Professional Documents
Culture Documents
Thiết kế và kích thước lưu trữ năng lượng cho các nhà máy điện PV nối lưới
Thiết kế và kích thước lưu trữ năng lượng cho các nhà máy điện PV nối lưới
L. Palma
Universidad de Concepción
Edmundo Larenas 219, Concepción, Chile
palma@ieee.org
Abstract—By their nature PV power generation can be energy storage that can compensate for these short-term power
considered static. This means they do not have inertia as rotating disturbances and can only generate power depending on their
machines do, and thus, they cannot handle transient load demands instantaneous solar irradiance [4-7].
that go over their instantaneous maximum power point. In
addition, when compared to traditional generators their power Usually in residential and commercial applications this
ramp rate is much steeper, being able to reach values of 90% per drawback is not relevant, as the size of the photovoltaic system
minute and higher. Both characteristics have an impact on power is small compared to the grid. However, as solar generation
system operation, especially in the case of large PV plants. For increases, the amount of small scale generation turns more and
example, due to their lack of inertia, a PV plant cannot participate more important, resulting in that the lack of short term energy
in primary frequency regulation, injecting active power during reserves can become a problem. On the other hand, in the case
system faults. Further, the rapid power ramp rate exhibit by PV of utility scale photovoltaic plants, the lack of inertia is a relevant
plants can also affect system stability due to the fast increase or issue for power system operation. As the relative size of the PV
decrease in generated power, which usually cannot be generation is not small, and therefore the lack of energy reserves
compensated by the rest of the generators in the grid. In this to contribute with active power during faults can compromise
regard, it has been shown that these two issues can be mitigated by system stability. Moreover, due to the nature of the solar
the addition of energy storage elements to the PV plant power resource, PV plant power rises or drops quickly as function of
conditioning system. However, to do so proper sizing, interfacing
instantaneous insolation [8-9]. For this reason, the rate of change
and control of the energy storage is required. To tackle this issue,
of power injected to the grid is much faster than that achieved
analysis of energy storage requirements for a grid connected
power plant is performed in this paper. As a result, sizing
by traditional rotating generators. This is a relevant issue from
guidelines and a design procedure for the required battery bank system stability point of view since this can produce a sudden
are developed. In addition, a control strategy to regulate the power excess or lack of power in the grid that cannot be compensated
ramp rate of the system is presented and its effectiveness verified by other slower sources in the system.
through computer simulations.
Inverter #1
Array #1 500 kW
I. INTRODUCTION
Environmental concerns coupled with the ever-increasing
energy demand is moving power generation towards renewable Step-up
transformer
energy sources such as wind, geothermal and solar. Among 380/ 20kV
these, the latter, is becoming one of the fastest development due 750V
878
PV available power III. ENERGY STORAGE INTERFACING TOPOLOGY
In utility scale PV generation systems, power conversion is
commonly done using a single stage approach in which sections
Power [p.u] of a large array are connected to a string inverter which typically
has a DC link voltage around 750V. Several of these inverters
Power injected to the grid
at maximum ramp rate are connected in parallel to reach the desired power level,
forming a common AC bus which connects to a step-up power
transformer which in turn connects to the grid (fig1).
There are mainly two possible options to interface an energy
storage element to such a system. One is the connection of the
t1 t2
time [minutes]
energy storage element in parallel with the array by means of an
auxiliary DC-DC converter (fig4). This approach has the main
Figure 3. Difference between power generated by the array and maximum advantage of being of simple control. However, this approach
allowed ramp rate has several drawbacks, being one of them the fact that the energy
From fig 3, power produced by the array and delivered to the storage must be divided between several inverters in order to
grid under ramp rate limitation are given by (3) and (4) as avoid exceeding their maximum power limit during charge and
discharge. In addition, connection of the energy storage element
follows.
to the inverter DC link perturbs normal operation of the
݉௩ ܲ ݐݐ ݐଵ (3) maximum power point tracking system, due to the its slower
ܲ ൌ ൜ ሾܹሿ dynamics.
ܲ ݐ ݐଵ
݉୫ୟ୶ ̴ ܲ ݐݐ ݐଶ (4)
ܲ௨௧ ൌ ൜ ሾܹሿ
ܲ ݐ ݐଶ
where, Po is the nominal power of the array, mpv the rate at 750V
which array power ramps up (or down), mmax_ramp the maximum
allowable ramp time, and t1 and t2 the times at which maximum Inverter
Array
values are reached. The difference between available and
Bi-directional
delivered power is the power that should be stored or delivered Energy
DC-DC
Storage
by the storage elementοܲ ൌ ܲ െ ܲ௨௧ . Taking this into
account the required energy storage size can be calculated by
integrating οܲ over the time period in which power should ramp
up resulting in (5), whit ko=60 which allows expressing the result Figure 4. Energy storage addition through an auxiliary DC-DC converter
in Joules instead of watt minute. Alternatively, the energy storage element can be
௧మ incorporated directly at the common AC bus through an
߱௧௦௧ ൌ ݇ න οܲ݀ ݐሾܬሿ (5) additional inverter as shown in fig 5. Although control of this
interfacing strategy is more complex, it is more advantageous
Considering the ramp rate limits given above it can be since energy storage can be concentrated into one block
calculated that the amount of energy storage required to facilitating the implementation of charging and discharging
compensate for the rapid ramping up and down is of 267 seconds strategies. Additionally, this approach has the advantage of
of nominal power. using a dedicated inverter to interface with the system, which
ensures that its operation won’t interfere with the optimal power
A comparison of the required energy storage for each of the generation of the PV array. Moreover, this approach can be used
three contingencies analyzed is shown in Table I. As can be seen as an add-on solution for exiting PV plants, which is also
the case of power ramp compensation is the most energy advantageous.
demanding, and thus, if a system has this amount of energy
stored it can supply power in all three cases. Therefore, the value
obtained for power ramp compensation can be used as a design
criterion for the required energy storage element resulting in an 750V
Step-up
transformer
element that can cover all the energy requirements of the system. 380/ 20kV
Inverter #1
Array #1 500 kW
Energy
Primary frequency control 45 Pnominal 12.5x10-3 Pnominal 750V Storage
879
As a result of the preceding analysis the second approach is Thus, for example for a system with a nominal power of 500
selected in this case for interfacing the energy storage element. kW the energy requirement calculated using (5) considering
that the maximum ramp rate is of 10%/minute, and that the PV
plant has a ramp rate of 90%/minute, is of 133.500 [kJ]; which
IV. ENERGY STORAGE BANK SELECTION AND DESIGN translates to 37.1 kwh. If the energy storage bank is
To meet the energy storage requirements calculated in the implemented using Li-ion batteries which have a DOD of 80%
previous sections two types of storage elements can be used, and a close cycle efficiency of 92%; and considering a bank
supercapacitors and batteries. Each of them has advantages and voltage of 750 V, results from (6) that the capacity of the
disadvantages as can be seen from Table II. For example, the required battery bank is of 67.2 Ah.
use of supercapacitors to implement the energy storage bank
provides fast charge and discharge times due to their high-
power density which is 10 kW/kg, and an elevated cycle life V. CONTROL SCHEME
(≈1.000.000). However, their main disadvantages are their low As discussed in the previous sections, to minimize the
energy density which is around 10 Wh/kg, and reduced cell impact on grid operation the power ramp rate of the PV plant
voltage which is of 2.7 V. These characteristics make needs to be limited. This is done by storing excess energy in a
supercapacitors a good solution for short term energy storage battery bank connected to the common AC bus when PV power
ranging from several seconds to few minutes. On the other ramps up, and by delivering the sored energy when PV power
hand, batteries are characterized for somewhat higher cell ramps down. To achieve this, the energy storage system
voltage, which ranges from 1.2 V/cell for Nickel-Metal and controller needs to detect the ramping up and down of the power
Nickel-Cadmium to 3.6 V/cell for Li-Ion. Moreover, the energy generated by the PV plant and to produce adequate switching
density of batteries is higher, ranging from 20 Wh/kg for Lead- signals for the battery interfacing inverter. To achieve these
acid to 150 Wh/kg Li-Ion, with a cycle life around 400-2500. goals the control logic shown in fig 6 is proposed. In this
All these characteristics make batteries a good alternative for scheme power produced by the PV plant is calculated by means
long term energy storage. of voltage and current of the PV array.
880
In this scheme the instantaneous power produced by the PV the results are scalable to different time scales without mayor
plant is calculated in terms of the array voltage and current. The differences.
resulting power is then fed into a differentiator block to obtain Operation of the system without the energy storage is shown
its rate of change, and whose magnitude and sign are then in fig. 9. As can be observed under this condition power
calculated in the following blocks. These results indicate produced by the two arrays ramps up rapidly at a rate higher
whether the PV generator is increasing or decreasing its power than 90% per second. And further, in the same fashion, power
output, and thus determines if the battery must be charged or injected by the PV plant to the grid follows.
discharged. Next the resulting magnitude of the power rate of
change is compared against a preset threshold in the comparator Ppvo1 Ppvo2 -Pgrid
[W]
block to decide if the battery is to be used. If the comparison is
25000
positive, a pulse is generated to command the battery Pgrid
20000
interfacing converter to operate. The duration of the charge or
discharge of the battery is preset according to the slope of the 15000
Ppvo_1
ramp rate defined by the grid codes. The power that the battery 10000
Ppvo_2
converter must absorb during the charging process or to deliver 5000
during discharge is calculated by the subsystem shown in fig. 8. 0
0 0.6 1.2 1.8 2.4 3
In this scheme, when the battery enable signal is received from Time (s)
the power ramp detection block, the corresponding maximum
allowed ramp rate signal is activated. This signal is then Figure 9. Power generated by the PV array and injected to the grid without
multiplied by the nominal power of the PV plant to generate the energy storage
active power reference signal, which is in turn fed into the PQ Next the simulation was repeated, adding the battery bank
controller of the inverter used to interface the battery bank with and interface converter to the power conditioning system. Fig.
the AC bus. 10 shows the control signals obtained from the power ramp
detection scheme. As can be seen, as power produced by the PV
abc feedback array increases, its rate of change raises rapidly (fig 10b). When
currents
this value goes above a preset threshold level, which in this case
Q reference is of 400 W/sec, a ramp up event is detected (fig 10c). This
Ramp
reference
abc reference signal in turn sets up the gating signal to start charging the
PQ signals for
controller inverter y bank (fig.
battery g 10d).
Baterry modulation
enable
P reference
PV plant
nominal power
881
Operation of the system under this condition is shown in Grid Integration of Renewable Energy Sources: A Survey”;IEEE
Transactions on Industrial Electronics, Vol. 53, No. 4, 2006, pp. 1002-
figure 11. As can be observed power generated by the arrays
1016.
follows the same fast rate of change as in the previous operation [2] F. Farret; M. Simoes; “Integration of Alternative Sources of Energy”;
condition exhibiting a ramp rate higher than 90%. On the other Wiley-IEEE Press, 2006; ISBN 0471712329.
hand, power injected to the grid follows the preset ramp rate of [3] M. Meinhardt et al; “Past, Present and Future of Grid Connected
Photovoltaic and Hybrid-Power Systems”; IEEE Powe Engineering
8.8% per second. The difference between generated power and
Society Meeting, vol 2, pp. 1283-1288, July 2000.
delivered power is absorbed by the battery bank, which initially [4] Y. Huang, J. Wang, F.Z. Peng; “Survey of the Power Conditioning
absorbs all the power produced by the PV array. Moreover, as System for PV Power Generation”; 37th IEEE Power Electronics
power delivered to the grid increases, power absorbed by the Specialists Conference, PESC 2006; pp. 1-6, June 2006 .
[5] X. Wang; M. Yue;”PV Generation Enhancement with a Virtual Inertia
battery bank is reduced until it reaches zero.
Emulator to Provide Inertial Responde to the Grid”; IEEE Energy
Conversion Congress and Exposition, ECCE, September 2014.
[W] Ppvo1 Ppvo2 P_batt -Pgrid [6] A. Hoke, D. Maksimovic;”Active Power Control of Photovoltaic Power
Systems”; 1st IEEE Conference on Technologies for Sustainability;
30K Pgrid SusTech 2013; pp. 70-77
20K [7] E. Waffenschmidt; R. Hui;”Virtual inertia with PV inverters using DC-
10K link Capacitors”; 18th European Conference on Power Electronics and
0K
Aplicationes; EPE16 ECCE Europe; 2016; pp. 1-10
[8] I. Mazahari; B. Parkhideh;”Comparing Ramp Rate Control Method for
-10K PV-Energy Storage Sistems in Cascaded and Paralell Architechtures”;
-20K Ppvo_1 and Ppvo2 IEEE International Telecominicatioons Energy Conference, INTELEC
-30K P batt 2016; pp. 1-6.
[9] N. Kim; B. Parkhideh;”Ramp-rate Control Strategy for Distributed PV-
0 5 10 15 20 ESS AC-stacked Inverter Architechture”; 8th IEEE International
Time (s)
Symposium on Power Electronics for Distributed Generations Systems;
Figure 11. System operation under PV array up and down ramps. PEDG 2017; pp. 1-6.
[10] A. Tani; M. Camara; B. Dakyo;”Energy Management in the Decentralized
PV plant ramping down process can also be observed from Generation Systems Based on Renewable Energy – Ultracapacitors an
fig. 11. As power produced by the PV array drops quickly, Battery to Compensate the Wind / Load Power Fluctuations”; IEEE
Transactions on Indutry Applications, Vol51, No 2; April 2015.
energy stored in the battery bank is delivered to regulate the [11] H. Zhou; T. hattacharya; D. Tran; T. Sing; T. Siew; A.
ramping down of the power conditioning system to an 8.8% per Khambadkone;”Composite Energy Storage System Involving Battery and
second rate. Ultracapacitor with Dyma,oc Energy Management in Micro Grid
Applications”; IEEE Transactions on Power Electronics, Vol 26, No 3;
March 2011.
[12] S. Manfredi; M. Pagano; “On the Use of Ultracapcitor to support
VII. CONCLUSION Microgrid Photovoltaic Power system”; International Confference on
Clean Electrical Power, ICCEP, June 2011, pp. 491-497.
[13] N.S. Jayalakshimi; D.N. Gaonkar; V. Kumar; R.P. Karthik;”Battery
PV power plants are limited by the instantaneous power Ultracapacitor Storage Devices to Mitigate Power Fluctuations for Grid
produced, and therefore do not have overload capability or Connected PV System”; Annual IEEE India Conference; INDICON
inertia as conventional rotating generator do. In addition, PV 2015; December 2015.
[14] W. Maranda, M. Piotrowicz; “Short-time Energy Buffering for
plants can exhibit rapid ramp up and down power Photovoltaic System”; 17th International Conference on Mixed Design of
characteristics which can be several times faster than Integrated Circuits and Systems; June 2010, pp. 525-528.
conventional power plants. All these characteristics interfere [15] M. Goranova; B. Dimitrov; “Applications of Supercapacitors in
with normal grid operation, and can impact its stability and Standalone Photovoltaic systems”; 18th International Symposium on
Electrical Apparatus and Technologies, SIELA, May 2014, pp. 1-4.
reliability, especially in the case of high power PV generation [16] C. Gravriluta; I. Candela; J. Rocabert; I. Etxeberria-Otadui; P.
plants. Rodriguez;”Storage System Requirements for Grid Supporting PV Power
It is shown in this paper that to mitigate these issues, the Plants”; IEEE Energy Conversion Congress and Exposition 2014, ECCE
2014; September 2014.
addition of energy storage elements to the power conditioning [17] P.K. Ray; S.R. Mohanty; N. Kishor;”Frequency Regulation of Hybrid
structure of the PV power plant becomes necessary. Moreover, Renewble Energy System for Large Band Wind Speed Variation”; Third
a method to calculate and properly size the required energy International Conference on Power Systrems; December 2009.
[18] J. Miller; G. Sartorelli;”Battery and Ultracapacitor Combinations – Where
storage element is presented. Further, a control scheme to Should the Converter Go?”; IEEE Vehicle Propulsion Conference, VPPC,
manage the charge and discharge of the energy storage bank to September 2010.
limit the PV plant power ramp rate is introduced. [19] L. Palma;” Analysis of supercapacitor connection to PV power
conditioning systems for improoved performance”; International
The validity of the of the proposed method is verified by Conference on Clean Electrical Power, ICCEP; June 2015; pp. 198-203
computer simulations, showing that it can effectively limit the [20] Coordinador Eléctrico Naciónal, https://www.coordinador.cl/
power ramp rates to 8.8% per minute. Thus, achieving the [21] J. Marcos, O. Storkel, L Marroyo, M.. Garcia, E Lorenzo:” Storage
recommended values set by the industry. Requirements for PV Power Ramp-Rate Control”: Solar Energy, Elsevier,
Vol. 99, January 2014, pp. 28-35
[22] D. Cormode, A. Cronin, W. Richardson, A. Lorenzo, A. Brooks, D.
REFERENCES DellaGiustina;” Comparing Ramp Rates from Large and Small PV
Systems, and Selection of Batteries for Ramp Rate Control”; 39th IEEE
[1] J.M. Carrasco, L. García, J.T. Bialasiewicz, E. Galván, R. Portillo, Ma. A. Photovoltaic Specialists Conference; PVSC 2013, June 2013.
Martín, J.I. León, N. Montero-Alonso; “Power Electronic Systems for the
882