Divesh - 387 - Edinburgh Tram Systemx
Divesh - 387 - Edinburgh Tram Systemx
A Clear Site 8 10 12
B Install Drainage 7 10 19
C Installed Piled Foundations 8 15 22
D Construct Steel Frame 8 12 22
E PPC Floor Slab 8 9 16
F Install Roof Finishes 6 10 20
G Attach External Cladding Panels 6 8 10
H Install Internal Partitions 8 10 12
I Install Electricity Services 12 15 24
J Install Drainage and Water Services 8 12 22
K Install Raised Floors 8 20 26
L Install Suspended Ceilings 10 14 24
M Commision, Clean and Handover 8 10 12
Total Variation 27
Standard Deviation 5.196152
Critical Path Total Duration Total Variation Standard Deviation
A - C - D - E - G- I - K - M 101 Days 27 5.2
51 11 62
Install Roof
Finishes
48 F 59
0 10 10 14 11 25 25 13 38 38 10 48 48 8 56
Cons. Steel Attach External
Clear Site Install Drainage Frame PPC Floor Slabs Cladding Panels
0 A 10 10 B 21 25 D 38 38 E 48 48 G 56
10 15 25
Install PPC Fo.
10 C 25
Legend
Standard Deviation LS
Act. Name
ES
62 10 72 72 19 91 91 10 101
Install Internal Install Raised Commission &
Partitions Floors handover
59 H 62 72 K 91 91 M 101
56 16 72 76 15 91
Install Electrcity Suspended
Services Ceilings
56 I 72 72 L 87
59 13 72
Install Drainage
Services
56 J 69
Duration LF
Act. Code EF
Activity C Activity Expected Time Start Date End Date
A Clear Site 10 ### Friday, July 30, 2021
B Install Drainage 11 Friday, July 30, 2021 ###
C Installed Piled Foundations 15 Friday, July 30, 2021 ###
D Construct Steel Frame 13 ### ###
E PPC Floor Slab 10 ### ###
F Install Roof Finishes 11 ### ###
G Attach External Cladding Panels 8 ### ###
H Install Internal Partitions 10 ### ###
I Install Electricity Services 16 ### ###
J Install Drainage and Water Services 13 ### ###
K Install Raised Floors 19 ### ###
L Install Suspended Ceilings 15 ### ###
M Commision, Clean and Handover 10 ### ###
0 10 20 30 40 50
100
100 10
100 50
50 80
20 80
20 90
20 60
10
10
10
60 70 80 90 100 110
90
100 50
100 20
50 100 40
50 100
60 40
Critical Path A - C - D - E - G- I - K - M
Variation 27
SD 5.196
Mean 101
Probability 95%
Effective 97.5% As 2.5% on both sides
Z value 1.96 from table
can be used to accommodate the resource constraint but cannot be done because the excavators are utlized in activity A.
ncrease the project duration by 11 days
d in activity A.
Critical Path Total Duration
A - B - C - D - E - G- I - K - M 112
0 10 10 10 11 21 21 15 36 36 13 49 49 10 59
Cons. Steel
Clear Site Install Drainage Install PPC Fo. Frame PPC Floor Slabs
0 A 10 10 B 21 21 C 36 36 D 49 49 E 59
62 11 73
Install Roof
Finishes
59 F 70
67 16 83 87 15 102
Install Electrcity Suspended
Services Ceilings
67 I 83 83 L 98
70 13 83
Install Drainage
Services
67 J 80
Legend
LS Duration LF
Act. Name
ES Act. Code EF
Activity C Activity Expected Time Start Date End Date
A Clear Site 10 ### Friday, July 30, 2021
B Install Drainage 11 Friday, July 30, 2021 ###
C Installed Piled Foundations 15 Friday, July 30, 2021 ###
D Construct Steel Frame 13 ### ###
E PPC Floor Slab 10 ### ###
F Install Roof Finishes 11 ### ###
G Attach External Cladding Panels 8 ### ###
H Install Internal Partitions 10 ### ###
I Install Electricity Services 16 ### ###
J Install Drainage and Water Services 13 ### ###
K Install Raised Floors 19 ### ###
L Install Suspended Ceilings 15 ### ###
M Commision, Clean and Handover 10 ### ###
0 10 20 30 40 50
100
100
100 50
50 80
20 80
20
20
60 70 80 90 100 110
90
60
10 90
10 100 50
10 100 20
50 100 40
50 100
60 40
120
Activity Code Activity Optimistic Time Most Likely Time Pessimistic Time
A Clear Site 8 10 12
B Install Drainage 7 10 19
C Installed Piled Foundations 8 15 22
D Construct Steel Frame 8 12 22
E PPC Floor Slab 8 9 16
F Install Roof Finishes 6 10 20
G Attach External Cladding Panels 6 8 10
H Install Internal Partitions 8 10 12
I Install Electricity Services 12 15 24
J Install Drainage and Water Services 8 12 22
K Install Raised Floors 8 20 26
L Install Suspended Ceilings 10 14 24
M Commision, Clean and Handover 8 10 12
0 10 10 10 13 23 23 18 41 41 12 53 53 10 63
Cons. Steel
Clear Site Install Drainage Install PPC Fo. Frame PPC Floor Slabs
0 A 10 10 B 23 23 C 41 41 D 53 53 E 63
66 11 77
Install Roof
Finishes
63 F 74
71 16 87 91 15 106
Install Electrcity Suspended
Services Ceilings
71 I 87 87 L 102
74 13 83
Install Drainage
Services
71 J 84
Legend
LS Duration LF
Act. Name
ES Act. Code EF
Duration(Days) 116
Target Duration 111
Normal Cost per day 56000
Total Cost 6496000
Penalty for late delivery 20000
Project cost without crashing 6516000
After crashing M
Duration 113
Cost 6371750
A-B-C-D-E-F-H-K-M
A-B-C-D-E-G-I-K-M
A-B-C-D-E-G-J-K-M
After crashing
A-B-C-D-E-F-H-K-M 110
A-B-C-D-E-G-I-K-M 110
A-B-C-D-E-G-J-K-M 108
M can be crashed
Activity Weeks to be crashed Cost
M 3 3750
After crashing
A-B-C-D-E-G-H-K-M 107
A-B-C-D-E-F-H-K-M 107
A-B-C-D-E-G-J-K-M 107
G can be crashed
After Crashing
A-B-C-D-E-G-I-K-M 105
F can be crashed
After crashing
A-B-C-D-E-F-H-K-M 104
A-B-C-D-E-G-J-K-M 104
A-B-C-D-E-G-H-K-M 104