Avida Atria Tower 3 Fit-Out Project Atria, Mandurriao, Iloilo City Progress Report AS OF JULY 03-09, 2021
Avida Atria Tower 3 Fit-Out Project Atria, Mandurriao, Iloilo City Progress Report AS OF JULY 03-09, 2021
PROGRESS REPORT
AS OF JULY 03-09, 2021
1. Painting works of wall 60% completed
2. Painting works on ceiling 60%
3. Painting works on Tubular Frame 100%
4. Painting works on Powder Room Door and Jamb 90% completed
5. Painting works on conwood 90%
6. Painting works on ACU enclosure 95% completed
7. Tile works on ACU enclosure 100% completed
8. Tile works on powder room wall 95% completed
9. Tile works on powder room floor 95% completed
10. On-going Lobby tile floor repair
11. Electrical works 30% completed
12. Picture.
1
2
3
Prepared by Noted by:
Engr. Jeremiah V. Gilbolinga Engr. Paul Lorenz Carmelo