre-existing conditions: epilepsy, mental health crisis,
14 diabetes, etc 0.1 0.3 0.2 0.1 0.1 0.1
- Minor Event Specific: sunburn, blisters, dehydration,
15 minor assaults, abrasions, etc 0.1 0.1 0.1 0.1 0.1 0.1
- Major Event Specific: drug/alcohol overdose, serious
16 assaults, falls, vehicle related trauma, etc 0.1 0.1 0.1 0.1 0.1 0.1
17 - Entertainer: illness e.g. laryngitis, etc 1 0.1 0.55 1 0.1 0.55
18 Environment
19 - Severe weather events: electrical storms, hail, etc 0.5 0.1 0.3 0.5 0.1 0.3
- Temperature events: unusually cold weather causing
20 hypothermia, etc 0.1 0.1 0.1 0.1 0.1 0.1
21 - Chemicals: hazardous agricultural spray, etc 0.5 0.1 0.3 0.5 0.1 0.3
22 - Flora and Fauna: mosquitos, snakes, nettles, etc 0.1 0.1 0.1 0.1 0.1 0.1
23 Technical
24 - Power: failure of lighting, audio-visual equipment, etc 1 0.1 0.55 1 0.1 0.55
25 Project
26 - Project is delivered over budgeted costs 0.5 0.3 0.4 0.5 0.1 0.3
27 - Project misses scheduled milestones 0.5 0.3 0.4 0.5 0.1 0.3
28 - Attendees are not satisfied 0.1 0.1 0.1 0.1 0.1 0.1
39
29 - Permits or council lodgements are not approved 0.5 0.1 0.3 0.5 0.1 0.3
AAAEM has managed large events, but has not jointly
30 coordinated a music event in community annual shows. 0.5 0.6 0.55 0.5 0.1 0.3
Very busy AAAEM team members. Communications and
31 linkages may be challenging. 0.5 0.3 0.4 0.5 0.1 0.3
32 AAAEM team members may have schedule conflicts. 0.5 0.3 0.4 0.5 0.1 0.3
MSS may not share its Lessons Learned on Annual Show
33 2018. This is the expected scenario. 0.5 0.6 0.55 0.5 0.3 0.4
Exhibitors and vendors may be reluctant to share
34 information. 0.5 0.6 0.55 0.5 0.3 0.4
MSS Board may not be sufficiently motivated to hand
35 over event management. 0.5 0.6 0.55 0.5 0.3 0.4
Tight income margins. Insufficient revenue possibilities
36 for AAAEM. 1 0.3 0.65 1 0.1 0.55
AAAEM’s and MSS’s relationship has just started. While
friendly at this stage, it is a very early and newly forming
37 relationship. 0.5 0.8 0.65 0.5 0.6 0.55
40
Probability & Impact Residual risk & impact
Impact on the project (e.g. WBS (see Risk (see Risk Assessment
Risk Number Risk description. Element) that is affected Assessment matrix) Risk responses Controls and contingencies Triggers to watch Action planning: status, owner, due date. Matrix) Frequency of review
Communication from Talent's Manager
Additional local talent with Status: Open
Availability or cancelation of primary talent - Brief Urbane is traveling from an international location Whole project cancelation or the view of a reduced Media releases relating to primary Owner: Project Steering Committee Monthly until 1 month prior to event, weekly from
1 and has commitments outside of Australia which could impact on his availability significant scaling down 0.55 Treat event talent Due Date: as announced 0.55 that point
The soundness of budget assumptions made by the Project Sponsor – a number of options are to be Status: Open
presented around ticket prices, expected attendance numbers and expenses associated with the Cost Management Plan, in Owner: Project Manager Monthly until 1 month prior to event, weekly from
2 Event. Project cost overrun - 0.4 Treat built contingency fund ticket sales, sales of specific ticket type Due Date: prior to PMP being released 0.1 that point
Stakeholder MSS Board communication relating to
Communication Plan stakeholder dissatisfaction Status: Open
Owner: Project Manager
Impact on existing Mytown Rural Show including but not limited to livestock, Equine Competitions, Movement of WBS elements such as Review WBS which relate Mytown Show competitions not being Due Date: Monthly until 1 month prior to event, weekly from
3 access to and from the Show for daytime visitors and vendors. bump in/bump out plan 0.1 Treat to other access plans entered by competitors 0.1 that point
Project cost overrun as additional Leverage off existing
AAAEM resources are required project team's expertise
Deadlines being missed of duties Status: Open
Delivery of PMP elements which Skill gap analysis of MSS assigned to MSS Board members and Owner: Project Manager Monthly until 1 month prior to event, weekly from
4 Expertise gaps in the primary stakeholder in large event management. relate to event set up 0.2 Treat Board other local human resources Due Date: 0.1 that point
Additional training of
volunteers.
41